BANARASI PRASAD GUPTA vs KOLKATA MUNICIPAL CORPORATION AND ORS.

Court
Calcutta High Court

M/L 17
05.10.2026
sb
Ct.3.
IN THE HIGH COURT AT CALCUTTA
CONSTITUTIONAL WRIT JURISDICTION
APPELLATE SIDE

WPA 23409 of 2026

Banarasi Prasad Gupta
Versus
The Kolkata Municipal Corporation & Ors.


Mr. Kajal Ray
… For the petitioner.

Mrs. Koyeli Bhattacharyya
Mr. Dipankar Ghosh
… For Kolkata Municipal Corporation.


1. The present writ petition has been filed, inter alia,
praying for a direction upon the respondents to ensure
that the unauthorized construction made by the private
respondents at Premises No. 16, Beniapukur Road,
Kolkata – 700014, be demolished.
2. According to the learned advocate for the
th
petitioner, in terms of the order dated 25 February,
2008 passed in WP No. 2494 (W) of 2008, the learned
Registrar General had filed an FIR which was tried as
G.R. Case No. 960 of 2008 by the Court of the learned
th
Metropolitan Magistrate, 5 Court, Calcutta. The
proceedings were disposed of by a judgment and order
th
dated 29 December, 2023, inter alia, holding that it is
proved beyond the shadow of reasonable doubt that
pursuant to the conspiracy, accused no.6 pretended
himself to be Dilip Biswas before the Registrar of
th
Assurances, Kolkata on 30 January, 2004, put his

2
WPA 23409 of 2026


photograph, signed his name as Dilip Biswas, and
accused no.5 identified accused no.6 as Dilip Biswas
before the Registrar of Assurances, Kolkata to register
th
General Power of Attorney dated 30 January, 2004,
which he would not have done had he knew that accused
no.6 is not actually Dilip Biswas. Hence accused nos. 5
and 6 have committed the offence under Secton 419
/120B of the Indian Penal Code. It is submitted that it is
now been held that Dilip Biswas put his signature on the
power of attorney and the sanctioned building plan was
obtained by fraud.
3. In this context I find that the petitioner was
inducted as a lessee in respect of the back portion of
premises no. 16 Benia Pukur Road. This portion was,
however, separated from the remaining portion of the
mother premises and was renumbered as 16/1 Hare
Krishna Konar Road and the remaining portion of the
mother premises came to be known as 16 Hare Krishna
Konar Road. Subsequently, a sanction building plan was
issued in respect of 16 Hare Krishna Konar
Road, the building was constructed. The petitioner had
previously approached this Court in W.P. 24893 (W) of
2006 with a prayer for direction upon the municipal
authority to revoke this sanctioned building plan dated
th
4 August, 2004. Such prayer was not allowed. The said
writ petition was disposed of upon directing the hearing
officer to hear the respective parties and pass a reasoned
order. The Special Officer in turn noting that illegal

3
WPA 23409 of 2026


construction had taken place in certain portions marked
as ‘A’, ‘B’, ‘C’ in the demolition sketch observed that the
demolition was required to be effected after final disposal
of the civil suit or any other further direction of the
learned Court. It was, however, further observed by the
Special Officer that no demolition order was required to
be passed in the remaining unauthorized construction
subject to the person responsible complying with the
conditions, namely obtaining a certificate from the
empanelled structural engineer certifying that the
structural stability and the foundation of the impugned
constructions were safe and sound and the materials
used as well as workmanship had been made as per the
latest edition of National Building Code of India. In the
wake of such order being issued, sanction fees for
regularization of the unauthorized portions were paid.
Though the person responsible complied with the
aforesaid direction and paid sanction fee the Executive
Engineer (C) Building Department of Kolkata Municipal
Corporation once again directed the demolition of the
portion marked ‘A’, ‘B’, ‘C’ in the demolition sketch plan.
4. A further writ petition being WP 14821(W) of 2007
was filed. The said writ petition was disposed of by
observing that the order of the Executive Engineer was
not in conformity with the order passed by the Special
Officer (Building). Accordingly, the order passed by the
Executive Engineer was quashed with the observation
that the parties to the proceedings including the

4
WPA 23409 of 2026


Corporation would abide by the decision of the Special
Officer (Building) until the order was varied and/or
modified in appeal by the Building Tribunal in B.T.
Appeal No. 45 of 2007. Since then, from time to time
various proceedings have been initiated including further
stop work notice issued by the municipality. Ultimately,
th
this Court by the order dated 30 January, 2009 in WP
13579 (W) of 2008 was inter alia pleased to direct the
municipality to issue occupancy certificate.

5. Mrs. Bhattacharyya, learned advocate
representing Kolkata Municipal Corporation by filing a
rd
report dated 23 September, 2026 would submit that in
terms of the aforesaid direction, partial completion
th
certificate had been issued on 20 January, 2014 vide
th
order dated 13 October, 2009. At present the premise is
fully occupied.
6. At this stage, the petitioner once again
approached this Court on the ground that the criminal
proceedings has come to a logical conclusion by the
th
judgment dated 19 July, 2025. The petitioner is seeking
to reopen the issue of grant of sanction plan in respect of
its adjacent premises wherein the petitioner does not have
any interest. The challenge is also not with regard to
unauthorized construction or grant of plan in deviation of
the building rules, rather the same is more of title
dispute.
7. In the peculiar facts as noted hereinabove, I am of
the view there is no scope to reopen the settled issue

5
WPA 23409 of 2026


which has long been decided by the order passed by this
Court as a valuable right on the basis of grant of
completion certificate has accrued. All occupiers are not
parties to this proceedings. This apart, there is no prayer
in the writ petition for recalling of the completion
certificate and the order passed by this Court.
8. In the light of the above, this Court is not inclined
to entertain the writ petition and the same is accordingly
dismissed.
Urgent photostat certified copy of this order, if
applied for be given to the parties upon compliance with
the requisite formalities.



(Raja Basu Chowdhury, J.)