PUNJAB ENERGY DEVELOPMENT AGENCY (PEDA) vs PUNJAB STATE ELECTRICITY REGULATORY COMMISSION (PSERC) & Ors

Court
Appellate Tribunal For Electricity
Case type
APPEAL No. 286 OF 2015 & APPEAL
Decided on
24-03-2026
<div> <i> Judgement in Appeal Nos. 286 of 2015 &amp; 328 of 2016 </i><br /> <br /> <b>IN THE APPELLATE TRIBUNAL FOR ELECTRICITY </b><br /> <b>(Appellate Jurisdiction) </b><br /> <b> </b><br /> <b>APPEAL No. 286 OF 2015 </b><br /> <b>&amp; </b><br /> <b>APPEAL No.328 OF 2016 </b><br /> <b> </b><br /> <b>rd</b><br /> <b>Dated: </b> <b>23</b> <b> March, 2026 </b><br /> <b> </b><br /> <b>Present: Hon`ble Ms. Seema Gupta, Officiating Chairperson </b><br /> <b> </b> <b>Hon`ble Mr. Virender Bhat, Judicial Member </b><br /> <b> </b><br /> <b>APPEAL NO. 286 OF 2015 </b><br /> <b>IN THE MATTER OF: </b><br /> PUNJAB ENERGY DEVELOPMENT AGENCY (PEDA) <br /> Through its Director, Shri Balour Singh, <br /> Having office at Plot No.1-2, <br /> Sector-33 D, Chandigarh- 160034 … Appellant(s) <br /> <br /> <b><i>VERSUS</i></b> <b><i> </i></b><br /> <br /> 1. PUNJAB STATE ELECTRICITY REGULATORY COMMISSION (PSERC) <i> </i><br /> Through its Secretary, <br /> Having office at SCO No.220-221, <br /> Sector-34-A, Chandigarh-160022. <i> </i><br /> <i> </i><br /> 2. PUNJAB STATE POWER CORPORATION LIMITED(PSPCL) <i> </i><br /> Through its Chairman-cum-Managing Director, <br /> Having office at The Mall, Patiala – 147001. <br /> <br /> 3. M/S ATLANTIC POWER PRIVATE LIMITED (APPL) <br /> Through its Managing Director, <br /> Having office at H.No.528, <br /> Behind Tagore Theatre, <br /> Sector-18 B, Chandigarh – 160018. …. Respondent(s) <br /> <br /> Page <b>1</b> of <b>35</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 286 of 2015 &amp; 328 of 2016 </i><br /> <br /> Counsel on record for the Appellant(s) : Mr. Aditya Grover <br /> Mr. Arjun Grover <br /> <br /> Counsel on record for the <br /> Respondent(s) <br /> : Mr. Sakesh Kumar for Res.1 <br /> <br /> Ms. Suparna Srivastva for Res.2 <br /> Mr. Tajendar K. Joshi for Res.3 <br /> <b>APPEAL NO. 328 OF 2016 </b><br /> <b> </b><br /> <b>IN THE MATTER OF: </b><br /> M/S ATLANTIC POWER PRIVATE LTD. (APPL) <br /> Through its Managing Director, Avtar Singh Gill, <br /> Having office at H.No.131- Amravati Enclave, <br /> P.O. Chandimandir, <br /> District Panchkula -134102. … Appellant(s) <br /> <br /> <b><i>VERSUS</i></b> <b><i> </i></b><br /> <br /> <br /> 1. PUNJAB ENERGY DEVELOPMENT AGENCY (PEDA) <br /> Through its Chief Executive Officer, <br /> Having office at Plot No.1&amp;2, <br /> Sector-33, Chandigarh- 160020. <br /> <br /> <i>2. </i> PUNJAB STATE POWER CORPORATION LIMITED(PSPCL) <i> </i><br /> Through its Managing Director, <br /> Having office at The Mall, Patiala – 147001. <br /> <br /> <i>3. </i> PUNJAB STATE ELECTRICITY REGULATORY COMMISSION (PSERC) <i> </i><br /> Through its Secretary, <br /> Having office at SCO No.220-221, <br /> Sector-34-A, Chandigarh-160022. <i> </i> …. Respondent(s) <br /> <i> </i><br /> <br /> <br /> Counsel on record for the Appellant(s) : Mr. Tajendar K. Joshi <br /> <br /> Page <b>2</b> of <b>35</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 286 of 2015 &amp; 328 of 2016 </i><br /> <br /> <br /> Counsel on record for the Respondent(s) : Mr. Aditya Grover <br /> Mr. Arjun Grover <br /> for Res. 1 <br /> <br /> Ms. Suparna Srivastva for <br /> Res.2 <br /> Mr. Sakesh Kumar for <br /> Res.3 <br /> <b>JUDGEMENT </b><br /> <b>PER HON’BLE MRS. SEEMA GUPTA, OFFICIATING CHAIRPERSON </b><br /> <i> </i><br /> 1. Appeal No. 286 of 2015 has been filed by Punjab Energy Development <br /> Agency, challenging the order dated 26.05.2015 in Petition No. 51 of 2014 and <br /> order dated 10.09.2015 in Review Petition No. 6 of 2015 in Petition No. 51 of <br /> 2014 passed by the Punjab Electricity Regulatory Commission. <br /> <br /> 2. Appeal No. 328 of 2016 has been filed by M/s Atlantic Power Private Ltd., <br /> challenging the order dated 26.05.2015 in Petition No. 51 of 2014 <b>(</b> hereinafter <br /> referred as <b> “Impugned Order”</b> ) passed by the Punjab Electricity Regulatory <br /> Commission. <br /> <br /> 3. Since these two appeals are cross appeals against the same order and are <br /> integrally connected, these are being disposed of by this Common Judgement. <br /> For the sake of convenience, the description of the parties is given here under as <br /> per appeal No.286 of 2015. <br /> <br /> <b><i>DESCRIPTION OF PARTIES: (as per Appeal No.286 of 2015) </i></b><br /> Page <b>3</b> of <b>35</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 286 of 2015 &amp; 328 of 2016 </i><br /> <br /> 4. Punjab Energy Development Agency <b>(</b> hereinafter referred as <b> “PEDA</b> ), the <br /> Appellant herein, is the nodal agency for the implementation of the NRSE Policy <br /> on behalf of the Government of Punjab for the development of NRSE projects. <b><i> </i></b><br /> 5. Respondent No 1 is the Punjab State Electricity Regulatory Commission <br /> <b>(</b> hereinafter referred as <b> “PSERC/State Commission”</b> ) is the State Electricity <br /> Regulator exercising the powers and discharging the functions as per the <br /> provisions of Electricity Act, 2003. <br /> <br /> 4. Respondent No 2 is Punjab State Power Corporation Ltd. <b>(</b> hereinafter <br /> referred as <b> “PSPCL”</b> ) is the distribution licensee supplying electricity to the <br /> consumers in the state of Punjab as per the provisions of Electricity Act 2003. <br /> <br /> 5. Respondent No 3 is M/s Atlantic Power Private Limited Power Ltd. <br /> <b>(</b> hereinafter referred as <b> “APPL”)</b> , is a company incorporated under the provisions <br /> of the Companies Act, 1956. M/s APL is Developer of the Project under reference <br /> who had preferred the petition seeking re-determination of tariff qua the project <br /> before the State Commission (Appellant in Appeal 328 of 2016). <br /> <br /> <b><i>FACTUAL MATRIX OF THE CASE: - </i></b><br /> <b><i> </i></b><br /> 6. The Government of Punjab with the aim to revive the Holy Bein rivulet, <br /> significant for its religious ties to Shri Guru Nanak Dev Ji, the first Sikh Guru, who <br /> was enlightened there and began his first Holy March in 1500 A.D, during the <br /> meeting on 11.03.2009, PSPCL (formerly PSEB) agreed to release 350 cusecs <br /> of water from Mukerian Hydel Channel Stage-II into the Holy Bein, and appointed <br /> a Project Coordinator to restore the ecology. <br /> <br /> Page <b>4</b> of <b>35</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 286 of 2015 &amp; 328 of 2016 </i><br /> <br /> 7. On 10.07.2009, PEDA invited bids for setting up a Mini Hydel Power Project <br /> with an estimated capacity of 500 kW on Build, Operate and Own (BOO) basis <br /> under the State New &amp; Renewable Source of Energy (NRSE) Policy, 2006, As <br /> per the bid documents, the estimated generation potential of the project was <br /> assessed at 32.85 lakh units per annum at a Plant Load Factor (PLF) of 75%. In <br /> the bid document, the applicable tariff was indicated as Rs 3.49 per unit ( base <br /> year 2006-07) with 5 annual escalation @3 % up to 2011-12 as per PSERC tariff <br /> order dated 13.12.2007. APPL, on behalf of its consortium, quoted an energy <br /> share payable to PEDA on actual generation, being 20% for the first 10 years and <br /> 30% for the subsequent 20 years. Pursuant thereto, APPL, alongwith its <br /> consortium, emerged as the highest bidder in the tendering process, and an <br /> allotment letter dated 20.08.2009 was issued to the said consortium, with APPL <br /> as the lead member, for setting up a 500 KW capacity Mini Hydel Project at <br /> Terkiana on Holy Bein on BOO basis under the NRSE Policy, 2006, stipulating a <br /> completion period of 665 days from the date of allotment. <br /> <br /> 8. On 27.08.2009, a Memorandum of Understanding (MOU) was executed <br /> between the PEDA and APPL for carrying out detailed survey and investigation <br /> of the project site and a Detailed Project Report (DPR) was submitted by APPL, <br /> which was approved by PEDA vide its letter dated 16.10.2009. As per the DPR <br /> submitted by APPL, the project capacity was of 650 KW capacity and estimated <br /> annual generation was projected at 54.60 lakh units at a PLF of 95%. <br /> <br /> 9. On 16.10.2009, an Implementation Agreement (IA) was signed between the <br /> PEDA and APPL followed by a Power Purchase Agreement (PPA) on 02.12. <br /> 2009, and the 650 kW capacity hydro project was subsequently commissioned <br /> and synchronized with the PSPCL 66 KV Grid on 31.08.2010. <br /> <br /> Page <b>5</b> of <b>35</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 286 of 2015 &amp; 328 of 2016 </i><br /> <br /> 10. On 31.01.2011, the power plant was forced to shut down on account of <br /> agitation by the local population due to severe water-logging in the agricultural <br /> fields, arising from an increase in the ground water level caused by the release <br /> of water from MHC-II into the Holy Bein. APPL, requested PEDA for resolution <br /> of the issue. <br /> <br /> 11. In the meetings held on 07.02.2011 &amp; 15.02.2011, implementation of an <br /> Escape channel was considered to be the feasible solution and same was to be <br /> constructed by Developer -APPL, and compensation of the cost of escape <br /> channel was envisaged by way of additional generation. Final approval of <br /> drawings and proposal was to be accorded by PSPCL and PID. <br /> <br /> 12. Initial drawings were submitted by developer on 23.02.2011 and after <br /> incorporating comments of the consultant and after several rounds of discussion <br /> with PSPCL and consultant and PID, drawing was approved by PEDA, PSPCL <br /> and PID on 05.10.2011. In the meantime, on 10.08.2011, a Tripartite Agreement <br /> (TPA) was executed between the PEDA, APPL and PSPCL for facilitating the <br /> restoration of the project. Pursuant thereto, on 03.04.2012, the work of Escape <br /> channel and allied works were completed by APPL and operation of the hydro <br /> project was restored. <br /> <br /> 13. On 18.11.2013, APPL, resorted to the Arbitration proceedings and filed <br /> Arbitration Case petition titled “M/s Atlantic Power Private Limited versus Punjab <br /> Energy Development Agency before the Punjab &amp; Haryana High Court, seeking <br /> appointment of nominee arbitrator on behalf of PEDA, so as to enable the two <br /> arbitrators already appointed by the APPL to appoint a third arbitrator to act as <br /> the Presiding Chairman of the Arbitral Tribunal with regard to payment of energy <br /> share to PEDA . <br /> Page <b>6</b> of <b>35</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 286 of 2015 &amp; 328 of 2016 </i><br /> <br /> 14. On 12.08.2014, APPL filed Petition No. 51 of 2014 before the State <br /> Commission seeking re-determination of tariff by treating April 2012 as the <br /> commissioning year, and submitted that due to construction of escape channel <br /> and closure of the project, the cost of the project has increased from Rs. 699 lacs <br /> to Rs. 1182 lacs and consequently the cost of generation has gone up from Rs. <br /> 2.74 per unit to Rs 5.63 per unit. APPL also sought waiver of the payment of <br /> energy share payable to the PEDA out of the energy generated and sold to the <br /> distribution licensee. <br /> <br /> 15. On 29.08.2014, Arbitration Case (No. 3 of 2014) preferred by APPL before <br /> the Punjab &amp; Haryana High Court came to be dismissed as withdrawn, with liberty <br /> granted to file a fresh petition in the event the tariff was not determined in <br /> accordance with law, considering that APPL had already approached PSERC for <br /> determination of tariff. <br /> <br /> 16. On 26.05.2015, State Commission passed the Order, impugned in the <br /> present appeal, holding that <br /> <i> </i><br /> <i>“54(i) The prayer of the petitioner for determination of tariff is not </i><br /> <i>allowed. The tariff for the project shall remain as per PPA i.e. as </i><br /> <i>determined by the Commission in its Order dated 13.12.2007 under </i><br /> <i>NRSE Policy-2006 of the Government of Punjab and agreed to in IA </i><br /> <i>dated 16.10.2009, PPA dated 02.12.2009 and TPA dated 10.08.2011 </i><br /> <i>by the parties. </i><br /> <i> </i><br /> <i>(ii)The petitioner is entitled to recover cost of Escape Channel (without </i><br /> <i>interest) from the percentage energy share of PEDA. The petitioner </i><br /> <i>shall satisfy PEDA about the actual cost incurred by the petitioner on </i><br /> <i>the construction of Escape Channel and associated works. PEDA shall </i><br /> <i>also not charge interest on the amount in arrears on account of its </i><br /> <i>percentage energy share since the synchronization of the project. After </i><br /> <i>recovery of cost of the Escape Channel and associated works, the </i><br /> Page <b>7</b> of <b>35</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 286 of 2015 &amp; 328 of 2016 </i><br /> <br /> <i>petitioner shall be liable to deduction of percentage energy share from </i><br /> <i>the energy bills of the petitioner and PEDA/PSPCL, as the case may </i><br /> <i>be, shall be entitled to percentage energy share as agreed to in the IA, </i><br /> <i>PPA and TPA. It is made clear that PSPCL is not liable to compensate </i><br /> <i>the petitioner from its energy share after it becomes entitled to the same </i><br /> <i>on the commissioning of its 18 MW MHP-11 Project. </i><br /> <i> </i><br /> <i>The petition is disposed of, in terms of above decisions and directions</i> .” <br /> <br /> 18. APPL preferred review (Petition No. 5 of 2015) of the Impugned Order, <br /> against the denial of compensation on account of interest liability on the loans <br /> availed during the period of closure of project and for construction of escape <br /> channel as well as Operation and maintenance expenses for the period when <br /> project was closed, which was disposed of by State commission vide order dated <br /> 06.11.2015. PEDA also preferred review (Petition No. 6 of 2015) before the <br /> State Commission, with regard to new facts about discharge of water, however <br /> same was dismissed by the State Commission vide order dated 10.09.2015. <br /> Aggrieved by the Impugned Order, both PEDA &amp; APPL have preferred Appeal <br /> No. 286 of 2015 and Appeal No 328 of 2016 respectively before this Tribunal. <br /> Following Paragraphs summarises the submissions made by the parties and our <br /> considerations and view. <b><i> </i></b><br /> <b>SUBMISSIONS URGED ON BEHALF OF PEDA </b><br /> <br /> <br /> 19. It is submitted that recovery from energy share of PEDA by APPL lies <br /> outside the jurisdiction of the State Commission. APPL considering the dispute <br /> to be arbitral in nature, sought appointment of an Arbitrator. By the doctrine of <br /> election, APPL could not later raise the same issue before the State Commission, <br /> nor could the Commission assume jurisdiction. APPL approached the State <br /> Commission by invoking Section 86(1)(a) of the Electricity Act, 2003, which <br /> empowers the Commission only to determine tariff, not to restrain PEDA from <br /> Page <b>8</b> of <b>35</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 286 of 2015 &amp; 328 of 2016 </i><br /> <br /> recovering energy share. Hence, the impugned orders on energy share are <br /> without jurisdiction. <br /> 20. The State Commission has erred while attributing the liability on account of <br /> cost incurred towards construction of the escape channel upon the PEDA. Under <br /> Clause 7.5 of the Implementation Agreement (IA), costs arising from Force <br /> Majeure events after project completion must be added to project cost. State <br /> Commission erred in holding that tariff was bidded; in reality, tariff remained same <br /> as generic tariff determined by the State Commission and bids were based on <br /> highest energy share. It is a settled position of law that the fundamental <br /> parameter forming the very basis of a bid cannot be altered, yet in the present <br /> case, the energy share, which constituted the basis of allotment of the Project, <br /> has been impermissibly altered by the State Commission while passing the <br /> Impugned Order. <br /> 21. State Commission failed to quantify escape channel costs and instead <br /> directed APPL to satisfy PEDA regarding actual expenditure, which is impractical. <br /> State Commission has wrongly observed that since the final design approved by <br /> PSPCL did not contain approval for discharge of 20% additional water, the APPL <br /> was not entitled to recover the cost of the escape channel by generating <br /> additional energy in terms of the MoM dated 15.02.2011. This finding completely <br /> ignores the undisputed fact that even after construction of the escape channel, <br /> the discharge of water into the Holy Bein was not fully restricted and the APPL <br /> continued to remain free to discharge water into the Holy Bein up to 20% over <br /> and above the quantity permitted through the approved escape channel. <br /> 22. State Commission has erred in construing the TPA dated 10.08.2011 as <br /> mandatory under the IA. The IA required a TPA only in specific contingencies, <br /> which did not arise here. The contractual framework was confined to the IA and <br /> PPA. The Commission misapplied the TPA provisions. The State Commission <br /> Page <b>9</b> of <b>35</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 286 of 2015 &amp; 328 of 2016 </i><br /> <br /> has thus misconstrued the date of signing of TPA mentioned therein in the IA, as <br /> at the time of signing the IA, none of the parties were aware about the contingency <br /> which has occurred. <br /> 23. The State Commission has wrongly attributed delay in approval of escape <br /> channel drawings on 05.10.2011, after a delay of seven months. The contingency <br /> was unforeseen by any of the parties and although the primary obligation to <br /> assess feasibility and conduct detailed investigations rest with the Developer-<br /> APPL, the PEDA, in the larger interest of the Project, took proactive steps to <br /> resolve the issue and it was specifically agreed that the Developer-APPL would <br /> submit drawings for creating an alternate route for water flow, i.e., the escape <br /> channel, to PSPCL and PID for approval. In the instant case as soon as the <br /> APPL submitted the final proposal on 27.06.2011 to PEDA / PID same was <br /> immediately approved on 05.07.2011 <br /> 24. The contention of the APPL that the TPA did not provide for supply of <br /> additional water for 20% extra generation towards compensation for the cost of <br /> the escape channel is misconceived. The TPA, while factoring in additional <br /> generation as compensation, expressly provided under Clause 13(B) and (C) that <br /> the Developer shall generate up to 5 million units of electricity per annum and, <br /> beyond that, share 50% of the excess energy with PSPCL towards compensation <br /> for excess water drawn from MHC-II. Further, as per the bid documents, <br /> generation of 3.285 MU per annum was envisaged against 350 cusecs of water <br /> at 75% PLF, and even after accounting for 20% additional generation, the total <br /> generation would remain below 4 MU per annum. Though not specifically worded, <br /> however the generation