Kotak Mahindra Bank Limited vs Naren Sheth The Resolution Professional Of Dbm Geotechnics & Construction Pvt. Ltd & Ors.

Court
National Company Law Appellate Tribunal
Case type
IA
Decided on
10-04-2026
<div> <b>NATIONAL COMPANY LAW APPELLATE TRIBUNAL </b><br /> <b>PRINCIPAL BENCH, NEW DELHI </b><br /> <b> </b><br /> <b>I.A. No. 7489 of 2025 </b><br /> <b>In </b><br /> <b>Comp. App. (AT) (Ins) No. 1952 of 2025 </b><br /> <b> </b><br /> <b>IN THE MATTER OF: </b> <b> </b><br /> <b>Kotak Mahindra Bank Ltd. </b> <b> …Appellant(s) </b><br /> <b> </b><br /> <b>Versus </b><br /> <b>Naren Sheth, The RP of DBM Geotechnics &amp; </b><br /> <b>Construction Pvt. Ltd. &amp; Ors. </b><br /> <b> …Respondent(s) </b><br /> <b>Present: </b> <b> </b><br /> <b>For Appellant </b> <b>: </b> Mr. Nakul Mohta, Ayush Kashyap, Rohit K. Debnath, <br /> Adv. <br /> <b>For Respondents </b> <b>: </b> Mr. J. Rajesh, Ms. Pallavi Pratap, Anupriya Dixit, Md. <br /> Arsalan Ahmed, Yashwardhan Aggarwal, Ali Abbas <br /> Masoodi, Adv. for R1 <br /> Mr. Harshit Khare, Ayuj Agrawal, Adv. for SBI <br /> <b> </b><br /> <b> </b><br /> <b>O R D E R </b><br /> <b>(Hybrid Mode) </b><br /> <b> </b><br /> <b>Per: Barun Mitra, Member (Technical) </b><br /> <b> </b><br /> <b> </b> I.A. No. 7489 of 2025 is an application filed by the Appellant praying <br /> for condonation of 112 days’ delay in re-filing of Company Appeal (AT) (Ins) <br /> No. 1952 of 2025. <br /> <b>2.</b> It is the submission of the Appellant that the delay occurred due to <br /> defects pointed out by the Registry in the appeal petition which was not only <br /> voluminous but contained documents which were illegible and required re-<br /> scanning, re-typing and re-compilation. The principal reason attributed for <br /> the delay was the impediments faced in the retrieval of certain original <br /> documents located in Mumbai which were not readily traceable. This resulted <br /> in 112 days delay in refiling despite diligent and bonafide efforts having been <br /><br /> made by the Applicant in curing the defects. The relevant excerpts from the <br /> pleadings made by the Applicant are as reproduced below: <br /> <i>“3. It is respectfully submitted that after filing the Appeal, the Registry </i><br /> <i>pointed out several defects requiring correction. The Appeal contains </i><br /> <i>multiple voluminous annexures, including forensic audit-related material, </i><br /> <i>minutes of CoC meetings, correspondence exchanged during CIRP, and </i><br /> <i>subsequent IBBI disciplinary orders. Several of these documents were not </i><br /> <i>fully legible and required rescanning, re-typing, and re-compilation to </i><br /> <i>satisfy the Registry’s requirements. </i><br /> <i>4. The process of curing the defects required the Appellant to retrieve </i><br /> <i>documents from internal archives and match them with the CIRP record, </i><br /> <i>many of which were not readily available in legible form. Further, the </i><br /> <i>original documents which were clear and required for the purpose of the </i><br /> <i>present Appeal were largely situated in Mumbai, and due to the IA No. </i><br /> <i>1000 of 2021 being sub-judice for a long period of time, the original records </i><br /> <i>were not easily traceable. This necessitated coordination between </i><br /> <i>different internal departments of the Appellant, resulting in unavoidable </i><br /> <i>administrative delay. </i><br /> <i>5. It is further submitted that the Registry’s objections required re-</i><br /> <i>pagination, restructuring of the index, cross-referencing of annexures, and </i><br /> <i>preparation </i> <i>of </i> <i>typed </i> <i>copies </i> <i>of </i> <i>multi-page </i> <i>audit </i> <i>records </i> <i>and </i><br /> <i>correspondence. The said process took considerable time despite diligent </i><br /> <i>efforts on the part of the Appellant.” </i><br /> <br /> <br /> <b>3.</b> Notice was issued by this Tribunal on 23.12.2025 in respect of the <br /> present I.A. and the Respondent granted time to file reply to the Application <br /> seeking condonation of delay in re-filing. The order reads as under: <br /> <i>“…….Notice be issued to the respondents in the amended memo of parties </i><br /> <i>in I.A. No. 7489 of 2025 praying for condonation of delay of 112 days in </i><br /> <i>re-filing of the appeal. Reply be filed within three weeks. List on 03rd </i><br /> <i>February, 2026.” </i><br /> <i> </i><br /> <b>4.