PULAK GHOSH vs THE STATE OF WEST BENGAL AND ORS
- Court
- Calcutta High Court
1
IN THE HIGH COURT AT CALCUTTA
CIVIL APPELLATE JURISDICTION
APPELLATE SIDE
Present:
The Hon’ble Justice Rajarshi Bharadwaj
And
The Hon’ble Justice Sudip Deb
MAT No. 459 of 2026
With
CAN No. 1 of 2026
(Assigned)
Pulak Ghosh
-Vs-
The State of West Bengal & Ors.
For the Appellant : Mr. Biswaroop Mukherjee
Mr. Partha Banerjee
For the State : Mrs. Manju Agarwal, Ld. AGP
Mr. Ranchandra Agarwal
For the Panihati Municipality : Mr. Soumyajit Bhattacharya
Heard on : 16.11.2026
Judgment on : 27.11.2026
Sudip Deb, J.:-
th
1. This intra-Court appeal arises out of a judgment and order dated 12
February, 2026, whereby the Learned Single Judge dismissed the writ
petition filed by the appellant herein. While dismissing the said writ
petition the Learned Single Judge, inter alia, held that there was no scope
for the Court to enquire into the plan which had been admittedly
sanctioned by the municipality.
2
2. The Learned Single Judge also held that, since there had been allegations
of certain interpolations in the sanctioned plan, the Court cannot on the
basis thereof call the State machinery to act. While dismissing the writ
petition, the Learned Single Judge further held that the provisions of
Section 217 of the West Bengal Municipal Act, 1993 (hereinafter referred
to as “the said Act”) made adequate provision for cancellation of
permission on the ground of misrepresentation. The Learned Single Judge
also held since the matter is sub-judice in the Municipal Appeal and the
Learned Court is in seisin of the matter, the issue of interpolation of the
document can be considered by the appeal Court at the time of hearing of
the appeal.
3. Being aggrieved by the said order, the appellant has filed the instant
appeal.
4. The Learned counsel for the appellant submitted that the Learned Single
Judge has erred in law while dismissing the writ petition. According to the
Learned counsel for the appellant, the Learned Single Judge ought to
have passed an order directing the Commissioner of Police, Barrackpore
Commissionerate, who has been impleaded as respondent no. 5 herein, to
enquire about the purported building plan which had been allegedly
th
sanctioned on 8 August, 2022, by the Chairman of Panihati Municipality
(the respondent no. 3 herein).
5. As such, it is argued that the instant appeal should be allowed directing
the respondent no. 5 to enquire about the genuineness of the alleged
th
sanctioned plan dated 8 August, 2022, and if interpolations are found,
3
th
the said sanctioned plan dated 8 August, 2022, be set aside and/or
quashed.
6. The Learned counsel for the municipality submitted that there was no
plan sanctioned by the Panihati Municipality being the respondent no. 3
herein. In this regard, he has relied on a report which was filed before this
Court in the form of an affidavit pursuant to an earlier direction of this
Court. The Learned counsel has referred to paragraph no. 3 of the said
report and submitted that the municipality has categorically stated that
there is no existence of the plan in the municipality as annexed in the writ
th
petition vide plan no.838 dated 8 August, 2022, appearing at the page
103 of the writ petition.
7. He further submitted that an appeal filed by the appellant challenging the
order of the Board of Councillors is still pending, and that the instant
appeal should accordingly be dismissed.
8. Heard the Learned counsel for the parties and perused the record.
9. The issues that fall for consideration in the instant appeal are firstly,
whether the Learned Single Judge has erred in law while dismissing the
writ petition on the ground that the issue relating to the alleged
th
interpolations in the sanctioned plan dated 8 August, 2022 can be urged
in the Municipal Appeal which is still pending. Secondly, whether there is
any scope for the Court to make an enquiry into the plan for alleged
th
interpolations of the sanctioned plan dated 8 August, 2022. Thirdly, in
absence of any sanction plan, what would be the fate of the unauthorized
construction.
4
10. Before deciding the aforesaid issues, it is important to ascertain the facts
of the case which are narrated hereinafter.
11. The appellant before us, along with his mother, namely, Mala Ghosh,
rd
since deceased, jointly inherited 1/3 undivided share lying and situated
under Mouza- Panihati, J.L. No. 108, R.S. No. 32, Touzi No. 155, Khatian
No. 186, Dag No. 118/841 along with the brick built structure thereon
within the local limit of Panihati Municipality under Ward No. 3, Holding
No. 54 being the Premises No. 138, Thakur Nitya Gopal Road, Post Office-
Panihati, Police Station- Khardah, District- North 24 Parganas, Kolkata-
700114, which is hereinafter referred to as “the said premises”. The
th
appellant along with his mother, since deceased, on 12 December, 2012,
entered into a development agreement with respondent no. 4 herein for
construction of G+3 storied building on the said premises. Thereafter, on
th
13 December, 2013, the appellant and his mother, since deceased,
executed a power of attorney in favour of the respondent no. 4 herein,
namely, M/s. Shibham Construction. According to the appellant, the
other co-sharers of the said undivided and un-demarcated land had also
entered into separate development agreement with separate power of
attorney in favour of the respondent no. 4 in connection with the
rd
remaining 2/3 share in the said premises for the same purpose.