from the project after accounting for 20% extra <br /> generation was duly capped in the TPA. Further, it is not the case of the APPL <br /> that water to the extent of 350 cusecs plus 20% was unavailable in MHC-II. It <br /> was feasible to discharge water post-generation both through the approved <br /> Page <b>10</b> of <b>35</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 286 of 2015 &amp; 328 of 2016 </i><br /> <br /> escape channel as well as into the Holy Bein to enable generation of additional <br /> energy, the APPL failed to establish that such additional generation was not <br /> possible. <br /> 25. The State Commission has wrongly observed that the Developer-APPL has <br /> come under economic stress during the period for which the he was not at all <br /> responsible, as the PEDA and PSPCL continue to gain dominance in the matter. <br /> Despite repeated reminders and contractual obligations, the Developer-APPL <br /> has neither installed flow meters nor handed over control of regulation gates to <br /> PSPCL, leaving no effective mechanism to regulate water drawal. <br /> 26. The State Commission has wrongly fastened the entire liability for <br /> construction of the escape channel upon PEDA, overlooking the fact that the <br /> tender was issued on the basis of assured discharge of 350 cusecs from MHC-II <br /> and envisaged a discharge capacity of 500 cusecs, with a clear stipulation that <br /> the bidder would undertake detailed investigations and surveys at its own level <br /> and submit a Detailed Project Report (“DPR”). In the present case, the Developer-<br /> APPL, after conducting its own detailed survey, submitted a DPR projecting <br /> significantly higher generation of 5.46 MU per annum at 95% PLF, as against the <br /> tendered expectation of 3.285 MU per annum at 75% PLF, <br /> 27. The State Commission has erred in holding that the Appellant–PEDA did <br /> not pursue recovery of its energy share and that an amount exceeding Rs. 1 crore <br /> was already due and payable by the Developer-APPL, despite the admitted <br /> position that the APPL has failed to pay any percentage energy share since <br /> commissioning of the Project. PEDA had repeatedly requested both the APPL <br /> and PSPCL for recovery of the energy share and only a solitary payment of Rs. <br /> 5,70,000/- was made by PSPCL to PEDA from the energy bills payable to the <br /> APPL. <br /> Page <b>11</b> of <b>35</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 286 of 2015 &amp; 328 of 2016 </i><br /> <br /> 28. The State Commission has also erred in holding that the PEDA benefited <br /> from the delayed completion of the Project on the premise that it was entitled to <br /> a percentage energy share for the extended period, whereas, in fact, the APPL <br /> was liable to pay energy share to the PEDA strictly on the basis of actual energy <br /> generated in accordance with the agreed terms and conditions, and no fixed or <br /> assured amount towards energy share was payable. The grouse of the <br /> Developer-APPL, of having spent additional cost on the construction of escape <br /> channel, was well taken by the concerned departments, including but not limited <br /> to the PEDA &amp; PSPCL and APPL was facilitated with option to recover the same <br /> by way of 20% extra generation of energy from the project; and in case the APPL <br /> failed to do so, the same in no eventuality can be attributed upon the PEDA. <br /> 29. Without prejudice, the State Commission has erred in law in fastening the <br /> entire liability for the cost incurred by Developer -APPL towards construction of <br /> the escape channel solely upon PEDA, ignoring that the decision to conceptualize <br /> and implement the Project was a joint decision of PSPCL and PEDA, with clearly <br /> defined allocation of roles and responsibilities. Without prejudice thereto, the <br /> Impugned Orders have been passed despite the State Commission itself having <br /> noted that PID was required to de-silt the Holy Bein to enable it to carry a <br /> discharge of 500 cusecs of water and bidder was to undertake detailed studies <br /> and investigations and submit a DPR accordingly. <br /> 30. Without prejudice, the State Commission has further erred in directing that <br /> the energy shares payable to the Appellant–PEDA shall be adjusted, while <br /> holding that the energy share payable to PSPCL upon commissioning of its 18 <br /> MW project shall remain unaffected, despite the admitted position that the <br /> decision to conceptualize and implement the Project was taken jointly by PID, the <br /> PEDA and PSPCL. All concerned departments acted collectively at every stage <br /> of the Project, and therefore, fastening the entire financial burden exclusively <br /> Page <b>12</b> of <b>35</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 286 of 2015 &amp; 328 of 2016 </i><br /> <br /> upon the Appellant–PEDA is arbitrary, discriminatory and contrary to settled <br /> principles of law. <br /> 31. The State Commission has failed to appreciate the contradictory and <br /> inconsistent stand taken by the Developer, who, during the pendency of the <br /> petition preferred by it, alleged non-availability of sufficient water for generation <br /> of additional energy, but subsequently, while filing its reply to the review petition, <br /> took a complete volte-face by contending that its plant was incapable of <br /> generating 20% additional energy on the ground that the plant parameters were <br /> fixed as per the DPR and that the intake, forebay, penstock and tailrace were <br /> designed only for 350 cusecs discharge. This plea is factually incorrect and <br /> contrary to the approved DPR, which provided for a 650 kW plant with 10% <br /> overload capacity and an intake size of 4.0 m × 2.5 m, yielding a cross-sectional <br /> area of 10 sq. m, through which, even at a conservative velocity of 1.5 m/sec, a <br /> discharge of approximately 15 cumecs (about 530 cusecs) could pass. Further, <br /> the drawings annexed by the Developer with its reply to the review petition were <br /> neither approved nor correct, as they incorrectly depicted the depth of the RCC <br /> intake duct as 3.356 m instead of the approved 2.5 m; in case the drawing <br /> submitted by the Developer along with the reply to the review Petition were relied <br /> upon, then, by taking the depth as 3.356 m, the discharge which can pass through <br /> the intake duct comes out to be 4.0 x 3.356 x 1.5 = 20.36 cumecs or 711 cusecs. <br /> Hence, the Petitioner had all the very opportunity to fetch 20% extra energy. <br /> 32. The State Commission has failed to appreciate that the water exit system <br /> from the powerhouse was designed with a discharge capacity of 350 cusecs <br /> through the escape channel, in addition to provision for further discharge of 20% <br /> thereof, i.e., 70 cusecs, into the Holy Bein, which itselfis capable of carrying <br /> substantially higher discharge than 70 cusecs, as is evident from the <br /> communication dated 29.05.2015 issued by the PID. Accordingly, the available <br /> Page <b>13</b> of <b>35</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 286 of 2015 &amp; 328 of 2016 </i><br /> <br /> water exit system was technically capable of handling discharge significantly in <br /> excess of an aggregate of 420 cusecs.Further, under the Tripartite Agreement <br /> dated 10.08.2011, control of the intake regulation gates of the powerhouse was <br /> to vest with PSPCL to regulate inflow into the Mini Hydel Project, while release of <br /> requisite water into the Holy Bein was to be effected through regulation gates to <br /> be provided by the Developer-APPL at the tailrace and controlled by the Punjab <br /> Irrigation Department. However, the Developer has neither made the intake and <br /> tailrace regulation gates operational nor handed them over to PSPCL and PID in <br /> terms of the contractual arrangements. <br /> <b>SUBMISSIONS URGED ON BEHALF OF RESPONDENT NO.1-PSERC </b><br /> 33. Both PEDA as well APPL have contended that in a petition under Section <br /> 86(1)(a), the State Commission could only decide the tariff and that compensation <br /> only for the cost of the escape channel is not envisaged under the section and <br /> moreover PEDA has additionally submitted it could not have been fastened with <br /> the liability for compensating the cost of escape channel and the same ought to <br /> have been passed on to consumer, if the generator could not absorb the same. <br /> In this context it is submitted that it was the error on the part of PEDA about its <br /> judgment that the Holy Bein could take 350 cusecs of water, whereas it could <br /> only take 200 cusecs, and it failed to understand as to what would happen to 150 <br /> cusec excess water. Accordingly, the State Commission fixed the liability on <br /> PEDA. The State Commission further observed that including the cost of the <br /> escape channel in the project cost would unjustly increase the tariff for consumers <br /> of PSPCL and therefore held that the Developer–APPL should be compensated <br /> from PEDA’s share of energy. It is submitted that during the period from <br /> completion of the project and its synchronization with the grid on 31.08.2010 until <br /> the execution of the Tripartite Agreement on 10.08.2011, the project was <br /> undoubtedly under economic and financial stress, as it was unable to earn <br /> Page <b>14</b> of <b>35</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 286 of 2015 &amp; 328 of 2016 </i><br /> <br /> sufficient revenue to service its debt and meet operation and maintenance <br /> expenses. The State Commission