Tmb Electronics vs Shanti Developers & Anr.

Court
Delhi High Court

$
* IN THE HIGH COURT OF DELHI AT NEW DELHI

% Judgment reserved on : 09.07.2026
Judgment delivered on : 19.08.2026
Judgment uploaded on : As per Digital Signature~

# CNR No. DLHC010075102024

+ FAO(OS) (COMM) 26/2024

TMB ELECTRONICS .....Appellant

versus
SHANTI DEVELOPERS & ANR. .....Respondents

Advocates who appeared in this case

For the Appellant : Mr. Arvind Nigam and Mr. Gautam
Narayan, Sr. Advocates with Mr. Jai Sahai
Endlaw, Mr. Ashish Kumar and Mr.
Abhinav Gupta, Advocates.

For the Respondents : Mr. Sunil Kumar Mittal, Mr. Anshul Mittal,
Mr. Sameer Dawar, Mr. Vishwam Mishra
and Mr. Vaibhav Garg, Advocates.
CORAM:
HON'BLE MR. JUSTICE V. KAMESWAR RAO
HON'BLE MS. JUSTICE MANMEET PRITAM SINGH ARORA

JUDGMENT
V. KAMESWAR RAO, J.

1. This appeal has been filed by the appellant challenging the judgment
dated 15.12.2013 passed by the learned Single Judge in a petition under
Section 34 of the Arbitration & Conciliation Act, 1996 (the Act, thereafter),


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:19.08.2026
15:33:47
FAO(OS) (COMM) 26/2024 Page 1 of 39

wherein the petition was dismissed. The appellant vide this appeal seeks the
following prayers:
“I. Allow the present appeal and set aside the Judgment dated
15.12.2023 in OMP Comm. 513/2023 passed by this Hon'ble
Court;
II. Set aside the Impugned Arbitral award dated 29.08.2023
passed by the Ld. Sole Arbitrator in the arbitral proceedings
between the Appellant and Respondents”

2. The facts as noted from the appeal are that the appellant/petitioner
engaged respondent no.1 for construction of a proposed factory building in
Kundli district, Sonipat, Haryana. The agreement dated 13.03.2018, (the
agreement) was executed between the parties & the respondent no.2 was
engaged as an Architect of the Project. In terms of Clause 30 of the
agreement, the work was to be completed within 12 months from the date of
signing of the Agreement i.e., March 2018. Disputes arose between the
appellant and the respondent no.1 and the respondent no.1 invoked Clause
36 of the agreement vide notice dated 21.08.2021. This Court appointed a
sole Arbitrator vide order dated 03.03.2022. The respondent no.2 was made
proforma respondent in the proceedings.
3. It was the case of the respondent no.1 before the learned Arbitrator
that, despite having completed the work in a timely manner, the bills which
were presented to the appellant remained outstanding.
4. According to the respondent no.1/claimant, it had completed the
original/stipulated work as well as the additional work in August/September
2020 and handed over the site to the appellant, no objections were raised
when the site was handed over. Even though the periodical bills were


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:19.08.2026
15:33:47
FAO(OS) (COMM) 26/2024 Page 2 of 39

verified in terms of the work done. The final bill dated 07.08.2021
amounting to Rs.13,37,98,982/- was the cumulative sum for the original
work and the additional work. It is their admitted case that they had received
payment of Rs.5,16,00,000/- which leaves the balance amount as
Rs.8,21,98,982/-. It was this said amount which formed a part of the claims
before the learned Arbitrator. The claims which were presented before the
learned Arbitrator, are as follows:
“(i) Rs.8,21,98,982/- towards work done and not paid for;
(ii) Rs.2,00,69,847/- towards loss of profits calculated at 15%
of the amount of the total bill;
(iii) Interest at the rate of 18% per annum; and
(iv) Costs.”

5. The appellant contested the claims raised by the respondent no.1 on
the ground that the respondent no.1 had been unprofessional and did not
finish the entire work. It acted against the terms of the agreement. It was the
case of the appellant that:-
(i) bill of Rs.25,00,000/- was not raised on completion of the work.
(ii) The rates for additional work done in terms of Clause 7 of the
agreement was not submitted.
(iii) The quality check for the material procured was never
submitted in terms of Clause 39 of the agreement.
(iv) Even the timeline under Clause 30 of the agreement for the
work was not followed and the prior reasons for delay were not
given as per Clause 31.


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:19.08.2026
15:33:47
FAO(OS) (COMM) 26/2024 Page 3 of 39

(v) The labour norms were not complied with contrary to Clause
11.
(vi) Issues related to deposit of GST for four invoices by the
respondent no.1 also cropped up i.e., the GST against the said
invoices was not deposited.
(vii) There were also issues regarding the submissions of the GST
submission on the final bill i.e., the GST amount was not
reported which brought the veracity of the final bill in question.
6. The case of the appellant before the learned Arbitrator was that, the
appellant upon inspection of the site, discovered that the foundation of the
building was not properly laid and there were issues of water damage in the
basement of the building.
7. After completion of pleadings, the learned Arbitrator framed the
following issues:
Point of determination
“(1) Whether the claimant is entitled to the reliefs claimed in
the statement of claim?
(2) Whether the claimant in entitled to interest, if yes, at what
rate?
(3) Cost?
(4) Relief?”

8. Before the learned Arbitrator, the parties agreed not to lead any oral
evidence and the appellant did not raise any counter claims. The learned
Arbitrator deemed it fit to split the reliefs claimed under the heading of the
amount due in terms of the final bill in paragraph 26 of the Arbitral awards


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:19.08.2026
15:33:47
FAO(OS) (COMM) 26/2024 Page 4 of 39

in the following manner:
“26. A perusal of the final bill would show that it has five
separate components being (1) towards work under the original
Agreement; (2) price escalation for steel and cement, (3) excess
steel consumed, (4) extra work done, and (5) Other
miscellaneous items and purchases. These are taken to be
separate sub-points of determination.”
9. The learned Arbitrator came to the conclusion that the respondent
no.1/claimant was entitled to a sum of Rs. 6,14,97,594/-. The other claims of
the respondent no.1 were rejected. The appellant/petitioner challenged the
award before the learned Single Judge vide a petition under Section 34 of
the Act, which was dismissed.
SUBMISSIONS ON BEHALF OF APPELLANT
10. Mr. Arvind Nigam and Mr. Gautam Narayan learned Senior Counsel
with Mr. Jai Sahai Endlaw, Advocate appearing on behalf of the appellant
would submit that, as per Clause 23 of the agreement, upon completion of
the work, a notice was to be issued by respondent no.2. The said work was
to be completed within a period of 12 months from the date of the signing of
the agreement. They have also drawn our attention to the payment terms to
state that the liability for the payment of GST would be borne by the
respondent no.1.
11. Mr. Nigam stated that, on 09.07.2021, the respondent no.1 issued a
notice to the appellant claiming that the works under the agreement were
completed by August/September 2020 and the amount of Rs.12,17,45,400/-
was to be paid by the appellant. On 07.08.2021, the respondent no.1 issued a
final bill wherein it had claimed an amount of Rs.13,37,98,982/- from the


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:19.08.2026
15:33:47
FAO(OS) (COMM) 26/2024 Page 5 of 39

appellant. Thereafter, the appellant as per letter dated 20.08.2021 denied that
no amount was left due and payable to the respondent no.1.
12. The case of the appellant is that the claim has been partially allowed
in contravention to Clause 23 of the agreement. According to Mr. Nigam,
the respondent no. 1 has neither pleaded nor proved that it ever issued a
notice of completion nor that it received a completion certificate.