12. However, the respondent no. 4 herein constructed a G+4 building on the
said premises instead of G+3, in violation of the terms and conditions
contained in the development agreement and the power of attorney. The
appellant had raised objection to the aforesaid wrongful and illegal acts of
the respondent no. 4.
5
13. Thereafter, the respondent no. 4 completed the construction and delivered
a flat measuring about 600 Square feet to the appellant from the land
owners’ allocation and the appellant along with his mother took
possession of the said flat for their residential purpose.
14. Thereafter, in 2015 the appellant on finding that the respondent no. 4
was erecting a wall at the common space in the said premises, lodged a
written complaint before the respondent no. 3 herein, namely, Chairman,
Panihati Municipality.
15. Since the respondent no. 3 did not take any step even after the appellant
and his late mother lodged a complaint, the appellant was compelled to
file a writ petition being WP No. 7256 (W) of 2016 before this Hon’ble
Court.
th
16. Thereafter, the said writ petition was finally disposed of on 18 July,
2016, directing the Board of Councillors to take appropriate steps in
terms of section 218 of the said Act strictly in accordance with the
procedure laid down in the law.
17. After receiving the said order, the Board of Councillors had initiated a
proceeding under Section 218 of the said Act and issued notice to the
respondent no. 4 but in spite of receiving the notice, the respondent no. 4
did not participate in the proceeding. Thereafter, the Board of Councillors
th
had passed an order on 29 August, 2016, directing the respondent no. 4
to demolish the unauthorized construction made in the said premises
within 15 days.
th
18. Subsequently, the said order dated 29 August, 2016, was recalled and
th
the Board of Councillors passed a fresh order on 7 September, 2016,
6
again directing the respondent no. 4 to demolish the unauthorized
construction made in the said premises within 15 days.
19. Being aggrieved by the said order, the respondent no. 4 herein had filed a
Municipal Appeal before the Learned Civil Judge (Junior Division) at
Sealdah being Municipal Appeal No. 1 of 2016 (as averred in the writ
petition) and obtained an ad interim ex parte order of status quo .
Thereafter, the appellant filed another writ petition being WPA 14015 of
th
2021 before this Hon’ble Court and by an order dated 16 September,
2021, a Co-ordinate Bench of this Court had directed the Board of
Councillors to proceed afresh in accordance with law by initiating a
proceeding under section 218 of the said Act.
20. Pursuant to the said order, the Board of Councillors initiated a de novo
th
proceeding and after hearing the parties, had passed an order on 5
August, 2022, directing the respondent no. 4 to remove the unauthorized
construction mentioned in the said order within 15 days.
21. Even after the said order, since the respondent no. 4 did not remove the
unauthorized construction, the Board of Councillors by way of another
th
order dated 28 February, 2023, directed the Public Works Department to
th
carry out the said order dated 5 August, 2022.
22. Thereafter, the respondent no. 4 filed a Municipal Appeal being no. 6 of
th
2022 challenging the said order of demolition dated 5 August, 2022
nd
before the Learned Civil Judge (Junior Division), 2 Court at
Barrackpore.
23. During the pendency of the said appeal, the respondent no. 4 without
making the petitioner a party also filed a civil suit being Title Suit No. 76
7
of 2023 along with an application under Order 39 Rule 1 and 2 of the
Code of Civil Procedure before the Learned Civil Judge (Junior Division),
nd
2 Court, Barrackpore on the self-same cause of action. The prayers
made therein are identical to the prayers made in the Municipal Appeal
being Appeal No. 6 of 2022. However, the Learned Trial Judge did not
grant any ad interim protection. Thereafter, the respondent no. 4 preferred
an appeal challenging the order of refusal of the Learned Trial Judge and
obtained an order of status quo from the appeal Court. The said appeal
was numbered as Misc. Appeal No. 27 of 2023.
th
24. Thereafter, on 16 March, 2023, the appeal being Misc. Appeal No. 6 of
2022 came up for hearing and the Appellate Court fixed a date for hearing
of the said appeal. According to the appellant the alleged sanctioned plan
which was produced before the Appellate Court has been interpolated.
Challenging the interpolation the appellant had filed the writ petition,
inter alia, praying for an enquiry to be made through respondent no. 5 or
by an authorized officer not below the rank of Superintendent of Police
th
relating to the alleged sanctioned plan dated 8 August, 2022.
25. As stated hereinabove, the Learned Single Judge dismissed the writ
petition on the grounds set out in the impugned order and summarized in
the preceding paragraphs.
26. On perusal of the record, we find that the Learned Single Judge has
recorded that the municipality being the respondent no. 3 herein has
sanctioned a building plan for construction in the said premises.
