Reliance Industries Ltd. And Anr. vs The Mumbai Metropolitan Region Development Authority (Mmrda) And 2 Ors.
- Court
- Bombay High Court
- Case type
- WP
- Decided on
- 08-04-2026
<div> <b>2026:BHC-OS:8906-DB</b><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> Shephali<br /> IN THE HIGH COURT OF JUDICATURE AT BOMBAY<br /> ORDINARY ORIGINAL CIVIL JURISDICTION<br /> WRIT PETITION NO. 242 OF 2018<br /> WITH<br /> INTERIM APPLICATION NO. 2172 OF 2020<br /> IN<br /> WRIT PETITION NO. 242 OF 2018<br /> 1. Reliance Industries Limited,<br /> A company incorporated under the <br /> Companies Act, 1956 having its <br /> Registered Office at Maker Chamber IV,<br /> rd<br /> 3 Floor, Nariman Point, <br /> Mumbai 400 021<br /> 2. Mr. Rajumal Nahar,<br /> having his office at having his office at <br /> th<br /> 6 Floor, “B” Wing, Fortune 2000, “G” <br /> Block, Bandra Kurla Complex,<br /> Bandra (East), Mumbai 400 051. …Petitioners<br /> SHEPHALI<br /> SANJAY<br /> MORMARE<br /> Digitally signed<br /> by SHEPHALI<br /> SANJAY<br /> MORMARE<br /> Date: 2026.04.09<br /> 15:15:50 +0530<br /> ~ versus ~<br /> 1. Mumbai Metropolitan Region<br /> Development Authority (MMRDA),<br /> an authority established under the <br /> Mumbai Metropolitan Region <br /> Development Authority Act, 1974 and <br /> having its head Office at Plot C-14 & <br /> C-15, ‘E’ Block, Bandra Kurla Complex,<br /> Bandra (East), Mumbai 400 051.<br /> 2. The Metropolitan Commissioner,<br /> Mumbai Metropolitan Region <br /> Development Authority, having office <br /> at Plot C-14 & C-15, ‘E’ Block, Bandra <br /> Kurla Complex, Bandra (East), <br /> Mumbai 400 051.<br /> Page 1 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:19 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> 3. The Deputy Metropolitan <br /> Commissioner,<br /> Mumbai Metropolitan Region <br /> Development Authority, having office <br /> at Plot C-14 & C-15, ‘E’ Block, Bandra <br /> Kurla Complex, Bandra (East), <br /> Mumbai 400 051. …Respondents<br /> PPEARANCES<br /> A<br /> For the Petitioners Mr. Vikram Nankani, Senior<br /> Advocate, with Mr. Vikramaditya<br /> Deshmukh, Mr. Ashwin Dave,<br /> Mr. Ameya Nabar & Ms. Swati Jain,<br /> i/b A. S. Dayal & Associates.<br /> For Respondents-MMRDA Dr. Birendra Saraf, Senior Advocate,<br /> with Mr. Nishant Chotani, Mr. Nivit<br /> Srivastava, Ms. Sneha Patil,<br /> Ms. Aditi Sinha, Mr. Hrishikesh<br /> Joshi & Ms. Isha Vyas, i/b Maniar<br /> Srivastava Associates.<br /> CORAM : SHREE CHANDRASHEKHAR, CJ &<br /> SUMAN SHYAM, J.<br /> nd<br /> RESERVED ON : 22 JANUARY 2026.<br /> th<br /> PRONOUNCED ON : 8 APRIL 2026.<br /> JUDGMENT (Per Suman Shyam, J) :- <br /> 1. Rule. Rule is made returnable forthwith. <br /> 2. By consent of the parties, the matter is taken up for final<br /> hearing.<br /> Page 2 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:19 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> th<br /> 3. Assailing the demand-cum-show cause notice dated 12<br /> September 2017 (Exhibit “R”), whereby, the Respondent No.1–<br /> Mumbai Metropolitan Region Development Authority (“MMRDA”)<br /> had demanded additional premium/penalty as per statements ‘A’<br /> and ‘B’ annexed thereto, for the alleged delay of 7 years and 12<br /> days in completion of construction of a Convention & Exhibition<br /> Centre and Commercial Complex on Plot No. C-64, ‘G’ Block,<br /> Bandra-Kurla Complex, Mumbai, the Petitioners have approached<br /> this Court by filing this Writ Petition invoking the jurisdiction of<br /> this Court under Article 226 of the Constitution of India. During<br /> the pendency of the Writ Petition, by the communication dated<br /> th<br /> 13 June 2019 (Exhibit “X”) a further amount of<br /> Rs.1116,83,10,102/- was demanded from the Petitioner No. 1 as<br /> additional premium, along with interest, towards extension of<br /> time for completing the construction of the building by using the<br /> additional built up area of 72,500 sq mtrs. allotted under the<br /> th<br /> Supplementary Lease Deed dated 13 July 2007. The said Notice<br /> is also under challenge in this Writ Petition. The facts and<br /> circumstances giving rise to the filing of the present Writ Petition,<br /> shorn of unnecessary details, are as hereunder.<br /> Page 3 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:19 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> 4. The Petitioner No.1 is a company incorporated under the<br /> provisions of the Companies Act, 1956. As per statements made in<br /> the Writ Petition it is engaged inter alia in the business of<br /> exploration of petroleum products and allied activities. Petitioner<br /> No.2 is a shareholder of the Petitioner No.1 company. The<br /> expression “Petitioner” shall here-in-after refer to the Petitioner<br /> No.1 company. The Respondent No.1, MMRDA, is a statutory<br /> authority constituted under Section 3 of the Mumbai Metropolitan<br /> Region Development Authority Act, 1974. Respondent Nos.2 and 3<br /> are its officers.<br /> 5. In the month of December 2005, Respondent No.1, being<br /> the owner of the land, had invited bids for leasing out Plot No. C-<br /> 64 admeasuring approximately 75,000 sq. mtrs. situated in ‘G’<br /> Block of Bandra-Kurla Complex (BKC) for the purpose of<br /> construction of “Convention and Exhibition Centre and<br /> Commercial Complex”. The Petitioner had submitted its bid for the<br /> said plot and was declared successful bidder. As such, by the letter<br /> th<br /> dated 15 February 2006, the Respondent No.1 had approved the<br /> proposal for leasing out the aforesaid plot of land to the Petitioner<br /> for a maximum permissible built-up area of 65,000 sq. mtrs. for<br /> Page 4 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:19 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> the Convention and Exhibition Centre and 50,000 sq. mtrs. for the<br /> Commercial Complex, aggregating to 1,15,000 sq. mtrs., for a<br /> total premium of Rs.1104 crores. Pursuant thereto, a registered<br /> st<br /> Lease Deed dated 1 September 2006 came to be executed by and<br /> in between the Petitioner and Respondent No.1 for leasing out the<br /> demised plot for a term of 80 years. Possession of the said plot of<br /> st<br /> land was handed over to the Petitioner on the same day i.e. on 1<br /> September 2006.<br /> st<br /> 6. Article 2(d) of the Lease Deed dated 1 September, 2006<br /> stipulates that the lessee shall, within three months from receipt of<br /> approval of plans, commence and within a period of four years<br /> from the date of the lease, build and completely finish the<br /> construction of the Convention and Exhibition Center and<br /> Commercial Complex, fit for occupation. Article 2(e) lays down<br /> that in case of failure to adhere to the said time limit, extension of<br /> time may be granted upon payment of additional premium at the<br /> prescribed rates. <br /> th<br /> 7. On 14 October 2006 the Petitioner had applied for<br /> permission to start excavation and removal of earth on site by<br /> attaching a report of the Structural Consultants. By the said letter,<br /> Page 5 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:19 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> the Petitioner had also informed the Respondents that it will not<br /> carry out any construction activity on the site without prior<br /> intimation to the MMRDA and also without obtaining the required<br /> statutory permissions.<br /> st<br /> 8. After the execution of the Leased Deed dated 1 September<br /> 2006, the FSI for the plots in block ‘G’ of BKC was increased from<br /> 2.00 to 4.00. As such, in the month of February 2007, the<br /> Petitioners had applied for allotment of additional built-up area of<br /> th<br /> 72,500 sq. mtrs.. By the letter dated 7 May 2007, the Respondent<br /> No.1 had approved the allotment of additional built up area of<br /> 41,000 sq. mtrs. for the Convention Centre and 31,500 sq. mtrs.<br /> for the Commercial Complex, aggregating to 72,500 sq mtrs.,<br /> against payment of premium of a total amount of Rs.696 crores.<br /> Upon allotment of the additional built up area, as aforesaid, a<br /> th<br /> Supplementary Lease Deed dated 13 July 2007 was executed by<br /> and between the parties in respect of the additional built-up area.<br /> 9. It would be pertinent to note herein that after the allotment<br /> of the additional built up area, Reliance Communication &<br /> Infrastructure Ltd., along with another, had instituted Writ Petition<br /> No.1165 of 2007 before this Court challenging the grant of the<br /> Page 6 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:19 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> additional FSI of 71,500 sq mtrs to the Petitioner for the<br /> Convention and Exhibition Centre (41,000 sq mtrs) and<br /> Commercial Complex (31,500 sq mtrs). The Petitioner was<br /> impleaded as Respondent No. 3 in that writ petition. By the<br /> th<br /> interim order dated 15 October 2007 passed in the said Writ<br /> Petition, a Division Bench of this Court had restrained the<br /> Petitioner from utilizing the additional FSI of 31,500 sq. mtrs.<br /> allocated for the Commercial Complex. <br /> 10. On 17/04/2008, the Petitioner submitted revised plans<br /> th<br /> seeking necessary approvals. Based on the same, on 12<br /> June,2008, Commencement Certificate (CC), upto the plinth level,<br /> only in respect of the Convention & Exhibition Centre plot “A’ of<br /> plot C-64 in Block “G” of BKC Complex, with total permissible<br /> built up area of 1,06,000sq mtrs. was issued in favour of the<br /> Petitioner. However, no CC was issued in respect of the<br /> commercial complex.<br /> 11. There is no controversy in this case about the fact that the<br /> proposed development was composite in nature with common<br /> th<br /> basement and foundation. As such, by the letter dated 28<br /> January 2009, the Petitioner had submitted progress report and<br /> Page 7 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:19 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> informed the Respondent No.1 that commencement of<br /> construction at site was affected due to the interim order passed<br /> by the court since the basement and foundation of the Convention<br /> & Exhibition Centre (CEC) as well as the Commercial Complex<br /> th<br /> (CC) was common. However, by letter dated 18 February 2009,<br /> the Respondent No.1 had replied that since there was no restraint<br /> order in respect of the Convention & Exhibition Centre, hence,<br /> the Petitioner to continue with the construction of the CEC as per<br /> CC (1,06,000 sq mtrs) and also expedite the final hearing of the<br /> proceeding pending in the court. The Petitioner was also asked to<br /> furnish Bank Guarantee of Rs 20 crores towards liquidated<br /> damage and Completion Guarantee for a sum of Rs 20 crores.<br /> th<br /> 12. In response to the above, by the letter dated 16 March<br /> 2009, the Petitioner had highlighted the design uncertainty in<br /> proceeding with the construction and had sought the guidance of<br /> the MMRDA in the matter. Due to the uncertain circumstances<br /> arising in view of the pending Court proceedings, the Petitioner<br /> had also sought extension of time to complete the project.<br /> However, in the meantime, the Commencement Certificate issued<br /> th<br /> earlier on 12 June 2008 had lapsed in June 2009.