13. He argued that, since the respondent no. 1 has admitted non-
compliance of Clause 23 of the agreement and also that no completion
certificate was issued by respondent no. 2, it shows that there was no
occasion for the learned Arbitrator to hold that the works under the
agreement were completed by respondent no.1 to the satisfactions of the
appellant and the respondent no.2. He also has stated that this ground was
also urged by the appellant before the learned Single Judge but did not
consider this aspect.
14. According to him, the learned Arbitrator has awarded GST to the tune
of Rs.1,72,70,328/- in favour of the respondent no.1. The impugned award is
expressly contrary to the payment terms under the agreement, which
provides that, all statutory liabilities including the GST would be the
responsibility of respondent no.1.
15. Mr. Nigam has submitted that, to establish the completion of the
works, the respondent no.1 only relied on the final bill dated 07.08.2021 and
Whatsapp messages showing the status of work at the construction site. It is
his case that the learned Arbitrator has awarded the amount under this claim
only on the basis of the final bill dated 07.08.2021.


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:19.08.2026
15:33:47
FAO(OS) (COMM) 26/2024 Page 6 of 39

16. According to him, without any reference to the material or evidence
on record, the learned Arbitrator came to a conclusion that the works under
the agreement was completed by respondent no. 1 during the months of
August-September, 2020. Such a finding is ex facie based on conjecture as
the learned Arbitrator ought to have determined the actual date of
completion of work or when the site was handed over to the appellant in
terms of the agreement. The impugned judgment observes that the
photographs of the site taken until August-September, 2020 clearly shows
that the work was still ongoing and the same is contrary to the stand taken
by the appellant/petitioner.
17. He submitted that, the learned Single Judge has also failed to consider
that ongoing work is not equivalent to completion of work and that the
respondent no. 1 had failed to establish that it had completed the work and
sought payment of the same in terms of the final bill dated 07.08.2021.
18. He has submitted that the learned Arbitrator has erroneously observed
that the working area has not been disputed by the respondent no.1. On a
perusal of the impugned award as well as the appellant’s Statement of
Defence, would reveal that the appellant had in fact disputed the completion
of work by respondent no. 1 in terms of the agreement. The said finding was
upheld by the learned Single Judge and such a finding is erroneous as the
same does not consider the grounds urged by the appellant. The final bill
dated 07.08.2021 was also denied by the appellant in its affidavit of
admission and denial and such a monetary entitlement thereunder was to be
supported with evidence as in accordance with law.
19. He submitted that the learned Arbitrator has overlooked the relevant


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:19.08.2026
15:33:47
FAO(OS) (COMM) 26/2024 Page 7 of 39

material on record, which would have proved that the respondent no.1 had
relied on various bills of different amounts and the value of work done, as
per notice dated 09.07.2021 the amount was Rs.12,17,45,400/-. As per the
bill shared vide email dated 21.12.2020, the final amount was
Rs.12,40,13,500/- and as per bill dated 07.08.2021, the amount was
Rs.13,37,98,982/-, such glaring inconsistencies ought to have led to the
respondent no.1 to prove its entitlement to the amount claimed, this material
has not been considered by the learned Arbitrator.
20. He submitted that from the documents filed by the respondent no. 1, it
is evident that respondent no. 1 has taken an inconsistent stand regarding
completion and verification of work including the quantum of work done.
The respondent no. 1 had in its communication dated 04.07.2020 claimed
that, it had executed the work and had called upon the appellant to verify the
work done. Thereafter, the respondent no. 1 stated that its work was verified
in August-September, 2020 but no proof of such verification in the
intervening period was produced. In terms of the letter dated 09.07.2021, the
respondent no.1 claimed that the verified value of its work was
Rs.12,17,45,400/-. The material on record discloses contrary stand taken by
the respondent no.1 which has been overlooked by the learned Arbitrator in
the impugned award on the basis of the final bill dated 07.08.2021 wherein
the amount claimed was Rs.13,37,98,982/- without verifying the actual work
done and also erred in concluding that the work was completed in August-
September, 2020. The amount awarded suffers from a patent illegality.
21. One of the submissions of Mr. Nigam is that the standard of proof
adopted is inconsistent with the findings to the other claims. The learned


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:19.08.2026
15:33:47
FAO(OS) (COMM) 26/2024 Page 8 of 39

Arbitrator while deciding other claims as raised by the respondent no.1 had
held that the same were liable to be rejected due to lack of evidence.
However, the learned Arbitrator had failed to consider the fact that, evidence
was lacking to sustain the claim for the amount due under the final bill dated
07.08.2021.
22. He submitted that, it is trite law that the burden of proof lies upon the
party who wishes to claim the existence of a certain factual position and if
one were to examine this case on the said principle, it would reveal that the
respondent no. 1 has not established the fact that it had carried out the work
against the amounts claimed in its final bill as per the drawings. Therefore,
since respondent no. 1 had not discharged its burden of proof, there was no
occasion for the learned Arbitrator to observe that the work was completed
by respondent no. 1 and is entitled for the said claim.
23. According to him, the learned Arbitrator has only considered the
lapses in the defense set up by the appellant, however, even if it were to be
assumed the same, it does not ipso facto prove the case of the respondent no.
1. The impugned judgment is based entirely on consideration of the lapses in
the defense set up by the appellant and has not considered that the burden of
proof to establish that whether such proof was adequately discharged or not.
He stated that this ground of challenge was specifically taken by the
appellant before the learned Single Judge but the same has not been
considered.
24. Mr. Nigam has placed reliance on the judgment in the case of Indian
Oil Corporation v. Shree Ganesh Petroleum, (2022) 4 SCC 463 to argue
that the Arbitral Tribunal cannot rewrite the terms of the contract and is


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:19.08.2026
15:33:47
FAO(OS) (COMM) 26/2024 Page 9 of 39

bound by the same. He has also relied upon the judgment in the case of
Navnirman Development Consultants India Private Limited v. Divisional
Commissioner and President District Sports Complex Executive
Committee, Pune, (2017) 8 SCC 603 to argue that the Court while
dismissing a challenge under Section 34 of the Act is duty-bound to pass a
reasoned order examining the ground urged by the applicant. He also has
relied on UHL Power Co. Ltd. v. State of H.P., (2022) 4 SCC 116 in
support of his arguments submitted that the Court while hearing an appeal
under Section 37 of the Act must examine the correctness of the order
passed within the confines of Section 34 of the Act. He also relied on the
following judgments in support of his case:
i. International Breweries Pvt. Ltd. v. Mohan Meakin Ltd.,
2023 SCC OnLine Del 7710 ;
ii. Delhi State Industrial and Infrastructure Development
Corporation Ltd. v. Bawana Infra Development Pvt. Ltd.,
2023 SCC OnLine Del 8295 ;
iii. Delhi State Industrial and Infrastructure Development
Corporation Ltd. v. M/s PNC Delhi Industrial Infra Pvt.
Ltd., 2024 SCC OnLine Del 2887 ;
iv. Flowmore Ltd. v. Skipper Limited, 2023 SCC Online Del
3696 ;
v. Five Star Construction Pvt. Ltd. v. Orchid Infrastructure
Developers Pvt. Ltd., 2024 SCC OnLine Del 41 ;
vi. Harcharan Dass Gupta v. Azad Hindi Coop Group
Housing Society Ltd., 2024 SCC OnLine Del 1109 ;
vii. Jaiprakash Hyundai Consortium v. Satluj Jal Vidyut