However, when a report was called for from the municipality in the form of
an affidavit by this Court, the municipality has categorically stated that
8
there is no existence of any plan in the municipality as annexed with the
th
petition being plan no. 838 dated 8 August, 2022. Therefore, from the
report itself it is clear that the municipality being respondent no. 3 has
th
never sanctioned any plan on 8 August, 2022. It is also important to
mention that the respondent no. 4 even after obtaining leave from this
Court to file an exception to the said report, had not filed the same.
27. We are, therefore, of the considered view that since no sanctioned plan is
shown to exist, the Appellate Court seized of Municipal Appeal No. 6 of
2022 shall proceed strictly in accordance with law.
28. Section 217 of the said Act also empowers the Board of Councillors to
cancel permission on the ground of material misrepresentation by the
applicant.
29. Section 217 of the said Act is quoted hereinbelow:-
“ 217. Power to Board of Councillors to cancel permission on the
ground of material misrepresentation by applicant. – If, at any
time, sanction or provisional sanction to erect any building has been
given and the Board of Councillors is satisfied that such sanction was
given in consequence of any material misrepresentation or fraudulent
statement contained in the plans, elevation sections or specifications or
land or any material particulars submitted in respect of such building, it
may cancel such sanction, and any work done thereunder shall be
deemed to have done without sanction.”
30. Section 218 of the said Act is also quoted hereinbelow:-
“ 218. Order for demolition or alteration of buildings in certain
cases. – (1) If the Board of Councillors is satisfied –
(a) that the erection of any building –
(i) has been commenced without obtaining sanction or
permission under the law, or
9
(ii) is being carried on or has been completed otherwise than in
accordance with the particulars on which such sanction or
permission was based, or after such sanction or permission has
been lawfully withdrawn, or
(iii) is being carried on or has been completed in breach of any
provision contained in this Act or in the Schedule or in any rules
or regulations in this behalf, or
(b) that any building or projection exists in violation of any
condition, direction or requisition lawfully given or made under
this Act or the rules or the regulations made thereunder, or
(c) that any material alteration of, or addition to, any building has
been commenced or is being carried on or has been completed in
breach of any provision contained in this Act or the Schedule or in
any rules or regulations in this behalf,
it may, after giving the owner of the building a reasonable opportunity
of being heard, make an order directing that such erection, alteration,
addition or projection, as the case may be, or so much thereof as has
been executed unlawfully, be demolished or altered and, upon such
order, it shall be the duty of the owner to cause such demolition or
alteration to the satisfaction of the Board of Councillors within such
period as may be fixed in this behalf. In default, such erection,
alteration, addition or projection, as the case may be, may be
demolished or altered by the Board of Councillors at the expense of the
said owner.
(2) The procedure relating to the opportunity of hearing to be given to the
owner of the building under sub-section (1) shall be such as may be
prescribed.
(3) An appeal against an order made by the Board of Councillors in this
behalf shall lie with the Court having jurisdiction.
[(4) Omitted.]
(5) Notwithstanding anything contained in the foregoing provisions of
this section or elsewhere in this Chapter, if the Chairman-in-Council is
of opinion that immediate action is necessary in respect of any building
10
being constructed, or any work being carried on, in contravention of the
provisions of this Act, it may, for reasons to be recorded in writing,
cause such building or work to be demolished forthwith.”
31. Therefore, according to us, the appellant may approach the Board of
Councillors by making necessary representation for alleged interpolations
th
made in the sanctioned plan dated 8 August, 2022 and is not without
remedy. It is also equally important to note that the Board of Councillors
have adequate power under section 217 of the said Act to pass an
appropriate order for cancellation of such sanction.
32. In view of the foregoing, we are of the considered view that there is no
necessity of passing any order of enquiry for ascertaining the genuineness
th
of the alleged sanctioned plan dated 8 August, 2022.
33. It is also an admitted position that there is no sanctioned plan as is
evident from the report of the municipality filed in the Court. However,
since the issue of demolition is pending before the Appellate Court, we do
not wish to adjudicate the issue of demolition in this appeal. Since, the
Appellate Court is in seisin of the matter, we direct the Appellate Court to
dispose of the appeal being Municipal Appeal No. 6 of 2022 pending
before it positively within six weeks from the date of communication of
this order without being influenced by any of the observations made
herein.
34. The appellant is also permitted to take appropriate steps strictly in
accordance with law relating to his allegation of interpolation in the
th
document, namely, the sanctioned plan dated 8 August, 2022 before the
appropriate authority and if steps are taken, the appropriate authority
shall consider the same and shall pass a detailed reasoned order within
11
four weeks from the date of taking such steps after giving an opportunity
of hearing to the appellant as well as to the other concerned parties.
35. With the aforesaid observations, the instant appeal stands disposed of.
Nothing survives in CAN No. 1 of 2026 and the same is also disposed of
accordingly.
36. Urgent photostat certified copy of this order, if applied for, be given to the
parties upon compliance with the all necessary formalities.
I Agree.
(Rajarshi Bharadwaj, J.) (Sudip Deb, J.)