<br /> Page 8 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:19 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> th<br /> 13. While the matter was poised as above, in the 129 Meeting<br /> th<br /> of the MMRDA held on 8 September 2011, the Respondent No.1<br /> had resolved to extend the time for allotment of additional FSI in<br /> th<br /> ‘G’ Block till December 2012. Accordingly, by the letter dated 8<br /> November 2011, the Respondent No.1 had offered additional<br /> built-up area to the Petitioner by recording that there would be no<br /> time limit for construction of such additional built-up area. <br /> 14. However, in view of the pendency of Writ Petition No 1165<br /> th<br /> of 2007 and the interim order operating therein, on 14 October<br /> 2010, the Petitioner had offered to surrender the additional built<br /> up area of 72,500 sq.mtrs and sought refund of the amount of Rs<br /> 1064 crores being the premium, along with interest, paid for the<br /> aforesaid built up area. The said request was followed by the<br /> rd th<br /> subsequent letters dated 3 August 2020 and 10 January 2012<br /> rehearing the request. In response to the above request of the<br /> st<br /> Petitioner, by the letter dated 1 February 2012, the Respondent<br /> No.1 had informed the Petitioner that its request for refund of<br /> lease premium by surrendering the additional built up area cannot<br /> be considered as there is no provision in the Leased Deed as well<br /> the Supplementary Lease Deed permitting the same. It was,<br /> Page 9 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:19 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> however, clarified that in so far as the request for extension of<br /> time for completion of construction on the plot under reference as<br /> st<br /> per Article 2(d) of the Lease Deed dated 1 September 2006, is<br /> concerned, the period during which the stay order of the court<br /> was under operation, will not be considered for computing the<br /> four years time period, meaning thereby, that the period, during<br /> which the interim order passed in Writ Petition No.1165 of 2007<br /> was operative, shall be excluded while computing the four-year<br /> st<br /> period stipulated under Article 2(d) of the Lease Deed dated 1<br /> September, 2006. Be it stated here in that the Writ Petition No<br /> th<br /> 1165 of 2007 was withdrawn on 12 March 2012 as a result of<br /> which, the stay order also got vacated on the same day.<br /> 15. In the wake of the aforesaid development, the Respondent<br /> th rd<br /> No.1, by letters dated 20 March 2012 and 3 April 2012<br /> approved allotment of further additional built-up area of 1,00,000<br /> sq. mtrs. and 25,000 sq. mtrs. against payment of premiums of<br /> Rs.1470 crores and Rs.367.50 crores respectively. With the<br /> allotment of the additional built up area of 1,25,000 sq mtrs, the<br /> total built-up area allotted by the Respondent No.1 to the<br /> Petitioner for construction to be carried out on the same plot, was<br /> Page 10 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:19 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> increased to 3,12,500 sq. mtrs. It is a matter of record that the<br /> Petitioner had paid an aggregate premium of Rs.4,005 crores to<br /> the Respondent No.1 for the allotment of the entire built up area<br /> of 3,12,500 sq. meters.<br /> 16. In view of the allotment of additional built-up area, as<br /> aforesaid, the Petitioner was required to revise the development<br /> plans for a composite structure and also obtain various statutory<br /> approvals afresh including the environmental clearance under the<br /> th<br /> EIA Notification dated 14 September 2006, height clearance from<br /> Civil Aviation Authorities, approval from the High Rise Committee,<br /> permission from the Municipal Corporation of Greater Mumbai<br /> and other statutory authorities. Accordingly, various approvals<br /> were obtained during the year 2013 and early part of the year<br /> 2014.<br /> th<br /> 17. On 26 June 2013, Environment Clearance for the proposed<br /> “ Convention & Exhibition Centre and Commercial Complex” over<br /> plot No. C-64 in Block-G of BKC was granted to the Petitioner for<br /> the entire FSI of 3,12,500 Sq. Mtrs. In the said communication<br /> also, the CEC & CC was shown as a composite construction. <br /> Page 11 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:19 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> 18. After compliance of the above requisites and submission of<br /> the revised plans, the Respondent No.1 had issued<br /> th<br /> Commencement Certificate dated 16 April 2014 for construction<br /> th<br /> upto the 7 floor level of the composite building comprising<br /> Convention & Exhibition Centre and Commercial Complex.<br /> Thereafter, further Commencement Certificates were issued on<br /> rd th th<br /> 23 December 2016, 17 April 2017 and 19 May 2017.<br /> st nd<br /> 19. In the meantime, in its 131 Meeting held on 22 October<br /> 2012, the Respondent No.1 had considered granting extension of<br /> time for completion of construction by taking note of the delay<br /> caused in obtaining multiple statutory permissions/ clearance<br /> form different agencies. After considering the matter, the<br /> Respondent No.1, vide Resolution No.1283 adopted in the said<br /> meeting, had recommended extension of time from four years to<br /> six years for completing the construction. The said resolution was,<br /> th<br /> however, kept in abeyance for some. Finally, in its 138 Meeting<br /> th<br /> held on 26 August 2015, the Respondent No.1 had resolved to<br /> amend Article 2(d) to provide six years time period for completion<br /> of construction in respect of plots leased after the date of the<br /> resolution and further resolved to constitute a One Man<br /> Page 12 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:19 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> Committee to examine the issue of recovery of additional<br /> premium in the cases where delay was attributable to time<br /> required for obtaining statutory permissions.<br /> 20. Notwithstanding the above developments,the Respondent<br /> no.1 had insisted on an undertaking from the Petitioner to pay<br /> the additional premium for grant of extension of time for<br /> th<br /> completing the construction of the building. As such, on 18<br /> November 2016, the Petitioner had submitted an undertaking to<br /> the above effect thus, agreeing to pay the additional premium for<br /> extension of time for completing the construction of the building<br /> over Plot No- C-64 in Block “G” of the BKC before receipt of<br /> Occupation Certificate or decision of the Authority, which ever was<br /> earlier, with a further undertaking not to create any third party<br /> liability on the project till receipt of the Occupation Certificate. <br /> 21. Based on such undertaking, the Respondent No 1 had issue<br /> th<br /> further Commencement Certificate dated 19 May 2017 for the<br /> th<br /> Fire Check floor and the 15 (part) floor. <br /> 22. While the above process was under way, the Respondent No.<br /> th<br /> 1 had issued the impugned Notice dated 12 September 2017,<br /> Page 13 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:19 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> st<br /> alleging that as per Article 2(d) of the Lease Deed dated 01<br /> September 2006, the Petitioner had the obligation to erect and<br /> completely finish the construction, fit for occupation, within four<br /> years from the date of execution of the Lease Deed. However,<br /> although, there was delay of 7 years and 12 days the Petitioner<br /> had failed to pay the penalty for the entire period of delay till<br /> completion of the construction, fit for occupation. It was further<br /> mentioned that the amount on account of delay in construction,<br /> along with interest, has been shown in Annexures “A” and “B”. It<br /> was alleged that the Petitioner had committed breach of the terms<br /> and conditions of the Deed of Lease. As such, the MMRDA had the<br /> power to recover the said amount as arrears of land revenue and<br /> also resume the land as per Articles 5 & 6 of the Lease Deed. The<br /> Petitioner was, therefore, called upon to remedy the situation<br /> within 30 days, failing which, the Authority will have the right to<br /> determine the lease and enter upon the leased premise and also<br /> proceed to recover the amount due as arrears of land revenue. <br /> 23. It would be pertinent to mention here-in that the Notice<br /> th<br /> dated 12 September, 2017 does not mention the amount claimed<br /> by the Respondent No. 1. The figures projected in the Statements<br /> Page 14 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:19 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> “A” & “B” annexed to the Writ Petition are also not legible.<br /> th<br /> However, it appears that upon receipt of the Notice dated 12<br /> th<br /> September 2017, the Petitioner had sent reply dated 11 October<br /> 2017 denying its liability to pay the amount claimed with a further<br /> th<br /> request to withdraw the show cause notice dated 12 September,<br /> 2017. However, no action was taken by the Respondents on such<br /> request made by the Petitioner.<br /> th<br /> 24. Aggrieved by the dated 12 September 2017 the Petitioner<br /> th<br /> had instituted Writ Petition on 30 November, 2017 which was<br /> th<br /> originally registered as Writ Petition (L) No 3395 of 2017. On 8<br /> December 2017, this Court, while issuing notice, had recorded the<br /> statement made on behalf of Respondent No.1 that till next date<br /> of hearing no coercive steps would be taken pursuant to the<br /> impugned notice. Records reveal that the said ad-interim order<br /> was extended by the court from time to time. Subsequently, the<br /> said writ petition was registered as Writ Petition No.242 of 2018<br /> i.e. the present Writ Petition.<br /> th<br /> 25. On 06 February 2019, the Architect engaged by the<br /> Petitioner had applied for part Occupation Certificate for the built<br /> th<br /> up area of 44,621 sq.mtrs. That apart, by the letter dated 18<br /> Page 15 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:19 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> February 2019, the Petitioner had deposited a sum of<br /> Rs.646,77,68,594 (Rupees Six Hundred and Forty Six Crores<br /> Seventy Seven Lakhs Sixty Eight Thousand Five Hundred and<br /> Ninety Four) after deducting TDS amount of Rs.21,32,20,676/-<br /> and furnished a Bank Guarantee of an amount of<br /> Rs.13,12,54,85,287/- (Rupees Thirteen Hundred Twelve Crores<br /> Fifty Four Lakhs Eighty Five Thousand Two Hundred and Eighty<br /> Seven) based on an alternate computation treating the delay to be<br /> st th<br /> for the period from 01 September 2010 to 17 February 2019. It<br /> was also mentioned in that letter that the amount was being<br /> deposited under protest and without prejudice to the rights and<br /> contention of the Petitioner in the pending Writ Petition.<br /> th<br /> 26. Upon receipt of the above amount, on 20 February 2019,<br /> the Respondent No.1 had issued part Occupation Certificate for<br /> th<br /> 44,621 sq. mtrs. However, soon thereafter i.e. on 13 June 2019,<br /> the Petitioner was served with another communication demanding<br /> payment of a further amount of Rs.1116,83,10,102/- as additional<br /> premium for the delay in completing the construction of the<br /> additional built up area as allotted under the Supplementary<br /> th<br /> Lease Deed dated 13 July 2007. <br /> Page 16 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:19 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> th<br /> 27. Despite the notice dated 13 June 2019, the Petitioner,<br /> through its Architect, had applied for further part Occupation<br /> Certificate for the built up area of 1,24,000 sq. mtrs. However, the<br /> Respondent No. 1 refused to process the same until the amount of<br /> Rs.1116,83,10,102/- was paid. Under such circumstances, the<br /> Petitioner had filed Interim Application No.2171 of 2020 arising<br /> out of this Writ Petition, seeking a direction upon the Respondent<br /> No.1 for issuance of Occupation Certificate without insisting upon<br /> payment of the additional premium. By the judgment and order<br /> th<br /> dated 12 July 2021 passed in the Interim Application No. 2171 of<br /> 2020, this Court had allowed the prayer made in the Interim<br /> Application and directed the Respondent No.1 to process the<br /> applications seeking Occupation Certificates including the<br /> rd<br /> application dated 3 February 2020, without insisting on payment<br /> of the amount mentioned in the subsequent demand notice dated<br /> th<br /> 13 June 2019. In the said order it was also observed that when<br /> the court was in seisin of the matter and considering the earlier<br /> th<br /> interim order dated 8 December 2017, the Respondents ought<br /> th<br /> not to have issued the notice dated 13 June 2019. By carrying<br /> out amendments in the writ petition, the Petitioner has<br /> th<br /> challenged the letter dated 13 June 2019.