Purbanchal Buildtech Pvt Ltd vs The State Of Assam And 6 Ors
- Court
- Gauhati High Court
Page No.# 1/15
GAHC010170382026
2026:GAU-AS:17161
THE GAUHATI HIGH COURT
(HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH)
Case No. : WP(C)/4385/2026
PURBANCHAL BUILDTECH PVT LTD
HOUSE NO 2 SEWALI PATH F A AHMED NAGAR SIX MILE GUWAHATI
KAMRUP METRO ASSAM 781022 REPRESENTED BY ONE OF ITS
DIRECTORS SRI BHASKAR GOSWAMI SON OF SRI AMBIKA PAD GOSWAMI
RESIDENT OF VILL BARGAON PO BIHDIA DISTRICT KAMRUP ASSAM
781381
VERSUS
THE STATE OF ASSAM AND 6 ORS
REPRESENTED BY THE SPECIAL COMMISSIONER AND SPECIAL
SECRETARY TO THE GOVT OF ASSAM ,PUBLIC WORKS BUILDING AND
NH DEPARTMENT, DISPUR ,GUWAHATI 06.
2:THE CHIEF ENGINEER
PUBLIC WORKS DEPARTMENT NH WORKS ASSAM CHANDMARI
GUWAHATI 03
3:THE BID EVALUATION COMMITTEE
REPRESENTED BY THE CHAIRMAN OFFICE FOT EH CHIEF ENGINEER
PUBLIC WORKS DEPARTMENT NG WORKS ASSAM CHANDMARI
GUWAHATI 781003
4:MS M P AGARWALLA
A T ROAD BOKAKHAT TOWN DISTRICT GOLAGHAT ASSAM 785612
5:THE UNION OF INDIA
REPRESENTED BY THE SECRETARY TO THE GOVT OF INDIA MINISTRY
OF ROAD TRANSPORT AND HIGHWAYS TRANSPORT BHAWAN 1
PARLIAMENT STREET NEW DELHI 110001
6:THE DIRECTOR GENERAL(ROAD DEVELOPMENT AND SPECIAL
Page No.# 2/15
SECRETARY)
MINISTRY OF ROAD TRANSPORT AND HIGHWAYS GOVT OF INDIA
TRANSPORT BHWAN 1 PARLIAMENT STREET NEW DELHI 110001
7:THE REGIONAL OFFICER
MINISTRY OF ROAD TRANSPORT AND HIGHWAYS RAJGARH ROAD
CHANDMARI GUWAHATI 78100
Advocate for the Petitioner : MR. K N CHOUDHURY, MR. TANUZ KASHYAP,N
GAUTAM,MR. R M DEKA
Advocate for the Respondent : DY.S.G.I., R MANDAL(R4),MR. R GHOSH(R4),MR. C
SHARMA(R4),S K PODDAR(R4),SC, PWD
BEFORE
HON’BLE MR JUSTICE ARUN DEV CHOUDHURY
For the Petitioner : Mr. R. M. Deka, Advocate.
For the Respondents : Mr. B. Choudhury, Standing Counsel, PWD.
Mr. S. K. Poddar, Advocate for respondent No.
4.
Date on which Judgment is
Reserved : NA
Date of pronouncement of
Judgment : 19.11.2026
Whether the pronouncement
is of the operative part of the
Judgment : NA.
Page No.# 3/15
Whether the full Judgment has
been pronounced : Yes.
JUDGMENT & ORDER (ORAL)
(A.D.Choudhury, J)
1. Heard Mr. R. M. Deka, learned counsel for the petitioner. Also heard Mr. B.
Choudhury, learned Standing Counsel for the Public Works Department, and Mr. S. K.
Poddar, learned counsel for the respondent No. 4.
2. The petitioner has approached this Court challenging the decision of the Bid
Evaluation Committee (for short, "BEC") declaring its technical bid non-responsive in
connection with the tender for execution of the Performance-Based Maintenance
Contract (PBMC) of NH-39 (New NH-129) covering the stretches from Km 30 to Km
46, Km 54 to Km 96, and Km 103 to Km 106 for a period of 5 years under the Public
Works Department, Golaghat National Highway Division, Assam.