cannot ignore the fact that no party other than <br /> the developer -APPL, who had invested in the project by raising term loans, was <br /> subjected to such financial stress during the said period, while with the passage <br /> of time the respondents continued to gain a position of dominance. In these <br /> circumstances of economic duress, for which the Developer-APPL was neither <br /> responsible nor blamed, the APPL was constrained to agree to the terms of the <br /> Tripartite Agreement, including Clause 15 thereof, on the basis of which <br /> PEDA/PSPCL have contended that the expenditure incurred towards <br /> construction of the Escape Channel was voluntarily agreed to be borne by the <br /> petitioner and was of no concern to PEDA/PSPCL. State Commission is of the <br /> considered view that although the additional cost incurred by the APPL on <br /> construction of the Escape Channel does not entitle it to re-fixation of the tariff by <br /> including the same in the project cost, the APPL is nonetheless entitled to be <br /> compensated for the expenditure so incurred, notwithstanding Clause 15 of the <br /> Tripartite Agreement. <br /> <b>SUBMISSIONS URGED ON BEHALF OF APPL </b><br /> 34. It is an admitted fact that APPL has commissioned and synchronized the <br /> hydro power plant with the Grid on 31.08.2010 and on 31.01.2011, the power <br /> plant was forced to shut down due to severe water-logging in the agricultural <br /> fields, arising from an increase in the ground water level caused by the release <br /> of water from MHC-II into the Holy Bein. It is submitted that PSPCL, PEDA and <br /> the APPL signed the Tripartite Agreement (TPA) on 10.08.2011, after a lapse of <br /> th<br /> approximately 7 months from the closure of the plant for construction of the <br /> escape channel. With regard to the contention that in the TPA, APPL had agreed <br /> to bear the cost of construction of the escape channel and the associated works, <br /> it is submitted that the APPL executed the TPA under economic and financial <br /> Page <b>15</b> of <b>35</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 286 of 2015 &amp; 328 of 2016 </i><br /> <br /> duress, as during the aforesaid period it was compelled to incur continuous <br /> operation and maintenance expenses without earning any revenue, or in the <br /> alternative, earning substantially reduced revenue on account of operation of the <br /> plant at curtailed discharge. <br /> 35. Further, the one-sided nature of the Tripartite Agreement is evident from <br /> the fact, inasmuch as the Minutes of Meetings dated 07.02.2011 and 15.02.2011 <br /> categorically recorded that while the cost of construction of the escape channel <br /> would initially be borne by the APPL, it would be duly compensated for extra cost <br /> so incurred; however, this assurance was not reflected in the TPA. It is further <br /> submitted that even the designs of the escape channel were approved by PSPCL, <br /> PEDA and PID only on 05.10.2011, after an inordinate delay of about 9 months. <br /> 36. The APPL commenced construction of the escape channel and completed <br /> the same at about Rs 2.10 crore considering term loan of Rs 1.50 crore from a <br /> bank and balance Rs 0.60 crore as equity by the promoters. Upon completion <br /> of the escape channel, water discharge of 350 cusecs was permitted and regular <br /> generation of power commenced on 30.04.2012, whereas prior thereto the plant <br /> had remained completely shut for a continuous period of three months, namely <br /> February, March and April 2011, and thereafter was constrained to operate at an <br /> average discharge of only about 140 cusecs till completion of the escape channel. <br /> During the period of closure, the Appellant also suffered substantial financial loss <br /> on account of O&amp;M expenses and other incidental charges and upon aggregation <br /> of all such expenses, including interest and allied costs, the total additional cost <br /> incurred in running the project amounted to Rs 4.82 Crore. <br /> 37. In the Impugned Order, liability of compensation of the cost of escape <br /> channel has been affixed on PEDA, against their entitlement of energy share and <br /> APPL has been directed to satisfy PEDA regarding the actual cost incurred on <br /> construction of the escape channel and associated works, while clarifying that <br /> Page <b>16</b> of <b>35</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 286 of 2015 &amp; 328 of 2016 </i><br /> <br /> PSPCL would not be liable to compensate the Appellant from its energy share <br /> after it became entitled thereto upon commissioning of its 18 MW MHP-II Project. <br /> It is submitted that neither PEDA nor PSPCL disputed that the claimed cost <br /> incurred on construction of the escape channel. In the Impugned Order, though <br /> it has been observed that the project remained closed for three months and <br /> thereafter operated at a reduced discharge, leading to insufficient revenue for <br /> debt servicing and meeting O&amp;M expenses during the period from <br /> synchronization on 31.08.2010 till 30.04.2012, however compensation was <br /> restricted to only to the cost incurred by the APPL on construction of the escape <br /> channel and that too without interest. It is submitted that The APPL continued to <br /> incur interest on loans for the project and the escape channel and also suffered <br /> O&amp;M expenses during the said period, including the complete shutdown, for <br /> which it was also entitled to compensation. The Commission further erred in <br /> declining re-determination of tariff, as the energy share of PEDA was inadequate <br /> even to compensate the Appellant for the cost of the escape channel. <br /> 38. Though the Minutes of Meeting dated 15.02.2011 record a decision that the <br /> Developer-APPL would be compensated by generation of 20% additional power, <br /> the same was neither practical nor feasible, particularly as the APPL was not <br /> even a participant in the said meeting. Hydro power generation is governed by <br /> fixed parameters of discharge and head, and as per the bid documents and <br /> approved DPR, the project was designed for a discharge of 350 cusecs and a <br /> head of 7.1 meters for optimum generation, which parameters stood finalized at <br /> the time of construction of the project in the year 2010. The presumption of PEDA, <br /> PSPCL and the State that an increase of 20% in discharge would result in a <br /> corresponding increase of 20% in generation is wholly erroneous in fact and in <br /> engineering principles. The forebay, intake, penstock and tailrace outlet were <br /> designed exclusively for a discharge of 350 cusecs, and any excess discharge <br /> would reduce the net available head, thereby lowering plant efficiency and <br /> Page <b>17</b> of <b>35</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 286 of 2015 &amp; 328 of 2016 </i><br /> <br /> adversely affecting the turbine, gearbox, induction generator, auxiliaries, <br /> transformers, protection systems and SCADA, all of which were designed for an <br /> installed capacity of 650 kW. Consequently, no additional energy was available <br /> for such compensation. <br /> 39. It is further submitted that the alleged 10% overload is based solely on rare <br /> and temporary variation in head, i.e., Mukerian Hydel Channel level variation from <br /> 7.25 m to 7.75 m, and is not meant for continuous operation, as sustained <br /> overload would adversely affect and damage the turbine, gearbox, induction <br /> generator, auxiliary panels, transformers, breakers, generator breaker, capacitor <br /> bank and the SCADA system, all of which are designed for 650 KW only. PEDA <br /> is erroneously confusing availability of water with discharge, as although the <br /> Mukerian Hydel Channel carries approximately 10,000 cusecs of water, electricity <br /> generation is possible only upon permitted intake/discharge through the MHP, <br /> which was designed, approved and constructed for 350 cusecs only, and <br /> therefore the claim of 20% extra discharge is wholly imaginary and without any <br /> technical or factual basis. <br /> 40. With regard to the contention that APPL has preferred the Arbitration route <br /> and filed a petition before the Punjab and Haryana High Court under Section 11 <br /> of the Arbitration and Conciliation Act, 1996 for appointment of an arbitrator, it is <br /> submitted that withdrawal of same was permitted on the ground that APPL had <br /> already approached the State Commission for determination of tariff and the <br /> order passed by the High Court does not restrict APPL claim before State <br /> Commission to only determination of tariff. APPL has been consistent in its claim <br /> and from the very first day submitted that PEDA has failed to perform its duty. <br /> Merely because the APPL stated before the High Court that the issue relating to <br /> energy share was arbitral in nature does not imply that the same could not be <br /> adjudicated by the State Commission. Arbitration is only an alternate mechanism <br /> Page <b>18</b> of <b>35</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 286 of 2015 &amp; 328 of 2016 </i><br /> <br /> for adjudication of disputes, the distinction being that the <i> lis</i> is decided by an <br /> arbitrator appointed under the Arbitration and Conciliation Act, 1996. The issue <br /> relating to the jurisdiction and appointment of an arbitrator stands conclusively <br /> settled by the judgment of the Supreme Court dated 13.03.2008 in <b><i>“Gujarat Urja </i></b><br /> <b><i>Vikas Nigam Ltd. v. Essar Power Limited” Appeal (Civil) No. 1940 of 2008.