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:19.08.2026
15:33:47
FAO(OS) (COMM) 26/2024 Page 10 of 39

Nigam Ltd., 2024 SCC OnLine Del 1237 ;
viii. M/s Bharat Sanchar Nigam Limited v. M/s EXNXT
Software Private Limited, 2017 SCC OnLine Del 9564 ;
ix. National Highway Authority of India v. Shree Jagannath
Expressways Pvt. Ltd., 2022 SCC Online Del 706 ; and
x. Smriti Debbarma v. Prabha Ranjan Debbarma and
Others, 2023 SCC Online SC 9 .
SUBMISSIONS ON BEHALF OF RESPONDENTS
25. Mr. Sunil Kumar Mittal, learned counsel appearing on behalf of the
respondent no.1 has at the very outset argued that the scope of an appeal
under Section 37 of the Act is very limited in nature and the appeal clearly
falls outside this Court under Section 37 of the Act.
26. According to him, the appellant has raised new contentions in the
present appeal which were neither part of the pleadings before the learned
Single Judge nor were incorporated in the Statement of Defense before the
learned Arbitrator, he stated, the same cannot be raised at this belated stage
to assail the impugned award. In this regard, he has placed reliance on the
judgment in the case of Union of India v. M/s. Susaka Pvt. Ltd. & Ors.,
[2017] 12 SCR. 430.
27. He submitted that even though, the appellant has taken a stand that the
measurement book was not placed on record in terms of Clause 16 of the
agreement, the said contention is absolutely misplaced. The agreement
between the parties clearly stipulates that only the structure work was to be
raised by the respondent no.1 for which the amount was payable on a lump


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:19.08.2026
15:33:47
FAO(OS) (COMM) 26/2024 Page 11 of 39

sum/per Sq. Ft. rate basis. Whereas, as per Clause 16 of the agreement only
extra items or any variation or those items, which were tabled as per item
rates, had to be paid based on the recordings of the measurement book.
Clause 16 of the agreement has nothing to do with the original agreement
work, which was executed on lump sum/per Sq. Ft. rates. The learned
Arbitrator had only awarded the amount in terms of the agreement/work
done as per the per Sq. Ft. rate.
28. On the contention that the respondent no.1 had taken a stand before
the learned Arbitrator that the measurement sheets were being submitted to
the Architect, however no such measurement sheets were ever produced, he
submitted that, even if, it is assumed that the measurement sheets were
submitted, they would have included only the additional work which was
not included in the agreement per Sq. Ft. rates. The measurement sheets
were part of the record, filed as Annexure C-8 to the Statement of Claims.
He has also stated that the appellant neither raised any plea regarding the
measurement book in its Statement of Defence nor before the learned Single
Judge. Even in the present appeal, the plea referring to Clause 16 of the
agreement has not been taken.
29. He submitted that the appellant vaguely argued their Statement of
Defense before the learned Arbitrator that the work was abruptly abandoned
by the respondent no.1 and the balance work was executed by the appellant.
The only claim made by the appellant before the learned Arbitrator was that
the respondent no.1 had apparently not deposited the GST which it had
charged from the appellant.
30. Mr. Mittal submitted that the entire Statement of Defense was based


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:19.08.2026
15:33:47
FAO(OS) (COMM) 26/2024 Page 12 of 39

purely on vague statements and the appellant did not file any counter claim
against the respondent no.1 which essentially translates to the fact that the
appellant had not alleged any breach of agreement by respondent no.1.
31. According to him, it is an admitted case that the parties agreed that
there would be no requirement of leading oral evidence before the learned
Arbitrator and the matter was to be decided on the basis of the record
submitted. The entire work was executed under the direct control of
respondent no. 2, who was engaged by the appellant. All the relevant
communications such as the final bill, completion of work and
inspection/verification of works was to be carried out by the respondent no.
2. The appellant had the best available evidence in the form of records of the
Architects/respondent no. 2 but they have neither submitted any record nor
sought to produce the respondent no. 2 before the learned Arbitrator in
support of their case.
32. He submitted that, on the perusal of the complete record, the only
issue before the learned Arbitrator was whether the respondent
no.1/Claimant had completed the work and if any payments were due to be
paid by the appellant herein.
33. According to him, the appellant never disputed their liability to pay
GST on the payments to be paid to the respondent no.1/Claimant under the
agreement. This argument has been taken by the appellant for the very first
time in the present appeal, which is too late in the day to raise such
contention. This factum would make it abundantly clear that the appellant in
fact never had any issue or difference regarding the charge of GST. In this
regard, he relied on Annexures A-4 and A-9 of the paper-book wherein the


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:19.08.2026
15:33:47
FAO(OS) (COMM) 26/2024 Page 13 of 39

respondent no. 1 in its Statement of Claim had specifically pleaded that the
final valuation also includes the applicable GST as per the relevant
provisions of law. This averment, according to Mr. Mittal, was never
disputed by the appellant before the learned Arbitrator or before the learned
Single Judge.
34. He submitted that, the only issue challenge in the appeal is that Claim
no. 1 was partially allowed by the learned Arbitrator and awarded a sum of
Rs. 6,14,97,594/- towards the works executed under the agreement while the
other claims were merely consequential.
35. He submitted that insofar as the issue of abandonment of work is
concerned, the allegation that, in November, 2019 only partially finished
work till the upper ground floor, the said allegation is without with any
evidence, various messages exchanged between the parties with
photographs, which formed part of the arbitral record, would show that the
work has been done up to the terrace above the second floor. He has also
stated that, as per the ledger of the appellant, payments have been paid by
the appellant to the respondent no. 1 as late as October, 2020. So, if this
argument was to be accepted then the appellant ought not to have made
payments continuously even after the abandonment of work, as alleged.
36. Another argument advanced by the appellant before the learned
Arbitrator was that respondent no. 1 did not serve any notice of completion
of work in terms of Clause 23 of the agreement. The said contention is
untrue for the reason that the same is evident from the fact that the notice of
completion dated 04.07.2020 had been given to the Architect/respondent no.
2 through email on 06.07.2020. The said document was admitted to have


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:19.08.2026
15:33:47
FAO(OS) (COMM) 26/2024 Page 14 of 39

been received by the appellant as is evident from the pleadings/Statement of
Defence. Subsequent to the said notice, the work was in fact inspected and
verified by the parties and accordingly, a final bill with revised notice was
sent to the respondent no. 2 vide email dated 21.12.2020. Thereafter, a legal
demand notice was issued by the respondent no. 1 herein on 09.07.2021,
which was served upon the appellant as well as the respondent no. 2. The
respondent no. 1 had also served its final bill dated 07.08.2021 upon the
appellant and the appellant was served with another legal demand notice
dated 21.08.2021 for the balance payment.
37. He submitted that, the appellant was fully aware of all the
communications and had known that the respondent no. 2 was regularly
verifying the works with respondent no. 1. The appellant chose to remain
silent and never disputed the fact that the work had been completed by the
respondent no. 1. Even in the reply letter, the appellant had neither
challenged the work being completed nor claimed that the work had been
abandoned by the respondent no. 1 or even the fact that the appellant
completed the balance of the work on its own.
38. According to Mr. Mittal, as per Clause 23 of the Agreement, the
Contractor/respondent no.1 shall give notice to the Architect/respondent
no.2 regarding the work having been completed and the work would then be
inspected by the Architect/respondent no.2. The Architect would then issue
a virtual completion certificate and pursuant to which, the
contractor/respondent no.1 shall remove all its belongings from the site. It is
an admitted fact that the entire work was carried out under the direct
supervision of the Architects/respondent no.2. Any failure of the Architect


