Smt. Sunita Joshi vs Indore Municipal Corporation
- Court
- Madhya Pradesh High Court
NEUTRAL CITATION NO. 2026:MPHC-IND:20615
1 WP-29898-2026
IN THE HIGH COURT OF MADHYA PRADESH
AT INDORE
BEFORE
HON'BLE SHRI JUSTICE SANDEEP N. BHATT
th
ON THE 28 OF JULY, 2026
WRIT PETITION No. 29898 of 2026
SMT. SUNITA JOSHI
Versus
INDORE MUNICIPAL CORPORATION AND OTHERS
Appearance:
Shri Vismit Panot, Advocate(through VC) for the petitioner.
Shri Rishi Tiwari, Advocate for the respondent(s).
ORDER
By way of present petition under Article 226 of the Constitution of India,
the petitioner is praying for the following reliefs :-
i.) The impugned order/notice dated 10.07.2026 issued by the respondents
may kindly be set aside.
ii.) The respondents may kindly be directed not to carry out any demolition
activity on the lawfully acquired property of the petitioner.
iii.) Any other relief which this Hon'ble Court deems fit in the facts and
circumstances of the case, may also kindly be granted in favor of the
petitioner.
2. Brief facts of the case are that the present petition is being filed by the petitioner
upon being aggrieved of the arbitrary order passed by the respondent no. 3 / Building
Officer, Zone No. 22, Indore Municipal Corporation on 10.07.2026, annexed herewith
as Annexure P/1 wherein the petitioner has been asked to remove the alleged
obstructive construction of the eaves (chajja) of her property, situated at 9-B, Amrat
Palace, Nipania & admeasuring 6.44 Sq. meter, within a period of 15 days.
Signature Not Verified
Signed by: PREETHA NAIR
Signing time: 29-07-2026
19:31:54
NEUTRAL CITATION NO. 2026:MPHC-IND:20615
2 WP-29898-2026
3 . Learned counsel for the petitioner contended that the impugned action of the
respondents is not only arbitrary but also illegal as it is aimed at demolition of a
lawfully raised construction at the petitioner’s property only. None of the adjoining
building owners have been given any notice so far & moreover the petitioner’s
property is prima facie not obstructive. as falsely described in the impugned
notice/order. He has further submitted that even if the existing arbitrary alignment of
laying the electricity poles is considered, still the electricity lines will be at a distance
of 2-3 feet from the eaves (chajja) area of the petitioner's building and, therefore, no
demolition as averred is necessary because the eaves (Chajja) will not be an
obstruction at all. It is further submitted that he petitioner purchased the property in
question in February. 2025. The building was already constructed in the year 2014
after obtaining all necessary permissions from the Gram Panchayat and on the basis of
a duly sanctioned building plan. At the time of approval of the colony layout by the
Gram Panchayat and the Town & Country Planning Department, the adjoining road
was sanctioned with a width of 60 feet, and the building plan was approved
accordingly. However, after more than ten years, the respondents have now proposed
to widen the said road to 100 feet and, on that basis, have treated the petitioner's eaves
(chhajja) as an obstruction. No acquisition proceedings or other legal process have
been initiated for such widening of the road. The petitioner's eaves form part of a
lawfully sanctioned construction and are situated beyond the road boundary. He has
further submitted that the respondent/authority has proceeded on the assumption that
the petitioner's eaves (chhajja) is obstructing the construction of a road proposed
under the Indore Development Plan. 2021. He submits that the said assumption is
incorrect. He further submits that the Firstly, the Indore Indore Development Plan.
2021Development Plan. 2021 has expired in the years 2021(on 31.03.2021) and by
referring to the Coordinate Bench judgment of this Court in the case of Raj Beesani v.
Signature Not Verified
Signed by: PREETHA NAIR
Signing time: 29-07-2026
19:31:54
NEUTRAL CITATION NO. 2026:MPHC-IND:20615
3 WP-29898-2026
State of Madhya Pradesh (Neutral Citation: 2026; MPHC-IND:3970), he has
submitted that the expired Development Plan cannot be relied upon to the prejudice of
landowners. He has further submitted the impugned order/notice has been issued in a
mechanical manner without properly considering the facts placed on record by the
petitioner. Though the petitioner's personal hearing was concluded nearly three
months prior to the issuance of the impugned order, the respondents neither carried out
a proper site inspection nor verified the actual position at the spot.
