Indian Oil Carporation vs M/Smetro Builders(Orissa)Pvt. Ltd

Court
Delhi High Court
Case type
Original Misc Petition Commercial
Decided on
02-04-2026
<div> <br /> $~16 <br /> * <b>IN THE HIGH COURT OF DELHI AT NEW DELHI </b><br /> <b><i>Date of Decision: 02.04.2026 </i></b><br /> + O.M.P. (COMM) 246/2016 <br /> INDIAN OIL CARPORATION .....Petitioner <br /> Through: Mr. V. N. Koura, Mr. Aditya <br /> Sharma and Mr. Shaurya <br /> Dahiya, Advocates <br /> versus <br /> <br /> M/SMETRO BUILDERS(ORISSA)PVT. LTD <br /> .....Respondent <br /> Through: Mr. Akhil Sachar, Ms. Sunanda <br /> Tulsyan, Ms. Shweta Pattanaik, <br /> Ms. Babita Rawat, Ms. Kashish <br /> Maheshwari and Ms. Gulnar <br /> Arora, Advocates <br /> <b>CORAM:</b> <br /> <b>HON&#x27;BLE MR. JUSTICE HARISH VAIDYANATHAN </b><br /> <b>SHANKAR</b> <br /> <br /> <b>% </b> <b> </b> <b> </b> <b> </b> <b>JUDGEMENT (ORAL) </b><br /> <b>HARISH VAIDYANATHAN SHANKAR, J. </b><br /> <br /> 1. The present Petition, filed under Section 34 read with Sections <br /> <b>1</b><br /> 28 and 31 of the <b>Arbitration and Conciliation Act, 1996</b> , assails the <br /> <b>2</b><br /> <b>Arbitral Award dated 20.11.2014</b> , in respect of Claim No. 2, <br /> rendered by the learned Sole Arbitrator in the arbitral proceedings <br /> titled <i>“Metro Builders (Orissa) Pvt. Ltd. v. Indian Oil Corporation </i><br /> <i>Limited.”</i> <br /> 2. By the Impugned award, the learned Arbitrator has allowed the <br /> claims preferred by the Respondent in respect of Claim No. 2, along <br /> <br /> 1<br /> Act <br /> 2<br /> Impugned Award <br /> Signature Not Verified<br /> Digitally Signed<br /> By:VARNIKA<br /> Signing Date:06.04.2026<br /> 18:20:17<br /> O.M.P. (COMM) 246/2016 Page <b>1</b> of <b>24</b> <br /><br /> <br /> with interest at the rate of 9% per annum, payable after the expiry of <br /> two months from the date of the award until the date of payment. <br /> 3. Learned counsel for the Petitioner, at the outset, confines the <br /> challenge to a singular, yet foundational ground that the Impugned <br /> Award is <i>ex facie</i> contrary to the express terms of the Contract. In <br /> support thereof, reliance is placed upon Clauses 4.3.5.0, 4.3.5.1, <br /> <b>3</b><br /> 4.3.5.2 and 4.3.6.0 of the <b>General Clauses of the Contract</b> , forming <br /> <b>4</b><br /> part of the <b>Agreement dated 26.07.2006</b> , which are reproduced <br /> herein below: <br /> <i>“</i> <b><i>4.3.5.0</i></b> Within 7 (seven) days of the occurrence of any act, <br /> event or omission which, in the opinion of the Contractor, is likely <br /> to lead to delay in the commencement or completion of any <br /> particular work(s) or operation(s) or the entire work at any job <br /> site(s), and as such would entitle the Contractor to an extension of <br /> time specified in this behalf in the Progress Schedule(s), the <br /> Contractor shall inform the Site Engineer and the Engineer-in-<br /> Charge in writing of the occurrence of such act, event or omission <br /> and the date of commencement of such occurrence. Thereafter, if <br /> even upon the cessation of such act or event or the fulfillment of <br /> the omission, the Contractor is of the opinion that an extension of <br /> time specified in the Progress Schedule relative to any particular <br /> operation(s) or item(s) of work or the entire work at any job site is <br /> necessary, the Contractor shall, within 7 (seven) days after such <br /> cessation or fulfillment, make a written request to the Engineer-in-<br /> Charge for extension of the relative time specified in the Progress <br /> Schedule. The Engineer-in-Charge may, at any time prior to <br /> completion of the work, extend the relative time of completion in <br /> the Progress Schedule for such period(s) as he considers necessary, <br /> if he is of the opinion that such act/event/omission constitutes a <br /> ground for extension of time in terms of the Contract and that such <br /> act/event/omission has, in fact, resulted in insurmountable delay to <br /> the Contractor. <br /> <br /> <b><i>4.3.5.1</i></b> The application for extension of time made by the <br /> Contractor to the Engineer-in-Charge shall contain full details of: <br /> (a) the notice under Clause 4.3.5.0, along with copies of the notices <br /> sent to the Engineer-in-Charge and the Site Engineer; <br /> (b) the activity in the Progress Schedule affected; <br /> <br /> 3<br /> GCC <br /> 4<br /> Agreement <br /> Signature Not Verified<br /> Digitally Signed<br /> By:VARNIKA<br /> Signing Date:06.04.2026<br /> 18:20:17<br /> O.M.P. (COMM) 246/2016 Page <b>2</b> of <b>24</b> <br /><br /> <br /> (c) the bottlenecks or obstructions perceived/experienced, and the <br /> reasons therefor; <br /> (d) the extension required on account of (c) above; <br /> (e) the extension required on account of reasons attributable