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:19.08.2026
15:33:47
FAO(OS) (COMM) 26/2024 Page 15 of 39

to issue Completion Certificate for the work cannot be construed against
respondent no.1.
39. As per Mr. Mittal, the only difference in these bills was that, in all the
bills the quantum of GST had varied on the account of the veracity of
measurement and quantity of work and extra work and the appellant being
aware of the fact that respondent no. 1 had been regularly submitting its
bills, neither raised the issue that the work was not completed nor that any
amount was not due or payable.
40. The only contention raised by the appellant before the learned
Arbitrator as well as before the learned Single Judge was that the respondent
no. 1 had received the GST amount from the appellant while the same was
not deposited with the GST department. In the impugned arbitral award as
well as in the impugned judgment had rightly held that the issue of whether
the respondent no. 1 had deposited the GST amount or not was not to be
gone into either by the learned Arbitrator or by the learned Single Judge. He
stated that the findings of the learned Arbitrator are well reasoned and ought
not to be interfered with.
41. He submitted that it would amount to re-appreciation of the entire
factual matrix and the law and Section 37 of the Act bars the Court to
reappreciate evidence. Similar is the position with the impugned judgment
of the learned Single Judge and the same also ought not to be interfered
with. It is his case that the appellant essentially seeks to reinterpret the
clauses of the agreement regarding the GST liability and has raised the said
plea for the first time in the present appeal. This issue had neither been
presented nor adjudicated before the learned Arbitrator and hence, cannot be


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:19.08.2026
15:33:47
FAO(OS) (COMM) 26/2024 Page 16 of 39

gone into at this juncture.
42. Another issue the appellant raised is that the learned Arbitrator had
shifted the burden of proof on the appellant herein instead of the respondent
no. 1 and hence, is contrary to Sections 101 and 102 of the Indian Evidence
Act, 1872. According to Mr. Mittal is completely misplaced and the said
provisions hold no relevance inasmuch as the arbitration proceedings are
concerned. In this regard, he has referred to Section 19 of the Act, which
clearly provides that the Tribunal is not bound by the Indian Evidence Act,
1872 (“Evidence Act”) or the Code of Civil Procedure, 1908 (“CPC”).
43. Mr. Mittal stated that it is trite law that the Arbitrator alone is the
authority to appreciate the quality and quantity of evidence and this Court
while exercising its jurisdiction under Section 34 or 37 of the Act cannot
question the findings of fact arrived at by the learned Arbitrator. He argued
that given the current factual matrix, this Court ought not to exercise its
jurisdiction under Section 37 of the Act and seeks dismissal of the present
appeal.
REJOINDER SUBMISSIONS ON BEHALF OF THE APPELLANT
44. Mr. Nigam in his rejoinder submissions has argued that the
contentions of the respondent no.1 / claimant that certain arguments had
neither been raised before the learned Arbitrator nor before the learned
Single Judge in the proceedings under Section 34 of the Act, are not true as
the payment terms of the agreement formed an integral part of the
proceedings before the learned Arbitrator. The impugned award being
inconsistent with the provisions of the agreement and the award is liable to


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:19.08.2026
15:33:47
FAO(OS) (COMM) 26/2024 Page 17 of 39

be set aside.
45. On the aspect of the payment of GST, Mr. Nigam, stated that the
respondent no.1 had not cleared the GST liability, which could also be seen
from the invoices (being No.22-19/20, 23-19/20, 13-19/20 and 14-19/20)
that were produced before the learned Arbitrator along with the Statement of
Defence, it do clearly establish that appellant had paid GST to the
respondent no.1.
46. He submitted that as per the ledger, the appellant made advance
payments to the respondent no.1 for which, bills were raised at a much later
stage, these invoices were not as per Sq. Ft. rate provided in the agreement,
but rather invoices breaking down the amounts paid by the appellant for
different materials and works. Hence, the argument that the appellant had
taken a contrary stand before the learned Arbitrator, does not stand.
47. On the issue of the admissibility of the documents, Mr. Nigam
submitted that the screenshots from the GST portal of the respondent no.1
was filed along with the Statement of Defence. He stated that the “ final bill
no. 005 of 2021-2022 ” which formed part of the pleadings before the learned
Arbitrator is at complete variance with the information uploaded by the
respondent no.1 on the GST portal. Such inconsistencies were inherent and
had been denied by the appellant, and there was no ground for the learned
Arbitrator to come to the conclusion that the working area was not disputed,
in the impugned award.
48. Mr. Nigam stated that, since the screenshot from the GST Portal are
public document, they ought not to be made subject to the strict rules of


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:19.08.2026
15:33:47
FAO(OS) (COMM) 26/2024 Page 18 of 39

CPC and the Evidence Act and the learned Arbitrator could have looked at
the same. As per Mr. Nigam, the Supreme Court in a judgment in the case of
Emkay Global Financial Services v. Gindhar Sondhi, (2018) 9 SCC 49,
had held that in terms of Section 34(2)(a) of the Act, for the purpose of
determination of the issues, information can be brought to the notice of the
Court by way of affidavit filed by both the parties.

49. He submitted that the burden of proof was not appropriately met by
the respondent no.1 before the learned Arbitrator. Mr. Nigam stated that,
even though a stand was taken by the respondent no.1 that the measurement
book in terms of Clause 16 of the agreement was only to be maintained for
extra items and not for works, payable as per Sq. Ft., this distinction which
is now drawn by the respondent no.1 is an artificial one, especially in terms
of Clause 16 of the agreement, which only talks about (a) item rates; (b)
variation; and (c) extra items. It is an admitted position that the respondent
no.1 has not assailed the aforesaid findings before the learned Arbitrator and
in these circumstances screenshots of certain WhatsApp message cannot
override the express provisions of the agreement.
50. The last limb of Mr. Nigam’s argument is that the learned Arbitrator
has granted interest @ 14% per annum against the awarded amount, which
is devoid of a contractual foundation and therefore, is contrary to Section
31(7) (a) of the Act and liable to be set aside. In light of the aforesaid, he
seeks the prayers made in the present appeal be allowed.
ANALYSIS AND CONCLUSION
51. Having heard the learned counsel of the parties and perused the


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:19.08.2026
15:33:47
FAO(OS) (COMM) 26/2024 Page 19 of 39

record, we deem it appropriate to summarise the claims and findings of the
learned Arbitrator as under:-