<br /> Page 17 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:19 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> 28. The Respondent Nos. 1 and 2 have opposed the Writ<br /> Petition by filing joint Reply. The plea taken by the Respondents in<br /> their Reply, reduced to their essence, is to effect that that the Writ<br /> Petition involves disputed questions of fact, which cannot be<br /> adjudicated in a Writ Petition; that the Writ Petitioners have an<br /> alternate, efficacious remedy by way of Civil Suit; that the dispute<br /> is purely contractual in nature involving interpretation of the<br /> terms and conditions of the contract, which cannot be entertained<br /> in a Writ Petition; that this is not a case of infringement of any<br /> constitutional, statutory or fundamental right of the Petitioner;<br /> that the Demand Notice has issued on account of breach of<br /> conditions of the Lease Deed and, therefore, the same does not<br /> involved violation of any constitutional right; that Articles 2(a)<br /> and 2(d) of the Lease Deed, which require completion of the<br /> construction within a period of four years from the date of Lease<br /> Deed are binding and mandatory clauses in the Lease Deed.<br /> Therefore, those are enforceable under the law; even if the delay<br /> in construction has occurred due to interim order of Court or on<br /> account of force majeure, even than, in view of Article 2(d), any<br /> extension of time could only been granted upon payment of<br /> additional premium. Since the MMRDA would not have any power<br /> Page 18 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> to waive such amount, therefore, payment of additional<br /> premium/penalty was inevitable in case of delay; that the restraint<br /> order of the Court was limited only to the additional area of<br /> 31,500 sq.mtrs. of commercial FSI. Therefore, the same did not<br /> prevent commencement and completion of construction of the<br /> Convention Centre; that allotment of additional built-up area was<br /> optional. Since the Petitioners have opted for the additional built-<br /> up area, therefore, the allotment of additional built up area<br /> cannot be a justifiable ground for the delay in completion of<br /> construction; that the Petitioners have issued an unconditional<br /> th<br /> undertaking on 14 December 2016 agreeing to pay the additional<br /> premium/penalty for grant of extension of time. Therefore, they<br /> would be bound by such undertaking; that the Writ Petitioner has<br /> approached this Court by suppressing material facts and<br /> th<br /> particulars pertaining to the undertaking dated 14 December<br /> 2016, therefore, the Writ Petition is liable to be dismissed on such<br /> count alone; that the decision of the MMRDA to extend the time<br /> period from four years to six years was applicable prospectively,<br /> i.e., with effect from August, 2015 and therefore, the same would<br /> not cover the case of lessees such as the Petitioner in respect of<br /> whom, the Lease Deed was executed prior to August, 2015. <br /> Page 19 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> 29. By filing Rejoinder, the Writ Petitioner, while denying the<br /> assertions made by the Respondents, has reiterated that it is a case<br /> of violation of fundamental right of the Petitioner guaranteed<br /> under Article 14 of the Constitution of India. It has further been<br /> asserted that even in contractual matters, unfair treatment<br /> extended by the State or its instrumentality would be amenable to<br /> writ jurisdiction of this Court; that due to the allotment of the<br /> additional built-up area and the integrated design of the project, it<br /> would be impossible to complete the original portion of the<br /> building within four years since it included common structures<br /> such as common basement and services, etc. The Petitioners have<br /> also denied the contention that the restraint order of the Court did<br /> not affect the integrated planning and common infrastructure of<br /> the project so as to permit bifurcation of the construction; it has<br /> also been alleged that the Petitioner being similarly situated<br /> Lessee, extension of time from four years to six years would be<br /> equally applicable to them as denial of such benefit would amount<br /> to unfair discrimination; the Petitioners have further contended<br /> that similarly situated entities such as Bharat Diamond Bourse &<br /> Indian Oil Corporation have been granted extension of time<br /> without levy of additional premium; it has also been contended<br /> Page 20 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> th<br /> that the undertaking dated 14 December 2016 was obtained<br /> under coercion viz. On the threat of withholding Occupation<br /> Certificate and, therefore, the same cannot preclude the Petitioner<br /> from agitating its grievance as per law; the Petitioner has also<br /> denied suppression of material facts. <br /> 30. In their additional Reply, the Respondents have controverted<br /> the statements made in the Rejoinder Affidavit while maintaining<br /> their original stand justifying the demand for the additional<br /> premium.<br /> 31. This Writ Petition was analogously heard along with three<br /> other Writ Petitions being Writ Petition No.864 of 2018, Writ<br /> Petition No.2377 of 2018 and Writ Petition No.3209 of 2017,<br /> involving similar issues wherein, identical reliefs were sought by<br /> the Writ Petitioner(s).<br /> 32. We have heard the learned Senior Counsel appearing for the<br /> parties and have also perused the pleadings and documents placed<br /> on record. <br /> 33. Mr. Vikram Nankani, learned Senior Counsel appearing for<br /> the Petitioners, has argued that the impugned demand notice<br /> Page 21 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> th<br /> dated 12 September 2017 and the subsequent communication<br /> th<br /> dated 13 June 2019 issued by Respondent No.1 seeking recovery<br /> of additional premium on account of alleged delay in completion<br /> of construction are arbitrary, illegal and unsustainable in law.<br /> According to the learned Senior Counsel, the demand proceeds on<br /> an erroneous interpretation of Clauses 2(a), 2(c) and 2(d) of the<br /> st<br /> Lease Deed dated 1 September 2006, in as much as under Clause<br /> 2(c), no construction work could commence until the plans and<br /> specifications were approved by the planning authority. It is<br /> therefore submitted that the timeline for completion of<br /> construction cannot be computed independent of such approvals.<br /> 34. The learned Senior Counsel further submits that the project<br /> contemplated construction of a Convention and Exhibition Centre<br /> and Commercial Complex as a composite development.<br /> Subsequent to the execution of the Lease Deed, Respondent No.1<br /> had allotted additional built-up area of 72,500 sq. mtrs. under the<br /> th<br /> Supplementary Lease Deed dated 13 July, 2007, and thereafter,<br /> further additional built-up area of 1,25,000 sq. mtrs. in the year<br /> 2012. The allotment of such additional built-up area required<br /> revision of the development plans and fresh statutory approvals<br /> Page 22 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> and therefore, the timelines originally contemplated under the<br /> st<br /> Lease Deed dated 1 September 2006 cannot be strictly applied to<br /> such construction.<br /> 35. The learned Senior Counsel further has submitted that the<br /> allotment of additional built-up area was unconditional and<br /> Respondent No.1 had itself clarified that there would be no time<br /> limit for construction of such additional built-up area. Therefore,<br /> by granting such additional development rights during the<br /> subsistence of the Lease Deed, Respondent No.1 must be deemed<br /> to have waived the condition relating to completion of<br /> construction within four years. <br /> 36. It is also submitted that the development of the project was<br /> affected by the order of injunction passed by this Court in Writ<br /> Petition No.1165 of 2007, which restrained utilization of a portion<br /> th<br /> of the additional built-up area until 12 March 2012. The<br /> Petitioners had requested Respondent No.1 to exclude the said<br /> period while computing the four-year period stipulated under the<br /> Lease Deed which was confirmed by the Respondent No. 1 vide<br /> st<br /> communication dated 1 February 2012. As such, such time line<br /> cannot be enforced.<br /> Page 23 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> 37. The Senior Counsel has further submitted that the project<br /> required several statutory approvals from various authorities<br /> including environmental clearance, aviation height clearance,<br /> approval of the High-Rise Committee and permissions from the<br /> Municipal Corporation of Greater Mumbai. According to the<br /> Petitioner, these approvals were obtained over a period of time<br /> and the commencement certificate for the integrated project was<br /> eventually issued only in the year 2014. The learned Senior<br /> Counsel therefore submits that the period of four years<br /> contemplated under Clause 2(d) of the Lease Deed must be<br /> construed in a commercially reasonable manner and the same<br /> must be computed only after approval of the development plans<br /> and issuance of the necessary commencement certificates.<br /> 38. The learned Senior Counsel has further argued that the<br /> Respondent No.1 had itself recognized the practical difficulties<br /> faced by developers in completing construction within four years<br /> th th<br /> and at its 138 Meeting held on 26 August 2015, resolved to<br /> amend the standard form of lease by extending the period for<br /> completion of construction from four years to six years. According<br /> to the Petitioner’s Counsel, restricting the benefit of the said<br /> Page 24 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> th<br /> decision only to leases executed after 26 August 2015 would be<br /> arbitrary and discriminatory, since all developers in Bandra-Kurla<br /> Complex are required to obtain similar statutory approvals. It is,<br /> therefore, contended that the impugned action of the Respondent<br /> No.1 violates Article 14 of the Constitution of India.<br /> 39. To sum up his arguments, the learned Senior Counsel has<br /> submitted that the present case is squarely covered by the decision<br /> of this Court rendered in the case of Raghuleela Builders Pvt. Ltd.<br /> & Anr vs. MMRDA & Ors. , whereby in identical fact situation and<br /> similar circumstances, this Court, by interpreting similar clauses in<br /> the lease deed, has held that the demand of additional premium<br /> on account of delay in completing the construction was arbitrary<br /> and illegal and, accordingly struck down such demand. <br /> 40. Dr. Birendra Saraf, learned Senior Counsel appearing for the<br /> Respondent Nos.1 and 2,on the other hand, has opposed the<br /> prayer made in the Writ Petition and has also questioned the<br /> maintainability of the Writ Petition by contending that the dispute<br /> between the parties arise out of contractual obligations contained<br /> in the Lease Deed and the Supplementary Lease Deed and the<br /> same involves several disputed questions of fact which cannot be<br /> Page 25 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> adjudicated in a writ petition in exercise of jurisdiction under<br /> Article 226 of the Constitution of India. He has further argued that<br /> the Writ Petition is hit by delay and laches and the relief prayed<br /> for is also barred by limitation. According to Dr. Saraf, , since the<br /> Petitioner had earlier sought extension of time for completion of<br /> construction and had not challenged the communications issued<br /> by Respondent No.1 at the relevant time, hence, the challenge<br /> made to such demand notices is not maintainable at this point of<br /> time. <br /> 41. The learned Senior Counsel for the Respondents has further<br /> argued that the recovery sought by Respondent No.1 is strictly in<br /> accordance with the provisions of the MMRDA Act, the MMRDA<br /> (Disposal of Land) Regulations, 1977 as well as the terms and<br /> conditions of the Lease Deed executed by and between the parties.