Container Corporation Of India Ltd. vs Hindustan Engineering And Industries Ltd.
- Court
- Delhi High Court
$~
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ O.M.P. (COMM) 11/2016, I.A. 847/2016 & I.A. 5605/2021
Judgment reserved on: 10.07.2026
Judgment pronounced on: 19.08.2026
CONTAINER CORPORATION OF INDIA LTD. .....Petitioner
Through: Mr. Sanjay Jain, Sr. Adv. with
Mr. R. K. Joshi, Mr. Ojusya
Joshi, Ms. Harshita Sukhija,
Mr. Nishank Tripathi and Ms.
Rishika Agrawal, Advs.
versus
HINDUSTAN ENGINEERING
AND INDUSTRIES LTD. .....Respondent
Through: Mr. Mohit Chaudhary, Mr.
Kunal Sachdeva, Mr. Lakshay
Yadav, Ms. Aarushi Suri and
Ms. Shreya Panday, Advs.
+ O.M.P. (COMM) 50/2016
HINDUSTAN ENGINEERING
& INDUSTRIES LTD. .....Petitioner
Through: Mr. Mohit Chaudhary, Mr.
Kunal Sachdeva, Mr. Lakshay
Yadav, Ms. Aarushi Suri and
Ms. Shreya Panday, Advs.
versus
CONTAINER CORPORATION
OF INDIA LTD. & ANR. .....Respondents
Through: Mr. Sanjay Jain, Sr. Adv. with
Mr. R. K. Joshi, Mr. Ojusya
Joshi, Ms. Harshita Sukhija,
Mr. Nishank Tripathi and Ms.
Rishika Agrawal, Advs.
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 1 of 109
CORAM:
HON'BLE MR. JUSTICE OM PRAKASH SHUKLA
JUDGMENT
% 19.08.2026
INTRODUCTION
1. The present two petitions under Section 34 of the Arbitration
1 th
and Conciliation Act, 1996 , arise out of the Arbitral Award dated 13
2
October 2015 rendered by the learned Sole Arbitrator, Justice
Lokeshwar Prasad (Retd.), in Arbitration Case No. 01/2010. OMP
(COMM.) NO.11/2016 has been filed by Container Corporation of
3
India Limited , whereas OMP (COMM.) NO.50/2016 has been filed
4
by Hindustan Engineering and Industries Limited . Both petitions
assail different portions of the impugned Award. Since the petitions
arise out of same arbitral award and issues are closely connected and
depended on each other, they are being disposed of by this common
judgment.
2. Brief Factual Matrix
2.1 CONCOR, a public sector undertaking under the Ministry of
Railways, Government of India, undertook the ‘Container Transport
5
Logistics Project’ , with financial assistance from World Bank. As
part of the project, CONCOR floated a global tender, being
International Competitive Bidding No. CON/T/ICB/CW/300 on
1
“the Act”, hereinafter
2
“impugned Award” hereinafter
3
“CONCOR” or “the Purchaser”, hereinafter
4
“HEIL” or “the Supplier”, hereinafter
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 2 of 109
16.04.1994 for the design, manufacture, and supply of 300 sets of
five-wagon container flat units, consisting of 1,500 bogie container
flat wagons. The contract allowed the quantity to be increased or
decreased by up to 15%.
2.2 CONCOR’s case is that the World Bank provided a loan of
about US$94 million for the project, a significant part of which was
allocated for purchasing container flat wagons. The wagons were not
intended to be procured as individual units, but as a fleet for container
transportation. They were required to be supplied in formations of
nine five-wagon sets, each formation comprising forty-five wagons
and constituting one rake, for deployment at Tughlakabad and
Kolkata.
2.3 For the purpose of selection, the tender process had two stages:
technical evaluation and commercial bidding. The technical bids,
which were opened on 15.09.1994, were first examined, and only
those bidders whose bids were found acceptable were permitted to
participate in the commercial stage. Eleven bidders participated in the
technical stage, out of whom five bidders proceeded to the commercial
stage.
2.4 The tender, as originally issued, had Clause 2.1 of the Technical
Specifications, which required the container flat wagons to be of a
proven design that had been in commercial use on an advanced
5
“project” hereinafter
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 3 of 109
railway system for at least two years. Clause 2.1, as originally framed,
read as under:
“ Proven design - The container flat wagons offered shall be of
proven design which has been in use on any advanced railway
system in commercial service for at least two years. The offered
design should have the capability of commercial operation up to a
speed of 100 kmph on Indian Railway track system. The Bidder
shall give the following information in respect of the container flat
offered in his Bid:…”
2.5 Before the submission of the technical bids, CONCOR issued
Amendment No. 1 dated 16.06.1994, whereby the Clause 2.1 was
amended to read: “ The container flat wagons shall have design
features which have been in use on any advanced railway system
successfully for at least two years. ”
2.6 Further amendments to the tender conditions were issued by
Amendment No. 2 dated 08.07.1994, Amendment No. 3 dated
06.08.1994 and Amendment No. 4 dated 04.09.1995. These
amendments formed part of the bidding documents applicable to the
bidders. Amendment No. 4 laid down requirements relating to the
submission of design data and important drawings.
2.7 HEIL submitted its technical bid on 11.09.1994. It submitted
two technical proposals. Proposal-I was based on technology from
Trinity Industries Inc., USA, while Proposal-II was based on a design
developed with RITES. In relation to the RITES-based proposal,
HEIL referred to the BFKX/BFKI container flat wagons and
represented that the relevant design features had been successfully
used on Indian Railways since 1975.
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 4 of 109
2.8 The representations contained in HEIL’s technical proposal are
relevant to determine the nature of the design and performance
obligations undertaken by HEIL under the Contract. During the
proceedings, CONCOR relied upon the tender documents,
Amendments Nos. 1 to 4, HEIL’s technical proposal, the
correspondence exchanged before submission of the commercial bid
and letter dated 20.09.1995 by the RITES. According to CONCOR,
these documents also showed that HEIL was aware of the amended
tender conditions before submitting its commercial offer.
2.9 After being qualified in the technical round, HEIL submitted its
commercial bid on 17.10.1995, which was opened on 19.10.1995.
HEIL quoted a price of about Rs.55.25 lakhs per five-wagon set for
the bid based on Trinity technology, while it quoted about Rs.51 lakhs
per set for the RITES-based proposal. The RITES-based bid also
offered an additional discount of Rs.50,000/- per set if 65% of the
payment was made against proof of dispatch, instead of on delivery at
the destination.
6
2.10 Through the Notification of Award dated 03.04.1996 ,
CONCOR accepted HEIL’s RITES-based design proposal and
exercised the option to increase the quantity by 15%. As a result, the
quantity was increased to 345 sets of five wagons each, totaling 1,725
wagons. The formal agreement was signed on 17.04.1996 for a total
6
“ Notification of Award” hereinafter
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 5 of 109
contract value of Rs.1,71,81,35,000/- (includes General Conditions
7
and Technical Specifications) .
2.11 As per the terms of the Contract, the project commences from
the date of the Letter of Intent, i.e., 03.04.1996. According to this
schedule, HEIL was required to submit design data and important
drawings by D+30, i.e., 03.05.1996. The prototype was to be shipped
by 01.08.1996, delivered by 31.08.1996, and prototype testing was to
be completed by 29.11.1996. Thereafter, bulk supplies were to
commence, with shipment by 28.12.1996 and delivery by 28.01.1997.
The entire quantity was to be shipped by 28.12.1997 and delivered by
28.01.1998.
3. RELEVANT CONTRACTUAL CLAUSES
3.1 Before turning to the events which arose during the
performance of the contract, it would be useful to take note of the
important terms of the contract agreed between the parties in regard to
their obligations in relation to design, drawings, prototype approval
and delivery. The following clauses also form the basis for this Court
to examine the parties’ rival contentions regarding responsibility for
delay and other issues challenged in the present petition:
i. Clause 1.1.1 of the Technical Specifications stated that the
scope of work included the design, manufacture, supply, and
commissioning of the wagons. It means that the contract was
7
“Contract” hereinafter
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 6 of 109
not simply for manufacturing wagons based on a complete
design provided by CONCOR. HEIL was responsible for
developing and providing the design needed to manufacture
wagons that met the contractual specifications and
operational requirements.
ii. Clause 1.2.1 required HEIL to submit design data,
calculations, and important drawings for approval before
manufacturing the prototype and before engaging
subcontractors for critical components. This approval
process allowed CONCOR and RDSO to review the
technical aspects at different stages.
iii. Clause 1.3 means that approval of the design was only an
approval of the general acceptability of the design features
and did not relieve HEIL of its responsibility for the
performance of the wagons. HEIL was also required to
specifically bring to CONCOR’s notice any deviation from
the contractual specifications in its proposal or drawings.
iv. Clause 1.6 required HEIL to make any changes needed
during prototype manufacture or testing without claiming
additional cost. Clause 1.7 required HEIL to submit
corrected drawings after prototype development.
v. Clause 1.13.1 stated that HEIL would remain fully
responsible for the design, construction, and performance of
the wagons, even after approval of drawings, inspection,
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 7 of 109
testing, or acceptance by CONCOR. This clause was
extensively relied upon by CONCOR before the Arbitrator
and this Court.
vi. The Contract also provided for advance payment to HEIL.
Clause 11 of the Special Conditions permitted CONCOR to
provide an interest-free advance against the required
security. Pursuant thereto, CONCOR paid HEIL an advance
of Rs.33,48,58,200/- on 21.06.1996. Clause 16.3 of the
General Conditions separately provided for payments
against proper invoices or claims. The advance payment was
a financial facility provided to help HEIL with mobilisation
and procurement of materials.
vii. Clause 17 of the General Conditions provided that prices
would remain firm except to the extent price adjustment was
permitted under the Special Conditions.
viii. Clause 12.1 of the Special Conditions prescribed the
following formula for price adjustment: P1 = P0 × {a +
b(L1/L0) + c(M1/M0)} − P0. The fixed component was
specified at 15 per cent, the labour component at 25 per cent
and the material component at 60 per cent.
ix. The same clause also specified the reference dates and
indices to be used for calculating the price adjustment. The
base date was thirty days prior to the closing date of the bid,
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 8 of 109
while the adjustment date was one month prior to the date of
shipment.
x. Clause 12.2(b) placed limits on the payment of escalation. It
provided that no price increase would be allowed beyond the
original delivery period unless the extension letter
specifically provided for it. It further provided that,
ordinarily, no escalation would be payable for delays caused
entirely by the Supplier. The Purchaser, however, was
entitled to the benefit of any reduction in prices.
xi. Clause 19 of the General Conditions required any changes or
modifications to the contract to be made in writing. Clause
22.1 required HEIL to follow the agreed delivery schedule.
Clause 22.2 provided for contractual consequences in case of
unjustified delay. Clause 22.3 required HEIL to inform the
Purchaser about events that could affect timely completion
and allowed the Purchaser to grant an extension of time after
considering the circumstances.
xii. Clause 23.1 allowed CONCOR to impose liquidated
damages at the agreed weekly rate, up to the specified limit,
for delays in delivery, except where the delay was covered
by force majeure . It did not require termination of the
contract before liquidated damages could be imposed.
xiii. Clause 24 dealt with termination for default, while Clause 25
dealt with force majeure events and protected the supplier
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 9 of 109
from the consequences of delay to the extent such delay was
caused by such events, subject to notice to CONCOR.
3.2 There are no differences between the parties as to the existence
of the aforesaid clauses. The real dispute, however, arises as to how
those clauses were to operate when the contract moved from the stage
of agreed terms to actual execution, and how those contractual
provisions were to be applied or interpreted to the events that unfolded
during its execution.
4. EVENTS OCCURRED DURING THE EXECUTION OF
THE CONTRACT
4.1 HEIL submitted the first set of drawings on 10.05.1996.
CONCOR pointed out that the drawings were incomplete and that
certain important design details had not been furnished.
4.2 On 11.06.1996, CONCOR noted that detailed drawings for the
slackless drawbar arrangement and twist locks had not been provided
and therefore, the final approval of the key drawings cannot be
granted. On the same date, RITES made certain changes to the
drawings. Conditional approval was, however, granted to enable HEIL
to proceed with prototype manufacturing.
4.3 The position was reiterated by RDSO in its letter dated
14.06.1996. It recorded that the arrangements for the slackless
drawbar and twist locks had not been included and that final approval
of the important drawings could not be given. Thus, from this stage
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 10 of 109
itself, it is evident there was a difference between the parties as to
whether the deficiencies in the drawings were issues falling within
HEIL’s design responsibility or requirements which newly introduced
by the CONCOR during the approval process.
4.4 The subsequent drawings were submitted over the following
months. The wheel manufacturing drawings, along with the finite
element analysis, were submitted on 06.08.1996. The drawings for
the keystone/slack-free drawbar arrangement were submitted on
05.10.1996 and approved on 16.10.1996. CONCOR calculated the
delay in submission of these drawings at about 173 days.
4.5 The drawing for the automatic twist-lock was submitted through
RITES on 17.01.1997. CONCOR calculated the delay of 274 days
with reference to the original contractual schedule. As per the HEIL,
delay is not attributable to them as the drawings had undergone
repeated modifications during the approval due to the requirements
raised by CONCOR and RDSO.
4.6 These developments also affected the progress of the prototype.
The prototype was to be shipped by 01.08.1996 and delivered by
31.08.1996. HEIL offered the first prototype in January 1997.
However, the prototype underwent further modifications and was
cleared for dispatch on 22.03.1997.
4.7 There was also an issue regarding the cylindrical roller
bearings. The first prototype received by RDSO did not have the
required bearings. These were subsequently provided in the second
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 11 of 109
prototype on 04.06.1997 which was finally approved by RDSO on
25.09.1997, following which the wagons were cleared for series
production. CONCOR also referred to subsequent letters of HEIL
dated 26.08.1998 and 18.01.2000 in relation to the date of final
approval.
4.8 The first rake was, however, not delivered within the original
schedule. It was required to be delivered by 28.01.1997, whereas it
was actually delivered on 28.04.1998. The delay also continued
beyond the prototype approval stage as well.
5. BULK SUPPLIES AND EXTENSIONS:
5.1 During this period, HEIL sought extensions of the delivery
period from time to time. CONCOR granted ten extensions, starting
from 06.01.1998, which extended the delivery period up to
31.12.1998. The second extension, communicated in October 1998,
extended the period up to 31.07.1999. The third extension dated
30.06.1999 extended it up to 31.03.2000, and the fourth extension
dated 21.03.2000 extended it up to 31.12.2000.
5.2 The fifth extension dated 27.12.2000 extended the delivery
period up to 30.04.2001. The sixth extension dated 29.03.2001
extended it up to 30.06.2001, followed by the seventh extension dated
21.06.2001 extending it up to 31.07.2001. The eighth extension dated
03.08.2001 extended the period up to 22.08.2001, the ninth extension
dated 21.08.2001 extended it up to 15.09.2001, and the tenth
extension dated 14.09.2001 extended the period up to 05.10.2001.
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 12 of 109
5.3 The extension letters are important because it recorded that the
extensions were granted without prejudice to CONCOR’s rights under
Clause 23 of the General Conditions, including its rights to claim
liquidated damages and other contractual remedies. HEIL accepted the
extensions and continued to perform the Contract.
5.4 During the extended period, CONCOR continued to correspond
with HEIL regarding the progress of supplies. On 17.12.1997,
CONCOR referred to the concerns expressed by the World Bank
review mission regarding the progress of the project. The parties
discussed the supply schedule on 06.02.1998, and on 20.08.1998
CONCOR raised the issue of the gap between the delivery of the first
rake and the subsequent supplies.
5.5 By letter dated 17.11.1998, CONCOR referred to Clause 23.1 in
relation to the delayed deliveries and stated that liquidated damages
could not be waived. On 11.03.1999, CONCOR again referred to the
delay and reserved its rights in respect of levying liquidated damages
and other contractual remedies.
5.6 On 02.07.1999, in response to HEIL’s request for further relief,
CONCOR agreed to defer immediate recovery subject to certain
conditions and reserved its rights in respect of liquidated damages if
the revised terms agreed between the parties were not met.
5.7 The correspondence during this period also records the
continuing differences between the parties regarding the reasons for
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 13 of 109
the delay. HEIL referred to the technical issues and other
circumstances affecting the progress of the work, while CONCOR
continued to raise concerns regarding the pace of production and
supply.
5.8 During the extended delivery period, there were also disruptions
at HEIL’s manufacturing plants. The Tiljala plant faced lockout and
industrial unrest from 12.06.1999 to 15.07.2000. At Santragachi plan
as well, the industrial disruption disturbed the HEIL’s work from
28.03.2001 to 28.05.2001.
5.9 From March to June 1999 and May to October 2000, the
difficulties also arose in regard to availability and transportation of
axles from Romania to Kolkata. The contract was finally completed
with the supply of the entire agreed quantity on 16.09.2001 after a
delay of 1326 days. The delay was spread over different stages of the
contract, beginning with the design and prototype stage and continued
throughout the manufacture and supply of the remaining wagons.
5.10 CONCOR held HEIL to be responsible for the delay and
imposed liquidated damages in terms of Clause 23 which forms the
basis of the disputes between the parties. As the disputes remain
unresolved, it was referred to arbitration.
5.11 Sri K.C. Tandon was appointed as the Arbitrator on 05.11.2002.
He conducted the proceedings for about six years but withdrew on
01.07.2008 on account of ill-health. He was substituted by Shri
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 14 of 109
Ashoka Baijal who entered upon the proceedings on 07.08.2008, but
he also withdrew on 22.10.2009 due to ill-health.
5.12 The repeated change in Arbitrators delayed the completion of
the proceedings. Finally, Justice Lokeshwar Prasad (Retd.) was
appointed as the Sole Arbitrator with the consent of both the parties,
who entered upon the reference on 22.03.2010. The impugned Award
notes that the pleadings, documents, evidence, and records from the
earlier proceedings were taken into consideration, and both parties
were heard on the basis of the complete arbitral record.
6. HEIL’S PLEADINGS AND CLAIMS BEFORE THE
TRIBUNAL:
6.1 HEIL filed its Statement of Claim on 17.12.2002. As recorded
in the impugned Award, the aggregate claim raised by HEIL was
approximately Rs.77.55 crores, including interest and other
consequential claims. The principal claim was for refund of
Rs.18,88,43,273/- recovered or adjusted by CONCOR towards
liquidated damages in terms of Clause 23.
6.2 HEIL’s claim for refund of liquidated damages was based on
the argument that time was not an essential condition of the contract.
HEIL contended that CONCOR had accepted the RITES-based
design, that delays in design development and approval were caused
by repeated technical comments and changes from CONCOR and
RDSO, and that later delays were due to events beyond its control.