Claim for amounts due under the
Final Bill dated 07.08.2021,
which included:
The Claim was partially allowed
by the Ld. Arbitrator.
(1)
1.1 Claim for work done under the
The Claimant was held entitled to
a sum of Rs. 6,14,97,594 against
the work done under the
Agreement.
1.2 Claim for price difference for
Agreement
The claim was rejected.
steel and cement.
1.3 Claim for excess steel consumed The claim was rejected
1.4 Claim towards extra work done The claim was rejected
1.5 Claim towards other
miscellaneous items and
purchases
The claim was rejected
(2) Claim for loss of profits The claim was rejected
(3) Claim for interest Interest at the rate of 14% was
awarded from 7.09.2021 till date
of payment.
(4) Costs Claimant was awarded
Rs.5,00,000/- plus Fee paid to the
Arbitrator towards Costs

52. The submissions on behalf of the appellant can be summed up as
under: -
52.1 On 09.07.2021, the respondent no.1 issued a notice to the
appellant that the works under the agreement were completed in
August 2020 and an amount of Rs.12,17,45,400/- has to be paid by
the appellant;
52.2 On 07.08.2021, the respondent no.1 issued a final bill wherein


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:19.08.2026
15:33:47
FAO(OS) (COMM) 26/2024 Page 20 of 39

it had claimed an amount of Rs.13,37,98,982/-;
52.3 Vide letter dated 20.08.2021, the appellant responded to the
final bill issued by respondent no.1 to state that no amount is due and
payable;
52.4 The claim has been awarded without considering the terms of
the agreement and in contravention with Clause 23 of the agreement;

52.5 The respondent no.1 never issued the notice for Completion
Certificate nor it received the Completion Certificate;
52.6 The grant of an amount of Rs.1,72,70,328/- as GST is contrary
to the payment terms under the agreement, which provides that all
statutory liabilities including the GST would be the responsibility of
respondent no.1;
52.7 The respondent no.1 relied on the final bill dated 07.08.2021
and Whatsapp messages showing the status of work at the
construction site, which formed the basis for the learned Arbitrator to
award the amount;
52.8 It is settled law that the agreement for work done can only be
awarded when a proof of measurement of work is submitted;
52.9 The final bill is not based on material on record. Similarly, the
photographs of the site taken until August-September, 2020 shows
that the work was still going on and as such contrary to the stand
taken by the respondent no.1;


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:19.08.2026
15:33:47
FAO(OS) (COMM) 26/2024 Page 21 of 39

52.10 There is a difference in the measurement of work under the
final bill as shared vide email dated 21.12.2020 and as such said
inconsistencies lend credence to the appellant’s submission that
respondent no.1 did not complete the work under the agreement;
52.11 The standard of proof adopted is inconsistent with the findings
to the other claims, which were rejected due to lack of evidence;

52.12 The learned Arbitrator cannot re-write the terms of the
contract, rather he is bound by the same; and
52.13 The learned Single Judge has erred in not interfering with the
impugned arbitral award under Section 34 of the Act.
53. On the other hand, the submissions on behalf of the respondents are as
under: -
53.1 The scope of the interference with the judgment is very limited
and this appeal does not fall within the scope of the judicial review
in an appeal under Section 37 of the Act;
53.2 New contentions are sought to be introduced in the present
appeal, which were neither pleaded before the learned Single Judge
nor incorporated in the Statement of Defence before the learned
Arbitrator;
53.3 The plea on behalf of the appellant that the measurement book
was not placed on record is misplaced since the agreement between
the parties stipulated that only structural work was to be raised by
the respondent no.1 for which amount was payable on lump sum per


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:19.08.2026
15:33:47
FAO(OS) (COMM) 26/2024 Page 22 of 39

Sq. Ft. rate basis and as such, clause 16 of the Agreement has no
applicability;
53.4 Though, no measurement sheets were submitted nor ever
produced before the learned Arbitrator. Even if it is assumed that the
measurement sheets were being submitted, they would have included
only the additional work which was not included in the
agreement/per Sq. Ft. rates;
53.5 The plea of the appellant that the respondent no.1 has
abandoned the work has not been proved inasmuch as the appellant
did not specify:
(i) at what stage and when did the respondent no.1 allegedly
abandon the work;
(ii) which agency or organisation was hired to execute the
remainder of the work;
(iii) what would have been the quantum of the balance work
allegedly executed by the appellant on its own;
(iv) and the fact that no notice or communication was ever issued
by the appellant to the respondent no.1 regarding the alleged
abandonment of work;
53.6 The parties had agreed not to lead any oral evidence and the
matter was decided on the basis of the record, the work had been
executed under the control of respondent no.2, the appellant had the
best available evidence in the form of record of Architect, but chose


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:19.08.2026
15:33:47
FAO(OS) (COMM) 26/2024 Page 23 of 39

not to submit any record nor did the respondent no.1 seek to produce
the respondent no.2 before the learned Arbitrator in support of its
case.
53.7 The appellant had never disputed its liability to pay GST on
the payments to be paid to the respondent no.1, which plea was taken
for the first time in the present appeal, which is too late in the day to
raise such a contention;
53.8 The payments were made by the appellant to the respondent
no.1 as late as upto October 2020 and as such the plea of
abandonment of work in November 2019 shall not arise; and
53.9 The plea of non-compliance of Clause 23 of the agreement is
untrue as the same was followed by issuance of notice of completion
dated 04.07.2020 which had been given to the Architect/respondent
no. 2 through email on 06.07.2020. The said document was admitted
to have been received by the appellant as is evident from the
pleadings before the learned Arbitrator in the Statement of Defence.
Subsequent to the said notice, the work was in fact inspected and
verified by the parties and accordingly, a final bill with revised
notice was sent to the respondent no. 2 vide email dated 21.12.2020;
54. Having noted the broad submissions made by the learned counsel for
the parties, the issue which requires consideration is in respect of the claim
allowed by the learned Arbitrator under the final bill.
55. The learned Arbitrator has divided the said claim under different
points. It is only Claim no. 1.1 which forms part of the challenge in the


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:19.08.2026
15:33:47
FAO(OS) (COMM) 26/2024 Page 24 of 39

present appeal and the same was for work done under the original
agreement, which reads as under: -
“Claim (1.1) Amount due under the final bill
26. A perusal of the final bill would show that it has five separate
components being (1) towards work under the original
Agreement; (2) price escalation for steel and cement, (3) excess
steel consumed, (4) extra work done, and (5) Other
miscellaneous items and purchases. These are taken to be
separate sub-points of determination.