</i></b> <br /> 41. It is further submitted that in terms of the bid documents of PEDA, release <br /> of discharge to the extent of 350 cusecs into Kali Bein was expressly assured, <br /> pursuant to the concurrence of the PSEB/PSPCL conveyed vide Memo No. Spl-<br /> 1 dated 25.05.2009. The DPR was prepared on the specific pre-condition that a <br /> full supply discharge of 350 cusecs would be made available in Holy Bein, in <br /> accordance with the bid documents. PEDA was, therefore, obligated to ensure <br /> continuous release of 350 cusecs of water into Kali Bein, which alone would <br /> enable regular generation of power up to 650 kW. However, PEDA failed to <br /> ensure the assured discharge of 350 cusecs in Kali Bein. It is also submitted that <br /> a MHL at the same site had been allotted on a BOO basis to M/s Polyplex <br /> Corporation Ltd. with an assurance of release of 500 cusecs of water; however, <br /> it was subsequently found that Kali Bein could not carry such discharge, leading <br /> to reduction of assured discharge to 350 cusecs and a corresponding reduction <br /> in project capacity from 750 kW to 500 kW, on account of which M/s Polyplex <br /> Corporation Ltd. withdrew from the project. These material facts were never <br /> disclosed to the APPL at the time of bidding. <br /> 42. PEDA has sought to contend that, in terms of the bid documents, the <br /> developer was required to conduct a survey of the project site, details of which <br /> were provided in Annexure–II to the bid documents, wherein the site was <br /> described as Western Bein (Holy Bein) Terkiana Head Works from RD 0 to RD <br /> 450 of MHC-II. The general layout drawing of the site was also annexed to the <br /> bid documents. APPL duly conducted the survey of the project site in accordance <br /> Page <b>19</b> of <b>35</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 286 of 2015 &amp; 328 of 2016 </i><br /> <br /> with the information so provided, however APPL can not be asked to survey Holy <br /> Bein of 130 Km from the project site to the Hari ke Pattan where the Bein falls. <br /> 43. The construction of the escape channel did not form part of the original <br /> scheme of the Mukerian Hydro Project, as the entire 350 cusecs of water was <br /> intended to be released into Holy Bein for feeding the Holy Sarovar of Gurudwara <br /> Sahib at Sultanpur Lodhi, however, in reality, Kali Bein was incapable of carrying <br /> more than about 125 cusecs. This position stands corroborated by the <br /> subsequent approval granted by the Irrigation Department to revised designs and <br /> drawings for release gates, under which only 125 cusecs of water is now <br /> permitted to be released into the Bein instead of 350 cusecs. These facts <br /> demonstrate that the information provided by PEDA in the bid documents <br /> regarding assured discharge was fundamentally defective and amounted to <br /> material misrepresentation, and that PEDA failed to ensure the assured <br /> discharge of 350 cusecs into Kali Bein, thereby perpetrating a fraud upon the <br /> developer-APPL. <br /> 44. The PEDA has contended that the incident constitutes a Force Majeure <br /> event under the Implementation Agreement, and it is admitted that Clause 7.5(v) <br /> of the I.A. dated 16.10.2009 provides that the additional cost incurred for remedial <br /> or alternative measures shall be added to the Project Completion Cost. The APPL <br /> had specifically contended before the State Commission that the expenditure <br /> incurred towards construction of the escape channel ought to be capitalized and <br /> included in the project cost, with a corresponding re-determination of tariff; <br /> however, the State Commission, in its discretion, did not accept the said <br /> contention. It is submitted that in the event this Tribunal is pleased to accept the <br /> plea of the Appellant, the cost so incurred may be directed to be added to the <br /> project cost and the tariff be re-determined accordingly, however for such <br /> purpose, the cost would necessarily include not only the capital expenditure of <br /> Page <b>20</b> of <b>35</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 286 of 2015 &amp; 328 of 2016 </i><br /> <br /> Rs 2.10 crore incurred on construction of the escape channel, but also the <br /> operation and maintenance expenses, interest costs and allied charges incurred <br /> during the period of complete shutdown of the plant from 29.01.2011 to <br /> 30.04.2012. <br /> 45. Regarding the contention of PEDA with regard to non-provision of flow <br /> meters by APPL, it is submitted that flow meters have no nexus with the discharge <br /> of water from the MHP, as ultrasonic sensors are installed at the intake and <br /> tailrace channels and the discharge is continuously monitored and regulated <br /> through the SCADA system controlling plant operations. Control mechanism of <br /> the discharge gate does not alter or enhance the discharge capacity, since the <br /> intake area of the plant is fixed by design. As already stated, the designed <br /> discharge capacity of the MHP is 350 cusecs and the construction of the escape <br /> channel has not, in any manner, enhanced or altered the discharge capacity of <br /> the plant. <br /> 46. State Commission has rightly held that the Appellant–PEDA stood to gain <br /> an enhanced percentage energy share by wrongly assuring that a discharge of <br /> 350 cusecs would safely pass through Holy Bein. It is submitted that but for such <br /> assurance, the APPL would not have agreed to offer a 20% energy share to <br /> PEDA. The contention of PEDA that the energy share was only to be computed <br /> on actual generation is misleading, as in the event of reduced generation <br /> insufficient even to cover O&amp;M expenses, interest and other costs, the 20% <br /> energy share could not have been offered. In view of the foregoing, the appeal <br /> filed by the PEDA is liable to be dismissed by this Tribunal. <br /> <b>SUBMISSIONS URGED ON BEHALF OF RESPONDENT NO.2 -PSPCL </b><br /> 47. It is submitted that, on the issue as to whether the construction of the <br /> Escape Channel constitutes a force majeure event and whether the cost thereof <br /> Page <b>21</b> of <b>35</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 286 of 2015 &amp; 328 of 2016 </i><br /> <br /> is required to be added to the capital cost for re-determination of tariff for the <br /> project, the State Commission, while unequivocally holding that the tariff <br /> determined pursuant to the competitive bidding process cannot be reopened or <br /> re-determined, has nevertheless taken cognizance of the fact that the generator <br /> was compelled to incur substantial additional expenditure on account of <br /> circumstances neither contemplated nor factored in at the bidding stage and <br /> wholly beyond the control of the generator, such expenditure having arisen, inter <br /> alia, due to the dominant bargaining position exercised by the Respondents <br /> during the relevant period, and it is in these circumstances that State Commission <br /> has deemed it just and appropriate to compensate the generator for the cost <br /> incurred towards construction of the Escape Channel. <br /> 48. Since PEDA derived commercial advantage in the form of enhanced <br /> energy share, it was held liable to bear the cost. The generator was allowed to <br /> recover the actual cost of construction, without interest, from PEDA’s energy <br /> share, subject to it duly satisfying PEDA, the actual cost incurred on the <br /> construction of the Escape Channel and associated works. PEDA was directed <br /> not to charge interest on arrears of its energy share since synchronization. Once <br /> recovery was complete, the agreed percentage energy share would resume, with <br /> PEDA/PSPCL entitled to its share strictly under the IA, PPA, and TPA. PSPCL <br /> shall not be liable to compensate the generator after commissioning of its 18 MW <br /> MHP-II Project. This approach balanced restitution for unforeseen expenditure <br /> with consumer interest and the sanctity of competitive bidding. <br /> 49. While PEDA had agreed to release 350 cusecs of water, responsibility for <br /> safely carrying it rested with the generator. Upon release of 200 cusecs, the <br /> inadequate cross-section of the Holy Bein caused waterlogging and farmer <br /> resentment, leading to project shutdown. The construction of the Escape <br /> Channel was thus permitted to enable the generator to ensure full generation <br /> Page <b>22</b> of <b>35</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 286 of 2015 &amp; 328 of 2016 </i><br /> <br /> from its plant, at the request of PEDA. Its design and construction did not fall <br /> within PSPCL’s scope, and no liability can be fastened upon PSPCL so as to <br /> burden consumers with higher tariff. Any issue relating to compensation is a <br /> matter strictly inter se between PEDA and the generator. The generator has <br /> already been adequately compensated relating to the construction of the Escape <br /> Channel, and accordingly the present Appeals being devoid of merit, are liable to <br /> be dismissed by this Tribunal. <br /> <br /> <b>DISCUSSION AND ANALYSIS</b> <br /> 50. Heard Mr. Aditya Grover, learned Counsel on behalf of PEDA, Mr Tajendra <br /> Joshi learned Counsel on behalf of APPL (the generator), Mr Sakesh Kumar <br /> learned Counsel on behalf of the State Commission and Ms Suparna Srivastava, <br /> learned Counsel on behalf of PSPCL and perused the written submissions of the <br /> parties and revenant documents. The State Commission in the Impugned Order <br /> has