HEIL further argued that since CONCOR had repeatedly granted
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 15 of 109
extensions and accepted delayed performance, it could not later
recover liquidated damages for the entire delay period.
6.3 HEIL relied on Annexure-C of its Statement of Claim to
demonstrate that the original design was significantly changed during
technical review, prototype development, and approval. According to
HEIL, the changes and the time taken in the approval process affected
the contractual schedule and contributed to the delay in supply.
6.4 HEIL also raised a claim for escalation under Clause 12 of the
Special Conditions. In support of the claim, HEIL relied upon
Annexure-F attached with Statement of Claims. In respect of the first
rake, this included the escalation bill submitted in April 1998, the
revised bill dated 25.08.2000, the forwarding letter dated 30.08.2000,
the labour and material price indices, exchange-rate documents and
subsequent correspondence.
6.5 Apart from liquidated damages and escalation, HEIL raised
several other claims, including expenses for change in spring material,
modification of jigs and fixtures, loss from scrapping work-in-
progress, idle labour costs, additional wheel sets and bearings, higher
freight charges, differential interest on margin money, bank guarantee
commission, restoration of conditional price reduction, interest, and
costs.
6.6 HEIL also claimed that the Rs.50,000/- reduction per five-
wagon set should not be applied to the contract price, since the
reduction was conditional upon CONCOR making 65% of the
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 16 of 109
payment against proof of dispatch. HEIL contended that, as CONCOR
did not make payment in accordance with that condition, it was not
entitled to the benefit of the reduced price.
6.7 Before the learned Arbitral Tribunal, HEIL relied upon the
clauses relating to extension of time and force majeure , and the
clauses in relation to approval of drawings and designs. As per HEIL,
liquidated damages were compensatory in nature and were not
recoverable in the circumstances pleaded by it. It also relied upon the
subsequent conduct of the parties, including the extensions of time,
acceptance of delayed supplies and continuation of the Contract
without termination.
7. CONCOR’S DEFENCEE AND COUNTER-CLAIM
BEFORE THE TRIBUNAL:
7.1 CONCOR argued that the delay was not caused by any act or
omission on its part. Before the Tribunal, CONCOR submitted that
HEIL was aware of the tender amendments before submitting its bid,
had confirmed compliance with the required design features, accepted
the contractual timelines, and was responsible for design development,
prototype compliance, and performance of the wagons.
7.2 CONCOR relied on the sequence of delayed drawings,
prototype development, and approvals. It argued that the technical
comments raised by CONCOR and RDSO were not changes
introduced by the Purchaser but were necessary to ensure that HEIL’s
drawings and components met the contractual specifications.
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 17 of 109
According to CONCOR, the conditional approvals and technical
clearances were part of the agreed approval process and did not shift
responsibility from HEIL, particularly in view of Clauses 1.3 and
1.13.1 of the Technical Specifications.
7.3 In relation to the extensions of time, CONCOR contended that
the extensions were granted to enable completion of the Contract and
without prejudice to its rights under Clause 23 and other contractual
provisions. It denied that the grant of extensions amounted to
acceptance of the delay or waiver of its right to claim liquidated
damages. CONCOR also disputed HEIL’s claim of force majeure and
contended that the requirements relating to notice and the effect of the
alleged events on performance under Clause 25 had not been satisfied.
7.4 CONCOR defended the levy and recovery of liquidated
damages under Clause 23 of the General Conditions and relied upon
8
Sections 73 and 74 of the Indian Contract Act, 1872 . It contended
that the delayed supply of the rakes affected container movement
operations and resulted in losses which were difficult to quantify.
According to CONCOR, the liquidated damages stipulated in the
Contract provided the agreed measure of compensation, subject to the
contractual limit.
7.5 CONCOR also raised counterclaims, which were stated in the
impugned Award to be approximately Rs.522.81 crores. The principal
claim was towards loss of traffic revenue on account of the non-
availability of wagons. Other claims included interest paid to the
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 18 of 109
World Bank on advance payments, additional bank guarantee charges,
exchange-rate losses and commitment charges. CONCOR also raised
a claim for compensation beyond the liquidated damages already
recovered.
7.6 CONCOR opposed HEIL’s escalation claims by relying on
Clauses 12.1 and 12.2(b) of the Special Conditions. It argued that
escalation was not automatic and could only be granted if the
contractual formula was satisfied, and on the basis of the prescribed
adjustment date and the applicable labour and material indices.
CONCOR further contended that escalation beyond the original
delivery period was not payable in respect of delays attributable solely
to HEIL.
7.7 CONCOR also opposed HEIL’s claim for restoration of the
conditional price reduction. It argued that HEIL had already received
the benefit provided under the Contract and that restoring the
reduction would go against the agreed commercial terms.
8. EVIDENCE AND ISSUES FRAMED:
8.1 The impugned Award records the oral evidence led by HEIL
through its witness K.C. Paharia and by CONCOR through its
witnesses Harpreet Singh, Anil K. Gupta and Harish Chandra.
8
“ICA” hereinafter
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 19 of 109
8.2 The witnesses were subjected to cross-examination, and the
parties placed extensive documentary material and written
submissions before the Tribunal.
8.3 CONCOR filed an application dated 05.04.2004 seeking
production of documents relating to utilization of the advance amount
of Rs.33.48 crores, procurement records for steel and critical
components, the dates of opening of letters of credit and related
material. By order dated 07.04.2004, the Tribunal directed HEIL to
produce the documents sought by CONCOR.
8.4 HEIL did not produce the complete set of documents as ordered
by the Tribunal. By order dated 03.05.2004, the Tribunal recorded the
position regarding the non-production of the documents and left the
issue to be addressed at the appropriate stage.
8.5 After completion of the pleadings and evidences, the Tribunal
framed twenty-eight issues, including Issue No. 27A. The following
issues were framed by the Tribunal after modifications:
“(1) Whether the claimant is entitled to claim refund of the
liquidated damages amounting to Rs. 18,88,43,273.00 or any other
amount deducted by the Respondent from the claimant’s bills?
-OPC
(2) Whether the Claimant is entitled to claim escalation charges
amounting to Rs. 30,45,01,960.45 (including interest) or any other
amount on that account from the Respondent? -OPC
(3) Whether the Claimant is entitled to claim from the Respondent
the extra costs incurred by it amounting to Rs. 1,03,77,517.37
(including interest) or any other amount owing to the change in
specifications of material of springs? -OPC
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 20 of 109
(4) Whether the Claimant is entitled to claim from the Respondent
the extra expenses incurred amounting to Rs. 20,27,250.00
(including interest) or any other amount on account of
modification of jigs and fixtures? -OPC
(5) Whether the Claimant is entitled to claim from the Respondent
an amount of Rs. 24,77,750.00 (including interest) or any other
amount towards loss suffered by the Claimant owing to the
scraping of the work in progress? -OPC
(6) Whether the Claimant is entitled to an amount of Rs.
8,48,72,500.00 or any other amount from the Respondent as
compensation on account of idling of workers? -OPC
(7) Whether the Claimant is entitled to claim from the Respondent
the extra expenses incurred amounting to Rs. 28,49,112.36
(including interest) or any other amount on account of supplying 8
wheel sets and 16 bearings to the Respondent? -OPC
(8) Whether the Respondent is entitled to a reduced price of Rs.
50,000 per set of 5 wagons? -OPC
(9) Whether the Claimant is entitled to claim from the Respondent
a compensation amounting to Rs. 92,25,511.75 or any other
amount on account of increased cost or freight? -OPC
(10) Whether the Claimant is entitled to claim from the Respondent
the differential interest amounting to Rs. 90,81,924.75 or any other
amount on marginal monies kept by the Claimant with its bankers
for the additional period to secure the Respondent by the
Performance Bank Guarantee and Advance Bank Guarantee?
-OPC
(11) Whether the Claimant is entitled to claim from the Respondent
the refund of commission amounting to Rs. 4,40,19,148.57
(including interest) or any other amount paid by the Claimant to
the bank on reducing basis for the additional period during which
it was compelled to keep the Advance Bank Guarantee and the
Performance Bank Guarantee valid? -OPC
(12) Whether the Respondent is entitled to claim amounts over and
above and in addition to the liquidated damages deducted from the
bills of the Claimant? -OPR
(13) Whether the claim of the Respondent on account of the loss of
traffic is within the purview of the contract between the parties?
-OPR
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 21 of 109
(14) Whether the delay in performing the contract was not
attributable to the Claimant? -OPC
(15) Whether the Claimant had submitted the complete drawings
meeting the technical specifications as required under the contract
in time? -OPC
(16) Who had sought the changes in the designs and the drawings
from time to time? -OPC
(17) Whether the Claimant was not aware that the contract is
financed by the World Bank and the payment of the bills have to be
made after the receipt of the money from the World Bank? -OPR
(18) Whether the lock out at the claimant's plant and the non-
availability of the vessels from Romania was a force majeure
condition? If so to what effect? -OPC
(19) Whether the Respondent is entitled to a claim of Rs. 514.43
crores or any other amount on account of the loss of traffic? -OPR
(20) Whether the Respondent is entitled to an amount of Rs.
5,65,75,112 or any other amount on account of interest paid by the
Respondent to the World Bank on the advance amount? -OPR
(21) Whether the Respondent is entitled to claim any additional
guarantee fee of Rs. 1,21,48,841 from the Claimant? -OPR
(22) Whether the Respondent’s claim on account of the exchange
rate fluctuations fall within the purview of the contract between the
parties? -OPR
(23) Whether the Respondent is entitled to an amount of Rs.
77,76,638 or any other amount on account of exchange rate
fluctuations? -OPR
(24) Whether the Respondent is entitled to claim additional
commitment charges amounting to Rs. 73,05,874 or any other
amount paid to the World Bank? -OPR
(25) Whether the claim Nos.2 to 9 are de hors the contract? -OPR
(26) Whether the Claimant was liable to make regular supplies of
the wagons after the approval of the prototype? -OPR
(27) Are the parties entitled to any interest? If so, at what rate and
what amount and for what period?
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 22 of 109
(27-A) Whether any of the parties is entitled to any cost, if so, to
what extent?
(28) Relief.”
9. AWARD AND ISSUE-WISE FINDINGS:
9.1 The Tribunal first considered the issue whether time was of the
essence of the Contract and relied upon the clauses given in the
Contract for extension of time, the repeated extensions granted by
CONCOR, and the continued acceptance of supplies. On that basis,
the learned Arbitral Tribunal concluded that time was not of the
essence of the Contract.
9.2 Subsequently, the Tribunal examined the tender conditions,
amendments and technical history of the procurement. It reproduced
both the original and amended versions of Clause 2.1 of the Technical
Specifications and, therefore, noticed that the contractual requirement
relating to “proven design” had subsequently been modified. It also
considered HEIL’s RITES based proposal and the subsequent process
of prototype development and approval.
9.3 The Tribunal’s main reasoning at pages 42 to 47 and 57 to 59
was based on the view that the amended Clause 2.1 had permitted a
design which was not a proven or tested design and that CONCOR
had deliberately opted for such design. The Tribunal further held that
the adoption of this design required changes at different stages,
including preparation of key drawings, approval of the prototype and
manufacture of the wagons, and that this was a major factor
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 23 of 109
contributing to the delay. On this basis, the Tribunal held that HEIL
could not be held responsible for the delay arising from the said
process.
9.4 While deciding Issue No.14, the Tribunal relied upon its earlier
findings that time was not of the essence of the Contract and that the
delay in performance could not, in the facts of the case, be attributed
to HEIL. The Tribunal did not repeat those findings while dealing
with Issue No.14, but stated that the reasons given earlier would form
part of its reasoning on the issue.
9.5 Issues Nos. 15 and 16 were dealt at pages 128 and 129 of the
impugned Award. The Tribunal recorded that these issues stood
covered by its findings on Issue No. 14 and, on that basis, decided
both issues in favour of HEIL. Issue No. 26, concerning the regularity
of supplies after approval of the prototype, was also dealt with in the
same manner, with the Tribunal referring to its findings on the
attribution of delay.
9.6 While deciding Issue No.18 at pages 60 to 67, the Tribunal
accepted HEIL’s case regarding the Tiljala and Santragachi
disruptions and the asserted non-availability of vessels for
transportation of axles from Romania. It held that the notices issued
by HEIL were sufficient in the circumstances and that CONCOR’s
continued acceptance of supplies weakened the objection regarding
delay in notice. The issue was, accordingly, decided in favour of
HEIL.
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 24 of 109
9.7 On Issue No.1, at pages 71 to 83, the Tribunal relied upon its
conclusions that time was not of the essence, delay was not
attributable to HEIL, extensions had been granted by CONCOR, and
circumstances beyond HEIL’s control had contributed to delay. On
that basis, it directed refund of the entire amount of Rs.18,88,43,273/-
recovered towards liquidated damages.
9.8 On Issue No.2, at pages 83 to 99, the Tribunal considered
HEIL’s escalation claim. In relation to escalation, the Tribunal
allowed only the first claim forming part of Annexure-F. It considered
the initial escalation bill dated 28/29 April 1998, the revised bill No.
SP-980010E-WGN/REV dated 25.08.2000, the forwarding letter
dated 30.08.2000, the relevant labour indices, foreign exchange
material and Metal Bulletin data relating to September 1995 and
December 1997.
9.9 The revised bill claimed a basic escalation amount of
Rs.49,39,893/-, sales tax of Rs.3,95,191.44 and a total amount of
Rs.53,35,084.44. The Tribunal excluded freight of Rs.2,00,000/- and
sales tax and awarded Rs.47,39,893/- towards the first rake escalation
claim.
9.10 The Tribunal rejected the escalation claims corresponding to
Serial Nos. 2 to 12 of Annexure-F for the reasons recorded at pages 94
to 98 of the award. It noted that, for these claims, the requisite
supporting material, including contemporaneous bills, invoices or
written demands, had not been produced. It also found that the
adjustment dates corresponding to the respective shipments had also
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 25 of 109
not been established, and the relevant labour, material and exchange-
rate indices had not been furnished. The Tribunal further noted that
the calculations appeared to have been made with reference to a
common date rather than the respective dates required under the
contractual formula.
9.11 On Issue No.3, at pages 99 to 107, the Tribunal rejected HEIL’s
claim for additional expenditure relating to spring material. It held that
HEIL was responsible under the Contract for meeting the required
specifications and that the evidence supporting the claim was
insufficient.
9.12 Issues Nos.4 and 5 relating to modification of jigs and fixtures
and loss on scrapped work-in-progress were not adjudicated since
HEIL, through its counsel on 16.09.2013, stated that the said claims
were not being pressed.
9.13 On Issue No. 6, dealt with at pages 108 to 113 of the award, the
Tribunal rejected HEIL’s claim of Rs.8,48,72,500/- towards idle
labour costs. It held that HEIL had failed to establish that the plant
remained unused during the period claimed, that 935 workers
remained idle on account of the wheel-set issue, or that the wage
expenses were incurred as a result of any action or instruction of
CONCOR.
9.14 On Issue No. 7, dealt with at pages 113 to 115, the Tribunal
considered HEIL’s claim relating to eight wheel sets and sixteen
bearings. It understood HEIL’s own pleadings to mean that these
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 26 of 109
supplies were outside the original scope of the Contract. Since the
Tribunal’s jurisdiction was confined to disputes arising out of the
Contract, it declined to adjudicate the claim and left HEIL at liberty to
pursue an appropriate remedy before the competent forum.
9.15 Issues Nos. 8 and 17 were considered together at pages 115 to
124 of the impugned Award. On Issue No. 17, the Tribunal held that
the fact that the project was financed in part by the World Bank did
not make CONCOR’s payment obligations dependent upon
reimbursement by the World Bank, as the World Bank was not a party
to the Contract. On Issue No. 8, the Tribunal held that CONCOR had
not satisfied the condition for retaining the price reduction and
accordingly directed payment of Rs.1,72,50,000/- to HEIL.
9.16 Issue No. 9, concerning the claim for increased freight, was not
pressed by HEIL on 19.09.2013 and was accordingly not adjudicated
by the Tribunal. Issue No. 10, relating to differential interest on
margin money, was rejected for reasons recorded at pages 125 to 127
of the impugned Award. The Tribunal held that HEIL had not
established that the interest earned was unreasonably low or that the
differential amount claimed was recoverable from CONCOR.
9.17 Issue No. 11, concerning bank commission for continuation of
guarantees, was rejected at pages 127 to 128 of the award. The
Tribunal held that maintenance of the guarantees formed part of
HEIL’s contractual obligations during the period of performance and
that the commission claimed, including for the period in question, had
not been sufficiently proved.
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 27 of 109
9.18 On Issue No. 25, dealt with at page 129 of the award, the
Tribunal recorded that Issues Nos. 4, 5 and 9 had been given up. It
then referred to its findings on Issues Nos. 2, 3, 6, 7 and 8 and held
that the remaining claims could not be treated as claims dehors the
Contract.
9.19 Issue No. 26, concerning the supply of wagons at regular
intervals after approval of the prototype, was also dealt with at page
129. The Tribunal referred to its findings on Issue No. 14 and, on that
basis, decided Issue No. 26 in favour of HEIL.
9.20 Issues Nos.12, 13 and 19 to 24 relating to CONCOR’s
counterclaims were considered together at pages 130 to 132. The
Tribunal recorded that the counterclaims were founded upon delay
attributable to HEIL. Since it had already concluded that time was not
of the essence and delay was not attributable to HEIL, it rejected all
the counterclaims.
9.21 Under Issue No. 27, the Tribunal awarded simple interest at the
rate of 9% per annum on the amounts found payable to HEIL, to be
calculated from the respective dates on which the amounts became
payable until the date of actual payment.
9.22 On Issue No. 27A, concerning costs, the Tribunal awarded costs
of Rs.22,50,000/- in favour of HEIL. The Tribunal also noted that
complete proof of the professional expenses claimed had not been
placed on record.
