Ramasethu Infrastructure Pvt Ltd vs Indian Railways Welfare Organisation
- Court
- Delhi High Court
$~42
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Date of Decision : 23.07.2026
+ FAO(OS) (COMM) 182/2026
RAMASETHU INFRASTRUCTURE PVT LTD .....Appellant
Through: Mr. M. Gireesh Kumar, Mr. Sanjay
Singh and Ms. Sneha Mathew, Advs.
versus
INDIAN RAILWAYS WELFARE ORGANISATION
.....Respondent
Through: None.
CORAM:
HON'BLE MR. JUSTICE V. KAMESWAR RAO
HON'BLE MS. JUSTICE MANMEET PRITAM SINGH ARORA
V. KAMESWAR RAO, J. ( ORAL )
CM APPL. 46579/2026 (Exemption)
1. Exemption is allowed, subject to all just exceptions.
2. The application stands disposed of.
CM APPL. 46580/2026 (For condonation of delay in re-filing )
3. For the reasons stated in the application, the delay of the 54 days in
re-filing the appeal is condoned. The same is allowed.
4. The application stands disposed of.
FAO(OS) (COMM) 182/2026
5. This appeal lays a challenge to the order of the learned Single Judge
dated 24.03.2026, whereby the learned Single Judge has dismissed the
Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:27.07.2026
14:55:03
FAO(OS) (COMM) 182/2026 Page 1 of 9
petition filed by the appellant herein under Section 34 of the Arbitration and
Conciliation Act, 1996, (“The Act”) challenging the award dated 23.12.2014
by stating in paragraph nos. 17 and 18 as under:-
“17. The learned Arbitrator has interpreted the force
majeure clause and has come to the conclusion that the
present event on which reliance is placed by the
Petitioner will not fall within the four corners of force
majeure clause. This Court is in agreement with the
view taken by the learned Arbitrator. Even otherwise,
as repeatedly held by the Apex Court, the
interpretation of a contract, predominantly, is in the
domain of the Arbitrator. An award cannot be set aside
just because another view is possible or sometimes is
even more preferable.
18. In the opinion of this Court, the challenge does not
fall within the parameters of Section 34 of the
Arbitration & Conciliation Act. The fact that another
conclusion is possible will not persuade this Court to
substitute its own conclusion to the one arrived at by
the Arbitral Tribunal unless it is said to be so perverse
that it shocks the conscience of the Court.”
6. Some of the relevant facts necessary for the purpose of deciding this
appeal are primarily that the appellant herein is a private limited company
engaged in business of development of infrastructure and other allied
activities. The appellant being a successful bidder of tender with regard to
project of construction of 140 dwelling units, was awarded the work vide
letter dated 27.12.2011. The time period for completion the project was 24
months. The appellant had deposited an earnest money of Rs.5,00,000/-,
which had been retained by the respondent and converted into security
deposit. It is the case of the appellant that immediately after the
Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:27.07.2026
14:55:03
FAO(OS) (COMM) 182/2026 Page 2 of 9
commencement of the tender work, the local residents started raising
objections and obstructing the work of the project site. The appellant sent
communications dated 05.03.2012 and 05.04.2012 respectively to the
respondent, expressing its inability to continue the work due to the hostile
attitude of the local public and non-availability of an unencumbered land.
7. It is noted that the respondent after taking into account the
communications of the appellant, met the District Collector and was advised
that the construction could be started. The same was informed to the
appellant by the respondent. It is also noted that the appellant herein wrote a
letter to the respondent, requesting for termination of the contract and also
sought for return of the bank guarantees given by the appellant, which is part
of the contract conditions. The respondent did not agree with the said
request of the appellant and asked the appellant to remain on the site.
8. The appellant thereafter invoked force majeure clause in the contract
and requested the closure of the contract vide communication dated
28.06.2012. In the meantime, the local residents had filed a petition before
the Madras High Court which had granted a stay on the project . In any case,
the petition was dismissed by the Madras High Court thereby vacating status
quo order dated 03.12.2012. Inability on the part of the appellant to carry out
the work resulted in termination of the work by the respondent. The only
case set up by the appellant before the learned Single Judge, was whether
the action of the appellant in discontinuing the work and demanding
foreclosure of the work and applications was justified and claim for bank
guarantees was justified or not.