(1.1.1) Claim for workdone under original agreement
27. The Agreement between the parties was entered into in
March, 2018. As per clause 30, the work was to be completed
within 12 months of the date of signature. As per the claimant,
the work was completed in August-September, 2020; while the
case of the respondent no.1 is that the same was never completed
and the project was abandoned by the claimant. In the statement
of defence, there is. no detail as to when the work was
abandoned or till what stage, the claimant had completed the
work. The pleadings of the respondent no.1 remain vague.
During the course of argument, Mr.Aziz submitted that the work
was done till the upper ground floor level only. In the written
submissions of the respondent no.1 (which has already been
eschewed), it is stated that the work was abandoned in
November, 2019.
28. The claimant has placed on record the screenshots of chats
on whatsapp groups at Annexure C-9 and C-10. Both the
respondent no.1 and the architect/respondent no.2 members the
first group, i.e. Annexure C- 9, titled “TMB 113 Kundli”. The
contents and existence of the said screenshots stand admitted by
the respondent no.1 in its affidavit of admission/denial of
documents. A perusal of the said screenshots shows that the
claimant was regularly giving updates regarding the work being
carried out; while drawings are being shared by the respondent
no.2. The chats show that the work was being carried out much


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:19.08.2026
15:33:47
FAO(OS) (COMM) 26/2024 Page 25 of 39

beyond November, 2019. At page 155 of the statement of claim,
the chat pertains to January, 2020 wherein drawings are being
sought. At page 160, photos showing progress of the work in
July, 2020 have been shared. Pertinently, the photos show
construction much beyond the upper ground floor level. The
chats go until 21.09.2020 when drawings of the front elevation
wall are being sought. This vindicates the stand taken by the
claimant that work was being carried out until August-
September, 2020.
29. As regards the abandonment of the work by the claimant, the
plea of the respondent no. 1 remains vague and unclear.
Additionally, the respondent no. I never objected to the alleged
abandonment of the work by the claimant. Admittedly, there is no
communication in this regard nor any penalty was imposed.
30. As regards the delay in execution of the work, the claimant
has attributed the same to the respondent no. 1. In any case, the
claimant continued to work much beyond the stipulated period
and was accepted by the respondent no.1. There is no clause in
the Agreement making time the essence of the contract nor has it
been the case of the respondent no.1. Coupled with the nature of
the contract and clauses 31-33 providing for extension, it is clear
that time was not the essence [see Hind Construction
Contractors v. State of Maharashtra, (1979) 2 SCC 70 (Paras 7-
9); and Arosan Enterprises Ltd. v. Union of India, (1999) 9 SCC
449 (Para 14)]. Even otherwise, the respondent no.1 having
accepted performance after the stipulated period, the case would
come under third paragraph of section 55 of the Indian Contract
Act. Hence, it is not open to the respondent no.1 to raise any
grievance qua the delay in completion. Till date, the respondent
no. I has not imposed liquidated damages nor is there any
counter claim before me.
31. The other defaults highlighted in the statement of defence
have also not been established. The issue of quality was material
was never raised when the work was being carried out under due
intimation to the respondent no.1 and its architect (respondent
no.2). Even accepting the stand of the respondent no.1 that the
parties shared good relations, this may justify the absence of any


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:19.08.2026
15:33:47
FAO(OS) (COMM) 26/2024 Page 26 of 39

formal communication, however surely a whatsapp message
would have been sent. The respondent no.1 has not been able to
pinpoint any non-compliance with labour norms.
32. The only other issue raised pertains to water coming out of
the basement. Again the statement of defence is completely silent
as to when the issue was faced or when it was intimated to the
claimant. Paragraph N of the statement of defence only reads as
under:
"N. That during the tenure of work when the
respondent inspect the basement of the concern
building found out that the foundation of the building is
not made properly due which there was higher risk of
demolition of building and can cause huge harm to life
and property. It is pertinent to mention here that
during inspection water was coming out from wall of
the basement due which building is at higher risk of
falling.''
33. The photos at page 41 to 45 are blurred and hardly anything
can be made out of the same. The videos show large amounts of
water pouring from the walls. However, it cannot even be
identified that the video pertains to the subject building or for
that reason, what walls are being shown. The vintage of the video
is also not clear. The title of the videos suggest that the same had
been made on 19.07.2022. While the whatsapp chats at page 163
of the statement of claim show that the issue had been flagged on
19.07.2021. In this regard, Mr.Dawar had rightly drawn
attention to clause 19 of the Agreement; which provides for a
"defects liability period" being "a period of six months from the
·date of completion or first rainy season whichever is early". The
said period expired in February March, 2021 and any defect
having been identified at best, in July, 2021 would be beyond the
same. Even otherwise, the respondent no.1 never called upon the
claimant to rectify the defect nor any proof of the work having
been rectified at the end of the respondent no.1 has been placed
on record. As such, the contention must be rejected.
34. Thus, I hold that the work was completed by the claimant in
August September, 2020 to the satisfaction of the respondents.


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:19.08.2026
15:33:47
FAO(OS) (COMM) 26/2024 Page 27 of 39

The next aspect concerns the entitlement of the claimant.
35. Admittedly, payments were made in advance to the claimant
and invoices were being raised subsequently. This practice
stands admitted though the parties contend the same to be at the
instance of the other. As such, the claimant cannot be faulted for
not having raised the final bill upon completion of the work. The
claimant has stated to have sent a letter dated 04.07.2020;
however, during the course of arguments it was admitted that the
same was sent by email and bounced. No such email has been
placed on record.
36. The claimant has then placed on record an email dated
21.12.2020 at page 111 of the statement of claim sent to the
architect enclosing a draft final bill (at page 126) for
Rs.12,40,13,500/-. This is followed by a notice dated 09.07.2021
alleging total value of the work to be Rs.12,17,45,400/-. In this
background, the final bill is stated to have been raised on
07.08.2021 for Rs.13,17,98,982/-. The covering letter itself
records as under:
"Although, the work was completed by us in all
respects August/September 2020, you kept on delaying
the payments accounts. Despite several reminders, you
have failed to honour your part of obligations under
the agreement of timely release of our payments. We
are therefore, submitting the Final Bill amounting to a
sum of Rs. 13,37,98,982/- with all the relevant details.
The balance payments due and payable by you to us is
Rs.8,21,98,982/-. You are required to make the
payment of the balance amount to us within a period of
one week from the date of receipt."
37. Considering the admitted practice of raising invoices
subsequent to payments, the claimant cannot be faulted for
having waited for sometime and then raised its final bill. Coming
to the amount, the item rates are given at page 33 of the
Agreement. The rates in the final bill remain lower to the same.
The working area has also not been disputed by the respondent
no.1. On comparison with the final bill sent on 21.12.2020, it is
noticed that the working area for "Roof Proj. on Second Floor"


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:19.08.2026
15:33:47
FAO(OS) (COMM) 26/2024 Page 28 of 39

and "Mumty & Proj." has been increased in the final bill dated
07.08.2021. Adjusting for this increase, the final amount comes
to Rs.9,59,46,266/-. Adding GST, it comes to Rs.11,32,16,594/-.
38. Of the said amount, the claimant claims that only
Rs.5,16,00,000/- has been paid; while the case of the respondent
no.1 is that Rs.5,17,19,000/-has been paid. The receipt of the
latter amount has not been denied in the rejoinder. The letter
dated 09.07.2021 sent by the claimant itself also states that the
amount of Rs.5.16 crores is an approximate figure. As such, I
believe the version of the respondent no.1 and hold that a sum of
Rs.5,17,19,000/- has already been paid. Deducting the said
amount, the claimant is held entitled to a sum of Rs.6,14,97,594/-
against the work done within the original scope of work.
39. It would be amiss to notice another contention of the
respondent no.1 that the claimant has failed to deposit GST
against the invoices raised and filed incorrect returns. Suffice it
to say that the same is for the concerned department to consider
and cannot to be a ground to nullify the claim of the claimant.”