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 28 of 109
9.23 Issue No.28 constituted the final relief. The Tribunal awarded
the following as a final relief:
“(i) that as against the claim, of the claimant, amounting to
Rs.53,78,40,317.79 (Rupees fifty three crores seventy eight lacs
forty thousand three hundred seventeen and seventy nine paisa
only) (the above figures exclude the amount of claim preferred in
issue nos 4,5 and 9, which were given up by the claimant and the
amount of interest claimed on the principal amount) this Arbitral
Tribunal awards a sum of Rs. 21,08,33,166/- (Rupees twenty one
crores-eight lacs thirty three thousand one hundred sixty six only)
in favour of the claimant and directs that the respondent shall pay
to the claimant the above sum of Rs. 21,08,33,166/- (Rupees twenty
one crores eight lacs thirty three thousand one hundred sixty six
only);
(ii) that the awarded amount of Rs. 21,08,33,166/- (Rupees twenty
one crores eight lacs thirty three thousand one hundred sixty six
only) shall carry simple interest @ 9% per annum from the date
the same had become due and payable to the claimant by the
respondent till actual payment;
(iii) that the respondent shall also pay a sum of Rs. 22,50,000/-
(Rupees twenty two lacs fifty thousand only) to the claimant
towards the cost of these proceedings; and
(iv) that the counter claims, preferred by the respondent, as
already decided, are hereby rejected.”
9.24 Since, both the parties were dissatisfied by the impugned
Award, they filed cross objection petitions under Section 34 of the
Act, before this Court. The objection petition filed by the CONCOR
was registered as OMP(COMM) NO.11/2016, whereas HEIL’s
objection Petition was registered as O.M.P. (COMM.) 50/2016.
10. CONCOR’S SUBMISSIONS IN OMP(COMM)
NO.11/2016:
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 29 of 109
10.1 Learned Senior Counsel appearing for the CONCOR argued
that the impugned Award suffers from patent illegality because the
Tribunal, despite noticing the amendment to Clause 2.1 of the
Technical Specifications, failed to give effect to its terms and
proceeded on an erroneous interpretation of the amended clause.
10.2 It was submitted that the original clause required an established
and proven wagon design, while the amended clause allowed designs
with features that had been successfully used for a period of two years.
Learned Counsel submitted that HEIL had submitted its bid after the
amendment and had represented that the design features in its RITES
proposal were already successfully used before in Indian Railways.
Therefore, the Tribunal erred in treating the Contract as an
experimental development project for which the purchaser knowingly
undertook the risk.
10.3 Learned Senior Counsel took the Court through the documents
forming part of the record, including Amendment Nos.1 to 4, HEIL’s
technical proposal, pre-bid correspondence and the RITES letter dated
20.09.1995. The submission was that HEIL and RITES were fully
aware of the amended terms of the Contract and HEIL had submitted
its bid with full knowledge of the amended technical specifications.
10.4 He relied upon Clauses 1.2.1, 1.3, 1.6, 1.7 and 1.13.1 of the
Technical Specifications. It was submitted that HEIL was required to
furnish complete design material within the timeline fixed as per the
Contract and any approval by CONCOR or RDSO amounted only to
technical acceptance and not a transfer the responsibility for design
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 30 of 109
and performance to CONCOR. It was further submitted that any
modifications required during prototype development were to be
carried out by HEIL without additional cost and that HEIL continued
to remain responsible for the design, construction and performance of
the wagons.
10.5 According to learned Senior Counsel appearing for the
CONCOR, the Tribunal’s erroneous understanding of the amended
Clause 2.1 formed the basis of its conclusion that HEIL was not
responsible for the delays in design development and prototype
approval and by proceeding on that basis, the Tribunal wrongly placed
the responsibility for these delays on CONCOR, and also wrongly
rejected the CONCOR’s claim for liquidated damages and its
counterclaims.
10.6 Learned Senior Counsel next relied upon the chronology of
design and drawing submissions. It referred to the incomplete drawing
submission dated 10.05.1996, subsequent submission of brake-beam
and wheel drawings on 06.08.1996, drawbar related drawings on
05.10.1996, automatic twist-lock drawings on 17.01.1997 and the
subsequent delay in prototype completion. According to him, these
delays had already occurred before the industrial disruptions and
shipping difficulties which HEIL subsequently relied upon as force
majeure circumstances.
10.7 It was further argued that Issues Nos.15 and 16 were separately
framed because HEIL’s Annexure-C claimed that changes were
introduced by CONCOR and RDSO. Learned Senior Counsel
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 31 of 109
submitted that CONCOR had specifically denied these allegations
through detailed item-wise replies. According to him, the Tribunal, by
treating these issues as covered by Issue No. 14, failed to examine the
to and fro of changes between the parties and determine whether those
changes were required to bring HEIL’s design in conformity with the
contractual requirements or amounted to new requirements introduced
by CONCOR or RDSO, and therefore, whether the resulting delay
was attributable to HEIL or to the Purchaser.
10.8 Learned Senior Counsel also assailed Issue No.26 on the ground
that it was an independent issue requiring adjudication. It was
submitted that even after final prototype approval, HEIL remained
responsible to supply rakes at regular intervals. The reliance was
placed on letters exchanged during that period demonstrating delays in
the subsequent supplies, and it was argued that the Tribunal failed to
determine whether these post-approval delays were attributable to
HEIL.
10.9 In regard to the extension letters on which the Tribunal has
relied upon, it was submitted that each extension was granted only to
allow completion of a public procurement Contract and not as a
waiver of its rights given in the Contract. It was contended that the
initial and subsequent extension letters expressly reserved CONCOR’s
right to levy liquidated damages under Clause 23 and to invoke its
other contractual remedies. Once HEIL accepted the extensions and
continued the work without objecting to these conditions, it was
submitted that the letters could not subsequently be given a different
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 32 of 109
meaning by the Tribunal. In support of its contention, reliance was
placed on Section 55 of the ICA.
10.10 In relation to liquidated damages, learned Senior Counsel relied
upon Clause 23 of the General Conditions and Sections 73 and 74 of
the ICA. It was argued that the Contract itself fixed the rate of
liquidated damages and the maximum amount that could be claimed
for delay. According to learned Senior Counsel, the delay in supplying
the operational rakes affected the container transportation activities,
and it was difficult to calculate the exact loss caused by each delayed
rake and therefore, CONCOR is entitled to claim the agreed liquidated
damages within the limit fixed under the Contract.
10.11 On force majeure , it was argued that the HEIL did not meet the
requirements of Clause 25 because it failed to give proper and timely
notice explaining the event, its duration, and how it affected
performance of the Contract. It was also submitted that even if the
claimed force majeure events were accepted, they could only account
for the delays occurring during the affected periods and could not
explain the earlier delays relating to the drawings, prototype
development and delivery of the first rake.
10.12 Learned Senior Counsel also referred to its application dated
05.04.2004 requesting HEIL to produce procurement and utilization
records, along with the Tribunal’s orders dated 07.04.2004 and
03.05.2004. It was argued that HEIL had failed to produce complete
records showing how the advance payment was utilised, whether
orders for steel and other key components had been placed and
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 33 of 109
whether letters of credit had been opened. According to him, the
Tribunal failed to consider the effect of this non-production
10.13 Regarding the first-rake escalation, the argument was that
Clause 12.1 provided a specific formula for calculating escalation and
required the adjustment date to be based on the shipment date. It was
submitted that HEIL had failed to establish the correct adjustment date
as required under the Contract and, therefore, the Tribunal erred in
allowing the escalation claim without properly applying the formula
provided under Clause 12.
10.14 Regarding restoration of the conditional price reduction, learned
Senior Counsel relied on letters dated 02.07.1999 and 07.07.1999. It
was argued that the parties had agreed to a revised payment
arrangement involving direct payment and subsequent reimbursement
and therefore, HEIL was not entitled to recover the reduced amount of
Rs.1,72,50,000/-.
10.15 It was also argued that the rejection of its counterclaims was
based only on the Tribunal’s finding that the delay was not caused by
HEIL which is itself in contravention of the explicit clauses of the
Contract. It was submitted that, even if finding on attribution of delay
is accepted, the counterclaims ought to have been examined separately
on the basis of the terms of the Contract, submissions advanced and
the evidence submitted and could not have been rejected merely on the
basis of the finding on Issue No. 14.
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 34 of 109
10.16 As far as limited scope of judicial review is concerned, it was
submitted that the amended Section 34 of the Act applies to the
present proceedings as the petitions were filed after Arbitration and
9
Conciliation (Amendment) Act, 2015 came into force. It was further
argued that, even if the award were examined under the earlier public
policy standard, the impugned findings would still be open to
challenge. Reliance was placed upon the principles laid down by the
Supreme Court in Ssangyong Engineering & Construction Co. Ltd.
v. NHAI .
10.17 Finally, it was submitted that sending the matter back to the
Tribunal would not be appropriate because the issues involved were
not merely of incomplete reasoning, but required reconsideration of
the evidence, interpretation of the Contract and determination of
responsibility for delay.
11. HEIL’S SUBMISSIONS IN OMP(COMM) NO.11/2016:
11.1 At the outset, Learned Counsel appearing for HEIL submitted
that CONCOR’s challenge essentially seeks a rehearing of the matter
on merits after a full-fledged arbitral adjudication. It was argued that
the impugned Award was passed by a former Judge after years of
proceedings involving witness evidence, cross-examination and
extensive documentary material, on the basis of which the Tribunal
had taken a plausible view. In such circumstances, Section 34 does not
permit this Court to re-examine disputed questions relating to the
design, technical approvals, force majeure or responsibility for delay.
9
“2015 Amendment Act” hereinafter
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
Signature Not Verified
O.M.P. (COMM) 11/2016 and connected matter Page 35 of 109
11.2 It was highlighted that the Tribunal had considered Amendment
No. 1 and interpreted the distinction between the original requirement
of a “proven design” and the amended requirement of “design
features”. According to him, the interpretation adopted by the Tribunal
was a plausible one based on the Contract, and this Court cannot
substitute its own interpretation merely because another view is
possible.
11.3 Learned Senior Counsel submitted that CONCOR had
consciously selected the RITES proposal over the Trinity proposal
after technical evaluation, exercised its option to increase the quantity
and continued with the Contract without raising any objection that the
design failed to meet Clause 2.1 and therefore, CONCOR could not
subsequently blame HEIL for difficulties arising from a design which
CONCOR had itself accepted.
11.4 It was also argued that the development of railway rolling stock
involved technical review, testing and safety checks, during which the
drawings went for changes and the mere fact that changes were made
to the drawings did not establish that HEIL’s original design was
defective or that the resulting delay was attributable to HEIL.
11.5 Regarding Issues Nos. 15 and 16, it was argued that Issue No.
14 was the main issue concerning responsibility for delay and that the
Tribunal had already considered the relevant facts and evidence in
detail at earlier part of the impugned Award. According to the learned
Counsel for HEIL, Issues Nos. 15 and 16 were closely connected with
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 36 of 109
Issue No. 14, and the Tribunal was not required to repeat the same
analysis separately under each issue. It was submitted that the findings
on Issues Nos. 15 and 16 had to be read along with the discussion and
findings under Issue No. 14 and on a holistic reading of the impugned
Award, the underlying reasons for Issue Nos.15 and 16 are clearly
discernable.
11.6 On the issue of time, HEIL relied on the clauses given in the
Contract for extension of time, the ten extensions granted by
CONCOR, the continued acceptance of supplies by the CONCOR and
the fact that the Contract was never terminated. It was argued that the
Tribunal’s finding that time was not of the essence was a matter of
interpretation of the Contract and, therefore, should not be interfered
with.
11.7 It was further pointed out that several extension letters referred
to Clause 22.3, which permitted extension of time after considering
the circumstances affecting performance. According to learned
Counsel for HEIL, CONCOR had continued the Contract for several
years by granting successive extensions and accepting delayed
supplies and therefore, at the later stage, the CONCOR cannot
attribute the delay for the entire extended period to HEIL and claim
compensation for the same.
11.8 On force majeure , reliance was placed on the industrial
disruptions at Tiljala and Santragachi and the problems in transporting
Romanian axles. It was argued that the Tribunal had considered these
events along with the technical issues and the approval process and,
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 37 of 109
after examining the evidence as a whole, had rightly concluded that
the entire delay could not be attributed to HEIL.
11.9 Regarding liquidated damages, he argued that the mere
existence of a clause for a fixed sum did not automatically entitle
CONCOR to recover it. Relying upon Sections 73 and 74 of the ICA,
it was submitted that CONCOR had failed to establish the loss caused
by the delayed deliveries and therefore, the Tribunal had rightly
rejected the claim for liquidated damages on the basis of the evidence
before it.
11.10 Regarding the application for production of documents, HEIL
argued that the Tribunal was aware of the orders dated 07.04.2004 and
03.05.2004 and had considered the parties’ submissions on the failure
to produce records. It was submitted that merely because the
impugned Award did not separately discuss whether an adverse
inference should be drawn did not mean that the Tribunal ignored the
issue.
11.11 On first-rake escalation, he supported the Tribunal’s decision
and relied on various documents, including the original escalation bill
dated 28/29 April 1998, revised bill dated 25.08.2000, covering letter
dated 30.08.2000, later correspondence dated 25.09.2000 and
26.11.2001, labour cost indices, exchange-rate confirmation from
Punjab National Bank, and Metal Bulletin data.
11.12 It was further argued that Clause 12.2(b) only limited escalation
claims after the original delivery period and did not cancel escalation
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 38 of 109
that had already accrued during the original Contract period. It was
submitted that the Tribunal correctly used December 1997 indices to
ensure that escalation was calculated only for the original delivery
period and did not include any increase during the extended period.
11.13 Regarding the conditional price reduction, learned Counsel
argued that the reduced price was available only if 65% payment was
released against proof of dispatch. Since CONCOR allegedly failed to
follow this agreed payment arrangement, HEIL submitted that
CONCOR was not entitled to retain the benefit of the reduced price.
11.14 Learned Counsel also raised an objection regarding the scope of
judicial review. It was submitted that the impugned Award was passed
on 13.10.2015, before the 2015 Amendment Act came into force, and
therefore the ground of “patent illegality” introduced under Section
34(2A) could not be applied for the analysis of the present facts. It
was further submitted that, even under the amended law, this Court
cannot re-examine the evidence or substitute its own view for the
findings of the Arbitral Tribunal on factual issues.
11.15 Learned Counsel for the HEIL submitted that the impugned
Award has to be read as a whole and that isolated observations cannot
be read out of the context of the Tribunal’s overall reasoning.
According to him, the Tribunal had considered the correspondence,
technical material and contractual provisions together before
concluding that the design approval and modification process
materially contributed to the delay and therefore, due to the limited
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 39 of 109
scope of interference of this Court under Section 34, no ground was
made out for disturbing the award.
12. HEIL’S CROSS-PETITION AND CONCOR’S RESPONSE
ON ESCALATION:
12.1 In O.M.P. (COMM.) 50/2016, HEIL has confined its challenge
to the rejection of escalation claims corresponding to serial numbers 2
to 12 of Annexure-F.
12.2 Learned Counsel appearing for HEIL submitted that escalation
under Clause 12.1 was a right flowing from the Contract and became
payable once the conditions of the prescribed formula were satisfied.
According to him, the necessary base indices, formula, quantities
supplied and basic prices were already available on record and
therefore, the Tribunal erred in rejecting them.
12.3 It was further submitted that the claim could not be rejected
merely because separate escalation bills or invoices had not been
raised. Relying upon paragraph 98 of McDermott International Inc.
10
v. Burn Standard Co. Ltd. , he argued that a right flowing from the
Contract cannot be rejected merely because a specific billing
procedure was not followed at the relevant time.
12.4 It was also submitted that once the Tribunal accepted the
calculation method for the first rake, the same method should have
been applied to the remaining rakes as well. According to learned
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 40 of 109
Senior Counsel, requiring separate bills or repeated demands would
serve no real purpose as CONCOR had already disputed HEIL’s
entitlement to escalation.
12.5 Per contra , learned Senior Counsel for the CONCOR disagreed
with this argument and submitted that Clause 12 does not provide for
an automatic or fixed percentage increase. It was argued that the
escalation formula requires consideration of specific factors for each
shipment, such as the relevant adjustment date, labour and material
indices, and the applicable price components. According to him, these
particulars could not be assumed or carried forward from the first-rake
claim.
12.6 Learned Senior Counsel for CONCOR relied upon the
Tribunal’s findings at pages 94 to 99 of the award. It was submitted
that the Tribunal had found that HEIL had not produced relevant
escalation bills, or supporting documents for Serial Nos. 2 to 12. It
was also pointed out that the Tribunal had also noticed that the same
date, 11.03.2002, had been shown against all these claims and also the
necessary details regarding shipment dates, adjustment dates, spares,
bogies and the relevant indices had not been furnished.
12.7 It was further submitted that the reliance on McDermott
International (supra) was misplaced. That decision did not dispense
with the requirement of proving the facts necessary to calculate an
escalation claim under the Contract. According to him, this Court
under Section 34 could not now supply the missing particulars, take
10
(2006) 11 SCC 181
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
Signature Not Verified
O.M.P. (COMM) 11/2016 and connected matter Page 41 of 109
fresh evidence or carry out calculations which had not been
established before the Tribunal.
12.8 It was also argued that HEIL was not seeking correction of a
legal error, but asking the Court to adjudicate eleven fresh monetary
claims by applying the escalation formula afresh to claims which had
been rejected by the Tribunal for failure to establish the necessary
factual details. It was submitted that Section 34 does not permit the
Court to convert the proceedings into an original adjudication of such
rejected claims.
13. QUESTIONS FOR DETERMINATION:
13.1 In view of the pleadings, the findings recorded in the impugned
Award and the grounds raised in the present petitions, this court finds
the following issues for consideration-
a. Whether the present challenge to the impugned Award is
maintainable under Section 34(2A) of the Arbitration and Conciliation
Act, 1996, on the ground of “patent illegality”, as introduced by the
Arbitration and Conciliation (Amendment) Act, 2015.
b. Whether the Tribunal’s interpretation of amended Clause 2.1 of
the Technical Specifications, and its finding attributing the whole
delay to CONCOR, was a valid and plausible interpretation of the
Contract, or whether such finding on responsibility for delay warrants
interference under Section 34 of the Act.
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 42 of 109
c. Whether the manner in which the Tribunal dealt with Issues
Nos. 15, 16 and 26, relating to the drawings, changes in design and
supplies after prototype approval affects the findings on delay and
liquidated damages. This also involves consideration of the effect of
non-production of documents, and the treatment of force majeure
periods.
d. Whether the extensions of time granted by CONCOR and the
reservations contained in the extension letters amounted to waiver or
acceptance of delayed performance, or otherwise affected CONCOR’s
entitlement to claim liquidated damages under the Contract and
Section 55 of the ICA.
e. Whether the Tribunal’s decision allowing the first-rake
escalation claim and to direct CONCOR to pay the amount deducted
as a conditional price reduction is sustainable under the terms of the
Contract or warrants interference under Section 34 of the Act.
f. Whether the Tribunal’s rejection of HEIL’s escalation claims
corresponding to Serial Nos. 2 to 12 of Annexure-F suffers from any
ground warranting interference under Section 34, and, if so, whether
the Court can grant relief by way of modification, severance or
remand.
g. Whether the Tribunal’s findings in relation to CONCOR’s
counter-claims, and interest warrant interference under Section 34,
and what effect, if any, the absence of an application under Section
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 43 of 109
34(4) has on the relief that may be granted, including the question of
severability of the award.