</b> Pursuant thereto, reply has been filed by the Respondent opposing the <br /> Application for condonation of delay in re-filing. Reply has been filed by the <br /> Respondent to the refiling delay condonation application of the Applicant. In <br /> Page <b>2</b> of <b>8</b> <br /> <b>I.A. No. 7489 of 2025 In CA(AT)(Ins) No. 1952 of 2025 </b><br /> <br /><br /> the reply, the Respondent has opposed the grounds of condonation cited by <br /> the Applicant by holding them to be bald and vague assertions and submitted <br /> as below: <b> </b><br /> <i>3. It is respectfully submitted that the Hon&#x27;ble Appellate Tribunal has </i><br /> <i>reiterated in a catena of judgements that delay in re-filing of the memo </i><br /> <i>of appeal can only be condoned if it is sufficiently explained. However, </i><br /> <i>in the present case the Appellant neither has sufficiently explained </i><br /> <i>the delay nor has provided any cogent reasons for the condonation of </i><br /> <i>the delay. It is submitted that it is no longer res integra that every </i><br /> <i>defect raised by the Registry must be explained and if the justification </i><br /> <i>provided by the Appellant is not reasonable, then such an application </i><br /> <i>along with the appeal must be rejected at the threshold. In this regard, </i><br /> <i>the Respondent would seek the kind leave of the Hon&#x27;ble Court to </i><br /> <i>place their reliance on the following judgements: </i><br /> <i>a.</i> <i> </i> <i>Technio Business Solutions vs Ancare Management </i><br /> <i>Pvt. Ltd. 2025 SCC OnLine NCLAT 1240. </i><br /> <i> </i><br /> <i>b.</i> <i>Lakhani Realty LLP vs Kailash Shah RP of Jaatvedas </i><br /> <i>Constructions Co. Pvt. Ltd. 2025 SCC OnLine NCLAT 1204. </i><br /> <i>c.</i> <i> </i> <i>Shri B. Mahesh vs Mr. Abhay Narayan Manudhane in </i><br /> <i>I.A. No. 1527 of 2025 in Company Appeal (AT) (Ins.) No. 419 </i><br /> <i>of 2025. </i><br /> <i>d.</i> <i> </i> <i>Bimla Maheswari vs Bank of Baroda and Anr. in I.A. </i><br /> <i>No. 13 of 2025 in Company Appeal (AT) (INS.) No. 25 of </i><br /> <i>2025. </i><br /> <i> </i><br /> <b>5.</b> We have also heard the submissions made by the Learned Counsels for <br /> both the parties and perused the material on record. The question which falls <br /> for determination is whether the Applicant has made out sufficient cause to <br /> explain the 112 days’ delay in re-filing of the Appeal for condonation thereof. <br /> <b>6.</b> It is the case of the Applicant that after filing of this Appeal, the Registry <br /> had pointed out several defects which required rectification. Since the appeal <br /> petition comprised of voluminous annexures including forensic audit <br /> material, minutes of CoC meetings, IBBI disciplinary orders etc. and many of <br /> Page <b>3</b> of <b>8</b> <br /> <b>I.A. No. 7489 of 2025 In CA(AT)(Ins) No. 1952 of 2025 </b><br /> <br /><br /> these required to be re-scanned and re-typed, the whole process was a time-<br /> consuming exercise. Additionally, compliance with the Registry’s procedural <br /> objections regarding re-pagination, index-restructuring, cross-referencing of <br /> annexures etc. needed time for compliance. To cap it all, it also entailed <br /> retrieval of original documents. As these documents were not easily traceable <br /> since they were lying in Mumbai, this further compounded the delay. Hence, <br /> despite the best of endeavours, curing of these defects took a lot of time and <br /> therefore, this delay having been occasioned by genuine reasons need to be <br /> construed liberally in the interest of justice. It was further contended that on <br /> similar grounds of distance coming in the way of timely search of original <br /> records, the Hon’ble Apex Court in <b><i>CA Ramachandra Dallaram Choudhary </i></b><br /> <b><i>vs. Adani Infrastructure &amp; Developers Pvt. Ltd.