3. The petitioner has also questioned the respondent authorities' decision to accept the
technical bid of Respondent No. 4, M/S M. P. Agarwalla, alleging that the bidder
suppressed material particulars concerning its existing commitments.
4. The Notice Inviting Tender (NIT) was issued on 21.02.2026. The petitioner
participated in the tender process. By the minutes of the Technical Bid Evaluation
Committee dated 11.06.2026, the technical bid of the petitioner was declared non-
responsive under Clause 20.8(viii) of the Request for Proposal (RFP) on the ground that
it had failed to fulfil the obligations to maintain highways in a satisfactory condition
despite two rectification notices issued in respect of earlier works executed under PWD
NH Works, Assam.
5. The petitioner submitted a representation dated 13.06.2026 challenging its
Page No.# 4/15
disqualification and also alleging that Respondent No. 4 had failed to disclose two
ongoing works involving approximately Rs. 56.07 Crore in its statement of existing
commitments.
6. The Bid Evaluation Committee, in its meeting dated 19.06.2026, considered the
petitioner's representation and decided not to alter its earlier decision. The Committee
also considered the allegation against Respondent No. 4, sought clarification from the
said bidder, and upon re-assessing its available bid capacity, found no ground for its
disqualification. The financial bid of Respondent No. 4 was thereafter evaluated along
with another bidder, and Respondent No. 4 was declared as the L1 bidder.
7. The petitioner had earlier approached this Court by filing WP(C) No. 3593/2026.
During the hearing, the petitioner came to know about the decision of the Bid Evaluation
Committee dated 19.06.2026 rejecting its representation and evaluating the financial bid
of Respondent No. 4. Accordingly, the earlier writ petition was withdrawn under the
order dated 22.07.2026, with liberty to institute fresh proceedings. Hence, the present
writ petition.
8. Mr. Deka, learned counsel for the petitioner, submits that the decision declaring the
petitioner's technical bid non-responsive is arbitrary and unsustainable. It is contended
that the petitioner had duly undertaken the maintenance works under the earlier
contracts and there was no material to establish that it had failed to discharge its
contractual obligations. Though the Bid Evaluation Committee recorded that the
petitioner had failed to maintain the highways despite two rectification notices, the
respondents have not produced any such notices along with their affidavit-in-opposition.
9. The learned counsel for the petitioner further submits that the letter/communication
dated 18.05.2026 issued by the Regional Officer, MoRTH, Guwahati, to the Chief
Engineer, PWD (NH Works), Assam, is merely an internal communication between two
departmental offices and cannot be termed a notice to the petitioner.
10. It is contended that the said letter concerns an estimate for rectification of defects
Page No.# 5/15
under the risk and cost provision of Clause 14.7 of that contract agreement. It is
submitted that from the aforesaid letter/communication, it is clear that initially an
estimate for approximately Rs. 32.99 Lakhs was submitted, which was modified and
sanctioned for Rs. 15.62 Lakhs principally towards pothole repairs over the stretch of
28.685 Km.
According to the petitioner, preparation and sanction of such estimate cannot establish
any failure on its part to maintain the highway in a satisfactory condition, nor can the
said estimate be treated as a notice as required under Clause 20.8(viii).
It is further contended that no notice under Clause 14.7 of that contract agreement was
served upon the petitioner, no amount was recovered from it, and no work was actually
executed by other agencies at its risk and cost. It is also argued that the petitioner was
not afforded any opportunity to explain its position before the estimate was prepared and
sanctioned. It is submitted that an internal estimate which was never acted upon against
the petitioner cannot form the basis of disqualification in a subsequent tender.
11. Mr. Deka, learned counsel for the petitioner, also refers to the letter dated 25.05.2026
issued by the Executive Engineer, Nagaon NH Division. Referring to the said letter, it is
submitted by Mr. Deka that the said letter itself acknowledges that the petitioner has
carried out granular filling in the potholes on 21.05.2026. The Executive Engineer had
also called upon the petitioner to submit monthly maintenance bills for the work
undertaken up to December 2025. It is contended that such communications cannot be
treated as proof of failure to maintain the highway, particularly when the petitioner had
undertaken the maintenance work.
12. Mr. Deka, learned counsel, further relies upon the subsequent NIT dated 21.07.2026
issued by the Regional Officer, MoRTH, Guwahati for another PBMC work under
Rangia National Highway Division. It is submitted that the petitioner participated in the
said tender process and its technical bid was declared responsive, following which its
financial bid was also opened.