ANALYSIS
14. APPLICABILITY OF THE ARBITRATION AND
CONCILIATION (AMENDMENT) ACT, 2015:
14.1 At the outset, as the challenge in the present petitions pertains to
the applicability of Section 34(2A) inserted by the 2015 Amendment
Act, which came into force on 23.10.2015, I deem it appropriate to
first deal with the said issue.
14.2 The question of the applicability of the 2015 Amendment Act to
“court proceedings” instituted on or after 23.10.2015 is no longer res
integra and has been considered by the Hon’ble Supreme Court in
11
several judgments. In BCCI v. Kochi Cricket (P) Ltd. , the Supreme
Court considered Section 26 of the 2015 Amendment Act and drew a
distinction between the arbitral proceedings themselves and the “court
proceedings” arising out of or in relation to such proceedings. It was
explicitly clarified that 2015 Amendment Act is applicable on “court
proceedings” commenced on or after 23.10.2015. The relevant
observations are reproduced below :
“ 39. Section 26, therefore, bifurcates proceedings, as has been
stated above, with a great degree of clarity, into two sets of
proceedings — arbitral proceedings themselves, and court
proceedings in relation thereto. The reason why the first part of
Section 26 is couched in negative form is only to state that the
11
(2018) 6 SCC 287
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 44 of 109
Amendment Act will apply even to arbitral proceedings
commenced before the amendment if parties otherwise agree. If the
first part of Section 26 were couched in positive language (like the
second part), it would have been necessary to add a proviso stating
that the Amendment Act would apply even to arbitral proceedings
commenced before the amendment if the parties agree. In either
case, the intention of the legislature remains the same, the negative
form conveying exactly what could have been stated positively,
with the necessary proviso. Obviously, “arbitral proceedings”
having been subsumed in the first part cannot re-appear in the
second part, and the expression “in relation to arbitral
proceedings” would, therefore, apply only to court proceedings
which relate to the arbitral proceedings. The scheme of Section 26
is thus clear: that the Amendment Act is prospective in nature,
and will apply to those arbitral proceedings that are commenced,
as understood by Section 21 of the principal Act, on or after the
Amendment Act, and to court proceedings which have
commenced on or after the Amendment Act came into force.”
(emphasis supplied)
14.3 The position was made explicit in Ssangyong Engineering &
12
Construction Co. Ltd. v. National Highways Authority of India ,
where the Supreme Court directly considered the applicability of the
amended Section 34. It held that the amended provision is applicable
to Section 34 applications filed on or after 23.10.2015, irrespective of
the date on which the arbitral proceedings had commenced. The said
principle squarely governs the present petitions and the relevant
observations are reproduced as follows-
“19 . There is no doubt that in the present case, fundamental
changes have been made in the law. The expansion of “public
policy of India” in ONGC v. Saw Pipes Ltd. [ONGC v. Saw Pipes
Ltd., (2003) 5 SCC 705] [“Saw Pipes”] and ONGC v. Western
Geco International Ltd. [ONGC v. Western Geco International
Ltd., (2014) 9 SCC 263 : (2014) 5 SCC (Civ) 12] [“Western
Geco”] has been done away with, and a new ground of “patent
illegality”, with inbuilt exceptions, has been introduced. Given
this, we declare that Section 34, as amended, will apply only to
Section 34 applications that have been made to the Court on or
12
(2019) 15 SCC 131
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 45 of 109
after 23-10-2015, irrespective of the fact that the arbitration
proceedings may have commenced prior to that date.”
(emphasis supplied)
14.4 As far as applicability of observations given in BCCI (supra) in
respect to Section 34 proceedings are concerned, it was clarified in
13
Shree Vishnu Constructions v. Military Engineering Service . The
Supreme Court clarified that the observations in BCCI (supra) were
made with reference to “court proceedings” under Sections 34 and 36
which had commenced after the 2015 Amendment Act came into
force. The relevant observations are as follows-
“25. The submission on behalf of the appellant, as above, cannot
be accepted for the simple reason that this Court
in BCCI [BCCI v. Kochi Cricket (P) Ltd., (2018) 6 SCC 287 :
(2018) 3 SCC (Civ) 534] was considering the Court proceedings
under Sections 34 and 36. To that, this Court interpreted Section
26 in paras 37 to 39, reproduced hereinabove, and held that the
Amendment Act is prospective in nature, and will apply to those
arbitral proceedings that are commenced as understood by Section
21 of the principal Act, on or after the 2015 Amendment Act and to
Court proceedings which have commenced on or after the 2015
Amendment Act came into force. Therefore, any observations
made by this Court in paras 37 to 39 in BCCI [BCCI v. Kochi
Cricket (P) Ltd., (2018) 6 SCC 287 : (2018) 3 SCC (Civ) 534]
shall be understood and construed with respect to Court
proceedings which have commenced on or after the Amendment
Act coming into force, namely, the proceedings under Sections 34
and 36. Therefore, the decisions of this Court in Parmar
Construction Co. [Union of India v. Parmar Construction Co.,
(2019) 15 SCC 682 : (2020) 2 SCC (Civ) 390] and Pradeep Vinod
Construction Co. [Union of India v. Pradeep Vinod Construction
Co., (2020) 2 SCC 464 : (2020) 1 SCC (Civ) 579] cannot be said to
be per incuriam and/or in conflict with the decision of this Court
in BCCI [BCCI v. Kochi Cricket (P) Ltd., (2018) 6 SCC 287 :
(2018) 3 SCC (Civ) 534].”
(emphasis supplied)
13
(2023) 8 SCC 329
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 46 of 109
14.5 The position also got affirmation in Hindustan Construction
14
Co. Ltd. v. Union of India , wherein the Supreme Court held:-
“66. The result is that Kochi Cricket [BCCI v. Kochi Cricket (P)
Ltd., (2018) 6 SCC 287 : (2018) 3 SCC (Civ) 534] judgment will
therefore continue to apply so as to make applicable the salutary
amendments made by the 2015 Amendment Act to all court
proceedings initiated after 23-10-2015.”
(emphasis supplied)
14.6 In view of the above, the position in law is clear and leaves no
scope for ambiguity. If the Section 34 proceedings are instituted after
23.10.2015, the amended Section 34 would apply.
14.7 In the present case, although the arbitral proceedings had
commenced much prior to the amendment came into force, the present
petitions under Section 34 were instituted after 23.10.2015, when the
2015 Amendment Act was already in force.
14.8 In view of the above, HEIL’s argument that the old law should
apply only because the impugned Award was passed before
23.10.2015 cannot be accepted. The relevant date for deciding the
applicable law is the date when the Section 34 petition was filed, and
not the date of the impugned Award.
14.9 Accordingly, since the present Section 34 petitions were filed
after 23.10.2015, this Court shall examine the challenge on the basis
of the amended legal framework.
15. SCOPE AND MEANING OF PATENT ILLEGALITY
14
(2020) 17 SCC 324
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 47 of 109
15.1 The main ground on which the present challenge is pressed is
that of “patent illegality” appearing on the face of the award. It is,
therefore, necessary to first examine the scope of this ground and the
limits within which the Court can interfere with an arbitral award on
that basis.
15.2 The applicability of the amended Section 34 has been dealt with
hereinabove. However, it has to be borne in mind that the application
of the amended provision does not enlarge the scope of judicial
review. Although the ground of patent illegality was expressly
recognised as a statutory ground by the 2015 Amendment Act, the
principle had already been recognised by the Hon’ble Supreme Court
15
in ONGC v. Saw Pipes Ltd. The Supreme Court held that, in
addition to the three grounds recognised in Renusagar Power Co. Ltd.
16
v. General Electric Co. , “patent illegality” could also constitute a
ground for setting aside an arbitral award. The Court further held that
such illegality must go to the root of the matter. The relevant
observations are reproduced below:-
“ 30. It is true that under the Act, there is no provision similar to
Sections 23 and 28 of the Arbitration Act, 1940, which specifically
provided that the arbitrator shall pass award within reasonable
time as fixed by the court. It is also true that on occasions,
arbitration proceedings are delayed for one or other reason, but it
is for the parties to take appropriate action of selecting proper
arbitrator(s) who could dispose of the matter within reasonable
time fixed by them. It is for them to indicate the time-limit for
disposal of the arbitral proceedings. It is for them to decide
whether they should continue with the arbitrator(s) who cannot
dispose of the matter within reasonable time. However, non-
providing of time-limit for deciding the dispute by the arbitrators
15
(2003) 5 SCC 705
16
1994 Supp (1) SCC 644
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 48 of 109
could have no bearing on interpretation of Section 34. Further, for
achieving the object of speedier disposal of dispute, justice in
accordance with law cannot be sacrificed. In our view, giving
limited jurisdiction to the court for having finality to the award and
resolving the dispute by speedier method would be much more
frustrated by permitting patently illegal award to operate. Patently
illegal award is required to be set at naught, otherwise it would
promote injustice.
31. Therefore, in our view, the phrase “public policy of India”
used in Section 34 in context is required to be given a wider
meaning. It can be stated that the concept of public policy connotes
some matter which concerns public good and the public interest.
What is for public good or in public interest or what would be
injurious or harmful to the public good or public interest has
varied from time to time. However, the award which is, on the
face of it, patently in violation of statutory provisions cannot be
said to be in public interest. Such award/judgment/decision is
likely to adversely affect the administration of justice. Hence, in
our view in addition to narrower meaning given to the term
“public policy” in Renusagar case [1994 Supp (1) SCC 644] it is
required to be held that the award could be set aside if it is
patently illegal . The result would be — award could be set aside if
it is contrary to:
(a) fundamental policy of Indian law; or
(b) the interest of India; or
(c) justice or morality, or
(d) in addition, if it is patently illegal.
Illegality must go to the root of the matter and if the illegality is of
trivial nature it cannot be held that award is against the public
policy. Award could also be set aside if it is so unfair and
unreasonable that it shocks the conscience of the court. Such
award is opposed to public policy and is required to be adjudged
void.”
15.3 The ground of public policy was also considered in DDA v. R.S.
17
Sharma and Co. , where the following was observed:
“21. From the above decisions, the following principles emerge:
17
(2008) 13 SCC 80
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 49 of 109
( a ) An award, which is
( i ) contrary to substantive provisions of law; or
( ii ) the provisions of the Arbitration and Conciliation Act,
1996; or
( iii ) against the terms of the respective contract; or
( iv ) patently illegal; or
( v ) prejudicial to the rights of the parties;
is open to interference by the court under Section 34(2) of the
Act.
( b ) The award could be set aside if it is contrary to:
( a ) fundamental policy of Indian law; or
( b ) the interest of India; or
( c ) justice or morality.
( c ) The award could also be set aside if it is so unfair and
unreasonable that it shocks the conscience of the court.
( d ) It is open to the court to consider whether the award is
against the specific terms of contract and if so, interfere
with it on the ground that it is patently illegal and opposed
to the public policy of India.
With these principles and statutory provisions, particularly,
Section 34(2) of the Act, let us consider whether the arbitrator
as well as the Division Bench of the High Court were justified
in granting the award in respect of Claims 1 to 3 and Additional
Claims 1 to 3 of the claimant or the appellant DDA has made
out a case for setting aside the award in respect of those claims
with reference to the terms of the agreement duly executed by
both parties”.
(emphasis supplied)
15.4 Thus, it is clear that the concept of patent illegality was not
unknown to the law governing arbitral awards even before the 2015
Amendment Act. The 2015 Amendment Act only gave statutory
recognition to this principle by introducing Section 34(2A) and at the
same time placed limits on its application by clarifying that an award
cannot be set aside merely on the ground of an erroneous application
of law or by reappreciating the evidence.
15.5 These limits are also consistent with the nature of the
jurisdiction exercised by the Court under Section 34. As held in
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 50 of 109
McDermott International Inc. (supra) , this Court cannot correct
every factual or legal error made by the Arbitral Tribunal. A challenge
under Section 34, therefore, cannot be used to re-examine the merits
of the dispute or to substitute the Court’s view with the Tribunal’s
view only because the Court’s view is more plausible.
15.6 The distinction becomes particularly important where the
challenge concerns the interpretation of the Contract by the Arbitral
Tribunal. Where the contractual terms are capable of more than one
reasonable interpretation, the interpretation adopted by the Tribunal, if
otherwise possible on the terms of the Contract, would ordinarily fall
within its domain, and this Court should endeavour to uphold it.
15.7 However, where the interpretation adopted by the Tribunal
disregards the terms of the Contract or gives them an effect which the
Contract does not permit, the question is no longer remains of merely
choosing between two possible views. Such an interpretation may
constitute an illegality going to the root of the award and may warrant
interference under Section 34, whether the challenge is considered
under the unamended or the amended Section 34.
15.8 This distinction has been recognised in DMRC Ltd. v. Delhi
18
Airport Metro Express (P) Ltd. , where the Supreme Court reiterated
that a reasonable interpretation of the Contract adopted by the
Tribunal cannot be interfered with merely because another
interpretation is possible. Similarly, in PSA Sical Terminals (P) Ltd.
18
(2024) 6 SCC 357
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 51 of 109
19
v. V.O. Chidambaranar Port Trust , and State of Chhattisgarh v.
20
Sal Udyog Pvt. Ltd. , the Supreme Court emphasised that an
arbitrator cannot rewrite the Contract or make a new agreement for the
parties or introduce terms which the parties had never agreed upon.
15.9 Thus, while the choice between two possible interpretations is
ordinarily left to the Tribunal, that discretion is not without limits.
Where the interpretation adopted has no basis in the Contract, ignores
its clear terms, or is otherwise such that no reasonable person could
have arrived at it, interference by this Court is permissible in such
circumstances. As explained in Ssangyong Engineering &
Construction Co. Ltd. (supra) , interference may also be justified
where the award is based on no evidence, ignores vital evidence, is
perverse, or proceeds on an interpretation of the Contract which is not
a possible view of its terms.
15.10 The principles which emerge from the above is that the Court
cannot re-examine the entire matter as an appellate court, reassess the
evidence or substitute its own view of the Contract merely because
another view is possible. However, the Court cannot uphold an award
where the Tribunal has proceeded on a meaning of the Contract which
the terms of the Contract do not support, or where material aspects
which were necessary for deciding the dispute have not been dealt
with.
19
2021 SCC OnLine SC 508
20
(2022) 2 SCC 275
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 52 of 109
15.11 Keeping the aforesaid principles in mind, this Court shall
proceed to consider the rival contentions raised against the Issues
framed and findings given by the Tribunal.
15.12 For clarity and proper consideration, the Court will examine
these issues with reference to the corresponding findings of the
Tribunal. The Court will first deal with the issues relating to the
interpretation of the Contract, attribution of delay and liquidated
damages, and thereafter will consider the findings on the individual
claims and counter-claims.
16. THE EFFECT OF AMENDED CLAUSE 2.1 AND ISSUE
NO. 14: ATTRIBUTION OF DELAY
16.1 It is not disputed by either party that the Tribunal was aware of
Amendment No. 1 and had reproduced the amended Clause 2.1 in the
impugned Award. Therefore, the challenge is not that the amendment
was ignored. The issue is whether the Tribunal correctly understood
the effect of the amendment when read with other clauses of the
Contract relating to design responsibility, approvals, and prototype
performance. Clause 2.1 and amended Clause 2.1 is reproduced herein
for better understanding-
Original Clause 2.1 : “Proven design. The container flat wagons
offered shall be of proven design which has been in use on any
advanced railway system in commercial service for at least two
years. The offered design should have the capability of commercial
operation up to a speed of 100 kmph on Indian Railway track
system. The Bidder shall give the following information in respect
of the container flat offered in his Bid:…”
Amended Clause 2.1 : “The container flat wagons shall have
design features which have been in use on any advanced railway
system successfully for at least two years.”
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 53 of 109
16.2 To my mind, the change brought by the amendment is clear.
The original Clause 2.1 required the container flat wagons to be of a
proven design that had been in commercial use on an advanced
railway system for at least two years. The amended clause required the
design features of the wagons to have been successfully in use on an
advanced railway system for at least two years. The amendment,
therefore, did not remove the requirement of performance experience
for those design features.
16.3 This distinction assumes significance in the present case
because HEIL’s own technical proposal referred to the BFKX/BFKI
container flat wagons and represented that the relevant design features
were similar to those used on Indian Railways since 1975. Therefore,
the representation made by HEIL was not that it was offering an
entirely new or untested design.
16.4 CONCOR accepted the RITES proposal after technical
evaluation on the basis of this representation. Meaning thereby, it was
clear to both parties that the Contract was not for developing a
completely new or experimental design from scratch. Rather, it was a
Contract for developing and supplying a specific wagon configuration
using design features which, as represented by HEIL, had been
successfully used for at least two years.
16.5 The Tribunal, however, while considering the original and the
amended Clause 2.1, proceeded to hold as follows:
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 54 of 109
“From the contents of the above clauses of the Agreement in
question, it is apparent that the Agreement in question was not a
simple Agreement for the supply of finished goods as has been
pleaded by the Learned Counsel for the respondent during the
course of arguments. On the other hand the same was an
Agreement, which was highly complex in nature because as
already pointed out as per requirement within two weeks of the
issue of Letter of Intent (LOI) the claimant was required to submit
to the respondent the design data and key drawings for approval.
Initially, the design of the wagons to be supplied by the claimant
had to be of a 'proven design', which had been in use on any
advanced railway system in commercial services for at least two
years but the same was amended and the claimant in terms of the
amended clause was required to offer flat wagons, having design
features, which had been in use on any advanced railway system
successfully for at least two years. As a result of the above
amendment it had become obligatory on the part of the claimant
to develop a new design of the flat wagons instead of a 'proven
design', which decidedly was likely to take more time as
compared to the initially contemplated design of the wagons,
which was a ‘proven design’.”
(emphasis supplied)
16.6 In my view, the above interpretation cannot be inferred on a
plain reading of the amended Clause 2.1. The amendment did not
provide that HEIL was required to develop a new or unproven design.
It merely substituted the requirement of a “proven design” of the
complete wagon with the requirement that the wagon should have
“design features” which had been successfully in use on an advanced
railway system for at least two years.
16.7 It is pertinent to note that the requirement of two years’
successful use was expressly retained in the amended clause.
However, the Tribunal while interpreting the amendment as permitting
a new and unproven design, gave no effect to this express requirement
of two years’ successful use. In doing so, the Tribunal proceeded on a
premise which is contrary to the express terms of the amended Clause
2.1.