to the <br /> Owner; <br /> (f) the extension required on account of force majeure; and <br /> (g) the total extension of time required for completion, taking the <br /> above into account and after eliminating all overlaps. <br /> <br /> <b><i>4.3.5.2</i></b> The opinion/decision of the Engineer-in-Charge in this <br /> behalf and as to the extension of time necessary shall, subject to the <br /> provisions of Clause 4.3.6.0 hereof, be final and binding upon the <br /> Contractor. <br /> <br /> <b><i>4.3.6.0</i></b> Notwithstanding the provisions of Clause 4.3.5.0 hereof, <br /> the Owner may, at any time, at the request of the Contractor made <br /> by way of appeal either against the decision of the Engineer-in-<br /> Charge taken under Clause 4.3.5.0 or against the Engineer-in-<br /> Charge’s refusal to take a decision under the said clause, grant <br /> extension of time for the work or any item or operation thereof for <br /> such period(s) as the Owner may consider necessary. The decision <br /> of the Owner as to the existence or otherwise of any grounds <br /> justifying the extension and as to the period(s) of extension <br /> necessary shall be final and binding upon the Contractor.” <br /> <br /> 4. Learned counsel for the Petitioner further submits that the <br /> contractual scheme clearly envisages a structured mechanism for <br /> seeking extension of time. In a situation where the Engineer-in-charge <br /> fails to render a decision, Clause 4.3.6.0 stands triggered, thereby <br /> empowering the Owner/Petitioner herein to adjudicate upon the <br /> request. <br /> 5. Learned counsel for the Petitioner submits that the aforesaid <br /> contractual procedure was duly adhered to in the present case. Once a <br /> decision had been rendered in accordance with the agreed contractual <br /> framework by the Petitioner herein, the learned Arbitrator could not <br /> have sat in appeal over the same, particularly when such decision was <br /> expressly agreed by the parties to be final and binding between them. <br /> 6. Such interference, it is urged by the learned counsel for the <br /> Signature Not Verified<br /> Digitally Signed<br /> By:VARNIKA<br /> Signing Date:06.04.2026<br /> 18:20:17<br /> O.M.P. (COMM) 246/2016 Page <b>3</b> of <b>24</b> <br /><br /> <br /> Petitioner, runs contrary to settled law laid down by the Hon’ble <br /> Supreme Court in <b><i>Mitra Guha Builders (India) Company vs. Oil and </i></b><br /> <b><i>5</i></b><br /> <b><i>Natural Gas Corporation Limited</i></b> , specifically Paragraph Nos. 23 <br /> and 26, which are extracted herein below: <br /> “ <b>23</b> . The question to be decided in this case is whether the <br /> liability of the respondent to pay liquidated damages and the <br /> entitlement of the appellants to collect the same from the <br /> respondent is an excepted matter for the purpose of Clause 20.1 of <br /> the General Conditions of Contract. The High Court has pointed <br /> out correctly that the authority of the purchaser (BSNL) to quantify <br /> the liquidated damages payable by the supplier Motorola arises <br /> once it is found that the supplier is liable to pay the damages <br /> claimed. The decision contemplated under Clause 16.2 of the <br /> agreement is the decision regarding the quantification of the <br /> liquidated damages and not any decision regarding the fixing of the <br /> liability of the supplier. It is necessary as a condition precedent to <br /> find that there has been a delay on the part of the supplier in <br /> discharging his obligation for delivery under the agreement. <br /> <b></b>* <br /> <b>26</b> . Quantification of liquidated damages may be an excepted <br /> matter as argued by the appellants, under Clause 16.2, but for the <br /> levy of liquidated damages, there has to be a delay in the first <br /> place. In the present case, there is a clear dispute as to the fact that <br /> whether there was any delay on the part of the respondent. For this <br /> reason, it cannot be accepted that the appointment of the arbitrator <br /> by the High Court was unwarranted in this case. Even if the <br /> quantification was excepted as argued by the appellants under <br /> Clause 16.2, this will only have effect when the dispute as to the <br /> delay is ascertained. Clause 16.2 cannot be treated as an excepted <br /> matter because of the fact that it does not provide for any <br /> adjudicatory process for decision on a question, dispute or <br /> difference, which is the condition precedent to lead to the stage of <br /> quantification of damages.” <br /> <br /> 7. Learned counsel for the Petitioner further places reliance upon <br /> the judgment of the Hon’ble Supreme Court in <b><i>Indian Oil </i></b><br /> <b><i>6</i></b><br /> <b><i>Corporation vs. NCC Limited</i></b> <b><i> </i></b> to emphasise the primacy of party <br /> autonomy in arbitral jurisprudence. It is submitted that the parties, <br /> <br /> 5<br /> (2020) 3 SCC 222 <br /> 6<br /> (2023) 2 SCC 539 <br /> Signature Not Verified<br /> Digitally Signed<br /> By:VARNIKA<br /> Signing Date:06.04.2026<br /> 18:20:17<br /> O.M.P. (COMM) 246/2016 Page <b>4</b> of <b>24</b> <br /><br /> <br /> having consciously agreed to a contractual regime conferring finality <br /> upon the decision of the Owner in specified circumstances, are bound <br /> by the same. The Impugned Award, in disregarding such agreed <br /> mechanism, is therefore contrary to both the contract and the <br /> governing legal principles. <br /> 8. <b><i>Per contra,</i></b> learned counsel for the Respondent supports the <br /> Impugned Award, contending that the same is legally sound and does <br /> not warrant interference under Section 34 of the Act. <br /> 9. Learned counsel for the Respondent submits that the Petitioner <br /> failed to adhere to the contractual procedure prescribed for seeking <br /> extension of time, thereby disentitling itself from any relief under the <br /> said clauses. <br /> 10. Learned counsel for the Respondent further relies upon <br /> Paragraph Nos. 12 to 18 of the Impugned Award to contend that the <br /> findings recorded therein are well-reasoned and fall within the domain <br /> of a plausible view. The said paragraphs are reproduced herein under: <br /> “ <b>12. </b> The relevant provisions of the GCC provide as follows: <br />  4.3.5.0-The Contractors shall make a written request to the <br /> Engineer in Charge for extension of relative time specified <br /> in the progress schedule and the engineer in charge may <br /> extend the time of completion for such periods as he <br /> considers necessary, if he is of the opinion that an act, event <br /> or omission constitutes the ground for extension of time in <br /> terms of the contract. <br />  4.3.5.1 the application for extension of time is required to <br /> furnish certain information relating to the extension <br /> required/necessitated on account of the bottle necks or <br /> obstructions perceived/experienced. <br />  4.3.5.2-The opinion/decision of the Engineer in Charge in <br /> this behalf and as to the extension of time necessary shall <br /> be subject of the clause 4.3.6.0 be final and binding upon <br /> the Contractor. <br />  4.3.6.0-Notwithstanding the provisions of clause 4.3.5.0 <br /> hereof, the owner may, at any time, at the request of the <br /> contractor, made by way of appeal, either against the <br /> Signature Not Verified<br /> Digitally Signed<br /> By:VARNIKA<br /> Signing Date:06.04.2026<br /> 18:20:17<br /> O.M.P. (COMM) 246/2016 Page <b>5</b> of <b>24</b> <br /><br /> <br /> decision of the Engineer in charge, taken under clause <br /> 4.3.5.0 or against the Engineer in charge&#x27;s, refusal to take a <br /> decision under the said clause, examine the correctness or <br /> propriety of the decision made by the Engineer in charge, <br /> and the decision of the owner shall be final and binding <br /> upon the contractor. <br /> The procedure defined for application and condoning the delay in <br /> completion of the project is as follows. Whenever there is a <br /> hindrance, the contractor has to put in the details of the hindrance <br /> and apply for extension of time to the Engineer in charge. A <br /> decision is taken by the engineer in charge on accepting or denying <br /> the application for condoning the delay. In case the contractor is <br /> not satisfied with the order of the engineer in charge, he can apply <br /> to the General Manager for a review of the order given by the <br /> engineer in charge. The decision of the General Manager is final <br /> and is exempted from any reference to arbitration. <br /> <b>13.⁠</b> ⁠The procedure actually followed was follows. The contractor <br /> applied from time to time for extension of the contract time. The <br /> engineer in charge did not give any decision but kept on giving <br /> provisional extensions. When the project was over, a delay <br /> statement prepared by the contractor and commented upon by the <br /> engineer in charge. <br /> <b>14.</b> To distinguish between claiming damages suffered due to delay <br /> and application of the price adjustment, the learned advocate of the <br /> Respondent has given two examples. First is the case of purchase <br /> of basmati rice. The contract provides that if more than 1% of the <br /> grains are the prescribed length, a price discount shall be applied. <br /> In the second case, for purchase of computers by the US Army, if <br /> the weight exceeded the prescribed limit of, say. 25kgs. then for <br /> every extra kg of weight of the computer, a price discount shall be <br /> applied. short of the <br /> <b>15.