Page No.# 6/15
According to the petitioner, the very same alleged failure to maintain the earlier highway
stretches was not treated as a ground for disqualification in the said tender, though the
tender was of the same nature and the evaluation was undertaken under the same
Regional Office. Therefore, it is contended that the impugned decision is discriminatory
and violative of Article 14 of the Constitution of India.
13. The learned counsel for the petitioner lastly submits that Respondent No. 4 had failed
to disclose the two ongoing works involving approximately Rs. 56.07 Crore in its
statement of existing commitments. Such non-disclosure, according to the learned
counsel, amounted to suppression of material particulars and ought to have resulted in
rejection of its technical bid under Clause 4.11.
It is also contended that the Bid Evaluation Committee adopted different standards while
evaluating competing bidders and thereby acted arbitrarily. Mr. Deka, in support of his
contentions, places reliance on the judgments of the Hon’ble Apex Court in the case of
Bachhittar Singh –Vs- State of Punjab and Another reported in 1962 SCC Online
SC 11 .
14. Per contra, Mr. B. Choudhury, learned Standing Counsel appearing for the respondent
PWD, submits that the decision of the Bid Evaluation Committee was taken upon
consideration of reports and communications received from the concerned Executive
Engineer, Nagaon National Highway Division regarding the petitioner's performance
under the earlier maintenance contracts. It is observed that although the petitioner had
undertaken certain repair works in the past, its maintenance performance on the
entrusted highway stretches was unsatisfactory. Despite the deterioration in road
conditions, the petitioner failed to undertake maintenance interventions commensurate
with the contractual requirements.
15. Mr. Choudhury, learned Standing Counsel, also submits that the letter dated
18.05.2026 of the Regional Officer, MoRTH, Guwahati, records that the estimate for
rectification of defects under Clause 14.7 of the contract agreement was necessitated by
non-maintenance of the highway stretch by the EPC contractor. The estimate was
Page No.# 7/15
examined and sanctioned for Rs. 15.62 Lakhs, and the State PWD was requested to take
necessary action against the EPC contractor under the provisions of the contract
agreement. It is submitted that the said communication, read with the other departmental
records, establishes that the maintenance deficiencies were not merely allegations but
were supported by contemporaneous official records.
16. It is further argued by Mr. Choudhury, learned Standing Counsel, that the letter dated
25.05.2026 of the Executive Engineer, Nagaon NH Division specifically records that the
petitioner has undertaken only granular filling of severe potholes and patch-damaged
portions, while the required bituminous topping and surfacing work remained to be
undertaken. The letter also records that geo-tagged photographs furnished by the
petitioner did not pertain to the project stretch, and the petitioner was accordingly
directed to undertake required bituminous surfacing immediately.
According to Mr. Choudhury, the Bid Evaluation Committee, upon considering these
materials and the representation of the petitioner, found no ground to alter its earlier
decision.
17. With regard to the allegation concerning Respondent No. 4, Mr. Choudhury, learned
Standing Counsel, submits that the Bid Evaluation Committee did not ignore the
petitioner's objection.
The Chairman of the Bid Evaluation Committee sought clarification from Respondent
No. 4, which was furnished by its letter dated 18.06.2026. The Committee thereafter
reassessed the bidder's available bid capacity after including two additional ongoing
works. Even after this inclusion, the available bid capacity was found to be
approximately Rs. 304.28 Crore, against the minimum required capacity of Rs. 57.41
Crore.
Therefore, it is submitted that the omission did not affect the bidder's eligibility in
respect of the prescribed bid capacity, and the Committee rightly declined to interfere
with the technical evaluation.
Page No.# 8/15
18. Mr. Choudhury, learned Standing Counsel has also placed reliance upon Tata Cellular
v. Union of India , reported in (1995) 1 SCC 478 , Jagdish Mandal v. State of Orissa ,
reported in (2007) 14 SCC 517 and Michigan Rubber (India) Ltd. v. State of
Karnataka reported in 2012 8 SCC 216 , to argue that this Court may not interfere with
the decision of the Bid Evaluation Committee in exercise of its power of judicial review
in the given facts of the present case, more particularly when the deficiency was writ
large based on materials available on record, and the Committee did not exceed its
remit; rather, it ascertained that the object of Clause 20.8(viii) is achieved in true spirit.