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 55 of 109
16.8 The Tribunal proceeded further on the same premise and held
that, by deleting the words “proven design”, CONCOR had knowingly
and deliberately permitted the use of a new and untested design and
had thereby assumed the risks and consequences arising from its
acceptance. The Tribunal’s relevant findings are as follows:
“To sum up it can be stated that by amending the language of
clause 2.1 of the Agreement and doing away with the word
'Proven Design', the respondent knowingly and deliberately made
way for the induction of a new design, knowing fully-well that the
new design was not a tested and tried design and thereby the
respondent took upon itself the risk of accepting an unproven
design and thus naturally the respondent took upon itself the
consequences, which may arise in future due to the acceptance of
an unproven design. It may not be out of place to mention that on
a specific query made by the Tribunal on the point as to what
compelled the respondent to switch over from a proven design to
an unproven design -no satisfactory explanation could be given by
the respondent to the above query of this Tribunal.”
(emphasis supplied)
16.9 In the above paragraph, the Tribunal held that CONCOR had
knowingly accepted an unproven design and had thereby undertaken
the risks and consequences arising from its development. The issue
with the above reasoning is that the deletion of the words “proven
design” cannot, by any stretch, lead to the conclusion that CONCOR
had agreed to undertake the risks associated with the development of a
new and untested design.
16.10 More importantly, as noted above, the Tribunal did not take into
account the express requirement of two years’ successful use of the
design features. Therefore, the interpretation by the Tribunal is not
merely another plausible view of the Contract but an interpretation
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 56 of 109
which no reasonable person could have arrived at on a reading of the
amended Clause 2.1.
16.11 The Tribunal’s interpretation of the amended Clause 2.1 also
has to be considered in the context of the other provisions of the
Technical Specifications dealing with design, approval, prototype and
performance. Clauses 1.2.1, 1.3, 1.6, 1.7 and 1.13.1 are relevant to
determining whether the amendment to Clause 2.1 was intended to
shift responsibility for design and subsequent technical development
from HEIL to CONCOR. The said clauses are reproduced below-
“ 1.2.1 Drawings
The Supplier shall develop the design based on the details in this
specification and sound engineering practices. The entire design
data including design calculations and the key drawings shall be
submitted to the Purchaser for the approval before commencing
manufacture of prototype or placing orders on sub-contractors.
The set of drawings must include key drawings of general
arrangement and of all structural, mechanical and pneumatic
components of wagon together with schematic diagra.
1.3 Approval of Design
Approval of design means general “acceptability” of the general
design features. Notwithstanding the approval, the Supplier will
be wholly and completely responsible for the performance of the
wagon offered. The Supplier when submitting design proposals
for approval to Purchaser shall draw specific attention to any
deviation or departure from the specifications involved in his
proposal or drawings.
1.6 Prototype
The Supplier shall manufacture one prototype S-wagon unit for
inspection and approval of Purchaser or his authorized
representative before commencement of series production. Series
manufacture shall not be proceeded with until prototype has been
approved by the Purchaser or his authorized representative. Any
modifications which may have to be carried out as against the
acceptance criteria detailed in Clause-13 as a result of various
trials shall be incorporated without any additional charges.
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 57 of 109
1.7 Modification of drawings
The Supplier, after inspection and approval of the prototype unit
shall correct, where necessary, his drawings to conform in every
respect with the unit so approved and shall submit two copies of
the corrected drawings to Purchaser
1.13 Guarantee
1.13.1 The Supplier shall be entirely responsible for the design,
construction and the efficient performance of the container flat
under contract notwithstanding any approval which may have
been given to the detailed drawings prepared by the Supplier or to
the manufacture of materials or parts employed by the Supplier
or to the test carried out by the Inspecting Officer.”
(emphasis supplied)
16.12 In my reading of the above clauses, the terms agreed between
the parties are clear. The Contract provides for approval of the design,
inspection and testing of the prototype. However, such approval or
testing did not relieve HEIL of its responsibility. Clauses 1.3 and
1.13.1 expressly provided that HEIL would remain responsible for the
performance of the design, construction and efficient performance of
the wagons.
16.13 The Tribunal’s finding that CONCOR had itself taken the risk
of accepting an unproven design and the consequences arising
therefrom, is clearly contrary to the above cited clauses. I am
conscious that this Court cannot substitute its own interpretation
merely because another interpretation is possible. However, the
present case is not one where the Tribunal has merely preferred one
possible interpretation over another. The error lies in the Tribunal
having failed to consider the clauses which directly dealt with the
allocation of responsibility between the parties, and which were
material to the conclusion that CONCOR had assumed the risk of
design development or for the issue of delay.
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 58 of 109
16.14 No doubt, these clauses permitted technical review by
CONCOR and RDSO and recognised that changes could arise during
prototype development. However, they expressly placed responsibility
upon HEIL for the design, compliance with the specifications and
performance of the wagons, notwithstanding approval, inspection or
testing.
16.15 The Tribunal was undoubtedly entitled to examine whether any
design change or technical requirement was a purchaser-directed
variation beyond the Contract specifications and whether any resulting
delay was caused by CONCOR or RDSO. This was also the purpose
of Issues Nos. 15 and 16. But that question had to be answered by
examining the particular changes and their effect on the agreed
schedule. The acceptance of the RITES-based proposal in itself is not
sufficient to transfer the entire responsibility for design development
to CONCOR.
16.16 HEIL’s argument that CONCOR could not later challenge a
design once it is accepted is only partly correct. The acceptance was of
HEIL’s proposal under the amended Clause 2.1, which permitted the
use of design features that had been successfully used earlier. It did
not amount to an acceptance of every design detail or drawing that
HEIL was required to submit during execution of the Contract.
16.17 Also, it is to be noted that the CONCOR’s acceptance of the
proposal did not give it an unrestricted right to demand a completely
different commercial design without contractual justification. The
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 59 of 109
relevant question that arises in such circumstances is whether a
particular change was required for compliance with the Contract or
constituted a new requirement introduced by CONCOR or RDSO.
Only after making that determination, the responsibility for the delay
could have been decided by the Tribunal.
16.18 However, when the issue of delay was adjudicated by the
Tribunal under Issue No.14, it simply relied upon its earlier findings
regarding the amended Clause 2.1 and the effect of the change in the
design requirement. The Tribunal treated the decision of CONCOR to
adopt the RITES-based design as a major factor for the abnormal
delay and, on that basis, attributed the resulting delay to CONCOR.
The relevant reasoning of the Tribunal is reproduced hereunder:
“…Since the present case of the parties mainly rests on facts, I do
not consider it necessary to deal with the impact of those decisions
on this Award. The position, which emerges out as a result of the
above discussion, briefly stated, is that for the abnormal delay in
the performance of the contract in question, the factors responsible
are not the alleged acts of commission and/or omission on the part
of the claimant but in the first place, as already explained in detail,
it was the intention of the parties to the Agreement in question not
to treat time as the essence of the contract. Besides the above fact,
the major factor, which has caused abnormal delay in the
completion of the project was the decision with regard to the
design of the wagons in question, chosen by none else but by the
respondent itself for which the respondent has to blame none else
but its own self. As already explained at length in the earlier part
of this award the respondent, instead of opting for a ‘proven
design’ had opted for all together a new design, which was not a
tested design as a result of which it had become impossible to
follow the time schedule and there was delay at every stage i.e. at
the stage of preparation of key drawings; approval of prototype
and even after the approval of prototype during the process of the
manufacture of the wagons in question. The question, as to what
prompted the respondent to prefer an unproven and untested
design, as compared to a tested design, a baffling question and
despite specific query by this Tribunal no satisfactory explanation
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 60 of 109
was forthcoming from the respondent though the claimant in the
written submissions has thrown some indications questioning the
motive of the respondent behind the above decision. However, this
Arbitral Tribunal, in these proceedings would not like to comment
on that controversy because the same is outside the scope of
reference made to this Tribunal except holding that the above
decision of the respondent was decidedly a major factor, which to
a great extent, was responsible for the above inordinate delay. The
other factors, such as the labour unrest and strike in the factories
of the claimant at Tiljala, Santragachi and non availability of
vessels at Romania, are the other causes which contributed to the
delay in the execution of the contract. All these factors decidedly
were beyond the control of the claimant and the correctness of the
same is not disputed even by the respondent except taking shelter
of technicalities by stating that the above occurrences were not
promptly notified by the claimant to the respondent. For the above
detailed reasons this Tribunal has no hesitation in holding that in
the given facts it would be wholly unjust to hold the claimant
responsible for the above delay.”
(emphasis supplied)
16.19 Thus, it is clear that the Tribunal’s finding on delay was not
based upon an examination of each individual cause of delay. The
Tribunal proceeded substantially on the conclusion that CONCOR had
chosen an unproven and untested design and that this decision was
responsible, to a substantial extent, for the delay in preparation of
drawings, approval of the prototype and subsequent manufacture of
the wagons.
16.20 Before attributing the delay to CONCOR, I am conscious that
Tribunal was not required to undertake a day-to-day examination of
each period of delay or to separately deal and give its findings on
every drawing, design change, technical observation, approval,
prototype issue or manufacturing stage. What the Tribunal was
required to examine was, broadly, whether the changes and
requirements which arose during the approval and development
process were part of HEIL’s contractual obligations or were additional
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 61 of 109
requirements introduced by CONCOR or RDSO, and, depending upon
that, to whom the resulting delay was attributable. If the Tribunal had
undertaken that exercise, no interference is warranted by this Court.
16.21 However, I am constrained to observe that the answer is in
negative. The Tribunal did not carry out the required analysis for
deciding responsibility for delay. Instead, it adopted a broad
assumption that is in itself was inconsistent with the terms of the
Contract as discussed earlier.
16.22 Further, it merely proceeded on the basis that the amended
Clause 2.1 had placed the responsibility for the subsequent design
development largely on CONCOR, without considering the other
clauses which continued to make HEIL responsible for the design and
performance of the wagons. Since this assumption formed the basis of
the Tribunal’s decision on Issue No. 14 and affected the findings on
liquidated damages and counterclaims, the error goes to the root of the
controversy.
16.23 For the reasons discussed above, I find that the Tribunal could
not attribute the entire consequence of the design development to
CONCOR without first determining the contractual responsibility for
the particular causes of delay. However, this does not mean that the
Tribunal’s finding is to be replaced by a finding that whole 1326 days
of delay was attributable to HEIL.
16.24 This Court is conscious of the limits of its jurisdiction under
Section 34. It is not for this Court to determine afresh whether a
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 62 of 109
particular design change was technically necessary, whether it
amounted to a variation or a correction, whether it was required by
CONCOR or RDSO, or what period of delay was attributable to each
such change. Nor is this Court required to re-examine the engineering
record and substitute its own assessment of the evidence. Those
questions would require examination of the evidence and fall outside
the limited scope of the present proceedings.
16.25 In view of the above, the finding on Issue No. 14 is set aside to
the extent that it rests on the incorrect assumption that the risk arising
from the design development was entirely that of CONCOR. This
does not mean that all 1,326 days of delay were caused by HEIL, nor
does this Court record any finding on the individual design-related
disputes. It only means that the Tribunal’s complete exoneration of
HEIL cannot be sustained on the reasoning adopted, as that reasoning
is contrary to the express terms of the Contract, and the related
findings must be reconsidered according to the terms of the Contract.
17. ISSUES 15 AND 16-DRAWINGS AND SOURCE OF
DESIGN CHANGES:
17.1 Issue No. 15 required the Tribunal to decide whether HEIL had
submitted complete and compliant drawings within the time limit
given in the Contract. This required consideration of the initial
drawings, communications regarding deficiencies in drawbar and
twist-lock details, dates of submission and approval of important
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 63 of 109
component drawings, and the parties’ different interpretations of the
contractual deadline.
17.2 On the other hand, Issue No. 16, required the Tribunal to
determine who was responsible for changes made to the designs and
drawings during the approval and prototype development process.
HEIL argued that several changes were introduced by CONCOR or
RDSO, relying on Annexure-C. CONCOR disputed this and
contended that the changes were required to bring the drawings and
components in compliance with the contractual specifications.
Therefore, the two issues were directly connected with the question of
responsibility for the resulting delay.
17.3 However, the Tribunal decided the Issue No. 15 and 16 only by
referring to its finding on Issue No.14 that the delay was not
attributable to HEIL. There is no finding in regard to determination of
whether the drawings submitted by HEIL were complete and
compliant with required specifications within the fixed time, or what
effect any deficiency or delay in their submission had on the
contractual schedule. The finding of the Tribunal on Issue No. 15 and
16 is reproduced below-
“Insofar as the above issues are concerned, the position is that the
above issues already stand covered by decision of issue No. 14,
already decided by this Tribunal in the earlier part of this Award.
For reasons already stated (not being repeated here for the sake of
brevity) while deciding issue No. 14, the above mentioned issues
are also decided in favour of the claimant and against the
respondent.”
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 64 of 109
17.4 The issue is not that the Tribunal failed to refer to every
document or technical observation. The difficulty is that the Tribunal
did not determine the questions which Issues Nos. 15 and 16 required
it to determine. There is no finding as to whether the drawings
submitted by HEIL complied with the contractual requirements at the
relevant stage, or whether the material changes relied upon by HEIL
were purchaser-directed changes or were required to bring the
drawings and components into conformity with the Contract.
17.5 The Court has considered HEIL’s submission that an arbitral
award must be read as a whole and that separate reasons need not be
given for every issue. That principle is accepted, and the Court has
accordingly considered the award as a whole, including the
conclusions recorded at pages 128 and 129 as well as the earlier
discussion. Even on such a reading, the necessary findings are absent.
The award does not determine whether HEIL’s drawings met the
requirements at the relevant stage or whether the material design
changes were the result of purchaser instructions beyond the agreed
terms or corrections required from HEIL for compliance with the
Contract.
17.6 This cannot be treated as a mere deficiency in drafting or as a
harmless omission to separately give findings on each issue. Issues
Nos. 15 and 16 required the Tribunal to determine who was
responsible for the delay in drawings and the subsequent design
changes, which was necessary to determine responsibility for the
resulting delay under Issue No. 14. The finding on Issue No. 14 then
formed the basis of the Tribunal’s decision on Issue No. 1 relating to
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 65 of 109
liquidated damages. Accordingly, Issues Nos. 15 and 16 could not be
disposed of merely by referring to Issue No. 14, when the
determination under Issue No. 14 itself depended upon identifying the
causes of delay in the design and drawing process.
17.7 This Court cannot cure that omission by independently
examining the technical documents itself or deciding who was right
about the engineering issues. Doing so would mean re-evaluating
evidence, which is not allowed under Section 34 of the Act. Therefore,
this Court can only examine whether the impugned Award can be
sustained when findings material to the determination of liability for
delay are not recorded by the Tribunal.
17.8 An Arbitral Tribunal is not required to discuss every document
or every submission. However, where extensive evidence has been led
on a particular issue, the Tribunal is required to deal with the material
aspects of that evidence and record its findings.
17.9 The requirement of reasons in an arbitral award has been
considered by the Supreme Court in Dyna Technologies (P) Ltd. v.
21
Crompton Greaves Ltd. , and thereafter in OPG Power Generation
22
Pvt. Ltd. v. Enexio Power Cooling Solutions India Pvt. Ltd. The
Supreme Court has recognised that an award is not to be interfered
with merely because the reasons could have been more elaborate.
However, where the reasoning discloses a flaw in the decision-making
process or the gaps are such that the basis of the decision cannot be
21
(2019) 20 SCC 1
22
(2025) 2 SCC 417
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 66 of 109
understood, the award may be interfered with under Section 34. The
relevant observations from OPG Power (supra) are as follows:
“80. We find ourselves in agreement with the view taken in Dyna
Technologies [Dyna Technologies (P) Ltd. v. Crompton Greaves
Ltd., (2019) 20 SCC 1, paras 27-43], as extracted above.
Therefore, in our view, for the purposes of addressing an
application to set aside an arbitral award on the ground of
improper or inadequate reasons, or lack of reasons, awards can
broadly be placed in three categories:
(1) where no reasons are recorded, or the reasons recorded are
unintelligible;
(2) where reasons are improper, that is, they reveal a flaw in the
decision-making process; and
(3) where reasons appear inadequate.
81. Awards falling in Category (1) are vulnerable as they would be
in conflict with the provisions of Section 31(3) of the 1996 Act.
Therefore, such awards are liable to be set aside under Section 34,
unless:
(a) the parties have agreed that no reasons are to be given, or
(b) the award is an arbitral award on agreed terms under Section
30.
82. Awards falling in Category (2) are amenable to a challenge on
ground of impropriety or perversity, strictly in accordance with the
grounds set out in Section 34 of the 1996 Act.
83. Awards falling in Category (3) require to be dealt with care. In
a challenge to such award, before taking a decision the Court must
take into consideration the nature of the issues arising between the
parties in the arbitral proceedings and the degree of reasoning
required to address them. The Court must thereafter carefully
peruse the award, and the documents referred to therein. If reasons
are intelligible and adequate on a fair reading of the award and, in
appropriate cases, implicit in the documents referred to therein,
the award is not to be set aside for inadequacy of reasons.
However, if gaps are such that they render the reasoning in
support of the award unintelligible, or lacking, the Court
exercising power under Section 34 may set aside the award.”
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 67 of 109
17.10 It is also settled that interference by this court is also
permissible where the Tribunal has not recorded any finding at all on a
material and contentious issue. In I-Pay Clearing Services (P) Ltd. v.
23
ICICI Bank Ltd. , the Supreme Court recognised that failure to
record a finding on a contentious issue may amount to patent
illegality. Relying upon I-Pay Clearing Services , this Court in
24
Divyam Real Estate (P) Ltd. v. M2K Entertainment (P) Ltd. , held
that where the arbitrator has not recorded a clear finding on a
contentious issue and the conclusion is in disregard of the evidence on
record, the award has to be set aside. The same principle was
considered by the Division Bench of this Court in Canara Bank v.
25
State Trading Corporation of India Ltd. , where it was held that
failure to record a finding on a contentious issue may amount to patent
illegality. The relevant observations are as follows:
“32. From the foregoing, it is evident that since the
arbitral award had not recorded a finding with regard to
the contentious issue of interest, it qualifies as a patent
illegality. In these circumstances, courts ought not to
accede to the request of the party to resume the arbitral
proceedings. Hence, in the absence of a "finding" on the
issue of interest, the learned Single Judge could not have
remitted the proceedings back to the Arbitral Tribunal.”