<br /> According to learned counsel, the clauses contained in the Lease<br /> Deed are statutory in nature. Therefore, under Article 2(e),<br /> extension of time for completion of construction can be granted<br /> only upon payment of additional premium at the prescribed rates<br /> which cannot be waived even by the MMRDA. <br /> Page 26 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> 42. Dr. Saraf has further argued that the Petitioner had<br /> furnished undertakings promising to pay the amount of additional<br /> premium for the delay in completing the construction. Therefore,<br /> the Petitioner cannot now resile from such promise.<br /> 43. The learned Senior Counsel for the Respondents has also<br /> argued that the reliance placed by the Petitioner on the judgment<br /> in Raghuleela Builders Pvt. Ltd. & Anr. (Supra) is misplaced in as<br /> mush as the said decision was rendered in the peculiar facts of<br /> that case. <br /> 44. To sum up his arguments, Dr. Saraf has submitted that the<br /> Petitioners have approached this Court without disclosing material<br /> facts and producing the relevant documents. Since they have<br /> approached this court with unclean hands, hence, the Petitioners<br /> are not entitled to any relief from the court of equity. As such, the<br /> Writ Petition be dismissed. <br /> 45. In support of his above arguments, Dr. Saraf, has relied<br /> upon the following decisions:-<br /> 1<br /> (a) State of Punjab and Ors. vs. Dhanjit Singh Sandhu<br /> <b>1</b><br /> (2014) 15 SCC 144.<br /> Page 27 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> (b) Atur Park-4 Co operative Housing Society Ltd. vs<br /> 2<br /> State of Maharashtra<br /> 3<br /> (c) State of Goa vs. Dr. Alvaro Alberto Mousinho<br /> Plea regarding Maintainability of the Writ Petition :-<br /> 46. Insofar as the plea regarding maintainability of the Writ<br /> Petition is concerned, at the very outset, it deserves to be<br /> mentioned herein that although the maintainability of the Writ<br /> Petition has been questioned inter-alia on the ground that several<br /> disputed questions of facts are involved there-in, yet, after<br /> examining the record, we find that the material assertions made in<br /> the Writ Petition are all based on documents annexed thereto,<br /> which are admitted documents. Moreover, in view of the plea<br /> raised by the Petitioner that the action of the Respondent No. 1 in<br /> levying additional premium/penalty for the delay in completion of<br /> construction is not only contrary to the terms and conditions of<br /> the Lease Deed, but also, arbitrary and illegal and hence, in<br /> violation of the fundamental rights guaranteed to the Petitioner<br /> under Article 14 of the Constitution, we are of the view that the<br /> <b>2</b><br /> 2023 SCC Online Bom 874.<br /> <b>3</b><br /> (2019) 10 SCC 465.<br /> Page 28 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> issues raised in the Writ Petition have an element of public law<br /> character.<br /> 47. In the case of Joshi Technologies International IBC vs. U.O.I.<br /> & Ors. , the Hon’ble Supreme Court has observed that there is no<br /> absolute bar to the maintainability of a Writ Petition, even in<br /> contractual matters or where there are disputed questions of fact<br /> or even when monitory claim is raised, provided, the Court is<br /> called upon to examine the issue which has a public law character<br /> attached to it. Having regard to the core controversy involved in<br /> this proceeding and considering the fact that the issues involved in<br /> this Writ Petition would call for determination by this Court based<br /> on interpretation of the relevant Articles of the Lease Agreement<br /> as well as the documents exchanged by and between the parties so<br /> as to ascertain fairness in the action of the Respondent No 1, we<br /> are unable to agree with the stand of the Respondents that the<br /> Writ Petition ought to be dismissed on the ground that it raises<br /> disputed questions of facts. <br /> 48. Likewise, from a reading of Section 44 of the MMRDA, Act<br /> 1974, we find that the provision for Appeal provided thereunder,<br /> is available for disputes regarding recovery of money due to the<br /> Page 29 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> authority as arrears of land revenue. Since the challenge made to<br /> the impugned demand notice is on the ground that the same is<br /> contrary to the terms of the Supplementary Lease Deed and hence,<br /> illegal and arbitrary as such, we are of the opinion that the said<br /> controversy cannot be effectively adjudicated in an Appeal filed<br /> under Section 44. Therefore, we reject the contention of the<br /> Respondents that the Petitioner has an effective and efficacious<br /> alternative remedy.<br /> 49. We also find that all material facts necessary for<br /> appreciating the controversy have been disclosed in the Writ<br /> Petition. Therefore, we are of the view that the Writ Petition<br /> cannot also be dismissed on account of suppression of material<br /> facts as well.<br /> 50. In so far as the grounds of delay and laches as well as the<br /> plea of the claim being barred by the Law of Limitations is<br /> concerned, save and except making a bald assertion on such count<br /> the Respondents have failed to mention as to on which date the<br /> cause of action for the petitioner to institute the proceeding had<br /> ceased and on what count. There is also no oral argument<br /> advanced to that effect. <br /> Page 30 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> 51. In Banda Development Authority, Banda vs. Motilal Agarwal<br /> 4<br /> & Ors. the Hon’ble Supreme Court has observed that no limitation<br /> has been prescribed for filing a Writ Petition under Article 226 of<br /> the Constitution of India. However, the High Court will treat the<br /> delay in filing the Writ Petition as unreasonable, if the same is<br /> filed beyond the period of limitation prescribed for filing a Civil<br /> Suit for a similar cause. From the above, it would be apparent that<br /> although un-explained delay in instituting a Writ Petition could be<br /> a valid ground to decline relief to the Petitioner, yet, the law of<br /> Limitation would not have strict application in a Writ Petition. <br /> 52. There is no dispute in this case about the fact that the<br /> Respondent No. 1 is an instrumentality of the State and, therefore,<br /> would be an “other authority” within the meaning of Article 12 of<br /> the Constitution of India. <br /> 53. Law is well settled that arbitrariness in the decision making<br /> process of the State or its instrumentality is a facet of Article 14 of<br /> 5<br /> the Constitution of India. In E.P..Royappa v State of Tamil Nadu , it<br /> was pointed out that Article 14 would strike at arbitrariness in<br /> State action and ensure fairness and equality of treatment. <br /> <b>4</b><br /> (2011) 5 SCC 394.<br /> <b>5</b><br /> (1974) 4 SCC 3.<br /> Page 31 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> 54. The present is not a proceeding simpliciter for enforcing a<br /> money claim but raises significant questions pertaining to the<br /> validity and fairness in the impugned action of the Respondent No<br /> 1, which are required to be adjudicated on the touch stone of<br /> Article 14. As such, we are of the considered opinion that such<br /> plea cannot be brushed aside merely on the ground of delay and<br /> laches, more so, since such delay has evidently not given rise to<br /> any parallel right of a third party. <br /> 55. In view of the foregoing discussions, we are of the view that<br /> the Writ Petition is maintainable in law as well as in the facts and<br /> circumstances of the case. <br /> 56. It would be further pertinent to note herein that in an<br /> earlier decision rendered by a co-ordinate Bench of this Court<br /> th<br /> dated 20 November 2019 in Raghuleela Builders Pvt. Limited<br /> and Anr. vs. The Mumbai Metropolitan Regional Development<br /> Authority & Ors. (Supra) wherein, identical issues were involved,<br /> this Court had entertained the Writ Petition. In that case also the<br /> th<br /> Petitioners had challenged a similar Demand Notice dated 12<br /> September 2017 issued by the Respondent No.1, by invoking<br /> similar provisions of the Lease Deed as well as the Supplementary<br /> Page 32 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> Lease Deed, demanding payment of a sum of Rs. 432 Crores as<br /> penalty for the delay in completion of construction of the building.<br /> That was also a case wherein, although the initial built up area<br /> was 30550 sq. meters, which was to be consumed by constructing<br /> 9 (nine) floors in the building, yet, subsequently, due to the<br /> increase in the FSI, the Respondent No.1 had allotted additional<br /> built up area of 67000 sq. meters to the Petitioner resulting in<br /> construction of 11 additional floors in the same building. Due to<br /> the addition in the built up area, the construction of the building<br /> could not be completed within four years, as stipulated in Article<br /> 2(d) of the original Lease Deed, as a result of which, Demand<br /> th<br /> Notice dated 12 September 2017 was served for recovery of<br /> penalty/additional premium along with interest calculated<br /> thereon. <br /> th<br /> 57. By the Judgment and Order dated 20 November 2019, in<br /> Raghuleela Builders Pvt. Ltd. & Anr. (Supra), the Division Bench<br /> th<br /> had set aside the impugned Demand Notice dated 12 September<br /> 2017 by holding that such a demand was not maintainable in the<br /> eyes of law. That apart, it was also observed that in view of the<br /> change in policy of the MMRDA increasing the time limit for<br /> Page 33 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> completion of the building “Fit for occupation”, from four years to<br /> six years, the demand for penalty/additional premium for delay in<br /> completion of construction within four years was ex-facie<br /> unreasonable, unjustified and discriminatory. <br /> 58. The Special Leave Petition (C) No. 6411 of 2020 preferred<br /> by the Respondent No.1 assailing the Judgment and Order dated<br /> th<br /> 20 November 2019 was dismissed by the Hon’ble Supreme Court<br /> th<br /> by the order dated 27 July 2020 after taking note of the findings<br /> recorded in paragraphs No. 38 and 40 of the Judgment and Order<br /> th<br /> dated 20 November 2019. However, it was clarified that since the<br /> judgment of the Division Bench of the Bombay High Court was<br /> rendered in the facts of that case, hence, it cannot influence any<br /> other matter in this behalf. With the above observation the Special<br /> Leave Petition was dismissed. <br /> th<br /> 59. In the order dated 27 July 2020 the Hon’ble Supreme<br /> Court, while dismissing the Special Leave to Appeal (C) No(s)<br /> 6411/2020, had observed as follows:-<br /> “We are not inclined to exercise our jurisdiction under Article<br /> 136 of the Constitution of India in the given facts of the case and<br /> more so as reflected from paragraphs 38 and 40 of the<br /> impugned judgment.<br /> Page 34 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> Mr. K. K. Venugopal, learned Attorney General for India<br /> expresses some apprehension on account of there being other<br /> matters pending.<br /> We clarify that the present matter is in the given facts of<br /> the case as stated aforesaid and thus, cannot be said to influence<br /> any other matter in this behalf. <br /> The special leave petition is dismissed in terms aforesaid.