9. The said issue was decided by the learned Single Judge by referring to
clause 6.2.25 of the tender document, which is the force majeure clause,
Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:27.07.2026
14:55:03
FAO(OS) (COMM) 182/2026 Page 3 of 9
which we reproduced as under:-
“6.2.25 Force Majeure Clause
i) If at any time during the continuance of this contract
the performance in whole or part by either party of any
obligation under this contract shall be prevented or
delayed by reasons of any war, hostility, acts of Public
enemy, Civil commotion, sabotage, serious losses or
damage by fire, explosion, epidemic, strike, lock-out or
acts of God (hereinafter referred to as 'Event')
provided notice of the happening of any such event is
given by either party to the other within 10 days from
the date of occurrence thereof, neither party shall by
reasons of such events be entitled to terminate this
contract, nor shall either party have any claim for
damages against the other in respect of such non
performance or delay in performance, and works under
the contract shall be resumed as soon as practicable
after such event has come to an end or ceased to exist
and decision of the engineer as to whether the works
have been so resumed or not shall be final and
conclusive; provided further that if the performance, in
whole or in part of any obligation under this contract
is prevented or delayed by reasons of any such event
for a period exceeding 90 days, either party may at its
option terminate the contract by giving notice to other
party.
ii) In case of such event for which the Contractor has
given timely written notice thereof to the Engineer,
Engineer shall make a fair and reasonable extension of
time for completion of the contract works. The
Contractor shall nevertheless constantly use his
endeavour to prevent delays and shall do all that may
reasonably be required to the satisfaction of the
Engineer.
iii) The contractor's right to an extension of time limit
for completion of the work in the above mentioned
cases is subject to the following procedures.
a) That within 10 days after the occurrence of case of
Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:27.07.2026
14:55:03
FAO(OS) (COMM) 182/2026 Page 4 of 9
FORCE MAJEURE but before the expiry of the
stipulated date of completion, he informs the Engineer
and IRWO in writing that he considers himself entitled
to an extension of the time limit.
b) That, he produces evidence of the date of occurrence
and the duration of the FORCE MAJEURE in an
adequate manner by means of documents drawn up by
reasonable authorities.
c) That, he proves that the said conditions have
actually interfered with the carrying out of the
contract.
d) That, he proves that the delay incurred is not due to
his own action or lack of action.
In the cases mentioned above for delays in completion
of the works, such failures or delays shall in no way
affect or vitiate the contract or alter the character
thereof or entitle the contractor to damage or
compensation thereof but the contractor shall apply for
extension of time at least 45 days before the completion
of the contract period and IRWO shall grant such
extension or extension of the completion dates as shall
appear to the Engineer reasonable in the
circumstances and his decision in the matter will be
final and binding on the contractor.
e) In all other cases, IRWO may grant extension of
time with levy of compensation against legitimate of
damages as per clause 6.2.25 (a) and (b) and without
escalation (i.e. original quoted rates will be paid.)”
10. The conclusion of the Tribunal on the force majeure clause can be
seen from paragraph no.9 of the order of the learned Single Judge, which we
reproduce as under:-
“9. The Arbitral Tribunal has gone into the definition
of force majeure by referring to various dictionary
meanings. The Tribunal has concluded as under:-
“5.3.4 Event of "Hostility" and "Public Enmity-The
term hostility is defined in Black's law dictionary as
Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:27.07.2026
14:55:03
FAO(OS) (COMM) 182/2026 Page 5 of 9
state of enmity between individuals or nations. An act
or series of acts displaying antagonism, hostile act or
state acts of war. The AT is of the opinion that there
was no enmity between the Respondents and the
R.W.A. as such. The action of nuisance, threats and
disruption of work by R.W.A was not by enmity but
motivated simply to scare away the contractor so that
no construction could take place on the plot and they
continue to use the plot as playground. Even in this the
R.W.A did not succeed as the work continued as per
Claimant's own admission (Para 5.2.4 above). Hence
the event of Hostility is not attracted. Similarly the
R.W.A, being a private body, cannot be termed as
"Public Enemy". Thus the AT is of the view that the
Force Majeure clause is not attracted.
5.3.5 Notwithstanding the conclusion that the Force
Majeure clause is not attracted, even if it is assumed
that the event of Hostility did exist, it lasted only for 40
days i.e. from 22-03-2012 to 05-05-2012. After 05- 05-
2012 the work was stayed as per the order of H.C. The
Claimant's argument of the period of 90 days has been
arrived at by adding 40 days of hostility and 50 days
(from 05-05-2012 to 25-06-2012) of the Stay order and
asked for termination of the contract. For the 50 days
period from 05-05-2012 to 25-06-2012 there was
neither any hostility nor the period under stay order
from the Court is covered as an event under Force
Majeure clause.
5.3.6 Thus the request of termination of the contract by
the Claimant was rightly rejected by the Respondent.