17.11 In the present case, insofar as Issues Nos. 15 and 16 are
concerned, the Tribunal has not recorded any reasons or findings on
the questions which those issues required it to decide. The Tribunal
merely stated that the issues stood covered by its decision on Issue
No.14. This is not a case where the reasons given are merely brief or
23
(2022) 3 SCC 121
24
2024 SCC OnLine Del 3786
25
(2022) 5 HCC (Del) 638
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 68 of 109
less elaborate than what may have been desirable. The findings
necessary to determine the issues are absent. The Tribunal did not
determine the principal factual questions arising under Issues Nos. 15
and 16, although those findings were material to its conclusion on
responsibility for delay and Issue No. 1 concerning liquidated
damages.
17.12 Even if the Tribunal’s finding that CONCOR required an
unproven design is accepted, the timelines given in the Contract was
still applicable and therefore, the Tribunal was still required to
examine whether the work was completed within those timelines and
who was responsible for any delay thereafter.
17.13 Accordingly, the Tribunal’s decision on Issues Nos. 15 and 16
in favour of HEIL are set aside. The Court has not undertaken the
technical examination itself. It has not held that all delays were caused
by HEIL or that every technical change was a purchaser-directed
variation. Those questions require examination of the contractual
documents, technical material and evidence and cannot be decided by
this Court in a proceeding under Section 34.
18. ISSUE 26-REGULAR SUPPLIES AFTER PROTOTYPE
APPROVAL:
18.1 Issue No. 26 arose at a later stage of the Contract, after the
prototype had received final approval for series production on
25.09.1997. The first rake was supplied only on 28.04.1998, and the
entire contractual quantity was completed in September 2001. Thus,
even if some of the earlier delay in design development and prototype
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 69 of 109
approval was attributable to the purchaser, the Tribunal was still
required to examine whether HEIL thereafter maintained the required
production and supply schedule.
18.2 The Tribunal, however, again disposed of Issue No.26 by
merely relying upon its finding on Issue No.14. It did not examine the
post-approval production and delivery schedule, the relevant
correspondence or the respective explanations of the parties for the
delay during this period. Accordingly, the finding on Issue No.26
suffers from the same fundamental omission and cannot be sustained.
18.3 This Court is not recording any finding that the post-approval
delay was attributable to HEIL, nor is it determining the extent of
liability, if any. Again, that issue would require consideration of the
evidence relating to the period after prototype approval and cannot be
determined in the proceedings under Section 34. It was within the
authority of the Tribunal who failed to adjudicate it.
19. TIME ESSENCE OF CONTRACT AND ISSUE 1-
LIQUIDATED DAMAGES:
19.1 The Tribunal has held that time was not the essence of the
Contract. CONCOR challenges this finding, mainly on the basis that
the Contract prescribed specific delivery schedules and provided for
liquidated damages in the event of delay. Therefore, the issue is
whether the Tribunal’s finding on this issue has to be interfered or not
within the limited scope of Section 34.
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 70 of 109
19.2 The decisions in National Council of Education Research &
26
Training v. Murli Industries Ltd., and Hind Construction
27
Contractors v. State of Maharashtra make it clear that this issue
cannot be decided merely by looking at one clause of the Contract.
The intention of the parties has to be gathered from the Contract as a
whole and the surrounding circumstances. In Welspun Specialty
28
Solutions Ltd. v. ONGC , the Supreme Court also recognised that
provisions permitting extension of time and the conduct of the parties
in granting such extensions may support a finding that time was not
intended to be of the essence.
“ 35. It is now settled that ‘whether time is of the essence in a
contract’, has to be culled out from the reading of the entire
contract as well as the surrounding circumstances. Merely having
an explicit clause may not be sufficient to make time the essence of
the contract. As the contract was spread over a long tenure, the
intention of the parties to provide for extensions surely reinforces
the fact that timely performance was necessary. The fact that such
extensions were granted indicates ONGC's effort to uphold the
integrity of the contract instead of repudiating the same.
xxxxxxxxx
42. This Court cannot interfere with this award, as the award is a
plausible view for the following reasons:
42.1. The Arbitral Tribunal's interpretation of contractual
clauses having extension procedure and imposition of liquidated
damages, are good indicators that ‘time was not the essence of the
contract’.”
19.3 In the present case, the Contract permitted extension of time.
CONCOR granted several such extensions, continued to accept
performance and did not terminate the Contract. These circumstances
were considered by the Tribunal in concluding that time was not of the
26
2025 SCC OnLine Del 6414
27
AIR 1979 SC 720
28
(2022) 2 SCC 382
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 71 of 109
essence. That conclusion, in the circumstances of the present case,
cannot be said to be interpretation which the contract or the conduct of
the parties could not support.
19.4 The difficulty, however, arises when the Tribunal carried this
finding further to answer question whether CONCOR was entitled to
claim compensation for delay. The two questions are separate. A
finding that time was not of the essence may preclude termination
merely on account of delay but it does not wipe out the other
contractual consequences attached to delayed performance.
19.5 It is in this context that Section 55 of the ICA assumes
relevance. The provision reads as follows-
“Effect of failure to perform at fixed time, in contract in which
time is essential
When a party to a contract promises to do a certain thing at or
before a specified time, or certain things at or before specified
times, and fails to do any such thing at or before the specified time,
the contract, or so much of it as has not been performed, becomes
voidable at the option of the promisee, if the intention of the parties
was that time should be of the essence of the contract.
Effect of such failure when time is not essential .--If it was not the
intention of the parties that time should be of the essence of the
contract, the contract does not become voidable by the failure to
do such thing at or before the specified time; but the promisee is
entitled to compensation from the promisor for any loss occasioned
to him by such failure.
Effect of acceptance of performance at time other than that
agreed upon .--If, in case of a contract voidable on account of the
promisor's failure to perform his promise at the time agreed, the
promisee accepts performance of such promise at any time other
than that agreed, the promisee cannot claim compensation for any
loss occasioned by the non-performance of the promise at the time
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 72 of 109
agreed, unless, at the time of such acceptance, he gives notice to
the promisor of his intention to do so.”
(emphasis supplied)
19.6 The above provision makes it clear that where a party accepts
performance after the agreed time, it may still claim compensation if,
at the time of such acceptance, it gives notice of its intention to do so.
19.7 In the present facts, most of the extension letters issued by
CONCOR clearly stated that the extensions were granted without
giving up its right to claim liquidated damages under Clause 23. The
correspondence, therefore, shows that CONCOR intended to allow the
Contract to continue while preserving its right to claim compensation
for the delay.
19.8 HEIL accepted these extensions and continued to perform the
Contract. There is nothing on record from which it can be
conclusively inferred that HEIL objected to the conditions attached to
the extensions or understood them to mean that CONCOR had
accepted the delay without any financial consequences. Therefore, the
extensions cannot be treated as a waiver of CONCOR’s right to claim
liquidated damages.
19.9 The fact that CONCOR did not terminate the Contract also does
not lead to a different conclusion. In a specialised public procurement
Contract involving rolling stock required for operations, continuing
the Contract may simply have been a practical decision to ensure
completion of the work. Mere decision to continue the Contract does
not mean that CONCOR gave up its right to claim liquidated damages
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 73 of 109
when the Contract permitted both extension of time and recovery of
compensation for delay.
19.10 The reliance placed by learned Counsel for HEIL, as also by the
Tribunal, on the distinction between Clauses 22.2 and 22.3 cannot be
accepted in the manner in which it has been applied. Clause 22.3
provides for extension of time where the Supplier encounters
conditions impeding timely performance. It does not state that an
extension granted thereunder would exclude the levy of liquidated
damages. More importantly, Clause 23.1 expressly makes the levy of
liquidated damages only “subject to Clause 25”.
19.11 However, the Tribunal proceeded on the footing that once an
extension was granted under Clause 22.3, liquidated damages could
not be imposed under Clause 23.1. According to this Court, there is
nothing in Clause 22.3 which says so. The Tribunal has thus added a
condition to the Contract which the parties themselves did not
provide. In doing so, the Tribunal overlooked the letters where
CONCOR expressly reserved their rights to impose liquidated
damages and the act of HEIL in continuing with the project.
19.12 The Supreme Court in Consolidated Construction Consortium
29
Ltd. v. Software Technology Parks of India , specifically dealt with
the argument that extension of time and levy of liquidated damages
cannot go hand in hand. In that case also extensions were granted on
several occasions while expressly reserving the employer’s right to
29
(2025) 7 SCC 757
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 74 of 109
levy liquidated damages. The Supreme Court set aside the view of the
learned Single Judge that mere grant of extension ruled out the
possibility of levy of liquidated damages:
“39. What the arbitrator noted in this case is that on a number of
occasions, the appellant had sought for time. On each occasion the
respondent was compelled to allow the appellant to carry on with
the work beyond the extended time period by granting further
extension, reserving its right to levy liquidated damages. It has
come on record that in the review meeting held on 18-12-2006, the
respondent had put the appellant to notice that grant of extension
of time for completion of the contract work would be without
prejudice to the right of the respondent to recover liquidated
damages. Though the first extended time-limit was till 28-2-2007,
further time had to be granted by the respondent on a number of
occasions thereafter till 30-6-2007, on each occasion reserving the
right to levy liquidated damages.
xxxxx
50. The learned Single Judge also observed that Clause 26 of the
contract agreement could not be read in isolation without
reference to Clause 27. The fact that the appellant was allowed to
carry on the contract work and to subsequently complete the same
cannot be denied. Once there is extension of time, there cannot be
a narrow interpretation to Clause 26. Purpose of extension of time
was only for completion of work. Extension of time and levy of
liquidated damages cannot go hand in hand. The contention of the
respondent would have been acceptable had there been no
extension in time or the work remained incomplete even after the
extended period. In such an event, the respondent would have been
justified to levy and recover liquidated damages. Once the
appellant had completed the work during the extended period of
time, claim of liquidated damages by the respondent could not be
accepted. Therefore, the arbitral award dated 10-5-2010 was set
aside.
51. We are afraid the learned Single Judge had clearly gone
beyond the grounds provided in Section 34 of the 1996 Act to set
aside the arbitral award. The learned Single Judge exceeded the
jurisdiction under Section 34 of the 1996 Act. There was no
justification for setting aside the arbitral award by taking a
different view. The view taken by the Arbitral Tribunal is certainly
a possible and plausible view. A different interpretation of Clause
26 other than the one taken by the Arbitral Tribunal is possible but
that will not bring the challenge to the arbitral award within the
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 75 of 109
four corners of Section 34. In any view of the matter, mere setting
aside of the arbitral award did not confer any benefit to the
appellant. In the circumstances, the Division Bench [Software
Technology Parks of India v. Consolidated Construction
Consortium Ltd., 2019 SCC OnLine Mad 39306] was justified in
reversing the order [Consolidated Construction Consortium Ltd. v.
Software Technology Parks of India, 2019 SCC OnLine Mad 1633]
of the learned Single Judge under Section 37 of the 1996 Act.”
19.13 A similar approach was adopted by this Court in GAIL (India)
30
Ltd. v. Punj Lloyd Ltd. , where the correspondence between the
parties showed that the employer had continued to monitor the delay
and had consistently reserved its right to levy liquidated damages. The
Court treated such correspondence as relevant in determining whether
the right to levy liquidated damages had been preserved.
19.14 However, the above decisions are not sufficient to establish
CONCOR’s entitlement to liquidated damages in the present case.
They only make it clear that grant of an extension where the right to
levy damages is expressly reserved, does not amount to a waiver of
that right. But that is not the end of the issue in the present case.
19.15 Before CONCOR can recover liquidated damages, it must first
be established that the delay for which damages are claimed was
attributable to HEIL. That finding is presently missing, as the
Tribunal’s earlier finding on responsibility for delay has already been
set aside. Until that question is answered, CONCOR’s reservation of
its right to claim liquidated damages cannot make the claim
recoverable.
30
2017 SCC OnLine Del 8301
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 76 of 109
19.16 Therefore, Clause 23 did not give CONCOR an automatic right
to keep the liquidated damages. The clause had to be read along with
Sections 73 and 74 of the ICA. The Supreme Court in ONGC Ltd.
(supra) and Kailash Nath Associates v. Delhi Development
31
Authority held that merely because a particular amount is mentioned
in the Contract as liquidated damages, that entire amount does not
automatically become payable. The Court still has to examine whether
the amount represents reasonable compensation for the loss caused by
32
the breach. In Construction & Design Services v. DDA , the
Supreme Court explained the manner in which such stipulated
amounts are to be considered and relevant observations are as follows-
“15. Once it is held that even in absence of specific evidence, the
respondent could be held to have suffered loss on account of
breach of contract, and it is entitled to compensation to the extent
of loss suffered, it is for the appellant to show that stipulated
damages are by way of penalty. In a given case, when highest limit
is stipulated instead of a fixed sum, in absence of evidence of loss,
part of it can be held to be reasonable, compensation and the
remaining by way of penalty. The party complaining of breach can
certainly be allowed reasonable compensation out of the said
amount if not the entire amount. If the entire amount stipulated is
genuine pre-estimate of loss, the actual loss need not be proved.
Burden to prove that no loss was likely to be suffered is on party
committing breach, as already observed.”
19.17 In view of the above, it appears that a liquidated damages clause
may be valid where it represents a genuine estimate of possible loss,
especially when actual loss is difficult to calculate. However, merely
mentioning an amount in the Contract does not automatically make it
payable. The entitlement to compensation still depends upon the
31
(2015) 4 SCC 136
32
(2015) 14 SCC 263
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 77 of 109
breach established, the losses arising from it and the amount of
reasonable compensation payable in the circumstances.
19.18 According, CONCOR’s claim for liquidated damages could not
be sustained merely because Clause 23 prescribed a fixed percentage
or maximum amount. However, HEIL could not claim a complete
refund merely because the Contract continued or because time was
held not to be of the essence. The entitlement to liquidated damages
had to follow from a determination of responsibility for the relevant
periods of delay and the application of Clause 23 read with Sections
73 and 74 of the ICA.
19.19 The Tribunal should have determined the delay for which HEIL
could be held responsible. This required an examination of the
different stages of the Contract and the causes of delay at each stage,
including whether any period was attributable to CONCOR, excused
under the Contract or covered by force majeure . These findings were
necessary before the Tribunal could determine whether the liquidated
damages claimed under Clause 23 were payable and, if so, to what
extent.
19.20 The difficulty is that the Tribunal did not undertake that
exercise. It directed refund of the entire amount of liquidated damages
on the basis of its incorrect assumption regarding responsibility for the
design issues, without recording the necessary findings as to the actual
causes and periods of delay. Accordingly, the direction for complete
refund was made without first determining the contractual
responsibility for the relevant periods of delay.
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 78 of 109
19.21 This goes beyond a mere error in appreciation of evidence. The
present case is also not one where this Court is merely preferring a
different view of the evidence or the Contract. The Tribunal proceeded
on an interpretation of amended Clause 2.1 which, for the reasons
already discussed, was contrary to its express terms and did not give
effect to the requirement of two years’ successful use of the relevant
design features.
19.22 This premise was then carried forward while determining
responsibility for delay and thereafter for Issue No.1. To that extent,
the reasoning of the impugned Award suffers from perversity, as the
conclusion on liquidated damages is not supported by the findings
necessary to sustain it under the Contract and amounts to patent
illegality appearing on the face of the award.
19.23 However, this Court cannot determine the correct quantum of
liquidated damages itself. Such a determination would require
examining who was responsible for the delay at different stages, the
contractual timelines applicable to those stages, the effect of the force
majeure events, whether there were concurrent or multiple causes of
delay, and whether the compensation claimed was reasonable. These
are factual matters which would require a fresh examination of the
evidence and cannot be undertaken by this Court as an original
adjudicatory forum under Section 34.
19.24 Since the decision on Issue No.1 (liquidated damages) was
based on the incorrect reasoning under Issue No.14 and depended on
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 79 of 109
unresolved questions under Issues Nos.15, 16 and 26, the finding on
Issue No.1, together with the consequential award of interest, is set
aside. This does not mean that CONCOR was automatically entitled to
keep the entire amount deducted as liquidated damages. It only means
that the Tribunal’s direction for a complete refund cannot be sustained
as it has been based on reasoning which has been found to be legally
unsustainable.
19.25 Accordingly, this Court records no final determination on the
amount, if any, payable towards liquidated damages. That question
remains open and parties are at liberty to avail appropriate remedy, if
any, in accordance with law.
19.26 It is made clear that this Court has not interfered with the
Tribunal’s limited finding that time was not the essence of the
Contract.
20. ISSUE 18-FORCE MAJEURE:
20.1 Issue No.18 concerns the force majeure events relied upon by
HEIL in explaining the delay in performance of the Contract. HEIL
relied upon the lock-out and labour unrest at its Tiljala and
Santragachi factories and the non-availability of vessels from
Romania. The Tribunal considered these events and accepted them as
circumstances falling within Clause 25 of the Contract.
20.2 The Tribunal also considered the notices issued by HEIL and
the correspondence between the parties and held that the requirements
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 80 of 109
of Clause 25 had been sufficiently complied with. On that basis, the
Tribunal treated the periods affected by these events as excused delays
and took the same into account while deciding the question of
liquidated damages.
20.3 This Court does not find any infirmity in the conclusion reached
by the Tribunal. The occurrence of industrial disruption, factory
problems and shipping difficulties involved an appreciation of the
evidence, which was within the Tribunal’s domain. The question
remains is what effect those events could have on the delay and on the
claim for liquidated damages.
20.4 The Tribunal relied on the above events to order a complete
refund of the liquidated damages. However, the Tribunal failed to
notice that the force majeure events relied upon by HEIL occurred at
different stages of the Contract. Some of them arose after substantial
delays had already occurred in the submission of drawings, prototype
development and delivery of the first rake.
20.5 For a proper analysis, the Tribunal should have considered each
event in relation to the period during which delay occurred and the
particular obligation which it affected. This required consideration of
the requirements of Clause 25, the duration of each event, the
milestones or supplies affected and the position of the parties
immediately before the event occurred.
20.6 The presence of multiple causes of delay does not remove a
party’s responsibility for the delay already caused by it. Depending
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 81 of 109
upon the Contract and the evidence, a subsequent force majeure event
may excuse or reduce responsibility for the period actually affected by
it. Mere occurrence cannot wipe out consequences for a delay which
had already taken place before that event.
20.7 This Court does not undertake any independent calculation of
delay periods or determine the number of days attributable to force
majeure . Doing so would require deciding the merits of the dispute,
which is not the role of the Court under Section 34.
20.8 In view of this Court, the Tribunal’s force majeure findings
could not justify a refund of the entire liquidated damages amount
once the underlying findings on Issue Nos.14, 15, 16 and 26 are found
unsustainable.