56. The findings of the learned Arbitrator while granting the claim of the
respondent no.1 for Rs.6,14,97,594/- are the following: -
56.1 As per Clause 30, the work was to be completed within 12
months from the date of signature. The work was completed in
August-September, 2020;
56.2 As per the appellant, the same was never completed and the
project was abandoned by the claimant;
56.3 In the Statement of Defence, there is no detail as to when the
work was abandoned or till what stage the claimant had completed
the work, as the pleadings of the appellant were vague. Though in
the written submissions of the appellant had stated that the work was


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:19.08.2026
15:33:47
FAO(OS) (COMM) 26/2024 Page 29 of 39

abandoned in November, 2019;
56.4 On the reliance placed by the respondent no.1 on the
screenshots of chats on Whatsapp groups (Annexure C-9 and C-10),
the same have been admitted by the appellant in its affidavit of
admission & denial of documents;
56.5 The screenshots showed that the respondent no.1 was
regularly giving updates regarding the work being carried out; while
drawings were shared by the respondent no.2. The chats show that
the work was being carried out much beyond November, 2019. The
photographs’ showed construction was much beyond the upper
ground floor level. The chats had gone on until 21.09.2020 when
drawings of the front elevation wall were being sought;
56.6 No communication of the appellant has been shown on the
alleged abandonment of the work by the respondent no.1;
56.7 On the water coming out of the basement, the Statement of
Defence was completely silent. No intimation was given to the
respondent no.1. The video showing large amount of water pouring
from the walls; it cannot be identified that the video pertains to the
subject building. The title of the video suggests that the same had
been made on 19.07.2022, whereas the issue was allegedly flagged
on 19.07.2021;
56.8 The work was completed by the claimant in August –
September 2020 to the satisfaction of the appellant/ respondent.


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:19.08.2026
15:33:47
FAO(OS) (COMM) 26/2024 Page 30 of 39

56.9 The payments were made in advance to the respondent no.1 and
invoices were being raised subsequently. As such, respondent
no.1/claimant cannot be faulted for having not raised the final bill
upon completion of the work;
56.10 The respondent no.1 placed on record an email dated
21.12.2020 sent to the architect enclosing a draft final bill for
Rs.12,40,13,500/-. This was followed by the notice dated 09.07.2021
alleging total value of the work to be Rs.12,17,45,400/-. In the
background of this, the final bill was stated to have been raised on
07.08.2021 for Rs.13,17,98,982/;
56.11 The working area has also not been disputed by the
respondent no.1. On comparison with the final bill sent on
21.12.2020, it was noticed that the working area for ‘Second Floor’
and ‘Mumty & Proj’ has been increased in the final bill dated
07.08.2021. Adjusting for this increase, the final amount comes to
Rs.9,59,46,266/-. Adding GST, it comes to Rs.11,32,16,594/-;
56.12 As the amount, Rs.5,16,00,000/- has been paid (through
the appellant claimed only Rs.5,17,19,000/-has been paid), so
deducting the said amount of Rs.5,17,19,000/-, the respondent no.1
was granted a sum of Rs.6,14,97,594/-.
57. On the aspect of GST, the case of the appellant was that the
respondent no.1/claimant has failed to deposit the GST against the invoices
raised. The learned Arbitrator held that, it is for the concerned department to
consider and cannot be a ground to nullify the claim of the respondent no.1.


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:19.08.2026
15:33:47
FAO(OS) (COMM) 26/2024 Page 31 of 39

58. One of the submissions of Mr. Nigam before us was that the awarded
amount of ₹ 6, 14,97,594/- also includes the GST amount of ₹ 1,72,70,328/-.
The appellant has raised the contention that, for the final bill claimed in the
arbitration, the respondent No.1 has not deposited the GST.
59. It is to be noted that the final bill submitted by the respondent no.1 to
the appellant on 07.08.2021 was not accepted by the appellant giving rise to
the disputes which was referred to the arbitration. After adjudication of the
rival contentions, the amount due and payable under the final bill has been
legally determined by the learned Arbitrator vide the impugned award dated
29.08.2023 as ₹11,32,16,594/- including GST. The amounts have thus been
crystalized vide the impugned award. In these facts, we unable to draw any
adverse inference against the respondent no.1 for the non-deposit of the GST
amount determined as ₹ 1,72,70,328/-. The appellant has not paid the
awarded amount of ₹ 6,14,97,594/- till date and therefore cannot raise any
grievance on this account. The appellant would be entitled to seek proof of
deposit of the GST component after it has paid the awarded amount. The
issue whether there is any violation of GST laws by the respondent no.1 in
deposit of the GST component will be decided by the statutory authorities
under GST Statute. We however direct that the appellant will be entitled to
seek proof of deposit of the GST component of the finally determined final
bill after it has paid the awarded amount with up-to-date interest.
60. On the stand taken by the appellant that the respondent no.1 had
abandoned the work and as a result, the appellant had to get the remaining
work completed by a third party, the learned Single Judge held that, no
evidence of such communication exchanged between the parties were noted


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:19.08.2026
15:33:47
FAO(OS) (COMM) 26/2024 Page 32 of 39

by the learned Arbitrator or shown to the Court to indicate either that the
work was abandoned by the respondent no.1 or completed through a third
party. In fact, a reference is made by the learned Single Judge on the
photographs of the site taken until August – September 2020. According to
the learned Single Judge, clearly depicted the work was going on and
directly contradicting the appellant’s stand.
According to the findings of the learned Arbitrator, the said plea was
vague and unsubstantiated.
61. The aforesaid is a finding of fact, even before us, Mr. Nigam could
not to show any communications sent by the appellant to the respondent
no.1 highlighting that the respondent no.1 has abandoned the work or for
that matter, the respondent no.1 has not restarted the work or the appellant
got the work completed through third party. The pleading does not specify
the date of abandoning the work (on November 2019), has not been accepted
by the learned Arbitrator.
62. That apart, the pleading does not show the name of the third party
through whom the balance work was completed by the appellant and the
cost paid by the appellant to the said third party. In fact, no counter-claim
has been made by the appellant seeking the difference of amount paid to the
third party.
63. On the final bill, the learned Single Judge has held in paragraph 15 of
the impugned judgment, as under:-
“15. The Final Bill in question delineates two components for
arriving at the claimed amount, i.e., the working area and the
rate applied. The rate applied specified in the Final Bill was less


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:19.08.2026
15:33:47
FAO(OS) (COMM) 26/2024 Page 33 of 39

than the contractually agreed rate, which is a finding of fact
rendered by the Arbitrator. Thus, the same does not warrant any
adverse inference by this Court. As regards the working area, the
Arbitrator has observed at Paragraph No.37 of the impugned
Award that –– “The working area has also not been disputed by
respondent no. 1”. In light of the foregoing observation, it is
evident that the Petitioner (referenced as ‘respondent no. 1’ by
the Arbitrator) did not dispute the working area in the course of
the arbitration. Therefore, the Arbitrator was justified in
concluding that the work claimed under the Final Bill had been
completed.”

64. Similarly, on the GST plea, the learned Single Judge has noted in
paragraph no.16 of the impugned judgment as under:-
“16. Mr. Mehta has placed significant emphasis on the fact that
the Final Bill was not reported to the GST authorities. While
non-compliance with tax regulations may indeed represent a
violation under the relevant tax laws, it is crucial to distinguish
the nature of this infraction. As the Arbitrator rightly observed,
this issue is separate from the current dispute and will follow its
independent course within the appropriate tax regulatory
framework. The primary concern of this Court in the present
matter is to assess the arbitral process and the resulting award’s
adherence to legal and procedural standards, not to enforce tax
regulations. Thus, while reporting of the Final Bill to the GST
authorities is a relevant fact, it does not directly impinge upon
the legitimacy of the claims.”