5.3.7 The stay by the High Court was vacated on 03-
12-2012 and the Respondent advised the Claimant to
restart the work. The claimant advised the Respondent,
vide its letter dated 24-12-2012, that after examining
the matter in detail they have apprehension that the
miscreants are planning to attack again for stoppage
of work. Hence they regret to inform that they are not
in a position to carry out work (Para 5.2.13). The
Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:27.07.2026
14:55:03
FAO(OS) (COMM) 182/2026 Page 6 of 9
Respondent, treating the refusal to restart work as
amounting to abandoning the work by the Claimant,
proceeded to determine / terminate the Contract as per
Clause 6.8 of the Tender conditions and forfeited the
security deposit of Rs. 5 Lakh and P.B.G of Rs. 83.62
Lakh by encashing the same.
5.3.8 The AT is of the view that the apprehension of the
Claimant was a mere presumption which had no basis,
nor based on any evidence or hard facts and the
Respondent was within its right to terminate the
contract and forfeit the security deposit & encash the
Performance Guarantee.
5.3.9 In regard to discharge of reciprocal obligation,
we uphold the contention of the Respondent that the
ownership of land by them was never disputed and that
has also been confirmed by the High Court of Chennai
when they dismissed the writ petition filed by the RWA.
The land was handed over to the Claimant free of all
encumbrances for starting the work and when the
disturbance took place the Respondent was fully
involved in getting it removed with the help Executive
& Judicial authorities.
53.10 Thus the Claims of the Claimant are rejected
and the award is Nil.”
11. The learned Single Judge by referring to the judgement of the
Supreme Court in the case of National Highways Authority of India v. ITD
Cementation India Ltd., (2015) 14 SCC 21 , has concluded that it cannot be
said that the interpretation given by the Arbitral Tribunal is so perverse that
it shocks the conscience of the Court. The learned Single Judge has also held
that the Arbitral Tribunal has applied literal construction of the contract
which cannot be faulted with as the same is permissible.
12. We have already produced the final conclusion drawn by the learned
Single Judge in paragraphs no. 17 and 18. The submission of learned
Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:27.07.2026
14:55:03
FAO(OS) (COMM) 182/2026 Page 7 of 9
counsel for the appellant is that the impugned order of the learned Single
Judge fails to correctly appreciate: -
i. that the award ignores vital evidence on record rendering it perverse;
ii. that the conclusion of the Tribunal that no force majeure condition
existed is contrary to the documented status quo order;
iii. that the right to encash the bank guarantee and forfeit Ernest Money
Deposit was wrongly invoked in the absence of an executed agreement;
and
iv.that the award suffers from patent illegality warranting interference
under Sections 34 and 37 of the Act.
13. Suffice to state that the Tribunal has held notwithstanding the
conclusion that the force majeure clause is not attracted even if it were to be
assumed that hostility existed, the same lasted only for around 40 days i.e.,
from 22.03.2012 to 03.05.2012. Post 05.05.2012, the work stopped as per
the order dated 03.05.2012 of the High Court of Madras. The Tribunal has
also noted the arguments on behalf of the appellant, or that the period of 90
days has been arrived at by adding 40 days of hostility and 50 days of the
stay order and as such, the appellant had rightly sought termination of the
contract, cannot be accepted.
14. Suffice to state, the said submission was not agreed to by the learned
Arbitral Tribunal for the simple reason that the period of 50 days when stay
granted by the Court was in operation, the same cannot be construed to be a
hostility nor an event defined as force majeure in terms of the contract.
15. It is this conclusion of the Arbitral Tribunal which has been upheld by
the learned Single Judge. Hence, the plea of the learned counsel for the
appellant that the finding of the Tribunal that there was no cause to invoke
Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:27.07.2026
14:55:03
FAO(OS) (COMM) 182/2026 Page 8 of 9
the force majeure clause is unsustainable, is unmerited.
16. One of the arguments of the learned counsel for the appellant is that
the appointment of the Arbitral Tribunal was unilateral. Suffice to state that
the said argument does not hold ground, as in this case the Arbitrator was
appointed on 20.06.2013 whereas the amendment to the Act was brought on
23.10.2015, whereby sub-section 5 was inserted into Section 12 of the Act.
The plea of unilateral appointment would not aid the case of the appellant as
this is a case governed by the Act which preceded the 2015 amendment,
wherein there was no statutory ground to seek dissolution of an Arbitral
Tribunal which comprised of unilaterally appointed Arbitrators. The
Supreme Court had highlighted the prospective applicability of the 2015
amendment of the Act in its judgment in the case of Board of Control for
Cricket in India v. Kochi Cricket Private Limited and Others, (2018) 6
SCC 287 .
17. Hence, we are of the view that the present appeal is without any merit
and is liable to be dismissed. We order accordingly.
V. KAMESWAR RAO, J
MANMEET PRITAM SINGH ARORA, J
JULY 23, 2026
sr