<br /> Pending applications shall also stand disposed of.”<br /> 60. It appears that the Respondent No. 1 had filed a Review<br /> th<br /> Petition seeking review of the order dated 27 July 2020, which<br /> was also dismissed by the Hon’ble Supreme Court vide order<br /> th<br /> dated 29 September 2020 passed in Review Petition (Civil) No.<br /> 1764 of 2020 arising out of SLP (C) No. 6411 of 2020.<br /> 61. From a plain reading of the decision rendered in Raghuleela<br /> Builders Pvt. Ltd. & Anr. (Supra) we are of the opinion that, even<br /> if the said decision is treated to have been rendered in the fact<br /> situation of that case, even then, we can take note of the legal<br /> principles emanating therefrom. In that view of the matter we are<br /> unable to agree with the submission of the learned Counsel for the<br /> Respondents that the decision in the case of Raghuleela Builders<br /> Pvt. Ltd. & Anr. (Supra) cannot be looked into by this Court even<br /> for the purpose of deciding the question of maintainability of the<br /> Writ Petition. <br /> Page 35 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> 62. It is to be noted herein that the question of<br /> maintainability of a Writ Petition is a mixed question of law<br /> and facts. Therefore, such question would obviously have to<br /> be considered having due regard to the peculiar facts and<br /> circumstances of each case. Having regard to the facts and<br /> circumstances of this case and considering the fact that a<br /> similar Writ Petition, raising similar issues in Raghuleela<br /> Builders Pvt. Ltd. & Anr. (Supra) had earlier been entertained<br /> by this Court, for the sake of maintaining uniformity in<br /> judicial decisions, we are not inclined to non-suit the Writ<br /> Petitioner merely on the plea of maintainability as raised by<br /> the Respondents. <br /> On Merits:-<br /> 63. During the Course of arguments, the learned Counsel for<br /> the Respondents has made it clear that the demand for additional<br /> penalty on account of delay in completing the construction had<br /> been raised by the Respondent No.1 in deference to Article 2(d) &<br /> st<br /> (e) of the Lease Deed dated 1 September 2006 which is as per<br /> Form ‘D’ of Regulation No 10 of the Mumbai Metropolitan Region<br /> Page 36 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> Development Authority (Disposal of Land) Regulations, 1977.<br /> Therefore, the question as to whether such a claim /demand of<br /> the Respondent No. 1 for payment of additional premium/ penalty<br /> on account of delay in completing the construction was<br /> maintainable in the eyes of law as well as in the facts and<br /> circumstances of the case would undoubtedly have to be answered<br /> by this court in the light of materials brought on record and by<br /> constructing the relevant clauses of the Lease Agreement. For the<br /> st<br /> above purpose Articles 2 (d) and (e) of the Lease Deed dated 1<br /> September 2006 would be relevant and therefore, the same are<br /> being reproduced herein-below for ready reference:-<br /> “(d) Time limits for commencement and completion of<br /> construction work: That the Lessee shall within three months<br /> from the receipt of approval of its plans and specifications of<br /> building or buildings intended to be erected on the said plot of<br /> land, commence and within a period of four years from the<br /> date of this lease at his own expense and in a substantial and<br /> workman like manner and with the sound materials and in<br /> compliance with the said Development Control Regulations<br /> and Building Regulations and all Municipal Rules, bye-laws<br /> and Regulations applicable hereto and in strict accordance<br /> with the approved plans, elevations, sections, specifications<br /> and details as specified in the Section 5, 6 & 8 of the said RFP<br /> and the said allotment letter, to the satisfaction of the<br /> Metropolitan Commissioner and conforming to the Bandra-<br /> Kurla Complex Notified Area, Development Control<br /> Regulations, 1979 & all other relevant Rules, Regulations &<br /> Acts and further as provided in Section 5 of the said RFP and<br /> the said allotment letter, build and completely finish fit for<br /> occupation a (i) “Convention & Exhibition Centre” and (ii)<br /> “Commercial Complex”to be used as (i) “Convention &<br /> Exhibition Centre” and (ii) “Commercial Complex” with all<br /> requisite drains and other proper conveniences thereto.<br /> Page 37 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> PROVIDED THAT the construction of Convention and<br /> Exhibition Centre will be commenced before the<br /> commencement of construction of Commercial Complex and<br /> Occupation Certificate of Convention and Exhibition Centre<br /> (65000 sq. mtr. shall be obtained prior to the request for<br /> Occupation Certificate of Commercial Complex (50000 sq.<br /> mtr) as set out in the said RFP and the said allotment letter<br /> the Lessee shall scrupulously observe the approved Work<br /> Execution Plan (copy Whereof is set out in the SIXTH<br /> SCHEDULE hereunder written).<br /> PROVIDED FURTHER THAT as set out in the said<br /> allotment letter, the Lessee shall submit the periodic progress<br /> report of the Convention and Exhibition Center say in the first<br /> week of every third month to the Metropolitan Commissioner,<br /> Mumbai Metropolitan Region Development Authority. The<br /> Evaluation Committee appointed by the Metropolitan<br /> Commissioner as referred in the Proviso to clause (a)<br /> hereinabove, will review the progress of the development of<br /> Convention Center report by the Lessee and submit its report<br /> to the Metropolitan Commissioner. The Evaluation Committee<br /> as indicated above will satisfy itself regarding the development<br /> of the Convention and Exhibition Center which has to be of<br /> international standards and if necessary the Evaluation<br /> Committee will make suggestions in that respect to the<br /> Metropolitan Commissioner and the Lessee shall incorporate<br /> changes so directed by the Metropolitan Commissioner.’<br /> (e) Extension of time stipulated for construction of<br /> building or development of land:<br /> (i) If the Lessee shall not perform and observe the<br /> limitations of the time mentioned in clause 2 (d) above<br /> for construction of the intended (i) “Convention &<br /> Exhibition Centre” on plot of land admeasuring 55000<br /> sq. mtr. and (ii) “Commercial Complex” on plot of land<br /> admeasuring 20000 sq. mtr. or otherwise development<br /> of said plot of land leased to him for reasons beyond<br /> his control, the Metropolitan Commissioner may<br /> permit extension of such time on payment of additional<br /> premium at the following rates:<br /> Up to 1 year _____ 25 percent of the<br /> respective premium paid<br /> for “Convention &<br /> Exhibition Centre” and<br /> “Commercial Complex”<br /> Page 38 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> Between 1 and 2 years___ 35 percent of the<br /> respective premium paid<br /> for “Convention &<br /> Exhibition Centre” and<br /> “Commercial Complex”<br /> Between 2 and 3 years ___ 40 percent of the<br /> respective premium paid<br /> for “Convention Exhibition<br /> Centre” and “Commercial<br /> Complex”<br /> (ii) If the Metropolitan Commissioner shall refuse to<br /> permit such extension of time or shall find the Lessee<br /> of having committed breach of any condition or<br /> covenant during limitation of time mentioned in clause<br /> 2(d) hereto before Metropolitan Commissioner may<br /> forfeit and determine the Lease: provided that in the<br /> event of such determination of lease 25 percent of the<br /> premium paid by the Lessee to the Lessor shall stand<br /> forfeited and the the remaining 75 percent of such<br /> premium shall be refunded to him; provided further<br /> that the power to so determine the Lease shall not be<br /> exercised unless and until the Metropolitan<br /> Commissioner shall be given to the Lessee or left on<br /> some part of the demised premises a nonce in writing<br /> of his intention to do so and of specific breach of the<br /> covenant or condition in respect of which forfeiture is<br /> intended and default shall have been made by the<br /> Lessee in remedying such breach within three months<br /> from the service of notice on him or the notice being<br /> left on the demised premises.”<br /> th<br /> 64. Article 2 of the Supplementary Lease Deed dated 13 July<br /> 2007 mentions that the incremental premises agreed to be<br /> constructed shall be deemed to be integral part of the demised<br /> st<br /> premise defined in Lease Deed dated 1 September 2006. Article 2<br /> reads as follows :-<br /> “2. It is here by agreed and declared by and<br /> between the parties hereto that all the conditions<br /> and covenants including the term of the lease as<br /> Page 39 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> contained in the said Deed of Lease shall be deemed<br /> to be incorporated herein and shall regulate the<br /> lease hereby granted. It is further agreed and<br /> declared by the parties hereto that the incremental<br /> premises hereby agreed to be constructed and to be<br /> leased by the lessor to the lessee shall be deemed to<br /> be the integral part of demised premises as defined<br /> st<br /> in the said Deed of Lease dated 1 September 2006<br /> and annexed hereto as ANNEXURE.”<br /> 65. At the very out set it must be noted here-in that as per<br /> Article 2(d) the lessee is required to complete the construction<br /> within four years from the date of execution of the lease deed.<br /> However, Article 2 (c) of the Lease Deed makes it clear that no<br /> work shall commence or be carried out contrary to the<br /> Development Control Regulations and the Building Regulations<br /> applicable to the plot of land and until the plans, elevations,<br /> sections, specifications and details shall have been approved.<br /> Therefore, in view of Article 2(c), the construction no construction<br /> can commence until all statutory approvals including the approval<br /> of building plan etc. are received. Article 2(a) of the Lease Deed<br /> mentions that the lessee shall, within three months, submit plans<br /> etc. for approval. However, there is no condition in the Lease Deed<br /> laying down any time line for granting of such approval by the<br /> Respondent No. 1.<br /> Page 40 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> 66. In a construction of this nature, permission of multiple<br /> statutory authorities including the Municipal Corporation, Fire<br /> department, Environment clearance, height clearance etc. will be<br /> necessary, without which even the Commencement Certificate<br /> cannot be issued. Unless the Commencement Certificate is issued,<br /> the construction work cannot commence. These statutory<br /> authorities are not bound by the terms and conditions of the Lease<br /> Agreement. Notwithstanding the same, the Lease Agreement is<br /> completely silent as to who will be responsible in case of delay in<br /> granting approval by these Statutory Authorities, coming in the<br /> way of early commencement and completion of the construction. <br /> 67. Not only that, the Lease Deed is also silent as to what would<br /> be the effect on the time line of four years for completion of the<br /> construction, as laid down in Article 2(d) in case, there is delay in<br /> granting of statutory approvals. As such, if there is delay in<br /> granting permissions/ approval by the statutory authorities for any<br /> reason whatsoever, leading to delay in commencement of<br /> construction, then in that event, the Lessee will be left with no<br /> scope to complete the construction within the stipulated time, that<br /> too, for no fault on its part. Notwithstanding the same, as per<br /> Page 41 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> Article 2(d), as interpreted by the Respondent No 1, the lessee<br /> would still be liable to pay penalty for the delay in completing the<br /> construction beyond the period of four years from the date of<br /> execution of the Lease Deed. Viewed from that perspective, Article<br /> 2(d) of the Lease Deed appears to be ex-facie unfair, unreasonable<br /> and hence, unconscionable. However, since the Articles of the<br /> Lease Deed are not under challenge, hence, the said aspect of the<br /> matter need not detain this Court. <br /> 68. As has been noted hereinabove, the initial built-up area,<br /> st<br /> which is the subject matter of Lease Deed dated 1 September<br /> 2006, was only 65,000 sq. mtrs. for the Convention & Exhibition<br /> Centre and 50,000 sq.mtrs for the Commercial Complex, totaling<br /> to 1,15,000 sq.mtrs. Article 2(d) of the Lease Deed providing four<br /> years’ time limit for completing the construction would, therefore,<br /> apply to the 1,15,000 sq. mtrs of built up area. <br /> st<br /> 69. Subsequent to the execution of the Lease Deed dated 1<br /> September 2006, there was increase in the FSI leading to<br /> allotment of additional built-up area of 72,500 sq. mtrs to the<br /> Petitioner. This 72,500 sq. mtrs was not within the ambit of the<br /> st<br /> original Lease Deed dated 1 September 2006. As such, the<br /> Page 42 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> th<br /> Supplementary Lease Deed 13 July 2007 had to be executed.