20.9 The Court has not disturbed the factual findings that the
industrial unrest and shipping difficulties occurred, nor has it
interfered with the Tribunal’s finding that the notice requirements
under Clause 25 were sufficiently complied with in the circumstances.
Those findings involved appreciation of evidence and were within the
Tribunal’s authority whose conclusion is plausible in view of this
Court.
20.10 The legal effect of those events, however, had to be confined to
the periods and contractual obligations actually affected by them. If
the events relied upon by HEIL occurred after substantial delays had
already taken place in the submission of drawings, development of the
prototype and delivery of the first rake, it had to be determined how
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 82 of 109
far those events contributed to the overall delay. They may, depending
on the evidence, excuse or reduce HEIL’s responsibility for the period
actually affected by them. But without determining their actual effect
on the delay, they cannot justify a refund of liquidated damages for the
entire period of delay.
20.11 Accordingly, the finding on Issue No. 18 is not disturbed to the
extent it records the occurrence of the force majeure events and
compliance with Clause 25. However, those findings cannot be
constituted as a complete defence to the claim for liquidated damages,
when the decision on Issue No. 1 was itself based on an incorrect
analysis of responsibility for delay.
21. EFFECT OF NON-PRODUCTION OF RECORDS:
21.1 CONCOR filed an application on 05.04.2004 seeking
documents relating to the use of the interest-free advance, purchase of
important components, placement of orders, and details of letters of
credit. On 07.04.2004, the Tribunal directed HEIL to produce these
documents. Later, on 03.05.2004, the Tribunal noted that the
documents had not been produced and left the parties to argue about
the impact of such non-production at the appropriate stage.
21.2 These documents were not irrelevant or unrelated to the dispute.
They were directly connected with HEIL’s explanation for the delay
that the delay was caused by external factors and not by any failure to
arrange resources, procure materials or plan performance properly.
The documents could have helped determine when critical materials
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 83 of 109
such as steel and other components, were ordered, whether
procurement began within the required contractual timeline, and
whether the advance payment was used in accordance with the agreed
schedule.
21.3 An arbitral tribunal is the primary judge for deciding what
effect should be given to a party’s failure to produce documents. It
could have concluded that the documents were unnecessary or that
their absence would not affect the outcome. However, where
documents are specifically requested, their production is directed by
the Tribunal and the question of their effect is left open, the impugned
Award should indicate whether that issue was considered before
reaching a conclusion on delay.
21.4 The impugned Award does not show any such consideration.
There is no finding as to whether the non-production affected HEIL’s
explanation regarding procurement, availability of materials or
mobilisation. Normally, an award cannot be set aside simply because
every piece of evidence is not separately discussed. However, in this
case, the omission becomes important because the missing documents
were directly related to the question of who was responsible for the
delays in drawings, procurement, and production.
21.5 This Court does not assume that HEIL misused the advance
payment or that procurement was in fact delayed by HEIL. Nor does
the Court draw any automatic adverse inference from the non-
production of the documents. The limited finding by this Court under
Section 34 is that the Tribunal completely absolved HEIL of delay
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 84 of 109
responsibility without showing that it had considered the effect of
non-production of documents that were specifically requested and
ordered to be produced.
21.6 This is a procedural issue and not a conclusion against HEIL.
The Tribunal had directed production of the documents, recorded that
they had not been produced and left the parties to address the
consequences at the appropriate stage. Having done so, the Tribunal
ought to have indicated in the final award whether the issue was
considered and what effect, if any, the non-production had on HEIL’s
explanation for the delay.
21.7 This omission alone does not affect every part of the award. Its
importance is that it supports the conclusion that the Tribunal did not
examine the question of delay responsibility on the basis of the
complete material placed before it.
22. ISSUES 12, 13 AND 19 TO 24-CONCOR’S
COUNTERCLAIMS:
22.1 The Tribunal rejected Issues 12, 13 and 19 to 24 mainly on the
ground that HEIL was not responsible for the delay. CONCOR’s
counterclaims included claims for loss of traffic revenue, World Bank
interest payments, guarantee charges, exchange-rate losses, and
commitment charges.
22.2 The entitlement to these claims involved questions separate
from the general finding on delay. It was necessary to consider
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 85 of 109
whether the particular loss was recoverable under the Contract,
whether it was caused by the alleged breach, whether it was proved by
the material on record, whether it overlapped with any other
contractual remedy, and whether any contractual limitation applied.
22.3 The problem with the impugned Award is that the Tribunal did
not separately examine these issues. The counterclaims were rejected
substantially because the Tribunal had already concluded under Issue
No. 14 that the delay was not attributable to HEIL. Once that
underlying finding cannot be sustained, the rejection of the
counterclaims cannot be sustained on the same basis when the
Tribunal did not examine the independent questions relating to the
individual claims.
22.4 This does not mean that CONCOR succeeds in any of its
counterclaims. The Court has neither awarded any amount nor held
that any particular loss was suffered or was recoverable from HEIL.
The Court has only found that the basis on which the Tribunal rejected
these counterclaims cannot be sustained.
22.5 Accordingly, the decisions on Issues Nos. 12, 13 and 19 to 24
are set aside to the extent that they rest on the finding that the delay
was not attributable to HEIL. The parties are at liberty to avail their
remedy in accordance with law.
23. ISSUE 2-ESCALATION FOR THE FIRST RAKE:
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 86 of 109
23.1 Issue No.2 was related to HEIL’s claim for escalation in respect
of the first rake. At the outset, it is to be noted that this claim is not
directly affected by the issues of delay responsibility or liquidated
damages. Therefore, the claim for first-rake escalation must be
examined separately because it depends on its own evidence,
interpretation of the Contract, and calculation.
23.2 HEIL initially submitted its escalation bill in April 1998. The
same was returned by CONCOR on the ground that the parameters for
calculation had subsequently been amended. Again, HEIL submitted a
revised bill dated 30.08.2000 for Rs.53,35,084/-, based on the revised
parameters furnished by CONCOR.
23.3 The revised claim included a basic escalation amount of
Rs.49,39,893/-, sales tax of Rs.3,95,191.44 and a total claimed amount
of Rs.53,35,084.44. HEIL relied upon labour cost indices, exchange-
rate details certified by a nationalised bank and Metal Bulletin data for
September 1995 and December 1997.
23.4 CONCOR opposed the claim on three main grounds. First, it
was contended that the date of adjustment adopted by HEIL was
contrary to Clause 12.1. Second, it was contended that no escalation
could be allowed beyond the original delivery date unless specifically
provided for in the extension letters. Third, it was contended that no
escalation could be allowed for any period of delay attributable to
HEIL.
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 87 of 109
23.5 The Tribunal considered Clauses 12.1 and 12.2(b) together and
held that the escalation clause permits adjustment of increase in costs
during the original contractual delivery period, but did not permit
escalation for the period of delay attributable to the supplier. In
reaching this conclusion, the Tribunal also relied upon Container
Corporation of India Ltd. v. Texmaco Ltd., O.M.P. 24/2010 , where a
similar clause was interpreted in the same way.
23.6 In my view, no interference is warranted with this finding.
Clause 12.2(b) provides that no price increase shall be allowed beyond
the original delivery dates unless specifically stated in the extension
letter. The finding at page 90 of the impugned Award records that “ the
claimant, as is evident from the material on record, has claimed
escalation only upto original delivery period ”. If the claim was
confined to the original delivery period, the requirement of a specific
communication in the extension letter did not arise.
23.7 The objections regarding the relevant dates, indices and
calculation also essentially require examination of the material and
evidence on record. The Tribunal considered the relevant date and the
supporting material and found the claim to be in line with the terms of
the Contract. Such questions of fact fall within the domain of the
Arbitral Tribunal and cannot be re-examined by this Court under
Section 34 merely because another view may be possible or merely
some factual error is committed by the Tribunal.
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 88 of 109
23.8 Under Section 34 of the Act, this Court also cannot replace the
Tribunal’s interpretation of the Contract simply because another
interpretation is plausible to this Court. The Tribunal considered the
relevant clauses, the material placed before it and the earlier decision
where the same clause was interpreted. Its interpretation of Clauses
12.1 and 12.2(b) is a possible interpretation of the Contract and does
not disclose an error of the nature which would warrant interference
under Section 34.
23.9 The objection regarding HEIL’s responsibility for delay also
does not affect the first-rake escalation claim. The Tribunal had
confined the escalation to the original delivery period and had not
awarded escalation for the delayed period.
23.10 The Tribunal also did not accept the claim mechanically. It
examined the supporting material and calculations and deducted the
freight component of Rs.2,00,000/- and the sales tax amount from the
claim, and awarded only the basic escalation amount that it found
justified. Therefore, the decision was not based on a lack of evidence
or in failure to consider the relevant clauses as extensively argued by
the learned Senior Counsel for the CONCOR. There is nothing that
shocks the conscience of this Court so as to warrant interference and
authorities relied upon are also of no avail.
23.11 CONCOR’s contention that the Tribunal travelled beyond the
pleadings also does not warrant interference. The Tribunal was
dealing with the escalation claim and the objections raised by
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 89 of 109
CONCOR to its entitlement and calculation. No new claim or relief
outside the dispute was granted.
23.12 Accordingly, the award of Rs.47,39,893/- for first-rake
escalation is upheld. The Tribunal’s award of simple interest at 9%
per annum on this amount is also valid and does not violate Section
31(7) of the Act, or any clause of the Contract. Therefore, the interest
on this issue is also upheld.
24. ISSUES 8 AND 17-CONDITIONAL PRICE REDUCTION:
24.1 Issues Nos. 8 and 17 relate to the payment arrangement between
the parties. Issue No. 8 is about the conditional price reduction offered
by HEIL, while Issue No. 17 concerns with the effect of the World
Bank financing arrangement on the payment obligations of CONCOR.
The Tribunal considered the original contractual terms as well as the
subsequent correspondence relied upon by the parties.
24.2 HEIL provided for a reduction of Rs.50,000/- per five-wagon
set, subject to the condition that 65% of the payment would be
released against proof of dispatch. The Notification of Award
accepted the above offer along with these commercial terms. Clause
16.3 of the General Conditions further provided for payment within
sixty days of submission of the invoice and the required documents,
while Clause 11(b) of the Special Conditions dealt with the stages of
payment for domestic goods.
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 90 of 109
24.3 CONCOR’s case before the Tribunal was that the payment
arrangement was altered after the parties entered into the Contract.
Reliance was placed on the letter dated 02.07.1999 and HEIL’s reply
dated 07.07.1999. According to CONCOR, under this arrangement
CONCOR had to make payment and HEIL had to bear interest at 10%
for the period from payment till reimbursement by the World Bank.
24.4 The Tribunal considered this contention. It examined the above
relied letters, and thereafter considered Clause 19 of the Agreement,
which laid down the manner in which any variation or modification of
the Agreement was to be made. The Tribunal held that the letters
dated 02.07.1999 and 07.07.1999 did not constitute an amendment or
novation of the Agreement and that the original payment terms agreed
initially were still operating.
24.5 In my reading of the impugned Award, there is no error in the
reasoning of the Tribunal. The Tribunal did not ignore the letters of
02.07.1999 and 07.07.1999. It has also considered the alleged
arrangement and rejected the contention that those letters had altered
the Agreement by relying on Clause 19. Thus, the Tribunal did not
proceed on the basis that the letters did not exist or the subsequent
arrangement was never agreed upon.
24.6 The contention that the Tribunal made out a new case by
relying upon Clause 19 also cannot be accepted. Clause 19 was part of
the Contract itself. Once CONCOR relied upon the letters of
02.07.1999 and 07.07.1999 as having changed the agreed payment
terms, the question whether such change was in accordance with
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 91 of 109
Clause 19 necessarily arose before the Tribunal and it was entitled to
examine the alleged arrangement in accordance with that clause. In the
end, the Tribunal gave primacy to clause of the Contract that was
agreed with the parties and I cannot find any fault in such approach.
24.7 I have also considered the plea of estoppel based on the
subsequent conduct of the parties. The subsequent payments were a
relevant circumstance but they cannot override the terms on which the
original payment condition was agreed. The Tribunal considered the
correspondence and the manner in which the parties acted
subsequently and rejected that contention.
24.8 Accordingly, the Tribunal’s finding cannot be said to be based
on ignoring the July 1999 letters or adopting an interpretation wholly
contrary to the Agreement. So long as the view taken is a possible and
plausible interpretation of the Contract, this Court cannot substitute its
own view for that of the Tribunal.
24.9 Therefore, the award of Rs.1,72,50,000/- towards restoration of
the conditional price reduction, along with the interest awarded on that
amount, is upheld.
24.10 For Issue No. 17, CONCOR’s contended that the project was
financed through the World Bank and that its obligation to make
payment to HEIL was dependent upon receipt of reimbursement from
the World Bank.
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 92 of 109
24.11 The Tribunal found that the Agreement was between CONCOR
and HEIL and that the World Bank was not a party to it. It also found
no provision making CONCOR’s payment obligation conditional
upon reimbursement from the World Bank. The July 1999 letters,
relied upon by CONCOR, may explain the arrangement regarding
reimbursement and the 10% interest, but it does not make receipt of
World Bank funds a condition precedent to payment.
24.12 No provision of the Contract has been shown which explicitly
makes CONCOR’s obligation to pay HEIL conditional upon receipt of
funds from the World Bank. Therefore, the finding on Issue No. 17
does not disclose any ground for interference under Section 34 and is
upheld.
25. HEIL’S CROSS-CHALLENGE TO REJECTION OF
ESCALATION ITEM 2 TO 12:
25.1 HEIL has challenged the rejection of the escalation claims at
Serial Nos. 2 to 12 of Annexure-F mainly on the ground that Clause
12 of the Special Conditions gives a contractual right to price
adjustment which is not dependent upon submission of a separate
escalation invoice. Reliance has also been placed on McDermott
International Inc. (supra) to contend that a claim may be raised
through correspondence or in meetings and that the absence of a
formal bill does not defeat the claim.
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 93 of 109
25.2 The Tribunal rejected the escalation claims for serial numbers 2
to 12 of Annexure-F for several reasons and not merely because
separate escalation invoices had not been submitted. It found that even
if Clause 16(2) of the General Conditions requiring submission of an
invoice is not applicable, HEIL was still required to satisfy the
conditions of Clause 12(2) of the Special Conditions for invoking the
price adjustment formula. The Tribunal specifically referred to the
requirement of furnishing the relevant labour and material indices and
other particulars necessary for applying the formula.
25.3 The Tribunal found that HEIL had not furnished the material
necessary to undertake that exercise for Items 2 to 12. It also noticed
that the Statement of Claim contained no particulars of these claims
apart from their inclusion in Annexure-F. This was a matter of
evidence and application of the terms of the Contract which the
Tribunal was entitled to consider.
25.4 The Tribunal also drew a comparison with Item No.1. In respect
of that claim, HEIL had submitted an invoice and the details required
under Clause 12(2). The Tribunal treated this conduct as significant
because it showed that, where HEIL itself sought the benefit of the
escalation formula, it had in fact furnished the requisite information.
25.5 The Tribunal also found an issue with the adjustment date.
Clause 12.1 required the adjustment date to be one month prior to the
date of shipment. The Tribunal noticed that the same date, 11.03.2002,
had been used for all claims from Serial Nos. 2 to 12, even though the
rakes were supplied on different dates. Therefore, the Tribunal found
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 94 of 109
that the claims did not follow the requirement of Clause 12.1. I find no
infirmity in this reasoning. The Tribunal considered the relevant
clauses and the evidence on record before rejecting the claims. The
interpretation adopted by the Tribunal in no way can be said to be a
view which no reasonable person could have arrived at.
25.6 HEIL’s reliance on McDermott International Inc. (supra).
does not help its case. That decision only explains that a claim does
not fail merely because a formal invoice has not been issued. It does
not dispense with the requirement of establishing the necessary
requirements as per the Contract and other factual basis for
quantification of an escalation claim.
25.7 Under Section 34, the Court cannot fill in the missing details by
assuming shipment dates, choosing adjustment dates, selecting
applicable indices, or recalculating the escalation formula for each
rejected claim. Doing so would mean that the Court is deciding the
claims afresh, which is beyond the limited scope of review under
Section 34. Nor can the Court grant these rejected claims by treating
the present proceedings as an appeal. Therefore, the rejection of the
escalation claims for serial numbers 2 to 12 is upheld, and OMP
(COMM) NO. 50/2016 filed by HEIL is dismissed.
26. ISSUES NOT OTHERWISE CHALLENGED AND THEIR
STATUS:
26.1 For completeness, the Court records the position of the
remaining issues dealt with in the impugned Award. Issue No.3
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 95 of 109
related to the alleged additional cost due to a change in spring
material. The Tribunal rejected this claim on contractual and
evidentiary grounds. Since neither party has challenged this finding, it
remains unchanged.
26.2 Issues Nos. 4 and 5 were withdrawn by HEIL before the
Tribunal and were therefore, not adjudicated on the merits. Issue No.
7, relating to additional wheel sets and bearings, was also not decided
on the merits. The Tribunal itself recorded that HEIL itself treated the
supply as outside the original Contract and left HEIL free to pursue
any remedy available in law. These positions have not been
challenged and therefore require no further consideration.
26.3 Issue No. 6 concerned HEIL’s claim for workers’ idling costs,
which the Tribunal rejected for want of sufficient evidence. Issue No.
9, relating to increased freight, was withdrawn by HEIL. Issues Nos.
10 and 11, concerning differential interest on margin money and bank-
guarantee commission respectively, were rejected by the Tribunal.
None of these findings has been challenged in the present proceedings,
and therefore, they remain undisturbed.
26.4 Issue No. 25 concerned whether certain claims were dehors the
Contract. Claims Nos. 4, 5 and 9 had already been given up by HEIL.
For Claims Nos. 2, 3, 6, 7 and 8, the Tribunal held that they were
within the terms of the Contract. Since these claims have already been
considered above, if required, no separate finding is required on Issue
No. 25.
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 96 of 109
26.5 Issue No.27 regarding interest will apply only to the amounts
that remain payable after this judgment. Since the award of refund of
liquidated damages has been set aside, the interest awarded on that
amount will also not survive. The interest awarded on the first-rake
escalation and the restoration of the conditional price reduction will,
therefore continue, while the interest relating to the refund of
liquidated damages cannot survive once the underlying amount is no
longer payable. As regards Issue No. 27A, under which costs were
awarded in favour of HEIL, the award of costs is within the discretion
of the Tribunal. Further, HEIL had succeeded in some of its claims
even after the modifications made to the award as discussed above,
and therefore, there is no reason to interfere with the Tribunal’s
decision on costs.