</i></b> <b> in </b> <b><i>Civil Appeal No. 5106 </i></b><br /> <b><i>of 2023</i></b> had over-ruled the decision of this Tribunal in not allowing refiling <br /> delay condonation of 115 days and held that a liberal approach ought to be <br /> adopted while considering applications for condonation of delay so that <br /> matters are decided on merits. In the present case too, since the Applicant <br /> could not trace some of the original records, the 112 days delay should be <br /> condoned. It was therefore asserted that since present is a case where the <br /> delay was caused by practical difficulties, the same needs to be given due <br /> consideration and the delay condoned so that the cause of substantial justice <br /> is well served. It was contended that the explanation offered constituted <br /> sufficient cause to justify the refiling delay, the delay should be condoned and <br /> let the matter be decided on a contested hearing. <br /> <b>7.</b> Repelling the grounds for delay condonation raised by the Applicant, <br /> the Respondent vehemently contended that these explanations are devoid of <br /> Page <b>4</b> of <b>8</b> <br /> <b>I.A. No. 7489 of 2025 In CA(AT)(Ins) No. 1952 of 2025 </b><br /> <br /><br /> merit; lack in bonafide and is wholly unsupported by any cogent material. The <br /> grounds of re-pagination, restructuring of appeal paper book, compilation of <br /> annexures, re-scanning of documents and retrieval of records from different <br /> locations relied upon by the Applicant are vague, routine and procedural in <br /> nature and they do not constitute sufficient cause for condoning such an <br /> inordinate and protracted delay of 112 days. It is further submitted that no <br /> defect sheet has been placed on record nor has any specific defect been <br /> identified, the redressal of which required so much time. The Applicant having <br /> failed to demonstrate due diligence and promptitude on their part clearly <br /> reflected negligence in prosecuting the appeal. Reliance was placed on the <br /> judgment of this Tribunal in <b><i>Dhanlaxmi Bank Limited Vs. Ritu Rastogi &amp; </i></b><br /> <b><i>Ors. in CA(AT)(Ins) No. 2131 of 2024</i></b> to contend that in the absence of <br /> satisfactory explanation for the period during which defects remained <br /> uncured, such delay cannot be condoned as it reflects lack of diligence. <br /> Reliance was further placed on the judgement of this Tribunal in <b><i>Govardhan </i></b><br /> <b><i>Nirman Pvt. Ltd. Vs. Vaibhav Khandelwal &amp; Anr. in CA(AT)(Ins) No. 1524 </i></b><br /> <b><i>of 2024</i></b> , wherein it has been held that delay in re-filing can be condoned only <br /> if the Tribunal is satisfied that the reasons cited were beyond the control of <br /> the Applicant. Additionally, reliance is placed on reliance is placed on yet <br /> another decision of this Tribunal in <b><i>Employees Provident Fund </i></b><br /> <b><i>Organisation Vs. H.L. Buildwell Pvt. Ltd. in CA(AT)(Ins) No. 1700 of 2024</i></b> , <br /> wherein this Tribunal had refused to condone delay in re-filing by observing <br /> that allowing such delay without convincing reasons would defeat the time <br /> bound insolvency resolution process envisaged under the IBC. <br /> Page <b>5</b> of <b>8</b> <br /> <b>I.A. No. 7489 of 2025 In CA(AT)(Ins) No. 1952 of 2025 </b><br /> <br /><br /> <b>8.</b> Coming to our analysis, in our considered view, the decisive factor in <br /> condonation of refiling delay is not as much the length and span of delay but <br /> the presence of sufficient and satisfactory cause to justify the explanation. We <br /> nevertheless cannot afford to ignore that it is well recognised that the <br /> statutory scheme of IBC mandates expeditious and time-bound adjudication. <br /> There is a need to bring about finality and certainty in litigation in IBC related <br /> matters as this Code has time-bound resolution as one of its primary and <br /> central objective. Re-filing delay can be condoned only when the Applicant <br /> can successfully demonstrate that the causes of delay were beyond its control. <br /> From the various judgments of this Tribunal relied upon by the Respondent, <br /> we clearly notice that this Tribunal has consistently held that merely by <br /> adverting to routine reasons like re-pagination, formatting issues, compilation <br /> of annexures/documents etc. cannot justify prolonged and unexplained delay <br /> in curing defects. In the present case, the explanation furnished by the <br /> Applicant is that their efforts were lost in a maze of generalised and routine <br /> internal administrative processes. Be that as it may, no defect sheet has been <br /> brought on record nor the specific defects pointed out by the Registry been <br /> disclosed nor any date-wise chronology of steps/measures taken to cure the <br /> defects have been furnished nor any material placed on record to show as to <br /> on which dates documents/records were sought, traced, rescanned, typed or <br /> recompiled. In absence of such particulars, this Tribunal is unable to assess <br /> whether the delay was genuinely unavoidable or whether the Appellant <br /> remained inactive and inert for substantial periods for unexplained reasons. <br /> There is force in the contention of the Respondent that most of the documents <br /> annexed with the Appeal were either electronic records or orders already <br /> Page <b>6</b> of <b>8</b> <br /> <b>I.A. No. 7489 of 2025 In CA(AT)(Ins) No. 1952 of 2025 </b><br /> <br /><br /> available on record, and therefore did not require any elaborate exercise of <br /> retrieval or reconstruction. Out of the annexures filed, only a limited number <br /> of documents pertained to original records, and therefore, the explanation <br /> that re-compilation and pagination consumed 112 days is ex facie <br /> unreasonable. The explanation that certain original records were situated in <br /> Mumbai or were not readily traceable also does not persuade us. The <br /> Respondent is not off the mark in contending that the Appellant cannot seek <br /> condonation on the basis of a generalized plea of logistical inconvenience and <br /> related difficulties, particularly when the Appeal was already filed and what <br /> remained to be done was curing of defects. This cannot legitimately explain a <br /> delay of as many as 112 days to invoke our discretion in favour of the <br /> Applicant’s plea for refiling delay condonation. We are, therefore, constrained <br /> to hold that the explanation offered is insufficient to warrant condonation of <br /> the delay. <br /> <b>9.</b> It is the case of the Applicant that even though there is a delay of 112 <br /> days in re-filing the Appeal, the same deserves to be condoned by adopting a <br /> liberal approach in the interest of justice by relying on the judgement of the <br /> Hon’ble Apex Court in <b><i>Dallaram Choudhary judgement supra</i></b> . There can <br /> be no quarrel with the above proposition laid down by the Hon’ble Supreme <br /> Court that a liberal approach may be adopted in appropriate cases. However, <br /> we cannot be oblivious of the fact that the Hon’ble Supreme Court in <br /> paragraph 14 of the said judgment has clearly observed that the said decision <br /> is not to be treated as a judicial precedent and that condonation of delay is to <br /> be decided on the facts and circumstances of each case. The Tribunal is, <br /> therefore, required to satisfy itself that sufficient cause and special <br /> Page <b>7</b> of <b>8</b> <br /> <b>I.A. No. 7489 of 2025 In CA(AT)(Ins) No. 1952 of 2025 </b><br /> <br /><br /> circumstances exist warranting such condonation. In the present case, for <br /> reasons already noticed in the preceding paragraph, we reiterate that the <br /> explanation furnished by the Applicant is general in nature, unsupported by <br /> material particulars and does not demonstrate due diligence on the part of <br /> the Appellant to cure the defects. Hence, the said judgment does not advance <br /> the case of the Applicant and the delay of 112 days in re-filing cannot be <br /> condoned. To our minds, the balance of convenience and equity therefore does <br /> not tilt in favour the Applicant. We do not find that any unavoidable or <br /> exceptional circumstance had come in the way of the Applicant which <br /> prevented them from refiling their application in a timely manner. <br /> <b>10. </b> Sufficient grounds not having been made out to justify the refiling delay <br /> of 112 days, IA No. 7489 of 2025 is rejected. Consequent upon the dismissal <br /> of IA for condonation of delay in refiling, the Memo of Appeal is also rejected. <br /> No costs. <br /> <br /> <b>[Justice Ashok Bhushan] </b><br /> <br /> <b>Chairperson </b><br /> <b> </b><br /> <b> </b><br /> <b> </b><br /> <b>[Barun Mitra] </b><br /> <b>Member (Technical) </b><br /> <b>Place: New Delhi </b><br /> <b>Date : 10.04.2026 </b><br /> <br /> <br /> <br /> Abdul <br /> <br /> <br /> <br /> <br /> Page <b>8</b> of <b>8</b> <br /> <b>I.A. No. 7489 of 2025 In CA(AT)(Ins) No. 1952 of 2025 </b><br /> </div>