Parmal (Deceased) Thr Lrs & Anr vs Union Of India & Anr

Court
Delhi High Court

$~
* IN THE HIGH COURT OF DELHI AT NEW DELHI

Reserved on: 07.04.2026
Date of decision:28.04.2026
Uploaded on: 28.04.2026


+ LA.APP. 101/2019 & CM APPL 76909/2025

PARMAL (DECEASED) THR LRS & ANR. Appellants

Through: Mr. Bhagwat Prasad Gupta, Adv.


Versus

UNION OF INDIA & ANR Respondent

Through: Mr. Sanjay Kumar Pathak, SC for R-
1/UOI with Mrs. K.K.Kiran Pathak,
Mr. Sunil Kr. Jha, Mr. M.S.
Akhtar, Advs.
Ms. Prity Sharma, Adv. for R-2/DDA.
CORAM:
HON'BLE MS. JUSTICE SHAIL JAIN
JUDGMENT
SHAIL JAIN, J.
1. The present Appeal has been preferred under Section 54 of the Land
Acquisition Act, 1894 [" LA Act "] against the Judgment and Award dated
10.04.2019 passed by the learned ADJ-01 (South-East), Saket Court, New
Delhi in LAC No. 44/2016 titled Parmal (Deceased) Through LRs & Anr.
v. Union of India & Anr . [" Impugned Award "], whereby the learned
Reference Court assessed the market value of the acquired land at
Rs.89,600/- per Bigha in respect of land situated in the revenue estate of
Signature Not Verified
Signed By:KAPIL
KUMAR
Signing Date:28.04.2026
16:40:18
LA.APP. 101/2019 Page 1 of 8

Village Kilokari, acquired vide Award No. 14/1992-93 pursuant to
Notification dated 23.06.1989 issued under Section 4 of the LA Act.

BRIEF FACTS
2. The acquisition commenced with a Notification dated 23.06.1989
issued under Section 4 of the Act for acquisition of lands in several villages,
including Village Kilokari, for the purpose of channelization of the River
Yamuna as part of the planned development of Delhi. This was followed by
a declaration under Section 6 of the Act dated 22.06.1990. The urgency
provisions under Section 17 of the Act were also invoked in respect of the
acquired land.
3. Pursuant to the aforesaid notifications, the Land Acquisition Collector
conducted proceedings and announced Award No. 14/1992–93 dated
19.06.1992 in respect of Village Kilokari, determining the market value of
the acquired land at Rs. 27,344/- per bigha. The determination was based on
the minimum price of agricultural land fixed by the Delhi Administration
under Office Order No. F.9(20)/80-L&B/4313-16 dated 03.05.1990, with a
pro rata deduction of 15% per annum on account of the earlier issuance of
the notification under Section 4, the land having been treated as ‘Sailabi’ in
nature. Possession of the acquired land was taken in phases on 27.12.1990,
22.09.1995 and 15.10.1996.
4. Aggrieved by the compensation so determined, the appellants sought
a reference under Section 18 of the Act by filing Petition No. R-213 dated
29.07.1992 before the Land Acquisition Collector, claiming market value at
Rs. 2,000/- per square yard along with statutory benefits. The said reference,
however, was forwarded to the learned Reference Court only on 08.01.2016,
Signature Not Verified
Signed By:KAPIL
KUMAR
Signing Date:28.04.2026
16:40:18
LA.APP. 101/2019 Page 2 of 8