19. Mr. S. K. Poddar, learned counsel for Respondent No. 4, while adopting the
arguments advanced by the learned Standing Counsel for the PWD, further argues that
once the petitioner was found to be disqualified, this Court may not further delve into
the allegation against the successful bidder. In support, the learned counsel places
reliance on Tata Motors Limited v. Brihan Mumbai Electric Supply & Transport
Undertaking (BEST) , reported in 2023 SCC Online SC 671 .
20. I have given anxious consideration to the rival submissions advanced by the learned
counsel for the parties and also perused the materials available on record, including the
bid documents.
21. The scope of judicial review in matters relating to tender evaluation and award of
public contracts is well settled. The Court does not sit as an appellate authority over the
decision of a tendering authority and is not required to substitute its own assessment for
that of technical experts. Interference is warranted where the decision-making process is
vitiated by arbitrariness, mala fides, irrationality, or violation of governing tender
conditions. The Court must examine the decision-making process and not undertake a
fresh evaluation of bids.
22. In Tata Cellular (supra), the Supreme Court explained the limits of judicial review in
contractual matters. The same principle was reiterated in Jagdish Mandal (supra),
wherein the Supreme Court held that before interfering in tender matters, the Court must
examine whether the process adopted or decision made by the authority is mala fide or
Page No.# 9/15
intended to favour someone, or is so arbitrary and irrational that no responsible authority
acting reasonably and in accordance with law could have reached such a decision. The
Court must also examine whether public interest is affected. If the answers are in the
negative, there should be no interference under Article 226 of the Constitution.
23. In Michigan Rubber (supra), the Supreme Court reiterated that, in matters of
formulating tender conditions and awarding contracts, greater latitude must be conceded
to the State authorities. It observed that where the State or its instrumentalities act
reasonably, fairly, and in the public interest, the Court's interference is very limited.
24. In BEST (supra), the Supreme Court reiterated that Courts should exercise
considerable restraint in contractual and commercial matters and should ordinarily
refrain from imposing their decision over that of the employer as to whether or not to
accept a particular bid, unless something very gross or palpable is demonstrated. It was
further observed that even where some defect in the decision-making process is noticed,
the discretionary jurisdiction under Article 226 must be exercised with great caution and
only in furtherance of public interest, and not merely on making out a legal point.
25. The aforesaid legal principles have to be kept in view while examining the impugned
decision of the Bid Evaluation Committee in the present case.
26. The tendering authority is responsible for ensuring satisfactory maintenance of
national highways and is required to assess the capability and past performance of the
contractors seeking to undertake such work. The Court would not ordinarily interfere
with such an assessment unless the decision is shown to be based on irrelevant
considerations, unsupported by the record, or otherwise vitiated by arbitrariness or
irrationality.
27. In the present case, the petitioner's technical bid was declared non-responsive under
Clause 20.8(viii) of the RFP.
Clause 20.8 provides that a bidder should not be a non-performing party either on the
date of opening of the tender or on the date of issue of Letter of Acceptance. The clause
Page No.# 10/15
further provides that a bidder shall be deemed to be a non-performing party if it attracts
any one or more of the enumerated conditions in any of its ongoing or completed
projects.
Clause 20.8(viii) specifically refers to failure to fulfil obligations to maintain a highway
in a satisfactory condition despite two rectification notices issued in this regard.
28. On an overall perusal of the bid document, in the opinion of this Court, the object of
the aforesaid condition is to ensure that a bidder seeking a fresh maintenance contract
has satisfactorily discharged its obligations under its existing or completed projects and
has not persisted in default despite being called upon to rectify the deficiencies.
The condition is directly connected with the nature of work for which the tender has
been issued and is intended to ensure that the contractor entrusted with maintenance of
public highways possesses the requisite capacity and has demonstrated satisfactory
performance in the earlier projects.
29. The Bid Evaluation Committee, in its meeting dated 11.06.2026, recorded that the
petitioner had failed to fulfil its obligation to maintain the highway in a satisfactory
condition despite two rectification notices in respect of Job No. 37/AS/2021-22/230 and
Job No. Br. 352/1/AS/2021-22/222. The Committee relied upon the reports of the
concerned Executive Engineer and the departmental records relating to the said projects.