held that tariff for the project shall be as determined in tariff order dated <br /> 13.12.2007 and no re-fixing of tariff was permitted, however, generator is entitled <br /> to be compensated for the cost of construction of Escape Channel, (without <br /> interest) from the percentage energy share of PEDA, and generator-APPL to <br /> satisfy the PEDA with regard to actual cost incurred on the construction of Escape <br /> Channel. PEDA (Appellant in Appeal No 286 of 2015) is aggrieved with regard to <br /> recovery of cost of escape Channel from the energy share of PEDA, while in <br /> terms of Implementation Agreement it is covered under the force majeure clause <br /> and, accordingly, its cost should have been added in the project Cost. PEDA has <br /> also contended that State Commission has acted beyond its jurisdiction with <br /> regard to adjustment of compensation against PEDA’s energy share while <br /> determining the tariff under Section 86 (1)(a). APPL ( the Appellant in Appeal <br /> No 328 of 2016) is aggrieved by the findings that it is to be compensated only <br /> with regard to cost of escape channel, ( as per satisfaction of PEDA) and prayed <br /> Page <b>23</b> of <b>35</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 286 of 2015 &amp; 328 of 2016 </i><br /> <br /> for compensation of entire cost including escape channel cost, carrying cost, <br /> interest as well as O&amp;M expenses incurred during the period of plant closure and <br /> generation of electricity at lower then rated capacity till completion of scape <br /> Channel. It has also been contended by APPL that energy share of PEDA is not <br /> sufficient to compensate such cost. Based on the elaborate submissions <br /> advanced by the parties, the following issues emerge for consideration. <br /> <b>Issue No 1: Whether construction of the Escape Channel constitutes a force </b><br /> <b>majeure event in terms of Implementation Agreement warranting addition </b><br /> <b>of its cost to capital cost for tariff re-determination. </b><br /> 51. As noted above, the bids for setting up the hydro project with estimated <br /> potential of 500 kW was invited by PEDA, in which location of project, estimated <br /> st th<br /> annual generation as well as tariff applicable was indicated from 1 to 30 year; <br /> as Rs 3.928 for the year 2010-11 and Rs 4.4045 for balance year in terms of <br /> order dated 13.12.2007 passed by the PSERC. Bid document also indicated that <br /> discharge of 200 Cusecs has been released into the Western Bein from the <br /> Mukerien Hydel Channel II, and same shall be increased to 350 Cusecs, which <br /> shall be sufficient to generate 500 kW for the proposed project. Against the <br /> st th<br /> applicable tariff mentioned from 1 year to 30 year in Annexure III of the bid <br /> document, the bidders were required to indicate the quantum of energy share in <br /> order to secure the project and obviously, bidder quoting highest energy share <br /> would emerge as successful bidder. Pursuant to the bidding process, APPL <br /> along with its consortium emerged as successful bidder, as it undertook to share <br /> 20% of the energy for the initial ten years and 30% for the subsequent twenty <br /> years, thereby agreeing to receive 80% of the generic tariff for the first ten years <br /> and 70% thereof for the balance twenty years. <br /> 52. An MOU was executed between PEDA and APPL on 27.08.2009 to <br /> undertake further investigation and prepare the DPR. APPL thereafter submitted <br /> Page <b>24</b> of <b>35</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 286 of 2015 &amp; 328 of 2016 </i><br /> <br /> the DPR for approval, in which considering discharge of 350 Cusecs in Holy bein, <br /> the capacity of project was envisaged as 650 kW with a 10 % overload capacity <br /> and 95% PLF of the project and an Implementation agreement was signed <br /> between PEDA and APPL on 16.10.2009 to undertake the project. The project <br /> was commissioned on 31.08.2010 and there is no dispute that Holy bein could <br /> not take discharge of 350 cusecs, as the same resulted in flooding of adjoining <br /> agricultural fields. Owing to public agitation on this account, the generation project <br /> remained shut down for a period of three months, from February 2011 to April <br /> 2011, and thereafter operated at a reduced capacity until completion of the <br /> Escape Channel in August 2011. <br /> <br /> 53. There is no dispute between the parties with regard to technical <br /> requirement of construction of escape channel, as same is considered essential <br /> to operate the generation project at its rated capacity. However, with regard to <br /> compensation for the cost of escape Channel, many contentions have been <br /> made by PEDA, some of which are contradictory like; a) referring to Force <br /> Majeure clause in Implementation Agreement contended to include it as <br /> additional Capital Cost meaning thereby increase in tariff to be passed on PSPCL <br /> and ultimately to consumer, b) referring to Tripartite agreement, contented that <br /> APPL has voluntarily agreed to build the escape channel at their cost and as <br /> such APPL should have been compensated by way of extra generation by <br /> utilizing envisaged 20% extra Discharge c) contended the liability of <br /> compensating the cost of escape channel only upon PEDA, while it was joint <br /> responsibility of PEDA/PSPCL/ PID for declaration of discharge of 350 cusecs in <br /> Holy bein in the Bid Document. The Contention noted above at b &amp; c are dealt in <br /> subsequent paragraph, Insofar as contention (a) is concerned,, it is of relevance <br /> to consider the provisions of Force Majeure clause contained in the <br /> Implementation agreement; which defines <i>Force Majeure</i> as an event political <br /> and nonpolitical event as contained in Clause 7.2 and 7.3, and which is beyond <br /> Page <b>25</b> of <b>35</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 286 of 2015 &amp; 328 of 2016 </i><br /> <br /> the reasonable control of party affected and claiming force majeure. It is also not <br /> disputed that the requirement to build escape channel, or flooding of agricultural <br /> field due to constraints in Holy bein to handle discharge of 350 cusecs in not on <br /> account of APPL. We note that in the Implementation Agreement, it is evident <br /> that there is no <i>force majeure</i> which relates to non – achievement of conditions <br /> specified in the bid documents, like the present one, to be constituted as a force <br /> <br /> majeure condition, on the part of APPL as well as Respondents. <br /> 54. In our view, the limitation in achieving a discharge of 350 cusecs at Holybein <br /> is not attributable to any supervening event post-bidding, but is the consequence <br /> of inadequate investigation and erroneous estimation by the tendering authority. <br /> It is a settled principle that an agency inviting tenders is bound by the assurances <br /> and conditions set out in the bid document and is under an obligation to exercise <br /> due diligence while framing bid specifications. In the present case, the entire <br /> bidding process was premised upon the assured discharge of 350 cusecs of <br /> water, which formed the basis for determined the plant size and the quantum of <br /> energy generation, thereby enabling bidders to assess financial viability and <br /> quote energy share to PEDA. Since the bids were submitted on the basis of the <br /> conditions specified in the bid document, and as tender documents and contracts <br /> constitute binding obligations, neither party can resile therefrom. The <br /> non-feasibility or non-achievement of the stated discharge cannot be construed <br /> as a force majeure event under the Implementation Agreement, nor can it justify <br /> inclusion of the cost of the escape channel in the capital cost so as to warrant an <br /> increase in tariff beyond the generic tariff specified in the bid document, which is <br /> applicable for the Mini/Micro hydel projects. Accordingly, we find no infirmity in <br /> the Impugned Order insofar as it declines re-determination of tariff on this ground, <br /> and the Impugned Order to that extent is upheld. <br /> Page <b>26</b> of <b>35</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 286 of 2015 &amp; 328 of 2016 </i><br /> <br /> <b>Issue No 2: Who bears liability for the cost of the Escape Channel — the </b><br /> <b>generator, PEDA, or PSPCL </b><br /> 55. Referring to Tripartite agreement, it has been contended on behalf of PEDA <br /> that APPL has voluntarily agreed to build the escape channel at their own cost <br /> and as such APPL should have been compensated by way of extra generation <br /> by utilizing envisaged 20% extra Discharge and has disputed the affixing of <br /> liability of compensating the cost of escape channel only upon PEDA. It is an <br /> admitted position that after commissioning of the project on 31.08.2010, APPL <br /> was directed by PEDA on 29.01.2011 to stop the release of water due to flooding <br /> of adjoint agricultural field and consequently the generation of the project was <br /> stopped from 31.01.2011 as conveyed by APPL vide its letter dated 31.01.2011. <br /> In order to resolve the issue, the matter was deliberated at Govt level in meetings <br /> dated 07.02.2011 and 15.02.2011 and in the meeting dated 15.02.2011 chaired <br /> at secretary level, Govt of Punjab, it was decided that Escape Channel, need to <br /> be built and to recover the cost of escape channel, regulator, and other <br /> associated works, the developer may be allowed to use 20% additional <br /> discharge. Decisions