4. Learned counsel for the petitioner further submitted that the Hon'ble Apex Court
has also clarified in the matter of Ajay Hasia vs. Khalid Mujib, (1981) 1 SCC 722 that
an arbitrary order issued by an authority which falls under the ambit of state is
violative of Article 14. He has further submitted that such view is further reaffirmed in
In Re: Directions in the Matter of Demolition of Structures, 2024 SCC OnLine SC
3292 and this Hon'ble Court has also applied these directions in WP
No.38618/2024[Shri Jagdish Prasad Versus Dewas Municipal Corporation And
Others ] and, therefore, he submits that as the respondents have not complied with
mandatory provisions and, therefore, the impugned action of the respondent/ Indore
Municipal Corporation needs to be set aside.
5. It is further submitted that the respondents have arbitrarily changed the original
alignment of the electricity line and shifted the electricity poles immediately adjacent
to the petitioner's building. He has submitted that although the poles had already been
erected at a distance of about 9 feet from the building at the same location, therefore,
the said action is not only contrary to the basic requirements of public safety but also
poses an unnecessary risk to the occupants of the buildings and the general
public. The impugned action of the respondents is arbitrary and without any legal
basis. Therefore, he submits that present petition is required to be allowed by
Signature Not Verified
Signed by: PREETHA NAIR
Signing time: 29-07-2026
19:31:54
NEUTRAL CITATION NO. 2026:MPHC-IND:20615
4 WP-29898-2026
considering the prayers made in the present petition and by considering the material
available on record, more particularly, the photographs which indicates the real
situation of the building/property in question.
6. Learned counsel for the respondent/Municipal Corporation has drawn my attention
towards the reply filed by the respondent/Corporation and has submitted that by way
of impugned notice, the petitioner has been directed to remove the obstructing
construction within a period of 15 days from construction/widening of the road as per
the Indore Development Plan, 2021. He has further submitted that the petitioner is
infact the author of the situation as she illegally constructed the balcony without
st nd rd
permission and contrary to the sanctioned building permission on 1 , 2 and 3 floor
of the subject building, which is required to be removed for widening of the subject
road. From a bare perusal of the building permission granted to the petitioner by the
then panchayat, it is evident that no balcony/eaves was sanctioned in the building,
despite which the petitioner constructed balcony/eaves on 1st, 2nd and and 3rd floor,
therefore, the construction of the aforesaid building is totally illegal. He has further
submitted that the impugned order has been passed after following due procedure of
law and granting sufficient opportunity of hearing to the petitioner and it does not
suffers from any illegality or arbitrariness and, thus, this petition is liable to dismissed.
He has also pointed out relevant facts of the case in Paragraph - 5 of his reply, narrated
in chronological order as follows :-
S.No. Date Event Annexures
Indore Development Plan, 2021
came into R/3existence, after
following the process
under sections 18. and 19 of the
Nagar Tatha Gram Nivesh
‘Adhiniyam, 1973. As per map
No. 4.1 of the plan the subject
road is 30 meter wide.
1 01/01/08
R/3
Public notice was issued
Signature Not Verified
Signed by: PREETHA NAIR
Signing time: 29-07-2026
19:31:54
NEUTRAL CITATION NO. 2026:MPHC-IND:20615
5 WP-29898-2026
in widely circulated newspapers
-Nai-duniya and Agniban for the
alignment exercise to be
conducted on 03.01.2026 by a
joint team of Revenue
Department,T&CP Department
and IMC.
2 26/12/25
R/4
A show cause
notice was issued by answering
respondent No.03 to the
petitioner’s husband, whereby,
the petitioner was directed to
remain present on 02.03.2026 at
11:00 AM along with all
relevant documents.
3 26/02/26
P/2
The team comprising of
officers of T&CP, Revenue
Department and Municipal
Corporation marked the center
line of the subject road on the
basis of Indore Deveploment
Plan, 2021; layouts, khasra
and maps using the DGPS
equipment.A panchnama was
drawn signed by the officials
and an attendance
sheet was also prepared on
which 11 persons signed while
others refused. An inspection
report was also prepared.