after a lapse of over 23 years, without any explanation from the Land
Acquisition Collector. The learned Reference Court nevertheless held the
Reference Petition to be within limitation.
5. The learned Reference Court, after framing issues and recording
evidence, disposed of the reference vide Award dated 10.04.2019. While
doing so, it placed reliance on earlier coordinate awards arising out of the
same Award No. 14/1992–93 pertaining to Village Kilokari, particularly the
award passed by the learned ADJ-02 (South), whereby compensation had
been enhanced to Rs. 89,600/- per bigha . Following the said determination,
the learned Reference Court held that the Award of the Land Acquisition
Collector did not reflect a reasoned assessment of market value and,
accordingly, enhanced the compensation to ₹89,600/- per bigha .
6. The learned Reference Court further awarded all statutory benefits,
including solatium @ 30% under Section 23(2) of the Act; the additional
amount @ 12% per annum under Section 23(1A) of the Act from the date of
notification under Section 4 till the date of the award or taking of
possession, whichever is earlier; and interest @ 9% per annum on the
enhanced amount for the first year and @ 15% per annum thereafter till the
date of deposit.
7. The present Appeal forms part of a larger batch of matters arising out
of the same Notification dated 23.06.1989 and the connected awards.
Appeals pertaining to Village Kilokari and adjoining villages, including
Nangli Razapur, Khizrabad and Garhi Mendu, were heard together by
coordinate bench of this Court, with LA.APP. No. 59/2007, Bed Ram v.
Union of India & Anr . , treated as the lead case. The said batch was finally
Signature Not Verified
Signed By:KAPIL
KUMAR
Signing Date:28.04.2026
16:40:18
LA.APP. 101/2019 Page 3 of 8

decided vide Judgment dated 26.09.2025 by the coordinate bench of this
Court.
8. However, despite the present Appeal arising out of the same
Notification dated 23.06.1989, the same Award No. 14/1992–93, and
pertaining to the same village, i.e., Village Kilokari, it was not listed along
with the batch matters and did not form part of the judgment dated
26.09.2025. The record discloses that due to inadvertence, LA Appeal No.
101/2019 was not placed before this Court along with the connected batch
matters at the time of hearing and disposal of the Bed Ram batch.
9. In these circumstances, the appellants moved CM APPL 76909/2025
under Section 151 of the Code of Civil Procedure, 1908, seeking that the
present appeal be placed before this Court and decided in terms of the
judgment passed in the lead case of Bed Ram (Supra) .
10. During the pendency of proceedings, the original petitioners expired
and were substituted by their legal representatives, who are prosecuting the
present Appeal.

SUBMISSIONS OF THE PARTIES

11. Learned counsel for the appellants submits that the issues involved in
the present appeal are identical to those considered in Bed Ram (supra) and
adopts the submissions advanced therein. Learned counsel for the
respondents does not dispute that the present appeal arises from the same
Notification and Award and, likewise, adopts the submissions advanced on
their behalf in the said batch, without raising any objection.


Signature Not Verified
Signed By:KAPIL
KUMAR
Signing Date:28.04.2026
16:40:18
LA.APP. 101/2019 Page 4 of 8

ANALYSIS AND FINDINGS
12. Section 54 of the Land Acquisition Act, 1894 confers appellate
jurisdiction upon this Court to examine the correctness of an award made
under Part III of the Act. The jurisdiction is co-extensive with that of a first
appeal, enabling re-appreciation of evidence and scrutiny of the
methodology adopted for determination of market value. However, in the
present case, such independent re-assessment is not warranted, as the issues
stand concluded by the decision in Bed Ram v. Union of India & Anr. ,
LA.APP. No. 59/2007 & connected matters, decided on 26.09.2025 . The
exercise before this Court is, therefore, one of application of a determination
rendered on an identical factual and evidentiary basis, guided by the
principles of judicial discipline and parity, rather than of independent re-
adjudication.
13. The present appeal arises out of the same notification dated
23.06.1989, the same Award No. 14/1992–93, and pertains to land situated
in Village Kilokari , forming part of the very batch adjudicated in Bed Ram
(supra) by a Coordinate Bench of this Court (hereinafter referred to as the
“Coordinate Bench” ). The said decision, rendered on an identical
evidentiary record, squarely governs the present appeal.
14. Before the learned Reference Court, evidence was led by the parties
and duly considered. At the appellate stage in the Bed Ram batch, pursuant
to the liberty granted by the Hon’ble Supreme Court by order dated
13.01.2015 and the consequential Orders dated 13.03.2015 and 30.07.2015
passed by coordinate bench of this Court, additional evidence was adduced
by way of affidavit, with the appellants examining AW-1 Sh. Kailash
Sharma in LA.APP. 59/2007 and AW-1 Sh. Karan Singh in LA.APP.
Signature Not Verified
Signed By:KAPIL
KUMAR
Signing Date:28.04.2026
16:40:18
LA.APP. 101/2019 Page 5 of 8