taken in the meeting dated 15.02.2011, as noted in the <br /> MOM is reproduced below: <br /> <i>“1. </i> <i>PEDA will prepare the drawings for the proposed regulator on Holy </i><br /> <i>Bein, associated works, culverts and the escape channel into tail race of </i><br /> <i>MHC-II (18MW) Project and send the same for vetting and approval by </i><br /> <i>PSPCL and Chief Engineer, Drainage, PID. The operation of the proposed </i><br /> <i>regulator in the bein will rest with the Drainage Deptt. So as to maintain </i><br /> <i>the discharge in the bein as per the requirement. </i><br /> <i>2. </i> <i>PSPCL and Irrigation Drainage Deptt. Will vet the drawings within </i><br /> <i>10 days, so as to execute the proposal expeditiously. </i><br /> <i>3. </i> <i>The Developer of Mini Hydel Project will utilize 420 cusecs of </i><br /> <i>discharge upto the commissioning of MHC-II 18 MW project, but the </i><br /> <i>discharge shall be limited to 350 cusecs after the commissioning of 18MW </i><br /> Page <b>27</b> of <b>35</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 286 of 2015 &amp; 328 of 2016 </i><br /> <br /> <i>project. This is subject to final approval of drawings and proposal by </i><br /> <i>PSPCL &amp; PID Deptt. </i><br /> <i>4. The Developer of MHP Project will construct and incur the entire </i><br /> <i>expenditure required for implementation of this scheme. The expenditure </i><br /> <i>to be incurred by the developer will be compensated from the 20% extra </i><br /> <i>energy available to him upto commissioning of MHP-II 18MW project, for </i><br /> <i>a period to be calculated by PEDA which will receive its share of the energy </i><br /> <i>as per the original bid. </i><br /> <i>5. </i> <i>From the date of commissioning of PSPCL MHC-II (18MW </i><br /> <i>Project), part of PEDA&#x27;s share of energy out of MHP Project at Terkiana </i><br /> <i>(650KW), will be given to PSPCL, to compensate for the energy loss due </i><br /> <i>to the small rise in tail race water level of MHC-II 18 MW project. The </i><br /> <i>details will be mutually worked out between PEDA &amp; PSPCL.” </i><br /> <i> </i><br /> 56. From the minutes of meeting, it is interesting to note that there was no <br /> representation of APPL, while it was attended by representatives of PSPCL, PID <br /> and PEDA, consultant and liability of construction of Escape Channel was placed <br /> upon the developer. Though there was consensus among the participants in the <br /> meeting that developer need to be compensated for the construction of Escape <br /> channel and other associated works, however feasibility/ acceptance of <br /> developer for compensation of cost of escape channel by way of extra generation <br /> by utilizing extra discharge up to 420 cusecs, till commissioning of 18 MW project <br /> of PSPCL, was not ascertained. It is further noted that in the said meeting, PEDA <br /> has agreed to share some of its energy share to PSPCL, from APPL project, to <br /> compensate for the energy loss due to small rise in tail race water level of MCHII <br /> 18 MW project of PSPCL, details were to be decided mutually between PEDA <br /> and PSPCL. Subsequently, PEDA vide its letter dated 19.04.2011 addressed to <br /> PSPCL (with a copy marked to APPL), confirmed that upon commissioning of <br /> PSPCL’s MHC -II ( 18 MW ) project, its entire energy share from APPL project <br /> shall be given to PSPCL. <br /> Page <b>28</b> of <b>35</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 286 of 2015 &amp; 328 of 2016 </i><br /> <br /> 57. PEDA has relied upon clause 15 of the Tripartite Agreement, between <br /> PEDA, PSPCL and APPL signed on 10.08.2011, in order to dispute affixing of <br /> liability on PEDA to compensate for the cost of Escape channel through <br /> adjustment of its energy share, referred clause is reproduced hereinbelow: <br /> <i>“15 The entire cost of the construction of the escape channel, regulator and </i><br /> <i>associated works including syphon etc. for crossing the Holy Bein as per the </i><br /> <i>design &amp; drawings will be borne by M/s. Atlantic Power Private Limited.” </i><br /> <br /> 58. In the context of Clause 15 of the TPA, State Commission, in the Impugned <br /> Order, has observed that Project has come under the financial stress due to <br /> closure of the project and it is only the developer i.e. APPL who has invested into <br /> the project and respondents assumed dominance position and dictated the terms <br /> in signing of TPA and the developer had no option but to sign the Tripartite <br /> agreement. We agree with the observation of the State Commission in this <br /> regard. Regulators play a crucial role in balancing the interests of developers, <br /> investors, consumers and their job is essentially to take a balanced approach <br /> where multiple stakeholders have competing priorities . It is of relevance to note <br /> that despite all the concerned stakeholders (PEDA, PID, PSPCL) acknowledging <br /> in the meeting on 15.02.2011 that the developer need to be compensated for the <br /> cost of escape channel and associated works, no reference to how developer be <br /> compensated has been mentioned in the Tripartite agreement. It is also an <br /> admitted fact that APPL’s project was closed for three months ( February 2011 to <br /> April 2011) thereafter operated at lower capacity due to discharge of only 140 <br /> cusecs of water and resumed generation on normal basis only on 30.04.2012 <br /> after completion of Escape Channel, thus during this entire period it is not difficult <br /> to imagine the economic duress conditions of APPL which has been <br /> acknowledged by State Commission and in spite of Clause 15 of the Tripartite <br /> Agreement, the State Commission has held that APPL to be entitled for <br /> compensation for the cost incurred towards construction of Escape Channel. <br /> Page <b>29</b> of <b>35</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 286 of 2015 &amp; 328 of 2016 </i><br /> <br /> 59. PEDA has contended, that no delay in approval of drawings can be <br /> attributed on the part of PEDA because as soon as the APPL submitted the final <br /> proposal on 27.06.2011 to PEDA / PID same was immediately approved on <br /> 05.07.2011. We also take note, that in the minutes of meeting held on 15.2.2011, <br /> responsibility of preparing the drawing has been entrusted upon the PEDA, and <br /> construction of Escape channel on the developer, however the drawings were <br /> said to be prepared and submitted by the developer-APPL on 23.02.2011 and <br /> after several rounds of discussion, drawings were finally approved on 05.10.2011 <br /> as recorded in the Impugned Order. We don’t feel it necessary to affirm the <br /> actual date of approval of drawings, more so when there is no dispute with regard <br /> to time taken in construction of Escape Channel. However, we note that <br /> considerable time has been taken in finalisation and approval of drawings, while <br /> it was the developer-APPL, who was suffering on account of less generation <br /> during this entire period. <br /> 60. We are in agreement with the observations recorded in the Impugned Order <br /> with regard to economic duress of the Developer. It has been held in the <br /> Impugned Order that cost of Escape channel (without interest) shall be <br /> compensated by PEDA by way of its energy share, which has been disputed by <br /> PEDA that State Commission fell beyond its jurisdiction with regard to energy <br /> share as same was arbitral in nature and as such it could not have altered the <br /> bidding condition and PEDA also contended that it was the joint responsibility of <br /> PEDA/PID and PSPCL with regard to declaration of 350 cusecs of water in the <br /> Holy bein. It is a fact that construction of escape channel was neither envisaged <br /> in the Bid documents, MOU and IA and in the event, bidders knew that they <br /> have to construct Escape channel at the time of bidding, the only variable <br /> available with the bidder was to adjust the same in the energy share they want to <br /> offer, as applicable tariff was already known. The entire bidding process was <br /> conducted by PEDA, with assurance of 350 cusecs of water discharge and <br /> Page <b>30</b> of <b>35</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 286 of 2015 &amp; 328 of 2016 </i><br /> <br /> bidders submitted their bid on that basis, and it is only the PEDA which receives <br /> the energy share from the project. In the event bidders knew that 350 cusecs of <br /> water discharge can not be effected and there would be extra cost to be incurred <br /> on construction of escape channel, the energy share quoted by the bidders <br /> could have been different or rather less. We therefore hold that there is no error <br /> in the Impugned Order with regard to affixing the liability for compensation of cost <br /> of escape channel upon PEDA. <br /> 61. There is no doubt that APPL has filed a petition for seeking appointment of <br /> an arbitrator before the High court of Punjab and Haryana and subsequent to <br /> filing a petition before State Commission for redetermination of tariff, permission <br /> was granted to withdraw the petition with liberty to file afresh in the event the tariff <br /> was not determined in accordance with law. It is noted that no restriction have <br /> been placed upon APPL with regard to raising of issues before the State <br /> Commission. It is also an admitted fact that PEDA itself has given up its energy <br /> share in APPL projects to PSPCL for compensating them for their energy loss in <br /> their 18 MW project on account of slight rise in tail race