R/5
4 03/01/26
R/6
R/7
On the basis of the Indore
Development Plan, 2021,
measurements were taken on
hoth sides and markings were
made on properties maintaining
a width of 15 meter | from the
centre line.
5
The petitioner submitted a reply
6 02/03/26 P/4
to notice dated 26.02.2026.
Notices were issued to the
petitioner referring to the
alignment done by the joint
team as mentioned above and
specific dimensions of the
obstructing construction were
mentioned. It was also directed
to remove the obstructing
construction.
7 30/03/26
P/5
Signature Not Verified
Signed by: PREETHA NAIR
Signing time: 29-07-2026
19:31:54
NEUTRAL CITATION NO. 2026:MPHC-IND:20615
6 WP-29898-2026
Petitioner’s husband filed a writ
petition No. 12846/2026,
“challenging the order
dated 30.03.2026.
8 07/04/26
Site inspection was carried out,
and it was found that the
petitioner had constructed eaves
on the first, second, and third
floors of the building situated on
the petitioner's
property.It was further found
that an unauthorized
construction measuring 9.20
metres x 10.00 metres had been
raised on the fourth floor.
9 08/04/26
R/8
This Hon’ble High Court while
deciding the aforementioned WP
No. 12846/2026,
has directed the answering
respondents to grant the
petitioner to grant another
opportunity of hearing in the
matter and also directed the
petitioner in the said petition to
appear before the respondent
on 22.04.2026 between 11:00
AM to 02:00 PM for
opportunity.of hearing
10 08/04/26
P/6
Hearing was conducted and on
behalf of the petitioner’s
husband remained present
and submitted a written
objection, however, no
document was submitted
showing authorization to him to
submit the aforementioned
objection.
11 22/04/26
P/7
As no document was filed
showing the| authorization to
Mr. Prafful Joshi to file
objection, thus, another notice
was issued to the petitioner
directing her to remain present
before the answering respondent
No. 03 for personal hearing.
12 24/04/26
P/8
The. petitioner remained present
before the answering
13 28/04/26
P/9
Signature Not Verified
Signed by: PREETHA NAIR
Signing time: 29-07-2026
19:31:54
NEUTRAL CITATION NO. 2026:MPHC-IND:20615
7 WP-29898-2026
respondent.No.03 and submitted
the objection.
The impugned notice was issued
after due}P/I consideration of
the entire objection raised y the
petitioner
and specific reasoning has been
given to each and
every objection raised by the
petitioner.
14 10/07/26
P/1
7. Learned counsel for the respondent further submitted that in view of the
aforesaid chronological events, the subject road has been marked as a 30-meter-
wide road under the Indore Development Plan, 2021, which came into force after
following the statutory procedure prescribed under Sections 18 and 19 of the
Madhya Pradesh Nagar Tatha Gram Nivesh Adhiniyam, 1973. The validity of the
Development Plan has never been challenged by the petitioner and, therefore, the
petitioner cannot claim any right contrary to the statutory Development Plan. He
has further submitted that the petitioner has deliberately suppressed the material
fact that before issuance of the impugned notice, multiple opportunities of hearing
were granted. Initially, notice dated 26.02.2026 was issued, thereafter another
notice dated 30.03.2026 was issued specifying the extent of encroachment.
Subsequently, pursuant to the order passed by this Hon'ble Court in W.P.
No.12846/2026, yet another opportunity of hearing was granted. Thereafter,
notices dated 24.04.2026 and personal hearing dated 28.04.2026 were also
afforded to the petitioner. Thus, the principles of natural justice have been
complied with in their fullest measure. He further submitted that the impugned
notice dated 10.07.2026 is not a mechanical order. The answering respondents
have considered each and every objection raised by the petitioner and has
Signature Not Verified
Signed by: PREETHA NAIR
Signing time: 29-07-2026
19:31:54
NEUTRAL CITATION NO. 2026:MPHC-IND:20615
8 WP-29898-2026
assigned detailed reasons for rejecting the same before directing removal of the
obstruction. Therefore, the allegation of non-application of mind is completely
misconceived. He further submitted that no portion of the petitioner's property has
been sought to be removed except the construction falling within the alignment of
the proposed 30-meter-wide road. The action initiated by the answering
respondents is in furtherance of a statutory Development Plan and is intended to
implement public-infrastructure for the benefit of the general public. The
petitioner cannot claim an indefeasible right to continue an obstruction over land
reserved for a public road. He further submits that the subject road is
already delineated in the development plan and the corporation mealy carries out
measurements and marking on the basis of the Development Plan.