</b> I have examined the argument from both the Respondent and <br /> the Claimant carefully. The objections raised by the Claimant to the <br /> levy of prescribed discount have merit. A construction contract is <br /> totally different from the contracts of purchase of rice and <br /> computers There are many stake holders in a construction contract <br /> including the architect, the engineer, the owner, the supplier of <br /> materials, and the contractor. Also, a construction contract is very <br /> complicated as compared to the simple illustrations given by the <br /> leamed Counsel. Nobody can foretell the weather, labour unrests, <br /> unavoidable delay in procuring materials not locally available and <br /> the various glitches in the process of construction. It is necessary, <br /> therefore. that every delay is evaluated in the light of the situation <br /> causing hindrance and a decision taken, clearly stating the basis of <br /> the decision, rather than arbitrarily rejecting a hindrance. <br /> <b>16.</b> The Claimant has alleged that notwithstanding the provisions <br /> of the GCC, the then Engineer in charge Mr L Kalaivanan RW-1 <br /> Signature Not Verified<br /> Digitally Signed<br /> By:VARNIKA<br /> Signing Date:06.04.2026<br /> 18:20:17<br /> O.M.P. (COMM) 246/2016 Page <b>6</b> of <b>24</b> <br /><br /> <br /> has stated that the General Manager has approved a <br /> recommendation on time extension made by him on the basis of the <br /> report of the site engineer and in consultation with the GM. The <br /> decision regarding non-extension of time etc. has not been taken by <br /> the Engineer in charge, who is the designated, competent authority <br /> as per the GCC. The Claimant has alleged that he has been <br /> deprived of right of appeal to the competent appellate authority <br /> since the Engineer in charge has not taken the decision regarding <br /> extension of time and condoning delay. He has further alleged that <br /> there has been no application of mind by the authority rejecting the <br /> claim. Reasons in support of the decision have not been recorded. <br /> The necessity of giving recorded reasons in support of the <br /> decisions has been recorded in a large number of Supreme Court <br /> judgements, copies of which have been appended in 152 pages. <br /> Extracts from some of the Apex Court decisions are as below. <br /> Case (2010)7 SCC, p21 of the Annexures: <br /> “ <i>The meaning and true import of arbitrariness is more easily </i><br /> <i>visualised than precisely stated or defined. The question whether </i><br /> <i>an impugned act is arbitrary or not, is ultimately to be answered </i><br /> <i>on the facts and in the circumstances of a given case. An obvious </i><br /> <i>test to apply is to see whether there is any discernible principle </i><br /> <i>emerging from the impugned act and if so, does it satisfy the test of </i><br /> <i>reasonableness.&quot;</i> <br /> Again, in the same case, the Apex Court has stated. <br /> <i>&quot;Arbitrariness in the making of an order by an authority can </i><br /> <i>manifest itself in different forms. Non-application of mind by the </i><br /> <i>authority making the order is only one of them. Every order passed </i><br /> <i>by a public authority must disclose due and proper application of </i><br /> <i>mind by the person making the order. This may be evident from the </i><br /> <i>order itself or the record contemporaneously maintained. </i><br /> <i>Application of mind is best demonstrated by disclosure of mind by </i><br /> <i>the authority making the order. And disclosure is best done by </i><br /> <i>recording the reasons that led the authority to pass the order in </i><br /> <i>question. Absence of reasons either in the order passed by the </i><br /> <i>authority or in the record contemporaneously maintained is clearly </i><br /> <i>suggestive of the order being arbitrary and hence legally </i><br /> <i>unsustainable.&quot; </i><br /> In another case, of Kranti Associates Pvt Ltd and Anr. v. Shri <br /> Massood Ahmad Khan and ors. on 8th Sept 2010. In Messrs Kranti <br /> Associates (supra) this court after considering various judgements <br /> formulated certain principles in para 51 of the judgement which are <br /> set out below. <br /> <i>a) In India, the judicial trend has always been to record reasons, </i><br /> <i>even in administrative decisions, if such decisions affect anyone </i><br /> <i>prejudicially. </i><br /> <i>b) A quasi-judicial authority must record reasons in support of its </i><br /> <i>conclusions. </i><br /> Signature Not Verified<br /> Digitally Signed<br /> By:VARNIKA<br /> Signing Date:06.04.2026<br /> 18:20:17<br /> O.M.P. (COMM) 246/2016 Page <b>7</b> of <b>24</b> <br /><br /> <br /> <i>c) Insistence on recording of reasons is meant to serve the wider </i><br /> <i>principle of justice that justice must not only be done, it must also </i><br /> <i>appear to be done as well. </i><br /> <i>d) Recording the reasons also operates a valid restraint on any </i><br /> <i>possible arbitrary exercise of judicial and quasi-judicial or even </i><br /> <i>administrative power. </i><br /> <i>e) Reasons reassure that discretion has been exercised by the </i><br /> <i>decision maker on relevant grounds and by disregarding </i><br /> <i>extraneous considerations. </i><br /> <i>f) Reasons have virtually become as indispensable a component of </i><br /> <i>a decision making process as observing principles of natural </i><br /> <i>justice by judicial, quasi-judicial and even by administrative </i><br /> <i>bodies. </i><br /> <i>g) Reasons facilitate the process of judicial review by superior </i><br /> <i>courts.&quot; </i><br /> <b>17. </b> To assess if these requirements are met in this case a reference <br /> is needed to the &quot;delay analysis after scrutiny by IOCL&quot; The <br /> statement has columns filled by the contractor stating hindrance/ <br /> start and end/ delay in days claimed. This is followed by columns <br /> filled by IOCL stating remarks/ delay considered/ delay <br /> considering overlapping period. The Claimant has brought out <br /> inconsistencies and lack of application of mind in not accepting the <br /> delay claimed by him. For example, Item 7 (delay caused by local <br /> labourers: 10 days) the remark is that it is not feasible as per <br /> contract. There are a number of delays for non-availability of <br /> materials, claim has been rejected without going into the reasons <br /> for delay. Item 33 (delay in availability of submersible pumps <br /> which are imported: 309 days) the remark is &quot;not tenable under the <br /> contract&quot;. The contractor has given the dates of placing order for <br /> the pumps, which were ordered well in time and could not be <br /> received due supplies to be made by the German manufacturer. The <br /> comment, again, is &quot;not tenable under contract&quot;. Other Iterns <br /> brought out by the Claimant pertain to non-availability of materials <br /> in the local market and which had to be ordered from outside <br /> Odisha. The orders were placed well in time and the supplies were <br /> not received within the expected period of delivery. Typical cases <br /> are Item 34 (delay of 83 days), Item 35 (delay of 221 days), Item <br /> 51 (delay of 18 days) and Item 41 (delay of 93 days). The remarks <br /> for not accepting the contractor&#x27;s version have again been <br /> summarily disposed by the IOCL with phrases like &quot;not tenable <br /> under contract&quot;, &quot;no hold- up&quot;, &quot;not admissible&quot;. The principles <br /> laid down by the apex court have not been followed. <br /> <b>18. </b> To summarise the pleadings of the Claimant, the provision in <br /> the contract that every hindrance will be reported within ten days, a <br /> decision given by the Engr in charge, and an appeal allowed by the <br /> GM have not been followed. As can be seen, the argument by the <br /> Respondents that the price discount is simple as in case of Basmati <br /> Signature Not Verified<br /> Digitally Signed<br /> By:VARNIKA<br /> Signing Date:06.04.2026<br /> 18:20:17<br /> O.M.P. (COMM) 246/2016 Page <b>8</b> of <b>24</b> <br /><br /> <br /> rice and computer provision is not valid, as construction contracts <br /> are much more complicated and claims like delays have to be <br /> evaluated on the basis of data provided. The conclusion that the <br /> norms laid down by the apex Court have not been followed cannot <br /> be avoided.” <br /> <br /> 11. Learned counsel for the Respondent further submits that the <br /> contents of the said paragraphs, as reproduced herein above, are <br /> immune from judicial intervention, given the narrow and <br /> circumscribed scope of interference as under Section 34 of the Act. <br /> 12. Learned counsel for the Respondent further submits that the <br /> “ <i>reasoning</i> ”, as given by the learned Arbitrator, does not suffer from <br /> perversity or patent illegality, and consequently, no case for <br /> interference is made out. <br /> <b><i> </i></b><br /> <b><i>ANALYSIS &amp; DECISION: </i></b><br /> 13. This Court has heard the learned senior counsel appearing on <br /> behalf of the parties at length and, with their able assistance, has <br /> carefully perused the paper book as well as the case laws relied upon <br /> by the respective parties. <br /> 14. Here, it is apposite to note that this Court is conscious of the <br /> limited scope of its jurisdiction while examining an objection petition <br /> under Section 34 of the Act. The contours of judicial intervention in <br /> such proceedings have been authoritatively delineated and settled by a <br /> consistent and evolving line of precedents of the Hon’ble Supreme <br /> Court. <br /> 15. In this regard, a three-Judge Bench of the Hon’ble Supreme <br /> Court, after an exhaustive consideration of a catena of earlier <br /> decisions, in <b><i>OPG Power Generation (P) Ltd. v. Enexio Power </i></b><br /> Signature Not Verified<br /> Digitally Signed<br /> By:VARNIKA<br /> Signing Date:06.04.2026<br /> 18:20:17<br /> O.M.P. (COMM) 246/2016 Page <b>9</b> of <b>24</b> <br /><br /> <br /> <b><i>7</i></b><br /> <b><i>Cooling Solutions (India) (P) Ltd.