Sunshine Engineers And Consultants vs M/S Vinni Chemicals Pvt. Ltd.
- Court
- Delhi High Court
$~46
* IN THE HIGH COURT OF DELHI AT NEW DELHI
# CNR No. DLHC010250732026
+ O.M.P. (T) (COMM.) 62/2026 & I.A. 15874/2026
SUNSHINE ENGINEERS AND CONSULTANTS.....Petitioner
Through: Mr. Aditya Sharma, Adv.
versus
M/S VINNI CHEMICALS PVT. LTD. .....Respondent
Through: Mr. Sahil Gupta, Adv.
CORAM:
HON'BLE MR. JUSTICE OM PRAKASH SHUKLA
JUDGMENT(ORAL)
% 13.08.2026
I.A. 21244/2026 (U.O. VI R. 16 r/w S. 151 CPC)
1. This application has been filed on behalf of the Respondent
1
under Section 151 of the Code of Civil Procedure, 1908 read with
Order VI Rule 16 CPC for expunging of scandalous, unsubstantiated
and prejudicial remarks/averments made against the Respondent and
its Counsel.
2. For the reasons stated in the application, the same is allowed
and the observations made by the learned Sole Arbitrator is expunged
from the letter dated 02.04.2026
3. The application stands disposed of.
O.M.P. (T) (COMM.) 62/2026
4. This petition is being preferred under Section 14 and 15 of the
1
“CPC”, hereinafter
Signature Not Verified
Signed By:GUNN
Signing Date:20.08.2026
20:03:25
O.M.P. (T) (COMM.) 62/2026 Page 1 of 5
2
Arbitration and Conciliation Act, 1996 seeking termination of the
mandate of the learned Sole Arbitrator and appointment of a substitute
Sole Arbitrator to adjudicate the disputes between the parties arising
out of the Definitive Supply Agreement dated 30.03.2023.
5. The parties had entered into the aforesaid agreement containing
an arbitration clause. Pursuant thereto, vide order dated 19.02.2025
passed in ARB.P.1755/2024, this Court appointed Hon’ble Mr. Justice
Ali Mohd Magrey, Former Chief Justice of High Court of J&K and
Ladakh, as the Sole Arbitrator under the aegis of Delhi International
3
Arbitration Centre .
6. The arbitral proceedings thereafter commenced and had
progressed to the stage of recording/cross-examination of the
Petitioner’s witness CW-1.
7. The Petitioner states that disputes between the parties include
its claim for approximately Rs.3 crores towards outstanding dues. The
Respondent, however, disputes the said liability and submits that no
amount is due or payable to the Petitioner.
8. The Petitioner submits that the Respondent had reportedly
sought adjournments and adopted dilatory tactics, thereafter raised
allegations of bias against the learned Sole Arbitrator and sought his
substitution. The Respondent, in its reply, disputes the said allegations
and contends that the delay in the proceedings was attributable to the
2
“the Act”, hereinafter
3
“DIAC”, hereinafter
Signature Not Verified
Signed By:GUNN
Signing Date:20.08.2026
20:03:25
O.M.P. (T) (COMM.) 62/2026 Page 2 of 5
Petitioner.
9. The Respondent further alleges that the learned Arbitrator had
repeatedly fixed dates without adequately consulting the Respondent
and had proceeded in its absence, thereby causing prejudice and
denying it a fair opportunity.
10. It is not necessary for this Court in the present proceedings to
adjudicate upon the merits of the underlying monetary dispute or upon
the respective claims and differences of the parties. The said issue
shall remain open for adjudication by the Arbitral Tribunal.
11. It is an admitted position that the learned Sole Arbitrator vide
communication dated 02.04.2026 recused himself from the arbitral
proceedings. Consequently, the mandate of the learned Arbitrator
stands terminated in terms of Section 24 of the Act necessitating the
appointment of a substitute Arbitrator.
12. In view of the aforesaid circumstances, and since both parties
are ad idem that, a substitute Sole Arbitrator is required to be
appointed, this Court considers it appropriate to appoint a substitute
Sole Arbitrator to continue the arbitral proceedings.
13. Accordingly, Mr. Justice Dilip Gupta, Former Senior Judge,
Allahabad High Court (Mob. No. +91-9415215086) is appointed as a
learned Sole Arbitrator to adjudicate the disputes arisen between the
parties. The learned Sole Arbitrator shall enter upon the reference
within two weeks from today.
Signature Not Verified
Signed By:GUNN
Signing Date:20.08.2026
20:03:25
O.M.P. (T) (COMM.) 62/2026 Page 3 of 5
14. The learned Sole Arbitrator will proceed to the arbitration
proceedings subject to furnishing requisite disclosures as required
under Section 12(2) of the Act within two weeks of entering reference.
15. The arbitration shall be carried under the rules and aegis of
DIAC. The learned Arbitrator shall be entitled to fees as per the
Schedule of Fees maintained by the DIAC.
16. It shall be open to the parties to raise all pleas, including
objection as to arbitrability and jurisdiction, before the learned Sole
Arbitrator who shall decide the same in accordance with law.
17. The learned Sole Arbitrator shall continue the proceedings from
the stage of which the earlier Arbitrator recused himself, i.e. , from the
stage of cross-examination of CW-1, subject to such procedural
direction as may be considered appropriate by the learned Sole
Arbitrator.
18. It is clarified that the observations made herein are only for the
purpose of deciding the present petition under Section 14 and 15 of
the Act. The learned Sole Arbitrator shall adjudicate the disputes
independently and on their own merits, uninfluenced by any
observations contained in the present order.
19. The Registry is directed to send a receipt of this order to Mr.
Justice Dilip Gupta, learned Arbitrator through all permissible modes
including email.
Signature Not Verified
Signed By:GUNN
Signing Date:20.08.2026
20:03:25
O.M.P. (T) (COMM.) 62/2026 Page 4 of 5
20. It is made clear that no party shall take any unnecessary
adjournment before the learned Sole Arbitrator.
21. Accordingly, the present petition is disposed of in the above
terms. Pending applications, if any, also stand disposed of.
OM PRAKASH SHUKLA, J.
AUGUST 13, 2026/ gunn
Signature Not Verified
Signed By:GUNN
Signing Date:20.08.2026
20:03:25
O.M.P. (T) (COMM.) 62/2026 Page 5 of 5