8 . Learned counsel for the respondent/Municipal Corporation further
submitted that in the writ petition itself, the petitioner has herself admitted that the
projecting Construction, i.e., the eaves (chhajja), extends beyond the boundary of
her plot. Once the petitioner has admitted that the said construction lies outside
the sanctioned plot boundary, she cannot claim any legal or vested right to retain
the same. The impugned notice seeks removal only of the obstructing projection
falling within the alignment of the proposed 30-meter-wide road and does not
seek demolition of any construction situated within the lawful boundaries of the
petitioner's property. He further submits that the present petition is nothing but an
attempt to delay implementation of the Development Plan. The petitioner has
approached this Court after availing repeated opportunities before the competent
authority, and despite a reasoned decision having been passed, has failed to point
out any procedural illegality, jurisdictional error or violation of any statutory
provision warranting interference under Article 226 of the Constitution of India.
Signature Not Verified
Signed by: PREETHA NAIR
Signing time: 29-07-2026
19:31:54
NEUTRAL CITATION NO. 2026:MPHC-IND:20615
9 WP-29898-2026
He further submitted that the petitioner has wrongly averred that the answering
respondents have proceeded on the assumption that the eaves(chhajja) of the
petitioner's house is obstructing the proposed road. The said allegation is wholly
false, misconceived and hence specifically denied by the respondents. He further
submitted that the impugned action is based upon the survey and inspection
carried out by the joint team comprising officers of the Town and Country
Planning Department, Revenue Department and Indore Municipal Corporation
pursuant to the directions issued by this Hon'ble Court. The centre line of the
subject road was determined after taking into consideration the sanctioned
layouts, revenue records and the Development Plan. Thereafter, measurements
were taken from the centre line on both sides and the exact extent of the
obstructing construction, including the projection (chhajja), was identified. Thus,
the impugned notice is founded upon actual measurements and scientific survey
and not on any presumption, as falsely alleged by the petitioner.
9. Learned counsel for the respondent/Municipal Corporation further submits
that the reliance placed by the petitioner upon the order passed in M.P.
No.4687/2025 (Raj Beesani and Others vs. State of Madhya Pradesh and Others)
is wholly misconceived and misplaced. The operation and effect of the said order
has been stayed by the Division Bench of this Hon'ble Court vide interim order
dated 13.05.2026 passed in Writ Appeal No.1413/2026. He has further submitted
that the petitioner has placed heavy reliance upon the judgments passed in Ajay
Hasia vs. Khalid Mujib(Supra), Directions in the Matter of Demolition of
Structures and Shri Jagdish v. Dewas Municipal Corporation and others(Supra)
and has attempted to contend that the petitioner is similarly situated on the ground
that the mandatory provisions of law have not been complied with by the
answering respondents. The said contention is wholly misconceived, vague and
Signature Not Verified
Signed by: PREETHA NAIR
Signing time: 29-07-2026
19:31:54
NEUTRAL CITATION NO. 2026:MPHC-IND:20615
10 WP-29898-2026
devoid of any factual or legal foundation. Infact, the petitioner has failed to
specify even a single statutory provision, rule, regulation or mandatory
requirement which is alleged to have been violated by the answering respondents.