</i></b> , while dealing with the grounds <br /> including conflict with the public policy of India and perversity, made <br /> certain pertinent observations, which are reproduced hereunder: <br /> <i>“</i> <b><i>Relevant legal principles governing a challenge to an arbitral </i></b><br /> <b><i>award</i></b> <br /> <b>30.</b> Before we delve into the issue/sub-issues culled out above, it <br /> would be useful to have a look at the relevant legal principles <br /> governing a challenge to an arbitral award. Recourse to a court <br /> against an arbitral award may be made through an application for <br /> setting aside such award in accordance with sub-sections (2), (2-A) <br /> and (3) of Section 34 of the 1996 Act. Sub-section (2) of Section 34 <br /> has two clauses, ( <i>a</i> ) and ( <i>b</i> ). Clause ( <i>a</i> ) has five sub-clauses which <br /> are not relevant to the issues raised before us. Insofar as clause ( <i>b</i> ) <br /> is concerned, it has two sub-clauses, namely, ( <i>i</i> ) and ( <i>ii</i> ). Sub-<br /> clause ( <i>i</i> ) of clause ( <i>b</i> ) is not relevant to the controversy in hand. <br /> Sub-clause ( <i>ii</i> ) of clause ( <i>b</i> ) provides that if the Court finds that the <br /> arbitral award is in conflict with the public policy of India, it may <br /> set aside the award. <br /> <b><i>Public policy</i></b> <br /> <b>31.</b> “Public policy” is a concept not statutorily defined, though it <br /> has been used in statutes, rules, notification, etc. since long, and is <br /> also a part of common law. Section 23 of the Contract Act, 1872 <br /> uses the expression by stating that the consideration or object of an <br /> agreement is lawful, unless, inter alia, opposed to public policy. <br /> That is, a contract which is opposed to public policy is void. <br /> <b></b>* <br /> <b>35.</b> In <b><i>Renusagar Power Co. Ltd.</i></b> <b> v. </b> <b><i>General Electric Co.</i></b> <b>, 1994 </b><br /> <b>Supp (1) SCC 644</b> , a three-Judge Bench of this Court observed <br /> that the doctrine of public policy is somewhat open—textured and <br /> flexible. By citing earlier decisions, it was observed that there are <br /> two conflicting positions which are referred to as the “narrow <br /> view” and the “broad view”. According to the narrow view, courts <br /> cannot create new heads of public policy whereas the broad view <br /> countenances judicial law making in these areas. In the field of <br /> private international law, it was pointed out, courts refuse to apply <br /> a rule of foreign law or recognise a foreign judgment or a foreign <br /> arbitral award if it is found that the same is contrary to the public <br /> policy of the country in which it is sought to be invoked or <br /> enforced. However, it was clarified, a distinction is to be drawn <br /> while applying the rule of public policy between a matter governed <br /> by domestic law and a matter involving conflict of laws. It was <br /> observed that the application of the doctrine of public policy in the <br /> field of conflict of laws is more limited than that in the domestic <br /> <br /> 7<br /> (2025) 2 SCC 417 <br /> Signature Not Verified<br /> Digitally Signed<br /> By:VARNIKA<br /> Signing Date:06.04.2026<br /> 18:20:17<br /> O.M.P. (COMM) 246/2016 Page <b>10</b> of <b>24</b> <br /><br /> <br /> law and the courts are slower to invoke public policy in cases <br /> involving a foreign element than when a purely municipal legal <br /> issue is involved. It was held that contravention of law alone will <br /> not attract the bar of public policy, and something more than <br /> contravention of law is required. <br /> <b><i></i></b><i></i>* <br /> <b>37.</b> What is clear from above is that for an award to be against <br /> public policy of India a mere infraction of the municipal laws of <br /> India is not enough. There must be, inter alia, infraction of <br /> fundamental policy of Indian law including a law meant to serve <br /> public interest or public good. <br /> <b><i></i></b><i> </i>*<br /> <b>40.</b> In <b><i>ONGC Ltd.</i></b> <b> v. </b> <b><i>Western Geco International Ltd.</i></b> <b>, (2014) 9 </b><br /> <b>SCC 263, paras 35, 38 &amp; 39</b> , which also related to the period prior <br /> to the 2015 Amendment of Section 34(2)( <i>b</i> )( <i>ii</i> ), a three-Judge <br /> Bench of this Court, after considering the decision in <b><i>ONGC </i></b><br /> <b><i>Ltd.