54/2011, and the respondents examining RW-1 Sh. Ravinder Dang, Naib
Tehsildar, Office of the Land Acquisition Collector, South/East, all of whom
were duly cross-examined before this Court, and such evidence was directed
to be read across all connected appeals. The evidentiary record is identical to
that considered in Bed Ram (supra) , and in the absence of any additional
evidence, the same findings also apply to present appeal.
15. The finding of the learned Reference Court that the reference was
within limitation has not been challenged in the present Appeal and is not
disturbed.
16. In Bed Ram (supra) , the Coordinate Bench undertook a
comprehensive evaluation of the evidentiary record and all relevant factors
governing determination of market value, including sale exemplars, the
nature and character of the land, its location and development potential, the
statutory framework, and the principle of parity. Upon such evaluation, the
registered Sale Deed dated 17.03.1988 pertaining to Village Kilokari at
Rs.2,07,500/- per Bigha was accepted as the highest, proximate and duly
proved exemplar. The ‘ Sailabi ’ classification adopted by the Land
Acquisition Collector was rejected as unsupported by the record, and the
land was held to possess significant development potential. The
respondents’ Sale Deeds were found not proved in accordance with law. The
determination was further reinforced by application of the principle of
parity, having regard to the same notification, public purpose, and uniform
LAC rate across the four villages, and was rendered pursuant to the
directions of the Supreme Court in Union of India v. Ram Lal & Ors. , Civil
Appeal No. 1939/2012 .


Signature Not Verified
Signed By:KAPIL
KUMAR
Signing Date:28.04.2026
16:40:18
LA.APP. 101/2019 Page 6 of 8

CONCLUSION
17. In view of the foregoing, the present Appeal is squarely governed by
the Judgment of the Coordinate Bench in Bed Ram v. Union of India &
Anr., LA.APP. No. 59/2007. The notification, the Award, the village, and
the evidentiary record being identical, no independent re-determination of
market value is warranted. No distinguishing feature of fact or law has been
brought to the notice of this Court. Judicial discipline and the principle of
parity require uniform application of the said determination to the present
Appeal, as any deviation would result in arbitrary and discriminatory
treatment of similarly situated landowners under the same notification,
which neither the statute nor the principles of fair compensation permit.
18. This Court thus, in consonance with the aforesaid position, deems it
apposite to Award compensation for the acquired land in Village Kilokari
at the rate of Rs.2,07,500/- per bigha , in terms of the determination of the
Coordinate Bench, there being no justification to depart therefrom in the
absence of any distinguishing feature.
19. The Appeal are accordingly allowed. The Appellant are entitled to
receive compensation at the rate of Rs. 2,07,500/- per bigha .
20. Since the Appellant have already received compensation at the rate of
Rs.89,600/- per bigha , the balance amounts shall be paid to the Appellants
along with interest and all other statutory benefits, in accordance with law.
21. Section 28A of the LA Act provides that where in an Award the Court
allows compensation to an applicant in respect of the acquired land, all
persons whose land had been similarly acquired would be awarded the same
compensation, even if they had not applied for the same. Once a particular
rate of compensation is judicially determined, the benefit of such rate must
Signature Not Verified
Signed By:KAPIL
KUMAR
Signing Date:28.04.2026
16:40:18
LA.APP. 101/2019 Page 7 of 8

be given to all persons whose land was acquired under the same
Notification. Thus, the appellant, whose land has been acquired in Village
Kilokari, shall be entitled to the enhanced compensation.
22. The CM APPL 76909/2025 filed under Section 151 of the Code of
Civil Procedure, 1908 seeking disposal of the present Appeal in terms of the
Judgment in Bed Ram (supra) is allowed . There shall be no order as to
costs.

SHAIL JAIN, J
APRIL 28, 2026
RM
Signature Not Verified
Signed By:KAPIL
KUMAR
Signing Date:28.04.2026
16:40:18
LA.APP. 101/2019 Page 8 of 8