The entire writ petition is conspicuously silent as to which provision of law has
not been complied with. In the absence of any specific pleading regarding the
alleged violation of a statutory mandate, the bald assertion that the mandatory
provisions have not been followed is liable to be rejected outright. He lastly
submitted that the action of the answering respondents has been undertaken
strictly in accordance with the provisions of the Madhya Pradesh Nagar Tatha
Gram Nivesh Adhiniyam, 1973, the Indore Development Plan, 2021, and
pursuant to the directions issued by this Hon'ble Court and, therefore, by
referring to various documents, he has submitted that the petitioner has failed to
make out a case for consideration under Article 226 of the Constitution of India
and, therefore the petition requires to be dismissed.
10. I have heard the rival submissions of the learned counsel for the parties and
considered the judgments relied upon by the petitioner. The judgment in M.P.
No. 4687/2025 (Raj Beesani and Others vs. State of Madhya Pradesh and Others)
was stayed in Writ Appeal No. 1413/2026 dated 13.05.2026; therefore, its ratio
does not require consideration at this stage. Furthermore, the record indicates that
the petitioner previously approached this Court, which directed the respondent
authority to afford the petitioner a hearing. Accordingly, due opportunity has been
granted.
11. Considering the chronology of events, the rival contentions made at the bar,
and the pleadings of the parties, it transpires that an initial notice was issued on
26.02.2026. Thereafter, another notice specifying the exact extent of the
encroachment was issued on 30.03.2026. Subsequently, in view of the order
Signature Not Verified
Signed by: PREETHA NAIR
Signing time: 29-07-2026
19:31:54
NEUTRAL CITATION NO. 2026:MPHC-IND:20615
11 WP-29898-2026
passed in W.P. No. 12846/2026, a further opportunity of being heard was granted
to the petitioner. Following this, a notice dated 24.04.2026 was issued, and a
personal hearing was conducted on 28.04.2026. Thus, prima facie, the principles
of natural justice have been duly satisfied. It further transpires that the Indore
Development Plan, 2021 mandates a 30-meter-wide road. The material available
on record clearly indicates that a joint measurement was carried out by an
inspection team comprising officials from the Indore Municipal Corporation, the
State Government, and other authorities. Pursuant to this inspection, it was
established that the eaves (chajjas), which were admittedly constructed on all
three floors without valid permission, extend beyond the boundary of the
petitioner's plot.
12. Therefore, considering that this Court has a very limited scope of judicial
review while exercising power under Article 226 of the Constitution of India, and
since it transpires from the record that the respondent authority has afforded all
necessary opportunities by issuing notice followed by a hearing, the prescribed
procedure has been followed in an appropriate manner. Prima facie, it cannot be
said that the impugned action is without basis, as the material available on record
indicates that there is an apparently illegal construction which also extends
beyond the petitioner's plot. The learned authority has rightly come to the
conclusion that, in view of the Indore Development Plan, 2021, such apparently
illegal construction requires to be removed.
13. It It is not the case of the respondent/authority that the entire construction of
the building is illegal; rather, only the projecting eaves (chajjas) of all three floors
were found to be unauthorized. It is evident that the authority, upon proper
application of mind, concluded that only this specific portion requires removal.
Signature Not Verified
Signed by: PREETHA NAIR
Signing time: 29-07-2026
19:31:54
NEUTRAL CITATION NO. 2026:MPHC-IND:20615
12 WP-29898-2026
This conclusion was reached after duly considering the measurements and the
construction permission of the petitioner, which established that the disputed
portion was erected without valid authorization.
14. Therefore, on all these grounds, it appears that the petitioner himself has
committed a breach of the provisions of law by raising construction beyond her
plot area, as indicated in the report. Moreover, the respondent authority is
implementing the provisions of the Indore Development Plan, 2021, which
provides for a 90-meter road intended for the better convenience of the city's
residents and citizens. Even otherwise, considering the larger public interest
involved in the matter as against the individual right of the petitioner, and in the
absence of any prima facie material indicating a breach of statutory provisions or
any form of arbitrariness, I find no reason to interfere with the impugned action
taken by the respondent authority. The said action is found to be in consonance
with the law and has been taken by following due procedure. Therefore, the
present petition deserves to be dismissed. Accordingly, the petition is dismissed
as no case is made out for interference under Article 226 of the Constitution of
India.
(SANDEEP N. BHATT)
JUDGE
pn
Signature Not Verified
Signed by: PREETHA NAIR
Signing time: 29-07-2026