</i></b> <b> v. </b> <b><i>Saw Pipes Ltd.</i></b> <b>, (2003) 5 SCC 705</b> , without exhaustively <br /> enumerating the purport of the expression “fundamental policy of <br /> Indian law”, observed that it would include all such fundamental <br /> principles as providing a basis for administration of justice and <br /> enforcement of law in this country. The Court thereafter <br /> illustratively referred to three fundamental juristic principles, <br /> namely: <br /> ( <i>a</i> ) that in every determination that affects the rights of a citizen or <br /> leads to any civil consequences, the court or authority or quasi-<br /> judicial body must adopt a judicial approach, that is, it must act <br /> bona fide and deal with the subject in a fair, reasonable and <br /> objective manner and not actuated by any extraneous <br /> consideration; <br /> ( <i>b</i> ) that while determining the rights and obligations of parties the <br /> court or Tribunal or authority must act in accordance with the <br /> principles of natural justice and must apply its mind to the <br /> attendant facts and circumstances while taking a view one way <br /> or the other; and <br /> ( <i>c</i> ) that its decision must not be perverse or so irrational that no <br /> reasonable person would have arrived at the same. <br /> <b>41.</b> In <b><i>Associate Builders</i></b> <b> v. </b> <b><i>DDA</i></b> <b>, (2015) 3 SCC 49</b> , a two-Judge <br /> Bench of this Court, held that <i>audi alteram partem</i> principle is <br /> undoubtedly a fundamental juristic principle in Indian law and is <br /> enshrined in Sections 18 and 34(2)( <i>a</i> )( <i>iii</i> ) of the 1996 Act. In <br /> addition to the earlier recognised principles forming fundamental <br /> policy of Indian law, it was held that disregarding: <br /> ( <i>a</i> ) orders of superior courts in India; and <br /> ( <i>b</i> ) the binding effect of the judgment of a superior court would <br /> also be regarded as being contrary to the fundamental policy of <br /> Indian law. <br /> Further, elaborating upon the third juristic principle (i.e. qua <br /> Signature Not Verified<br /> Digitally Signed<br /> By:VARNIKA<br /> Signing Date:06.04.2026<br /> 18:20:17<br /> O.M.P. (COMM) 246/2016 Page <b>11</b> of <b>24</b> <br /><br /> <br /> perversity), as laid down in <b><i>ONGC Ltd.</i></b> <b> v. </b> <b><i>Western Geco </i></b><br /> <b><i>International Ltd.</i></b> <b>, (2014) 9 SCC 263</b> , it was observed that where: <br /> ( <i>i</i> ) a finding is based on no evidence; or <br /> (ii) an Arbitral Tribunal takes into account something irrelevant to <br /> the decision which it arrives at; or <br /> (iii) ignores vital evidence in arriving at its decision, such decision <br /> would necessarily be perverse[ <b><i>Associate Builders case</i></b> <b>, (2015) </b><br /> <b>3 SCC 49, para 31</b> ]. <br /> To this a caveat was added by observing that when a court applies <br /> the “public policy test” to an arbitration award, it does not act as a <br /> court of appeal and, consequently, errors of fact cannot be <br /> corrected; and a possible view by the arbitrator on facts has <br /> necessarily to pass muster as the arbitrator is the ultimate master of <br /> the quantity and quality of evidence to be relied upon when he <br /> delivers his arbitral award. It was also observed that an award <br /> based on little evidence or on evidence which does not measure up <br /> in quality to a trained legal mind would not be held to be invalid on <br /> that score. Thus, once it is found that the arbitrator&#x27;s approach is not <br /> arbitrary or capricious, it is to be taken as the last word on facts. <br /> <b><i>The 2015 Amendment in Sections 34 and 48</i></b> <br /> <b><i></i></b><i></i>* <br /> <b><i>In contravention with the fundamental policy of Indian law</i></b> <br /> <b>51.</b> As discussed above, till the 2015 Amendment the expression <br /> “in contravention with the fundamental policy of Indian law” was <br /> not found in the 1996 Act. Yet, in <b><i>Renusagar Power Co. </i></b><br /> <b><i>Ltd.</i></b> <b> v. </b> <b><i>General Electric Co.</i></b> <b>, 1994 Supp (1) SCC 644</b> , in the <br /> context of enforcement of a foreign award, while construing the <br /> phrase “contrary to the public policy”, this Court held that for a <br /> foreign award to be contrary to public policy mere contravention of <br /> law would not be enough rather it should be contrary to: <br /> ( <i>a</i> ) the fundamental policy of Indian law; and/or <br /> ( <i>b</i> ) the interest of India; and/or <br /> ( <i>c</i> ) justice or morality. <br /> <b><i></i></b><i> </i>*<br /> <b>55.