26.6 Issue No.28, which contains the final relief, will operate in the
modified form resulting from this judgment.
27. SECTION 34(4): REMISSION POWER OF THIS COURT
27.1 Section 34(4) of the Act empowers the Court, where
appropriate, to adjourn the proceedings under Section 34 and afford
the Arbitral Tribunal an opportunity to resume the arbitral proceedings
or take such other action as may eliminate the grounds for setting
aside the award. The provision is intended to address defects which
can be remedied by the Arbitral Tribunal without requiring the Court
to enter into the merits of the dispute.
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 97 of 109
33
27.2 In Kinnari Mullick v. Ghanshyam Das Damani , the Supreme
Court explained the limited nature of the power under Section 34(4).
The Constitution Bench in Gayatri Balasamy v. ISG Novasoft
34
Technologies Ltd. , has also clarified that a request under Section
34(4) need not necessarily be in writing and that the Court may, in an
appropriate case, exercise the power if there is a request by a party.
27.3 In this case, neither party made a request for the matter to be
taken back to the Tribunal for reconsideration. More importantly, the
defects identified above are not confined to an omission to clarify an
otherwise concluded finding. They concern the absence of findings on
material questions which formed the basis of the award.
27.4 This distinction is important. In I -Pay Clearing Services Pvt.
Ltd. (supra), the Supreme Court considered the scope of Section 34(4)
where the award did not contain a finding on a material issue. The
Court held that Section 34(4) may be used where there is inadequate
reasoning or a gap in the reasoning supporting a finding already
recorded. However, where there is no finding on a contentious issue at
all, the defect cannot be cured by asking the Tribunal to supply
reasons or fill the gap. In such a case, the Court may set aside the
award rather than remit the matter under Section 34(4). The relevant
observations read as follows-
“ 39. Further, Section 34(4) of the Act itself makes it clear that it is
the discretion vested with the Court for remitting the matter to
Arbitral Tribunal to give an opportunity to resume the proceedings
or not. The words “where it is appropriate” itself indicate that it is
33
(2018) 11 SCC 328
34
(2025) 7 SCC 1
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 98 of 109
the discretion to be exercised by the Court, to remit the matter
when requested by a party. When application is filed under Section
34(4) of the Act, the same is to be considered keeping in mind the
grounds raised in the application under Section 34(1) of the Act by
the party, who has questioned the award of the Arbitral Tribunal
and the grounds raised in the application filed under Section 34(4)
of the Act and the reply thereto.
40. Merely because an application is filed under Section 34(4) of
the Act by a party, it is not always obligatory on the part of the
Court to remit the matter to Arbitral Tribunal. The discretionary
power conferred under Section 34(4) of the Act, is to be exercised
where there is inadequate reasoning or to fill up the gaps in the
reasoning, in support of the findings which are already recorded in
the award.
41. Under the guise of additional reasons and filling up the gaps in
the reasoning, no award can be remitted to the arbitrator, where
there are no findings on the contentious issues in the award. If
there are no findings on the contentious issues in the award or if
any findings are recorded ignoring the material evidence on
record, the same are acceptable grounds for setting aside the
award itself. Under the guise of either additional reasons or filling
up the gaps in the reasoning, the power conferred on the Court
cannot be relegated to the arbitrator. In absence of any finding on
contentious issue, no amount of reasons can cure the defect in the
award.
42. A harmonious reading of Sections 31, 34(1), 34(2-A) and 34(4)
of the Arbitration and Conciliation Act, 1996, make it clear that in
appropriate cases, on the request made by a party, Court can give
an opportunity to the arbitrator to resume the arbitral proceedings
for giving reasons or to fill up the gaps in the reasoning in support
of a finding, which is already rendered in the award. But at the
same time, when it prima facie appears that there is a patent
illegality in the award itself, by not recording a finding on a
contentious issue, in such cases, Court may not accede to the
request of a party for giving an opportunity to the Arbitral
Tribunal to resume the arbitral proceedings.”
27.5 The defects in the present case go beyond a mere gap in
reasoning. The Tribunal would have to reconsider the effect of the
amended Clause 2.1, determine responsibility for the disputed design
changes, examine whether the drawings were complete and compliant
within the stipulated time, consider the period of production and
supply after prototype approval, assess the effect of the non-
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 99 of 109
production of procurement records, determine the periods of force
majeure and their effect on the delay, and thereafter reconsider the
question of liquidated damages.
27.6 These are not matters which can be cured by adding reasons to
findings already recorded. The Supreme Court in Gayatri Balasamy
(supra) has also clarified that the power under Section 34(4) is
discretionary and is intended to address defects which can properly be
cured within the arbitral proceedings. It is not meant to be used where
the Court would, in substance, be sending the matter back for a fresh
adjudication of issues which were not decided or which require a fresh
appreciation of the evidence.
“56. As elucidated above, if a fog of uncertainty obscures the
exercise of modification powers, the courts must not modify the
award. Instead, they should avail their remedial power and
remand the award to the Tribunal under Section 34(4). Under the
sub-section, either party—whether the one challenging the award
under Section 34 or the one defending against such a challenge—
may request the Court to adjourn the proceedings for a specified
period. If the court deems it appropriate, it may grant such an
adjournment, allowing the Arbitral Tribunal to resume
proceedings or take necessary corrective measures to eliminate the
grounds for setting aside the award. Thus, Section 34(4) provides a
second opportunity for a party to seek recourse through arbitral
channel.
57. However, the power of remand permits the Court only to send
the award to the Tribunal for reconsideration of specific aspects.
It is not an open-ended process; rather, it is a limited power,
confined to limited circumstances and issues identified by the
Court. Upon remand, the Arbitral Tribunal may proceed in a
manner warranted by the situation — including recording
additional evidence, affording a party an opportunity to present
its case if previously denied, or taking any other corrective
measures necessary to cure the defect. In contrast, the exercise of
modification powers does not allow for such flexibility. Courts
must act with certainty when modifying an award — like a
sculptor working with a chisel, needing precision and exactitude.
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 100 of 109
Therefore, the argument that remand powers make modification
unnecessary is misconceived. They are distinct powers and are to
be exercised differently.
58. Section 34(4), derived from the Model Law, is discretionary in
nature. This is evident from the use of the word “may” in the
provision. The Court may invoke this power when it identifies a
defect in the award that could lead to its setting aside. In such
cases, the Court may seek to prevent this outcome by granting the
Arbitral Tribunal an opportunity to rectify the defect.
59. While it is not appropriate to establish rigid parameters or a
straitjacket formula for the exercise of this power, it is clear that
Section 34(4) does not authorise the Arbitral Tribunal to rewrite
the award on merits or to set it aside. Rather, it serves as a
curative mechanism available to the Tribunal when permitted by
the Court. The primary objective is to preserve the award if the
identified defect can be cured, thereby avoiding the need to set
aside the award. Accordingly, a court may not grant a remand
when the defect in the award is inherently irreparable. A key
consideration is the proportionality between the harm caused by
the defect and the means available to remedy it.
60. While exercising this power, the Court must also remain
mindful that the Arbitral Tribunal has already rendered its
decision. If the award suffers from serious acts of omission,
commission, substantial injustice, or patent illegality, the same
may not be remedied through an order of remand. Clearly, there
cannot be a lack of confidence in the Tribunals' ability to come to a
fair and balanced decision when an order of remit is passed.
61. Thus, an order of remand should not be passed when such
order would place the Arbitral Tribunal in an invidious or
embarrassing position. Additionally, remand may be inappropriate
when it does not serve the interests of the parties, particularly in
time-sensitive matters or where it would lead to undue costs and
inefficiencies. Once an order of remand is granted, the Arbitral
Tribunal has the authority to vary, correct, review, add to, or
modify the award. Notably, under Section 34(4), the Tribunal's
powers, though confined, remain nonetheless substantial. This
stands in contrast to the Court's narrow role under the rest of
Section 34.
62. This Court in Kinnari Mullick v. Ghanshyam Das Damani
[Kinnari Mullick v. Ghanshyam Das Damani, (2018) 11 SCC 328 :
(2018) 5 SCC (Civ) 106] , referred to and laid down the
preconditions for exercising the power of remand under Section
34(4). It held that the Court cannot exercise the power of remand
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 101 of 109
suo motu in the absence of a written request by one of the parties.
Secondly, once an application under Section 34(1) has been
decided and the award set aside, the Court becomes functus officio
and cannot thereafter remand the matter to the Arbitral Tribunal.
Consequently, the power under Section 34(4) cannot be invoked
after the Court has disposed of the Section 34(1) application.
63. We are unable to accept the view taken in Kinnari Mullick
[Kinnari Mullick v. Ghanshyam Das Damani, (2018) 11 SCC 328 :
(2018) 5 SCC (Civ) 106] , which insists that an application or
request under Section 34(4) must be made by a party in writing.
The request may be oral. Nevertheless, there should be a request
which is recorded by the Court. We are also unable to agree that
the request must be exercised before the application under Section
34(1) is decided. Section 37 (Annexure A) permits an appeal
against any order setting aside or refusing to set aside an arbitral
award under Section 34. To this extent, the appellate jurisdiction
under Section 37 is coterminous with, and as broad as, the
jurisdiction of the Court deciding objections under Section 34.
Hence, the contention that the Tribunal becomes functus officio
after the award is set aside is misplaced. The Section 37 Court still
possesses the power of remand stipulated in Section 34(4). Of
course, the appellate court, while exercising power under Section
37, should be mindful when the award has been upheld by the
Section 34 Court. But the Section 37 Court still possesses the
jurisdiction to remand the matter to the Arbitral Tribunal.
64. Our reasoning does not breach the principle of party
autonomy. [ Rather, it acknowledges that the parties opting for
arbitration also consent to be governed by the applicable statute
governing arbitration — in this case, the 1996 Act. Further,
principle of party autonomy should not be extended to an extreme
to urge that the party misunderstood the law and consequently the
consent is invalid. While it is true that a mistake of law may vitiate
consent in certain contexts, the interpretation here restricts the
Court's role to that of limited judicial scrutiny in terms of the 1996
Act.] Neither does it confer appellate powers on the courts.
Instead, it adheres strictly to the parameters stipulated in Sections
34 and 37 of the 1996 Act. The power of the appellate court in civil
proceedings under Order 41 of the Code, is as broad as that of a
trial court, both in terms of facts and law. Contrastingly, the
Court's authority under Sections 34 and 37 of the 1996 Act is
limited by the silhouette of Section 34.
65. In Dyna Technologies (P) Ltd. v. Crompton Greaves Ltd.
[Dyna Technologies (P) Ltd. v. Crompton Greaves Ltd., (2019) 20
SCC 1] , this Court emphasised that the issuance of a reasoned
award is not a mere formality under the 1996 Act. For an award to
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 102 of 109
be termed “reasoned”, it must meet three essential yardsticks: it
must be proper, intelligible, and adequate. The purpose behind
Section 34(4) is clear: it allows for an award to become
enforceable after granting the Tribunal an opportunity to cure any
defects. This power is exercisable when the Arbitral Tribunal has
failed to give any reasoning or the award exhibits gaps in
reasoning and these defects can be cured, thereby preventing
unnecessary challenges. The underlying intent is to provide an
effective, expeditious forum for addressing curable defects, which
Section 34(4) facilitates.
66. In I-Pay Clearing Services (P) Ltd. v. ICICI Bank Ltd. [I-Pay
Clearing Services (P) Ltd. v. ICICI Bank Ltd., (2022) 3 SCC 121 :
(2022) 2 SCC (Civ) 49] , this Court clarified that Section 34(4)
does not grant the authority to review or reconsider previous
findings or conclusions. As discussed earlier in this judgment, the
scope of the power under Section 34(4) is not to be restricted to a
rigid, straitjacket formula. Rather, it depends on the specific facts
and circumstances of each case. Being a discretionary power, it is
to be exercised by the Court judiciously, keeping in mind the
grounds raised in the application under Section 34(1). The Court
should be prima facie satisfied that the wrong and illegality in the
award are curable. While doing so, the Court need not record the
final finding on the contentious issue at hand; however, not every
request for such relief is warranted. The discretion must be
exercised with caution, and only when it is evident that an
adjournment will allow the Arbitral Tribunal to resolve the issues
and remove the grounds for setting aside the award. However,
Section 34(4) is an enabling provision — it does not compel the
Tribunal to take corrective action, leaving it free to either amend
or refuse to amend the award.”
(emphasis supplied)
27.7 In the present case, it is clear that the defects cannot be cured
merely by supplying additional reasons to the findings already
recorded. They require a fresh examination of the contractual
obligations, disputed facts and evidence on which the Tribunal’s
conclusions were based. Section 34(4) cannot be used to give the
Tribunal an opportunity to reconsider the merits of the dispute after
the findings forming the basis of the award have themselves been
found unsustainable.
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 103 of 109
27.8 The long history of the arbitration also cannot be ignored,
though it is not by itself the basis for the decision. The arbitration
commenced in 2002. Two earlier arbitrators withdrew on account of
health reasons, the present Tribunal took over in 2010, and the award
was ultimately rendered in 2015. At this stage, directing a complete
reconsideration of the merits would effectively require the dispute to
be reopened after more than two decades of arbitral proceedings. This
is a factor which also weighs against invoking Section 34(4) in the
present case.
27.9 Accordingly, I do not find it appropriate to invoke Section 34(4)
in the present case.
28. ISSUE-WISE DISPOSITION, SEVERABILITY AND
OPERATIVE ORDER:
28.1 Issue No.1 is set aside. Therefore, the direction requiring
CONCOR to refund Rs.18,88,43,273/- towards liquidated damages,
together with the interest on it does not survive. This Court has not
held that CONCOR is entitled to retain the entire amount. The parties
shall be at liberty to avail their remedy, if any, in accordance with law.
28.2 Issue No.2 is upheld in entirety, including the award of
Rs.47,39,893/- towards escalation for the first rake and the rejection of
the escalation claims at Serial Nos.2 to 12 of Annexure-F. No further
amount is payable under this issue.
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 104 of 109
28.3 Issue No.3 remains undisturbed. The rejection of the claim
towards additional spring material cost has not been challenged.
28.4 Issues Nos.4 and 5 remain undisturbed as the claims were
expressly given up before the Tribunal.
28.5 Issue No.6 remains undisturbed. The rejection of the claim
towards alleged idling of workers has not been challenged.
28.6 Issue No.7 remains undisturbed in the terms of the impugned
Award. This Court has not examined the merits of the claim
28.7 Issue No.8 and 17 are upheld. CONCOR shall pay HEIL
Rs.1,72,50,000/- towards the amount deducted as conditional price
reduction in respect of 345 sets.
28.8 Issue No.9 remains undisturbed, as a claim not pressed before
the learned Arbitral Tribunal.
28.9 Issues Nos.10 and 11 remain undisturbed. The rejection of those
claims has not been challenged before this Court.
28.10 Issues Nos.12, 13 and 19 to 24, relating to CONCOR’s
counterclaims, are set aside only to the extent that their rejection rests
on the finding that delay was not attributable to HEIL. This Court
does not determine the entitlement, causation or quantum of any
counterclaim.
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 105 of 109
28.11 Issue No.14 is set aside. The finding that the delay was wholly
not attributable to HEIL was based on an erroneous interpretation of
the amended Clause 2.1 read with the other terms of the Contract
governing responsibility for design and performance.
28.12 Issues Nos.15 and 16 are set aside because the Tribunal did not
render the necessary findings on whether HEIL submitted complete
and timely drawings and whether the material design changes were
purchaser-directed variations or supplier obligations arising from as
per agreed conditions.
28.13 Issue No.18 survives to the extent that the Tribunal’s factual
findings regarding the occurrence of the alleged force majeure events
are not disturbed. However, in view of this Court, those findings
cannot be the basis to sustain the complete refund of liquidated
damages for the entire period of delay.
28.14 Issue No.25 has no independent monetary consequence. It shall
operate in line with the findings recorded in this judgment and the
surviving individual claims.
28.15 The findings on Issue No.26 are set aside. The question of
whether HEIL maintained regular supplies after final prototype
approval was a distinct factual issue which was not independently
adjudicated by the Tribunal.
28.16 Issue No.27 concerning interest survives only in respect of the
principal amounts above.
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 106 of 109
28.17 Issue No.27A, relating to costs, is upheld as HEIL has
succeeded on some of its claims even after the modifications made by
this judgment.
28.18 Issue No.28, which contains the final relief granted in the
award, will apply in the modified form after considering the parts of
the impugned Award that have been set aside or upheld by this
judgment.
28.19 This Court finds that the portions of the impugned Award which
are set aside can be separated from those which are sustained. The
refund of liquidated damages and rejection of CONCOR’s
counterclaims rested on the finding regarding responsibility for delay,
whereas the first-rake escalation and conditional price reduction were
mainly decided on the basis of separate clauses and after appreciation
of material on record. Therefore, these findings can stand
independently.
28.20 As recognised in Gayatri Balasamy (supra) . , a Court can
preserve parts of an arbitral award that can stand independently, as
long as doing so does not require the Court to decide the merits again.
Accordingly, the Court has retained the parts of the award that are
independently valid and set aside only those parts affected by the
grounds given under Section 34.
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 107 of 109
28.21 Accordingly, OMP (COMM) No. 11/2016 filed by CONCOR is
partly allowed. The impugned Award is set aside to the extent that it
directs CONCOR to refund of Rs.18,88,43,273/- towards liquidated
damages under Issue No. 1. The interest awarded on that amount is
also set aside.
28.22 The rejection of CONCOR’s counterclaims under Issues Nos.
12, 13 and 19 to 24 is set aside to the limited extent stated above. No
amount is awarded on those counterclaims, and no finding is recorded
on their merits, entitlement or quantum.
28.23 The award of Rs.47,39,893/- towards first-rake escalation,
together with simple interest at 9% per annum as directed by the
Tribunal, is upheld.
28.24 The award directing payment of Rs.1,72,50,000/- towards the
conditional price reduction, together with simple interest at 9% per
annum as directed by the Tribunal, is also upheld.
28.25 OMP (COMM) No. 50/2016 filed by HEIL is dismissed. No
fresh calculation, modification or remission is directed in respect of
those claims.
28.26 The petitions and all pending applications therein stand
disposed of in the aforesaid terms.
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 108 of 109
28.27 The Registry shall place a copy of this judgment in both the
petitions.
OM PRAKASH SHUKLA, J
AUGUST 19, 2026/at/pa
Signature Not Verified
Signed By:ANUBHAV
TRIPATHI
Signing Date:20.08.2026
17:01:03
O.M.P. (COMM) 11/2016 and connected matter Page 109 of 109