<br /> th<br /> However, as had been noted above, soon thereafter, i.e. on 15<br /> October 2007, an interim order was passed by this High Court in<br /> Writ Petition No. 1165 of 2007 which had affected the<br /> construction work, at least in sofar as 31,500 sq. mtrs pertaining<br /> to the Commercial Complex is concerned. The aforesaid stay order<br /> th<br /> remained in force until 12 March 2012. Therefore, although a<br /> th<br /> plinth Commencement Certificate (CC) was issued on 12 June<br /> 2008 permitting construction upto the plinth level, yet, in view of<br /> the composite design of the Convention & Exhibition Centre as<br /> well as the Commercial Complex, having common foundation and<br /> basement, the Petitioner could not commence construction due to<br /> the operation of the stay order. The said fact was also informed to<br /> th<br /> the Respondent No. 1 vide communication dated 28 January<br /> 2009. <br /> 70. From the statements made in the Writ Petition and from the<br /> examination of various documents on record, including EIA<br /> th<br /> Certificate dated 26 June 2013 as well as Article 2 of the<br /> th<br /> Supplementary Lease Deed dated 13 July 2007, it is evident that<br /> although the area of 72,500 sq. mtrs was allotted subsequently,<br /> Page 43 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> yet, it was treated as an integral part of the construction to be<br /> carried out with the original built up area.<br /> th<br /> 71. The Writ Petition No. 1165 of 2007 was withdrawn on 12<br /> th<br /> March 2012. As such, on 20 Mach 2012, i.e., after the<br /> withdrawal of the Writ Petition No. 1165 of 2007, the Respondent<br /> No. 1 had approved the allotment of additional 1,00,000 sq. mtrs<br /> rd<br /> to the Petitioner and, thereafter, on 3 April 2012, another 25,000<br /> sq. mtrs was allotted thus, increasing the total allotment of built-<br /> up area upto 3,12,500 sq. mtrs. The Commencement Certificate<br /> upto the seventh floor level pertaining to the 3,12,500 sq. mtrs<br /> th<br /> was issued only on 16 April 2014.<br /> 72. In a composite construction of this nature involving complex<br /> layouts, warranting multiple Commencement Certificates to be<br /> issued by the Respondent No. 1, it is inconceivable that the Lessee<br /> would adhered to two different timelines for construction of the<br /> original allotment and the additional built-up area, the<br /> construction whereof is to be carried out over the same plot and in<br /> respect of the same construction. Since the construction in this<br /> case was evidently and admittedly not severeable in nature,<br /> Page 44 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> therefore, we cannot but hold that there could only be one date of<br /> completion of the entire building “fit for occupation”. <br /> 73. In view of the above discussion, we are also of the opinion<br /> that although a plinth Commencement Certificate was issued on<br /> th<br /> 12 June 2008 granting permission to complete the construction<br /> only upto the plinth level, yet, in view of the pending Court<br /> th<br /> proceeding, and operation of the interim order dated 15 October<br /> 2007 such certificate was not capable of being acted upon and,<br /> accordingly, was also not acted upon by the Petitioner. Thereafter,<br /> the Commencement Certificate for the entire building came to be<br /> th<br /> issued on 16 April 2014. Therefore, commencement of<br /> construction only took place pursuant to the issuance of the<br /> th<br /> Commencement Certificate dated 16 April 2014.<br /> 74. We also find from the materials on record that in view of<br /> th<br /> the long continuation of the interim order dated 15 October<br /> 2007, the Petitioner wanted to surrender the additional built-up<br /> area of 72,500 sq. mtrs under the Supplementary Lease Deed<br /> th<br /> dated 13 July 2007 but the said proposal was declined by the<br /> th<br /> Respondent No. 1. On the contrary, on 8 November 2011, the<br /> Respondent No. 1 had issued a communication categorically<br /> Page 45 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> representing that there would be “no time-limit” for construction<br /> of the additional built-up area.<br /> st<br /> 75. Further, by the communication dated 1 February 2012, the<br /> Respondent No. 1 had also confirmed that the period, during<br /> which, the stay order passed by the Court was in force, shall not<br /> be counted for computing the time-limit of four years. <br /> th<br /> 76. The reflections made in the communication dated 8<br /> st<br /> November 2011 as well as 1 February 2012, in our opinion,<br /> clearly holds out a promise to the Petitioner by the Respondent No<br /> 1, based on which, the Petitioner had altered its position. Under<br /> such circumstance, the Respondent No. 1 cannot subsequently<br /> resile from such promise. Therefore, any action on the part of the<br /> Respondents to act contrary to the reflection made in the letters<br /> th st<br /> dated 8 November 2011 and 1 February 2012 prejudicially<br /> affecting the interest of the Petitioner would be hit by the doctrine<br /> of promissory estoppel and hence, would be liable to be interfered<br /> with by this court. (See Motilal Padampat Sugar Mills Co. Ltd. vs.<br /> 6<br /> State of Uttar Pradesh & Ors).<br /> <b>6</b><br /> (1979) 2 SCC 409.<br /> Page 46 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> 77. It would be significant to note here-in that it is not a case<br /> where the construction was delayed due to negligence on the part<br /> of the Lessee. On the contrary, it appears from the materials on<br /> record that the construction was delayed due to delay in issuance<br /> of statutory approvals including environment clearance. Since<br /> even as per the terms and conditions of the Lease Deed, the<br /> construction cannot commence without the approval of the plan<br /> and issuance of the Commencement Certificate, hence, by a<br /> reasonable and harmonious construction of the Articles of the<br /> Lease Deed, we hold that, in such a case, the time line of four<br /> years for completing the construction under Article 2(d) ought to<br /> be computed from the date of issuance of the Commencement<br /> Certificate and not from any prior date.<br /> 78. Having regard to the facts and circumstances of this case,<br /> we find that even the condition precedent for invoking the Article<br /> st<br /> 2(d) of the Lease Deed dated 1 September 2006 was not met in<br /> this case in as much as the construction of the original built-up<br /> area was evidently completed by the Petitioner within the period<br /> of four years from the date of issuance of the Commencement<br /> th<br /> Certificate i.e. 14 April 2014 by the Respondent No. 1 after<br /> Page 47 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> excluding the period during which the interim order passed by the<br /> High Court was in force. As such, viewed from that angle also, in<br /> our opinion, there was no legal justification for the Respondent<br /> No.1 to insist on additional premium/penalty from the Petitioner<br /> under Article 2(d) on account of alleged delay in completing of<br /> the construction beyond the period of four years.<br /> 79. In the above context, it would be relevant to note here-in<br /> that, even if the provision of Article 2(d) of the Lease Deed dated<br /> st<br /> 1 September 2006 is given full weightage, even then, the four<br /> years period for completing the construction reckoned from the<br /> th<br /> date of executions of the Lease Deed would expire on 30 August<br /> th<br /> 2010. The interim order passed by the Court on 15 October 2007<br /> th<br /> was vacated on 12 March 2012. Therefore, the said order had<br /> remained in force for a period of 4 (four) years 4(four) months<br /> and 26 (twenty six) days, i.e. 1610 days’ in total. If the said period<br /> is added to the completion period, then in that event, even under<br /> Article 2(d), the Petitioner would be entitled for 8 years, 4<br /> st<br /> months, 226 days’, with effect from 1 September 2006, to<br /> complete the construction without seeking extension of time. In<br /> view of the determination made here-in above, such period of 8<br /> Page 48 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> th<br /> years 4 months 26 days will have to be counted from 14<br /> April,2014 i.e the date on which the first effective Commencement<br /> Certificate facilitating the commencement of construction of the<br /> building was issued. If that be so, by such interpretation of the<br /> Clauses of the Contract, we are of the view that the time available<br /> to the Petitioner to complete the construction of the initial built up<br /> area, without seeking extension of time, would be till August<br /> 2022. In so far as the additional built up area is concerned, in<br /> th<br /> view of the communication dated 8 November 2011, there would<br /> be no time restriction applicable for completing the construction<br /> of the additional built up area. As such, the question of seeking<br /> time extension for completing the construction of the additional<br /> built up area would not at all arise in the eyes of law. <br /> 80. After a careful examination of the documents brought on<br /> record, we find that there is no clarity as to on which date the<br /> construction of the entire built-up area of 3,12,500 sq. mtrs was<br /> actually completed by the Petitioner. The impugned Notice dated<br /> th<br /> 12 September 2017 which had imposed additional premium/<br /> penalty upon the Petitioner for delay of 7 years 12 days in<br /> completing the construction also does not furnish any relevant<br /> Page 49 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> particulars in support of the above allegation. The said notice also<br /> appears to be totally vague as regards basis for arriving at the<br /> conclusion that there was 7 years 12 days delay. It is also not<br /> clear, if the penalty was applied for the alleged delay in<br /> completing the construction of the total built-up area including<br /> the Additional Built-up Area or any part thereof. <br /> 81. Be that as it may, if the projection made by the Respondent<br /> th<br /> No. 1 in the impugned notice dated 12 September 2017 is taken<br /> into account on their face value, even then, if such delay has been<br /> th<br /> computed with effect from 30 August 2010 i.e. on expiry of 4<br /> st<br /> years from the date of execution of the Lease Deed dated 1<br /> September 2006, the question of delay of seven years twelve days<br /> by excluding the period during which the interim order of the<br /> court was operating, would not arise in this case. We say so<br /> because there was substantial delay in granting statutory<br /> approvals and Commencement Certificate which period, in our<br /> view, would also have to be added to the time available to the<br /> Petitioner to complete the construction. <br /> 82. It is pertinent to note herein that the Respondent No. 1 had<br /> made recovery of substantial amount from the Petitioner as<br /> Page 50 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:21 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> additional premium/penalty for delay in completion of<br /> construction. However, a transparent procedure valid in the eyes<br /> of law has not been followed in the matter. This we say so because<br /> the Respondent No. 1 had never served any default notice to the<br /> Petitioner intimating that it would be liable to pay penalty due to<br /> delay and completion of construction. There was also no notice<br /> ever served upon the Petitioner indicating as to on which date, the<br /> four years period mentioned in Article 2(d) of the Lease Deed<br /> st<br /> dated 1 September 2006, would come to an end. Such prior<br /> notice, in our opinion, was sine- qua- non in view of the<br /> intervening developments in the matter , particularly the<br /> operation of the interim order passed by this Court. Before<br /> demanding and/or recovering the amount of penalty, no Show<br /> Cause Notice was also required to be served upon the Petitioner<br /> giving it an opportunity to show cause as to why such penalty<br /> should not be recovered by the Respondents. However, no such<br /> notice was served. Therefore, the entire process of recovery, in our<br /> view, was not only conducted in a completely arbitrary, whimsical<br /> and capricious manner but the same was also in violation of the<br /> principles of natural justice. <br /> Page 51 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:21 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> 83. It must be borne in mind then that in a matter of this nature<br /> where penalty is sought to be levied alleging default committed by<br /> a party, unless allegation is admitted, the recovery of penalty<br /> cannot be based on mere ipse dixit of the authority more so, if the<br /> controversy arises out of implementation of terms and conditions<br /> of a contract wherein the authority itself is a party. In such<br /> matters, the recovery would be permissible only after that<br /> controversy is resolved in accordance with the law. <br /> 84. In the above context, it would be pertinent to mention<br /> herein that even as per Rule 11(A) of the MMRDA (Disposal of<br /> Lands) Regulations 1977, no action to determine the lease could<br /> be initiated by the Metropolitan Commissioner without serving<br /> prior notice as regards specific breach of the covenants and<br /> conditions in respect of which, default has been alleged. <br /> 85. In so far as the undertaking given by the Petitioner to pay<br /> the additional premium/penalty and the consequent deposit of the<br /> amount of Rs 646,77,68,594 /- is concerned, it must be noted<br /> herein that the Writ Petitioner had not only objected to the<br /> demand for payment of additional premium/penalty for the<br /> alleged delay in completing the construction but had also<br /> Page 52 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:21 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> deposited the amount under protest, thereby, categorically<br /> conveying that the deposit was not made voluntarily or in<br /> discharge of its contractual obligation. Such protest was not only<br /> raised contemporaneously but the same was also in writing and<br /> unambiguous in nature, thus, putting the Respondent No. 1 on<br /> clear notice that the Petitioner has not accepted the decision in<br /> principle.<br /> 86. It also appears from the materials on record that apparently<br /> due to the pressure mounted by the Respondent No. 1 demanding<br /> payment of additional premium/penalty, the Petitioner was<br /> compelled to deposit the penalty as otherwise the Petitioner would<br /> not only be prevented from obtaining the Occupation Certificate<br /> thus, causing serious economical prejudice to its interest but the<br /> same would also expose the Petitioner to the risk of termination of<br /> the Lease. Since the Petitioner had evidently made the deposit of<br /> penalty under duress and under compelling circumstances, hence,<br /> the principles of waiver, estoppel and acquiescence would not<br /> operate against the Petitioner in this case. From the protest raised<br /> by the Petitioner, it was apparent that the Petitioner had reserved<br /> its right to agitate the matter at an appropriate time, thus, keeping<br /> Page 53 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:21 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> the cause alive. Therefore, we hold that the claim for refund of the<br /> amount made by the Petitioner would not be barred under the law<br /> merely on account of the undertaking given by it.<br /> 87. Section 72 of the Indian Contract Act provides that a person<br /> who receives payment made by the payee under coercion must<br /> repay or return the same. <br /> 88. In Fatima Khatoon Chowdrain vs. Mahmoed Jan Chowdhury<br /> (1868) 12 Moo Ind App 65, the Privy Council has held that<br /> payment made not voluntarily but under species of compulsion<br /> would be liable to be returned.<br /> 89. In Valpy vs Manley (1845) 1 CP 594, the Court of England<br /> & Wales has held that money paid under the constraint of threats<br /> to interfere with the legal right is sufficient to make it recoverable.<br /> 90. In Ram Kishen Singh vs. Dooli Chand (1881) 8 IA 93 before<br /> the Privy Council, it was held that if a person pays money to save<br /> his property which has been wrongly attached in execution, he is<br /> entitled to recover it.<br /> Page 54 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:21 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> 91. Relying upon the case of Ram Kishen Singh (Supra), the<br /> Privy Council in the case of Kanhaya Lal vs The National Bank of<br /> 7<br /> India Limited has held that if a payment is made under protest<br /> and involuntarily, under coercion, the party making such payment<br /> would be entitled to claim refund of the same.<br /> 92. Materials on record unequivocally go to show that the<br /> deposit of penalty was dehors any proper demand raised in<br /> writing but was forced under the circumstances created by the<br /> Respondent No. 1, as noted above. Hence, by any stretch of<br /> reasonable reckoning, the deposit of the penalty as well as the<br /> undertaking, cannot be treated as voluntarily so as to prevent the<br /> Petitioner to seek refund of the amount in accordance with law. <br /> 93. In view of the foregoing discussion, we are of the un-<br /> hesitant opinion that the demand for payment of the<br /> penalty/additional premium for alleged delay in completing the<br /> construction was not maintainable under Article 2(d) & (e) of the<br /> Lease Deed. Moreover, such amount was realized by the<br /> Respondent No. 1 in a most arbitrary, high handed, unfair, and<br /> unreasonable manner by subjecting the Petitioner to undue<br /> <b>7</b><br /> 1913 SCC Online PC 4.<br /> Page 55 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:21 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> pressure and threat of termination of the Lease, thus putting its<br /> business interest in peril. The Petitioner was made to deposit the<br /> amount of penalty under coercion. The imposition of the penalty<br /> was also not preceded by proper Show Cause notice thus, acting in<br /> clear contravention of the principle of natural justice. Therefore,<br /> consequences under the law on such counts must follow.<br /> 94. In the case of State of Punjab and Ors. vs. Dhanjit Singh<br /> Sandhu (Supra) relied upon by Dr. Saraf, the allottees of the land<br /> had accepted the terms and conditions of the allotment letter and<br /> also took possession but they did not raise any construction within<br /> the specified time, as a result of which, due to violation of specific<br /> condition, the authority wanted to go for resumption of the plot.<br /> In that case, the allottees, after availing the benefit of extension,<br /> had later on demanded refund. It was in such context that the<br /> Apex Court has held that as per the doctrine of “ approbate and<br /> reprobate ” a party cannot be permitted to “ blow hot and cold” at<br /> the same time. In Atur Park-4 Co operative Housing Society Ltd. vs<br /> State of Maharashtra (Supra), the core question, as projected in<br /> paragraph 30, was as to whether, the Petitioner there-in could be<br /> the permitted to seek compensation and seek acquisition under<br /> Page 56 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:21 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> Fair Compensation Act for the land belonging to it which was<br /> affected by an adjoining road.In Dr Alvaro Alberto Mousinho De<br /> Noronha Ferreira (Supra), the controversy was as regards<br /> conversion of land from agricultural to non-agricultural land and<br /> the applicability of rates there-in. Therefore, the above decisions<br /> relied upon by Dr. Saraf in our view, are distinguishable on facts<br /> and as such, the same would not be of any assistance to the<br /> Respondents in the facts and circumstances of this case.<br /> 95. Having held as above, we deem it appropriate to record<br /> here-in that although the learned Counsel for the Petitioner has<br /> argued that this case is squarely covered by the decision rendered<br /> in Raghuleela Builders Pvt. Ltd. & Anr . (Supra),yet, the said<br /> assertion has been strongly contested by the Respondent’s Counsel<br /> by submitting that in view of the observations made by the<br /> th<br /> Hon’ble Supreme Court in the order dated 27 July 2020, no<br /> reliance can be placed on the said judgment on any count for the<br /> purpose of deciding the present Writ Petition. On a careful<br /> examination of the decision in Raghuleela Builders Pvt. Ltd. &<br /> Anr . (Supra) we also find that the said decision was rendered in<br /> the facts of that case. However, it is important to note here-in that<br /> Page 57 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:21 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> one of the question raised in the said proceedings was pertaining<br /> to the question as to whether, the decision of the MMRDA to apply<br /> the extension of time from 4 years to 6 years for completing the<br /> construction only to the post August 2015 was valid in the eyes of<br /> law, is also a question raised in the present proceeding. While<br /> answering the said question, it was held in Raghuleela Builders<br /> Pvt. Ltd. & Anr . (Supra), as follows:-<br /> “38. The MMRDA constituted a single member committee of<br /> retired Judge of the Supreme Court to decide whether the<br /> MMRDA should give concession in recovery of premium<br /> considering the time required for plot owner to obtain<br /> permissions from various authorities for construction of building<br /> thereon. It is contended that one member committee has<br /> concluded that the charging of premium for extension of time<br /> for completing construction in Bandra-Kurla Complex area,<br /> specifically in case where additional built up area has been<br /> allotted by the MMRDA, was illegal. In its 138th meeting held<br /> on 26th August 2015, the MMRDA had acknowledged the<br /> difficulties faced by the lessees and that the condition of<br /> completion of construction within 4 years of the execution of the<br /> lease was adversely affecting the tendering process. The<br /> MMRDA had appointed an expert one man committee of retired<br /> Supreme Court Judge in that regard. The single member<br /> committee has advised that the period of 6 to 7 years be granted<br /> for completion of construction.