30. The subsequent departmental communications dated 18.05.2026 and 25.05.2026
further disclose the deficiencies noticed in the maintenance of the two highway
stretches.
The letter dated 18.05.2026 records that the State PWD submitted an estimate for
rectification of defects under Clause 14.7 of the contract agreement. The estimate,
initially submitted for approximately Rs. 32.99 Lakhs, was examined and modified to
Rs. 15.62 Lakhs.
The communication specifically records that the estimate was necessitated due to the
EPC contractor's failure to maintain the highway stretch and requests the State PWD to
Page No.# 11/15
take necessary action against the contractor under the provisions of the contract
agreement.
31. The other communication dated 25.05.2026 issued by the Executive Engineer, Nagaon
National Highway Division records that the petitioner had undertaken granular filling in
the potholes, but the required bituminous surfacing remained incomplete. Accordingly,
the petitioner was called upon to undertake the necessary surfacing work immediately.
32. Mr. Deka, learned counsel for the petitioner, sought to discredit the aforesaid materials
on the ground that the letter dated 18.05.2026 was an internal communication and no
notice under Clause 14.7 of that contract was served upon it. It has also been contended
that no amount was recovered from the petitioner and no work was actually executed by
any other agency at the risk and cost of the petitioner.
33. The aforesaid contentions, in the opinion of this Court, do not adequately address the
nature of the decision taken by the Bid Evaluation Committee. The Committee was
examining the petitioner's performance under earlier contracts in the context of the
eligibility condition prescribed under Clause 20.8(viii) of the RFP.
34. The fact that proceedings under the risk and cost provisions had not culminated in
actual recovery or execution of the rectification work through another agency, by itself,
shall not establish that the petitioner had satisfactorily discharged its maintenance
obligations. The preparation and sanction of an estimate under Clause 14.7 and the
direction to take necessary action against the EPC contractor are relevant departmental
records concerning the petitioner's performance.
35. It is true that Clause 20.8(viii) refers to failure to maintain the highway in a
satisfactory condition despite two rectification notices issued in this regard. The
requirement prescribed under the said clause has to be applied in accordance with its
terms. The Court cannot dispense with an express requirement of the tender document or
substitute a different condition in its place. At the same time, the judicial inquiry in the
present case is not to determine afresh the extent of maintenance work undertaken by the
Page No.# 12/15
petitioner or its ultimate financial liability under the earlier contracts. The relevant
inquiry is whether the decision of the Bid Evaluation Committee, which recorded the
issuance of two rectification notices and relied upon the departmental assessment of the
petitioner's performance, is so arbitrary and palpably irrational as to warrant interference
in exercise of the power of judicial review under Article 226 of the Constitution of India.
36. Clause 20.8(viii) does not prescribe any particular form for a rectification notice. Read
in the context of a maintenance contract, the expression must be understood to mean a
written communication by the Authority or its Engineer addressed to the Contractor that
identifies the maintenance deficiencies and calls upon the Contractor to rectify them.
The nomenclature of the communication is not decisive, but the substance of such
requirement. Therefore, it cannot be said that the Bid Evaluation Committee acted upon
any extraneous consideration or deliberately departed from the foundational requirement
of having good past performance as prescribed under the RFP.
37. Tested on that touchstone, the Minutes of the Bid Evaluation Committee dated
11.06.2026 specifically record that the petitioner failed to maintain the highway in a
satisfactory condition despite two rectification notices in respect of Job No.
37/AS/2021-2022-230 and Job No. BR.352/1/AS/2021-2022/222. This is a recorded
finding of fact of the tendering authority arrived at on the basis of the report of the
concerned Executive Engineer and the departmental records. The petitioner, either in its
representation dated 13.06.2026 or in the writ petition, has not pleaded that no
communication calling upon it to rectify the defects was ever issued or received by it,
but has relied on such allegations of deficiencies.
38. The Committee's recording is corroborated by the petitioner's own case. The letter
dated 25.05.2026 (a reply to the petitioner’s own letter dated 22.05.2026), on which the
petitioner itself relies, is addressed to the petitioner and records that only granular filling
had been undertaken, and calls upon the petitioner to carry out the required bitumen
surfacing immediately. It is thus a communication of the very nature contemplated under
Clause 20.8(viii). The petitioner's own assertion that it carried out granular filling on
Page No.# 13/15
21.05.2026 also indicates that deficiency in the stretch had been brought to its notice.
