ABDUL MAJID MATTOO vs NATIONAL HIGHWAY AUTHORITY OF INDIA AND ORS.
- Court
- Jammu and Kashmir High Court
Item No.76
Suppl List
IN THE HIGH COURT OF JAMMU & KASHMIR AND LADAKH
AT SRINAGAR
Arb P No.25/2025
ABDUL MAJID MATTOO
...PETITIONERS/APPELLANT(S)
Through:
-
Mr.
Hakim Suhail Ishtiyaq, Advocate.
Vs.
NATIONAL HIGHWAY AUTHORITY OF INDIA & ORS. …RESPONDENT(S)
Through:
-
Mr. Ilyas Laway, GA.
Mr. Adil Asmi, Advocate.
CORAM: HON’BLE MR. JUSTICE RAJNESH OSWAL, JUDGE
ORDER(ORAL)
1) This petition has been filed under Section 34 of the
Arbitration and Conciliation Act, 1996 (for short “the Act”) for
setting aside the arbitral award dated 10.06.2025 passed by
the learned Arbitrator/Divisional Commissioner, Kashmir, in
a petition filed by the petitioner for enhancement of
compensation on account of acquisition of his land by
respondent Nos. 1 and 2 under the National Highways Act,
1956.
2) The petitioner has assailed the award on the following
grounds:
I. That the learned Arbitrator has passed the award
without affording an opportunity of hearing to the
petitioner to substantiate his case;
Arb P No.25/2025 Page 1 of 7
II. That the impugned award suffers from non-
application of mind as the petitioner had filed an
application for amendment of claim on 11.04.2025,
whereas the impugned award does not take note of
any such application filed by the petitioner;
III. That the award impugned is hit by Section 34(2)(b)(ii)
of the Act, being in conflict with the policy of India,
as the same has been passed without providing an
opportunity to lead evidence to the petitioner.
3) Respondent Nos. 1 and 2 have filed their response stating
therein that the petitioner's land comprising Survey Nos. 1066
and 1067 in Village Rakh-i-Shilwat was acquired and as per
the record, the land is recorded as orchard, i.e. agricultural
land and not commercial land. It is further stated that the
valuation of the structures was carried out by PWD (R&B)
Department, Sumbal, as per the valuation Schedule, 2018,
which, at the relevant point of time, was the most recent
schedule uniformly applied across the Union Territory of J&K.
The Deputy Commissioner, Bandipora, assessed the
compensation after due process and awarded the same in
favour of the petitioner in terms of award dated 21.10.2023.
4)
It is further stated that during the course of proceedings,
the learned Arbitrator directed the Deputy Commissioner,
Arb P No.25/2025 Page 2 of 7
Bandipora, as the competent authority for land acquisition, to
constitute a team and re-evaluate the structures standing over
the land. Accordingly, the same was done and a report was
submitted before the learned Arbitrator. During arbitral
proceedings, the petitioner filed an application seeking
amendment of the claim petition, thereby relying upon fresh
assessment from the R&B Department, but without filing the
actual amended claim petition. Learned Arbitrator, after
considering all the materials including the fresh R&B report,
partially enhanced the compensation for the structure and also
held that access from highway shall be ensured by NHAI
during demolition and reconstruction of the weighbridge so as
to avoid any disruption to the operations of the godown
currently leased to Food Corporation of India, but expressly
rejected the petitioner's claim for revaluation on the ground
that the land continues to be recorded as an
agricultural/orchard in revenue records. It is stated that the
Court while hearing the petition under Section 34 of the Act
does not sit as an appellate Court over the arbitration award
and the evidence cannot be re-appreciated.
5) Mr. Hakeem Suhail Ishtiaq, learned counsel appearing
for the petitioner, has argued that the petitioner had filed an
application for amendment of the claim petition wherein some
more claims were made by the petitioner, but the learned
Arb P No.25/2025 Page 3 of 7
Arbitrator did not take note of the said application and without
affording any opportunity of hearing to the petitioner passed
the award impugned. He has further argued that, in fact, no
proceedings were conducted by the learned Arbitrator after
issuance of notice dated 24.04.2025 and straightway award
was passed.