<br /> 39. The lease deed entered into by the MMRDA with the<br /> lessees are as per form D, prescribed under the MMRDA<br /> (Disposal of Lands) Regulations 1977. Clause 2(a) of the lease<br /> deed provides that for building plans to be submitted to country<br /> and town planing division for approval within 3 months from<br /> the date of lease. Clause 2(c) of the lease deed provides that no<br /> work is to be carried out until all plans, elevations, specifications<br /> are approved by the concerned authorities. Clause 2(d) provides<br /> that within 3 months of the approval of plans, the lessee is to<br /> commence construction which is to be completed within four<br /> years of the lease. Clause 2(e) provided for extension of time.<br /> Clause 2(e) contemplates a situation when the time for<br /> completion of construction can be extended, parties to the<br /> Page 58 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:21 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> contract contemplated that certain uncertainties or situations<br /> may arise which may require more time for completion of the<br /> construction. In view of this, time is not essence of the contract<br /> between the parties and rightly so since construction of any<br /> building in Bandra Kurla Complex, several permissions are<br /> required from the various authorities and not only from the<br /> MMRDA who is planning authority for the Bandra Kurla area,<br /> namely,<br /> (1) The environmental clearance under the<br /> Environmental Impact Notification from the Ministry of<br /> Environment and Forest.<br /> (2) Building height clearance from the Ministry of<br /> Civil Aviation because of the close proximity to Airport.<br /> (3) Clearance from the high rise committee.<br /> (4) Permission from the the MCGM.<br /> (5) Permission from the traffic police.<br /> Each of these authorities is required to be approached<br /> separately since there is no single window clearance / nodal<br /> agency which would co-ordinate with the aforesaid authorities<br /> for granting of all necessary permissions. In view of the delay in<br /> obtaining permissions which are beyond the control of lessee, no<br /> work could be carried out as per clause 2(d) of the lease deed.<br /> 40. The MMRDA had issued a letter of allotment dated 20th<br /> March 2012 allotting additional 67,000 sq. meters at<br /> consideration of 984 crore. Part payment of Rs.196 crore was<br /> received on 20th March 2012. The supplementary lease deed<br /> was executed for additional built up area of 67,000 sq. meters.<br /> The letter of allotment dated 20th March 2012, the acceptance<br /> of part payment of consideration for additional built up area<br /> allotted, diluted the time period of four years and there was no<br /> question of application of condition of occupation certificate for<br /> built up area within 4 years when additional built up area was<br /> allotted for raising additional 11 floors on the same building.<br /> 41. The resolution passed by MMRDA for extending the time<br /> period for completing construction from 4 years to 6 years only<br /> for leases executed after 26th August 2015 also appears to be<br /> arbitrary, discriminatory, without basis and justification. The said<br /> set of circumstances are prevailing for the construction being<br /> carried out under the leases executed prior to 26th August 2015.<br /> Therefore, not extending this benefit of this extension of time<br /> from 4 years to 6 years to the prior leases in respect of other<br /> plots in the BKC, is completely arbitrary, discriminatory,<br /> capricious and violative of Article 14 of the Constitution of<br /> Page 59 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:21 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> India. There is no reasonable basis or justification for this<br /> decision. The classification sought to be made between the<br /> leases prior and subsequent to 26th August 2015 is not founded<br /> on intelligible differentia and neither does this differentia has<br /> any logic, rational, nexus to the object sought to be achieved.<br /> The MMRDA has sought to treat equals as unequal. The lessees<br /> of plots are being discriminated on the basis of their date of<br /> execution of their leases. The lessees who are placed in similar<br /> circumstances prevailing for construction in Bandra Kurla area<br /> are entitled to equal treatment guaranteed under Article 14 of<br /> the Constitution of India.” .<br /> 96. It is not in dispute that the Lease Deed involved in<br /> Raghuleela Builders Pvt. Ltd. & Anr . (Supra) was also in Form ‘D’<br /> of the Regulations of 1977 wherein the same Articles 2 (d) and (e)<br /> were involved. The Writ Petitioner there-in was also a similarly<br /> situated lessee, from whom, penalty for delay in completing the<br /> construction beyond the period of 4 years was raised by the<br /> Respondent No 1. The Petitioner in that case had also raised<br /> identical plea as regards the applicability of the time extension<br /> th<br /> Clause. The Lease Deed in that case was also executed prior to 26<br /> August 2015. If that be so there can be no doubt about the fact<br /> that the legal principles discussed and the findings & observations<br /> recorded in paragraphs 38 and 41 of Raghuleela Builders, in so<br /> far as uniform applicability of the 6 years time extension clause is<br /> concerned, would be applicable to the facts of the present case as<br /> well. Therefore, we hold that by applying the principles parity, the<br /> Respondent No. 1 would be duty-bound to extend the same<br /> Page 60 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:21 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> benefit of extension of time for completion of construction to six<br /> years to the present Petitioner as well. <br /> 97. In the facts and circumstances of this case, we are also of<br /> the opinion that there is no legal justification for the Respondent<br /> No. 1 to confine the benefit of the time extension clause only to<br /> th<br /> those Lease Agreements which were executed after 26 August<br /> 2015 as such an approach would be highly arbitrary and<br /> discriminatory in nature. Therefore, having regard to the peculiar<br /> facts and circumstances of this case, we do not find any justifiable<br /> ground to take a different view on the aforesaid issue. <br /> 98. Law is well settled that for maintaining judicial discipline<br /> and propriety, a decision rendered by a Coordinate Bench on the<br /> same issue must be respected and followed by a Coordinate<br /> 8<br /> Bench. In the case of Mary Pushpam vs. Televi Curusumary & Ors.<br /> the Hon’ble Supreme Court has observed that when a decision of a<br /> Coordinate Bench of the same High Court is brought to the notice<br /> of the Bench, it is to be respected and would be binding, subject to<br /> the right of the Bench of such co-equal forum to take a different<br /> view and refer the question to a larger Bench. In other words, any<br /> <b>8</b><br /> (2024) 1 SCR 11.<br /> Page 61 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:21 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> decision of a Coordinate Bench would be binding on a Bench of<br /> equal strength subject to the condition that if a different view is<br /> sought to be taken in the matter, then the issue would have to be<br /> referred to a larger Bench.<br /> 99. The above legal principle has taken a firm footing in the<br /> Indian Jurisprudence by a long line of judicial pronouncements.<br /> We do not deem it necessary to burden this judgment by referring<br /> to all those decisions. However, suffice it to mention here-in that<br /> unless there are justifiable grounds to take a different view in the<br /> matter warranting reference to a larger Bench, the previous<br /> decision of a coordinate Bench would be binding on a Bench of<br /> equal strength.<br /> 100. Consequently, it is held that notwithstanding Article 2(d) of<br /> st<br /> the Lease Deed dated 1 September 2006, in view of the decision<br /> taken by the Respondent No 1 to extend the period of construction<br /> from four years to six years, the Petitioner, being a similarly<br /> situated Lessee, would also be entitled to six years’ time for<br /> completion of the construction. Since, the Commencement<br /> Certificate for the entire built up area of 3,12,500 sq. mtrs. was<br /> th<br /> issued by the Respondent No.1 only on 16 April 2014, as such,<br /> Page 62 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:21 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> we are of the opinion that the Petitioner would be entitled to six<br /> th<br /> years’ time period, with effect from 16 April 2014, for completing<br /> the construction for the simple reason that in view of the built-up<br /> area subsequently allotted to the Petitioner, there was no scope to<br /> th<br /> commence construction of the composite construction prior to 14<br /> April 2014. Therefore, adding the period of 4 years 4 month and<br /> th<br /> 26 days, during which period, the interim order dated 15<br /> October 2007 was in force, the Petitioner, in our opinion, would<br /> be entitled to total time period of 10 years 4 months 26 days with<br /> th<br /> effect from 14 April 2014. Alternately, even if the period of 10<br /> st<br /> years 4 months 26 days is counted from 1 September 2006, i.e.,<br /> the date of the Lease Deed, even then, the Petitioner would be<br /> entitled to such period of time for completing the construction of<br /> the initial built-up area without seeking extension of time. In so<br /> far as the additional built up area is concerned, in view of the<br /> communication dated 08/11/2011, as noted above, no time limit<br /> would at all be applicable for the construction of such built up<br /> area. <br /> 101. Therefore, we are constrained to hold that the condition<br /> precedent so as to invoke Articles 2(d) & (e) of the Lease Deed<br /> Page 63 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:21 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> st<br /> Dated 1 September, 2006 was not met in this case. As such, we<br /> are also of the view that no additional premium/ penalty was<br /> either payable or recoverable from the Petitioner on account of<br /> delay in completing the construction. <br /> 102. For the reasons stated above, this Writ Petition succeeds<br /> and the same is hereby allowed in terms of payer clauses(a),(a)<br /> (i),(a)(ii)(a)&(b). The impugned Demand Notices dated<br /> th<br /> 12/09/2017 and 13 June 2019 are accordingly, set aside.<br /> 103. Consequently, we hold that the Petitioner would be entitled<br /> for refund of the amount of Rs.646,77,68,594 (Rupees Six<br /> Hundred and Forty Six Crores Seventy Seven Lakhs Sixty Eight<br /> Thousand Five Hundred and Ninety Four) deposited as additional<br /> premium/ penalty for the alleged delay in completion of the<br /> construction. The Respondent No 1 is, therefore, directed to<br /> refund the aforesaid amount to the Petitioner within a period of<br /> 90 (ninety) days from the date of receipt of the Certified Copy of<br /> this order, failing which, the amount would carry interest at the<br /> same rate at which, interest was payable by the Petitioner under<br /> the Lease Agreement due to delay in paying premium, to be<br /> calculated from the date of this order till the date of the refund. <br /> Page 64 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:21 :::</i></b><br /><br /> Reliance-oswp-242-2018-J-R.doc<br /> <br /> 104. In so far as the Bank Guarantee(s) furnished by the<br /> Petitioner including that for an amount of Rs.13,12,54,85,287/-<br /> (Rupees Thirteen Hundred Twelve Crores Fifty Four Lakhs Eighty<br /> Five Thousand Two Hundred and Eighty Seven ) the same shall be<br /> kept valid for a period of 90 (Ninety) days from the date of this<br /> order. <br /> 105. With the above observations, the Rule is made absolute.<br /> 106. The Writ Petition stands disposed of.<br /> 107. Parties to bear their own cost. <br /> 108. In view of disposal of the Writ Petition, nothing survives in<br /> the Interim Application and the same is disposed of accordingly. <br /> (SUMAN SHYAM, J) (CHIEF JUSTICE) <br /> Page 65 of 65<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:21 :::</i></b></div>