65. The learned Single Judge agreeing with the conclusion drawn by the
learned Arbitrator has noted in paragraphs 17 & 18 of the impugned
judgment, as under:-
“17. For adjudicating the claims presented in arbitration, the
crucial question the Arbitrator needed to determine was whether
the work was actually completed. Contrary to Mr. Mehta's
assertions, the Court observes that the Arbitrator's conclusions
were not solely based on the Final Bill. Instead, the Arbitrator


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:19.08.2026
15:33:47
FAO(OS) (COMM) 26/2024 Page 34 of 39

conducted a comprehensive review of all available evidence. This
included not just the Final Bill but also other substantial
materials, such as admitted WhatsApp messages and the
averments made in the Statement of Defence. These pieces of
documentary evidence collectively supported the conclusion that
the work was indeed completed by Respondent No.1.
Furthermore, the Petitioner has failed to present any compelling
material that effectively counters Respondent No.1’s assertion of
having executed the work. Without such evidence to refute the
claims, the Arbitrator's reliance on the breadth of the material on
record appears well founded and reasonable.

18. The totality of evidence presented on record supports the
conclusion that the amount detailed in the Final Bill is indeed
due and payable to Respondent No.1. The Petitioner has not
successfully established its defence, and each of the grounds
raised has been methodically addressed and refuted by the
Arbitrator, as detailed in the above extracted Paragraphs No. 28,
29, 30, and 31. The Arbitrator's factual findings, grounded in a
careful appreciation of the evidence, appear reasonable and
well-justified. Consequently, these findings do not warrant any
interference under Section 34 of the Act.”

66. From the above, it is clear that the learned Single Judge has observed
that the learned Arbitrator has straightway not accepted the final bill. The
claim no. 1.1 awarded by the learned Arbitrator was on the basis of the
Whatsapp message, and the averments made in the Statement of Defence,
such a conclusion of the learned Arbitrator cannot be disagreed with.
67. Keeping in view the premise on which the learned Arbitrator has
granted the claim of the respondent no.1, with which, the learned Single
Judge has agreed and it is not a case of no evidence or the conclusion drawn
by the learned Arbitrator is palpably perverse, given the scope of the
interference in a petition under Section 34 of the Act, we are of the view that


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:19.08.2026
15:33:47
FAO(OS) (COMM) 26/2024 Page 35 of 39

no interference is called for with the impugned judgment passed by the
learned Single Judge.
68. Mr. Nigam has relied upon the following judgments for the following
propositions in the following manner :-
68.1 Insofar as Indian Oil Corporation (supra) is concerned, the
Supreme Court held that the award ignoring the terms of contract
would not be in the public interest. In the said case, the award in
respect of lease rent and lease terms was in patent disregard of the
terms and conditions of the lease agreement and thus, against public
policy. The said judgment has no applicability in the facts of this
case.
68.2 Insofar as International Breweries Pvt. Ltd. (supra), Bawana
Infra Development Pvt. Ltd. (supra), Flowmore Limited (supra),
Five Star Construction Pvt. Ltd. (supra), Harcharan Dass Gupta
(supra), Jaiprakash Hyundai Consortium (supra), and M/s Exnxt
Software Private Limited (supra) are concerned, the issue in these
judgments was with regard to the award of an Arbitral Tribunal
against the public policy of India and the jurisdiction of the Court of
first appeal to re-examine and correct the finding of the facts. The
Courts have held that the said rule has one exception where the
finding is based on no evidence or the finding of fact defies logic or
which is perverse or so irrational that no reasonable person would
have arrived at the same conclusion. The aforesaid proposition of
law has not applicability to the facts of the appellants case.


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:19.08.2026
15:33:47
FAO(OS) (COMM) 26/2024 Page 36 of 39

68.3 Insofar as Shree Jagannath Expressways Pvt. Ltd. (supra) is
concerned, the issue was whether the impugned award is contrary to
the terms of the fee notification or concession agreement. The
Supreme Court held that, in the said case, the Tribunal accepted the
claim without any evidence to establish the amount of loss as
claimed. The Supreme Court also held that it is well settled that the
Court cannot reappreciate/re-examine the evidence in proceedings
under Section 34 of the Act. The said judgment does not help the
case of the appellant.
68.4 Insofar as Navnirman Development Consultants (India)
Private Limited (supra) is concerned, the Supreme Court held that
the order which decided the lis between the parties should have
contained the brief facts of the case, the stand of the parties
impugning and defending the action, the submissions of the parties in
support of their stand, legal provisions, if any, applicable to the
controversy involved in the lis , and lastly, the brief reasons as to why
the case of one party deserved acceptance or rejection.
The facts as noted from the said judgment is that, according to
the Supreme Court, the High Court while dismissing the appeal did
not set out even the factual controversy properly much less in detail
and not dealt with any of the grounds taken by the parties in their
pleadings and in that respect the matter was remanded back to the
High Court to be considered afresh.
68.5 Insofar as UHL Power Company Limited (supra) is concerned,
the said judgment has no applicability in the facts of the present case


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:19.08.2026
15:33:47
FAO(OS) (COMM) 26/2024 Page 37 of 39

and is against the petitioner.
68.6 Insofar as Kamal Construction Co. v. Delhi Development
Authority and Another, 2012 SCC OnLine Del 4972 is concerned,
the said judgment has no applicability in the facts of the present case.
68.7 Insofar as K. C. Skaria v. Govt. of State of Kerala and
Another, 2006 SCC OnLine SC 72 is concerned, the said judgment
has no applicability in the facts of the present case.
68.8 Insofar as State of Rajasthan and Another v. Ferro Concrete
Construction Private Limited, 2009 SCC OnLine SC 868 is
concerned, the arbitrator awarding claim equating it as proof without
looking for or insisting on proof, held, is legal misconduct and error
apparent on face of the award. In the said case, the issue was with
regard to the moral misconduct against the Arbitrator. In the case in
hand, such is not the situation. The said judgment has no applicability
in the facts of the present case.
68.9 Mr. Nigam with regard to the screenshots taken by appellant of
the respondent no. 1 from the GST portal is concerned, would rely
upon the judgment in the case of Emkay Global Financial Services
Limited v. Girdhar Sondhi, 2018 SCC OnLine SC 1019 . He
contends that it is permissible for information that is relevant for
purpose of determining issues arising under Section 34(2)(A) of the
Act.
68.10 Insofar as Smriti Debbarma (Dead) through Legal
Representative (supra) is concerned, the Court held that the factual


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:19.08.2026
15:33:47
FAO(OS) (COMM) 26/2024 Page 38 of 39

background in the said case, the general principle under Section 101
of the Evidence Act is applicable. The said judgment has no
applicability in the facts of the present case.
69. There is no dispute on the proposition of law as held by the Supreme
Court / this Court in the judgments as relied upon by Mr.Nigam. Surely, the
law as held by the Supreme Court has to be tested in the facts of each case.
Surely, we can conclude that the above judgments, are clearly
distinguishable on the facts, which arise for consideration in such
judgments.
70. In view of our above discussion, the appeal is devoid of any merit and
liable to be dismissed. We order accordingly.

V. KAMESWAR RAO, J

MANMEET PRITAM SINGH ARORA, J
AUGUST 19, 2026 /sr