The assessment of adequacy of such maintenance work essentially falls within the
domain of the technical authorities. This Court would not be justified in undertaking a
fresh technical evaluation of the work or substituting its own assessment as regards the
petitioner's performance for that of competent authority.
39. Clause 20.8 requires that a bidder should not be a non-performing party either on the
date of opening of the tender or on the date of issuance of the Letter of Acceptance. The
communications relied upon precede the Committee meetings dated 11.06.2026 and
19.06.2026, and necessarily precede the issuance of any Letter of Acceptance. The
petitioner has not demonstrated that the notices were withdrawn or that the deficiencies
were fully cured before either of the said dates. The Committee was, therefore, entitled
to treat the petitioner as a non-performing party within the meaning of Clause 20.8(viii).
40. The reliance placed by the petitioner on Bachhittar Singh (supra) does not advance
the case further. The decision lays down that an order of a State Government which is
not communicated to the person concerned remains provisional and binds no one. The
principle of Bachhittar Singh does not apply to the use of departmental records by the
tendering authority while assessing the performance of a bidder.
41. Coming to the argument on the acceptance of the technical bid of the petitioner in
another PBMC tender under Rangiya NH division, in the opinion of this Court, it
constituted a subsequent procurement process and its technical evaluation was
undertaken in the context of the requirements of that tender. The responsiveness of the
petitioner's tender in that contract does not automatically render the decision taken in the
present case arbitrary. The decision under challenge must be examined on the basis of
the materials considered by the Bid Evaluation Committee and the requirements
governing the present tender. The NIT dated 21/07/2026 was issued after the impugned
decision dated 11/06/2026 for a different division and involved a separate evaluation.
Article 14 of the Constitution of India guarantees equality before law. It does not entitle
Page No.# 14/15
a bidder to insist that a view taken in one procurement on a different record must bind
the authority in another; the plea of discrimination therefore fails.
42. The other contention of the petitioner concerns the acceptance of the bid of
Respondent No. 4, M/s M. P. Agarwalla. In this regard, the Supreme Court's decision in
BEST (supra) is relevant. In that case, the Supreme Court, after upholding the
employer's decision declaring the appellant's bid technically non-responsive, held that
the High Court ought not to have proceeded further to examine the correctness of the
employer's decision in declaring another bidder eligible. The Supreme Court observed
that once the appellant stood disqualified from the tender process, it was not necessary
for the Writ Court to undertake a further examination of the eligibility of the successful
bidder, particularly when proceedings were directed towards ascertaining the private
rights of an unsuccessful bidder, and no independent public interest consideration
warranted such examination.
43. Even otherwise, the Committee did not ignore the petitioner's objection. It sought
clarification from Respondent No. 4, which was furnished by letter dated 18.06.2026,
and recomputed its available bid capacity after including the two omitted works. Even
after such inclusion, the available bid capacity was found to be approximately Rs.304.28
crores as against the minimum requirement of Rs.57.41 crores. The omission thus had
no bearing on the eligibility of Respondent No. 4 and conferred no advantage upon it.
No material has been placed to show that the omission was deliberate or made to secure
eligibility that Respondent No. 4 did not otherwise possess. The Committee's view that
the omission did not warrant rejection of the bid under Clause 4.11, therefore, cannot be
termed perverse, and no element of public interest warrants interference at the instance
of a bidder who stands disqualified.
44. For the reasons recorded above, this Court finds no ground to hold that the decision of
the Bid Evaluation Committee declaring the petitioner's bid technically non-responsive
suffers from any arbitrariness, irrationality, or illegality warranting interference under
Article 226 of the Constitution of India. The decision is founded upon relevant materials
Page No.# 15/15
concerning the petitioner's performance under the earlier maintenance contracts and
bears a rational connection with the object of the eligibility condition prescribed under
Clause 20.8(viii) of the RFP.
45. Accordingly, the writ petition stands dismissed. The interim order, if any, stands
vacated. The State respondent authorities shall be at liberty to proceed with the tender
process in accordance with law.
46. No order as to costs.
JUDGE