6) Per contra , Mr. Laway, learned GA, has submitted that
the learned Arbitrator has taken note of the amendment
application and has, in fact, rejected the claim of the petitioner
in part. He further submitted that in the award it is recorded
that hearing in the petition was conducted.
7) Mr. Adil Asmi, learned counsel for the respondent, has
submitted that there is no legal infirmity in the award in terms
of Section 34 of the Act which warrants indulgence by this
Court.
8) Heard and perused the record.
9) The petitioner filed a petition for grant of compensation
in terms of Section 3G(5) of the National Highways Act, 1956,
seeking enhancement of compensation and the following
claims were made by the petitioner:
SUMMARYY OF CLAIM STATEMENT
Claim
No.
Description of Claim Amount (in Rs)
1. Enhancement of
compensation payable
for the land acquired
Rs. 14,56,377/- for the land
acquired and Rs. 61,14,345/- for
the structures, besides the
Arb P No.25/2025 Page 4 of 7
from un-irrigated
horticulture to
commercial category
solatium under Section 30(1) and
amount equivalent to 12% of the
market rate from the date of
issuance of notification under
Section 4 till passing of award or
taking of possession under Section
30(3) of the Act of 2013 followed by
the multiplier of (4) which is much
higher than what has been
awarded by the Competent
Authority.
2. Enhancement of
compensation payable
for the structures.
61,14,345/-
3. Cost of arbitration 10,00,000/-
4. Interest @16%
10) The claim was objected to by respondent No.3. During the
pendency of the petition, the petitioner filed an application
seeking amendment of the claims. However, only last page of
the said application and the affidavit are available in the record
received from the learned Arbitrator. In the application seeking
amendment of the claims, the petitioner had raised some more
claims, in addition to the claims already made before the
learned Arbitrator. Further, the notice dated 22.04.2025
reveals that the amendment application was received by the
Arbitrator, and in terms of the aforesaid notice, Executive
Engineer, PWD (R&B) Division, Sumbal, was directed to
furnish reply to the same by or before 26.04.2025. Thereafter,
in terms of another notice dated 24.04.2025, the non-
applicant, i.e. National Highways Authority of India, was
directed to remain present before the Court on 28.04.2025.
11) The record shows that the learned Arbitrator maintained
no minutes of the proceedings. Moreover, while the impugned
Arb P No.25/2025 Page 5 of 7
award rejected part of the petitioner’s claim set out in the
amendment application, it was passed without affording an
opportunity of being heard to the petitioner.
12) It is clearly established that the impugned award was
passed in complete violation of the principles of natural justice.
The Hon'ble Supreme Court of India in OPG Power
Generation (P) Ltd. v. Enexio Power Cooling Solutions
(India) (P) Ltd. , (2025) 2 SCC 417, has observed as under:
“56. Without intending to exhaustively enumerate
instances of such contravention, by way of illustration,
it could be said that:
( a ) violation of the principles of natural justice;
( b ) disregarding orders of superior courts in India or
the binding effect of the judgment of a superior court;
and
( c ) violating law of India linked to public good or
public interest, are considered contravention of the
fundamental policy of Indian law.
However, while assessing whether there has been a
contravention of the fundamental policy of Indian law,
the extent of judicial scrutiny must not exceed the limit
as set out in Explanation 2 to Section 34(2)( b )( ii )”.
13) Consequently, an award passed in violation of the
principles of natural justice, specifically without hearing the
parties, cannot sustained and is liable to be set aside.
14) In view of above, the present petition is allowed and the
award passed by the learned Arbitrator is set aside and the
matter is remitted to the Arbitrator to decide the petition
preferred by the petitioner afresh after affording due
opportunity of hearing to all the contesting parties. Needless
Arb P No.25/2025 Page 6 of 7
to say that this Court has not examined the merits of the
respective claims of the parties and has set aside the award
solely on the ground of violation of principles of natural justice.
This Court is sanguine that the learned Arbitrator shall
conclude the proceedings within the time limit prescribed
under the law.
15) A copy of this order be sent to the learned Arbitrator for
information and compliance.
(Rajnesh Oswal)
Judge
SRINAGAR
29.09.2026
“Bhat Altaf-Secy”
Whether the Order is speaking: YES
Whether the Order is reportable: YES
Arb P No.25/2025 Page 7 of 7