head. While dealing with <br /> the petition filed by APPL for redetermination of tariff for its project, the State <br /> Commission did not find merit in re-determination of tariff, but taking cognizance <br /> of the fact that the generator was compelled to incur substantial additional <br /> expenditure in construction of Escape Channel, the State commission held that <br /> APPL is entitled to be compensated for the extra cost incurred and liability of <br /> compensation was affixed on PEDA. In such a situation, while determining the <br /> tariff under Section 86 (1) (a), of the Electricity Act, State Commission could have <br /> directed PEDA to pay for the cost of Escape Channel upfront, being held <br /> responsible for incurrence of extra cost, which is well within the jurisdiction of <br /> State Commission. In an alternative, instead of mulching PEDA with upfront <br /> payment of cost for the Escape Channel, State Commission directed to adjust the <br /> cost of escape channel against the energy share of PEDA in APPL project, in our <br /> Page <b>31</b> of <b>35</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 286 of 2015 &amp; 328 of 2016 </i><br /> <br /> view, such a direction cannot be said to fall outside the jurisdiction of the State <br /> commission while determining tariff under Electricity Act. In view of the forgoing <br /> deliberation, we find no error in the Impugned Order on this issue. <br /> 62. It has been contended on behalf of APPL, that energy share of PEDA is <br /> insufficient to compensate for the cost of Escape Channel. We find merit in these <br /> submissions, specially in the view that PEDA has made a settlement with PSPCL <br /> whereby it agreed to transfer its energy share to PSPCL post commissioning of <br /> its 18 MW project to compensate it for the energy loss due to rise in tail race <br /> head. In terms of implementation agreement, APPL has quoted the energy share <br /> of 20 % for first 10 years and 30 % for subsequent 20 years to and considering <br /> that liability has been affixed on PEDA to compensate for the cost of escape <br /> channel, the said cost shall be adjusted from the energy share due to PEDA in <br /> terms of Implementation Agreement, and only subsequent to adjustment of the <br /> cost of escape channel, PEDA can transfer its energy share to PSPCL post <br /> commissioning of their 18 MW project. Matter of adjustment of compensation, to <br /> PSPCL, for the energy loss if any, shall be settled between PSPCL and PEDA. <br /> PEDA is at liberty to make upfront payment to APPL for the outstanding cost on <br /> account of construction of the Escape Channel and continue with its arrangement <br /> of allocating its energy share from the APPL project to PSPCL, post <br /> commissioning of its project. <br /> <b>Issue No 4 : Can cost of Escape Channel be compensated to APPL by extra </b><br /> <b>20 % discharge </b><br /> 63. It has been contended by PEDA that the cost of the Escape Channel could <br /> have been compensated by producing additional energy on account of the extra <br /> discharge, and that APPL failed to utilize the same. Theoretically, more water can <br /> result in higher energy generation, but only if the turbine and generator are <br /> designed to accommodate the increased flow. In practice, however, turbines are <br /> Page <b>32</b> of <b>35</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 286 of 2015 &amp; 328 of 2016 </i><br /> <br /> optimized for a specific flow range, and efficiency may decline beyond that point. <br /> Excess discharge can also lead to cavitation, vibration, or mechanical damage, <br /> and in certain cases the generator may not be rated for higher output. Further, <br /> there may be hydraulic constraints in the penstock, gates, and other structures, <br /> which may not safely pass the additional flow. <br /> 64. In view of the above, we find merit in the submissions of APPL that <br /> increased discharge does not ispo facto result in additional energy generation <br /> and there machines being not capable of generating extra energy even if higher <br /> discharge is allowed. As already mentioned above, the developer was not <br /> consulted before arriving at such a decision and though some submissions have <br /> been made by PEDA before this Tribunal, however PEDA has not drawn our <br /> attention to any such feasibility assessment/ consultation with developer to <br /> establish whether APPL’s project is capable of producing extra energy if allowed <br /> 420 cusecs of discharge instead of 350 cusecs as stated in the bid, to <br /> compensate for the cost of Escape Channel. Accordingly, the decision taken in <br /> the meeting dated 15.02.2011 that the cost of the Escape Channel to be borne <br /> by APPL, could be compensated if extra discharge of 420 cusecs was allowed <br /> until commissioning of the 18 MW project of PSPCL lacks any technical or <br /> feasibility basis. It is therefore unnecessary for us to delve further in this, <br /> regarding other contentions like absence of flow meter to monitor the actual <br /> discharge more than 350 cusecs. This issue is, therefore, decided against PEDA. <br /> <b>Issue No 5 : Amount of compensation for Escape Channel </b><br /> <br /> 65. It has been contended on behalf of APPL that it should be compensated for <br /> the complete cost incurred including cost of Escape channel, carrying cost, <br /> interest and O&amp;M expenses incurred when the project remained closed or <br /> operated at lower capacity and tariff be re-determined. In the preceding <br /> Page <b>33</b> of <b>35</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 286 of 2015 &amp; 328 of 2016 </i><br /> <br /> paragraphs, the Impugned Order has been upheld regarding disallowing of tariff <br /> re-determination. With regard to cost claimed on other accounts by PEDA, we <br /> are of the view that the economic duress of APPL has been appreciated both by <br /> State Commission as well as this Tribunal, in spite of clause 15 of the TPA, and <br /> considering that matter of compensating APPL for the cost of Escape Channel <br /> has also been discussed in the meeting dated 15.02.2011, it was in the interest <br /> of justice and to encourage small hydro generation projects, this Tribunal has <br /> upheld the Impugned Order with regard to compensation for the cost of Escape <br /> Channel ( without interest). We cannot ignore the fact, that APPL never took up <br /> the matter with PEDA for compensating it with the cost of Escape Channel and <br /> other related cost, even after signing of TPA, as our attention has not been drawn <br /> to any communications/representation with PEDA in this regard and APPL chose <br /> to conveniently include all the cost in the capital cost in the petition filed before <br /> State Commission and has simply asked for re-determination of tariff, meaning <br /> thereby that same shall need to be passed on to the consumer. We also take <br /> note that in the Impugned Order it has been held that PEDA will also not charge <br /> interest on the amount in arrears on account of its energy share. As per the <br /> submissions made by PEDA, they have received only Rs 5,70,000/-, for their <br /> energy share in the project. Considering the circumstances of the present case, <br /> we do not find merit in the contention of APPL with regard to compensation <br /> towards carrying cost, interest, O&amp;M expenses, or any other additional costs <br /> beyond the cost of construction of the Escape Channel. The said contention of <br /> <br /> APPL is accordingly rejected.<br /> <br /> 66. We, however take note that in the Impugned order, the State Commission <br /> has left the finalization of cost of Escape channel to be decided amongst PEDA <br /> and APPL and as contented by both the parties, we are also of the view that there <br /> may be issues in reaching settlement of the cost between the PEDA and APPL <br /> because of competing expectations and accordingly, the Impugned Order is <br /> Page <b>34</b> of <b>35</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 286 of 2015 &amp; 328 of 2016 </i><br /> <br /> interfered and matter is remanded to the State Commission for undertaking the <br /> prudence check of cost incurred by APPL for the works related to construction of <br /> Escape Channel, for which APPL shall be compensated for the cost so approved <br /> by adjustment against PEDA’s energy share in terms of the Implementation <br /> Agreement. <br /> <b>ORDER</b> <br /> 67. In view of above deliberations, the Impugned Order is modified to the limited <br /> extent that the State Commission shall undertake a prudence check of the cost <br /> incurred by APPL towards construction of the Escape Channel and APPL shall <br /> be compensated for the cost of escape channel so worked out (without interest ) <br /> against the energy share of PEDA in terms of Implementation Agreement. Only <br /> upon full adjustment of the cost of Escape Channel to APPL, from energy share <br /> of PEDA or by upfront payment for the outstanding cost of escape channel by <br /> PEDA to APPL, if they wish to do so, PEDA can give its energy share to PSPCL <br /> to compensate it for the energy loss. <br /> The Captioned Appeals and pending IAs, if any, are disposed of in above terms <br /> <br /> <b>rd</b><br /> <b>PRONOUNCED IN THE OPEN COURT ON THIS 23</b> <b> day OF MARCH, 2026. </b><br /> <b> </b><br /> <b> </b><br /> <b>(Virender Bhat) </b><br /> <b>Judicial Member </b><br /> <b>(Seema Gupta) </b><br /> <b>Officiating Chairperson </b><br /> <b> </b><br /> <b>REPORTABLE / NON-REPORTABLE </b><br /> <i> </i><br /> <i>pd/dk/ag </i><br /> Page <b>35</b> of <b>35</b> <br /> </div>