</b> The legal position which emerges from the aforesaid discussion <br /> is that after “the 2015 Amendments” in Section 34(2)( <i>b</i> )( <i>ii</i> ) and <br /> Section 48(2)( <i>b</i> ) of the 1996 Act, the phrase “in conflict with the <br /> public policy of India” must be accorded a restricted meaning in <br /> terms of <i>Explanation 1</i> . The expression “in contravention with the <br /> fundamental policy of Indian law” by use of the word <br /> “fundamental” before the phrase “policy of Indian law” makes the <br /> expression narrower in its application than the phrase “in <br /> contravention with the policy of Indian law”, which means mere <br /> contravention of law is not enough to make an award vulnerable. <br /> To bring the contravention within the fold of fundamental policy of <br /> Indian law, the award must contravene all or any of such <br /> fundamental principles that provide a basis for administration of <br /> Signature Not Verified<br /> Digitally Signed<br /> By:VARNIKA<br /> Signing Date:06.04.2026<br /> 18:20:17<br /> O.M.P. (COMM) 246/2016 Page <b>12</b> of <b>24</b> <br /><br /> <br /> justice and enforcement of law in this country. <br /> <b>56.</b> Without intending to exhaustively enumerate instances of such <br /> contravention, by way of illustration, it could be said that: <br /> ( <i>a</i> ) violation of the principles of natural justice; <br /> ( <i>b</i> ) disregarding orders of superior courts in India or the binding <br /> effect of the judgment of a superior court; and <br /> ( <i>c</i> ) violating law of India linked to public good or public interest, <br /> are considered contravention of the fundamental policy of <br /> Indian law. <br /> However, while assessing whether there has been a contravention <br /> of the fundamental policy of Indian law, the extent of judicial <br /> scrutiny must not exceed the limit as set out in <i>Explanation 2</i> to <br /> Section 34(2)( <i>b</i> )( <i>ii</i> ). <br /> <b><i></i></b>* <br /> <b><i>Patent illegality</i></b> <br /> <b>65.</b> Sub-section (2-A) of Section 34 of the 1996 Act, which was <br /> inserted by the 2015 Amendment, provides that an arbitral award <br /> not arising out of international commercial arbitrations, may also <br /> be set aside by the Court, if the Court finds that the award is visited <br /> by patent illegality appearing on the face of the award. The proviso <br /> to sub-section (2-A) states that an award shall not be set aside <br /> merely on the ground of an erroneous application of the law or by <br /> reappreciation of evidence. <br /> <b>66.</b> In <b><i>ONGC Ltd.</i></b> <b> v. </b> <b><i>Saw Pipes Ltd.</i></b> <b>, (2003) 5 SCC 705</b> , while <br /> dealing with the phrase “public policy of India” as used in Section <br /> 34, this Court took the view that the concept of public policy <br /> connotes some matter which concerns public good and public <br /> interest. If the award, on the face of it, patently violates statutory <br /> provisions, it cannot be said to be in public interest. Thus, an award <br /> could also be set aside if it is patently illegal. It was, however, <br /> clarified that illegality must go to the root of the matter and if the <br /> illegality is of trivial nature, it cannot be held that award is against <br /> public policy. <br /> <b>67.</b> In <b><i>Associate Builders</i></b> <b> v. </b> <b><i>DDA</i></b> <b>, (2015) 3 SCC 49</b> , this Court <br /> held that an award would be patently illegal, if it is contrary to: <br /> ( <i>a</i> ) substantive provisions of law of India; <br /> ( <i>b</i> ) provisions of the 1996 Act; and <br /> ( <i>c</i> ) terms of the contract [See also three-Judge Bench decision of <br /> this Court in <b><i>State of Chhattisgarh</i></b> <b> v. </b> <b><i>SAL Udyog (P) Ltd.</i></b> <b>, </b><br /> <b>(2022) 2 SCC 275</b> ]. <br /> The Court clarified that if an award is contrary to the substantive <br /> provisions of law of India, in effect, it is in contravention of <br /> Section 28(1)( <i>a</i> ) of the 1996 Act. Similarly, violating terms of the <br /> contract, in effect, is in contravention of Section 28(3) of the 1996 <br /> Act. <br /> <b>68.</b> In <b><i>SsangyongEngg. &amp; Construction Co. Ltd.</i></b> <b> v. </b> <b><i>NHAI</i></b> <b>, (2019) </b><br /> <b>15 SCC 131</b> this Court specifically dealt with the 2015 <br /> Signature Not Verified<br /> Digitally Signed<br /> By:VARNIKA<br /> Signing Date:06.04.2026<br /> 18:20:17<br /> O.M.P. (COMM) 246/2016 Page <b>13</b> of <b>24</b> <br /><br /> <br /> Amendment which inserted sub-section (2-A) in Section 34 of the <br /> 1996 Act. It was held that “patent illegality appearing on the face <br /> of the award” refers to such illegality as goes to the root of matter, <br /> but which does not amount to mere erroneous application of law. It <br /> was also clarified that what is not subsumed within “the <br /> fundamental policy of Indian law”, namely, the contravention of a <br /> statute not linked to “public policy” or “public interest”, cannot be <br /> brought in by the backdoor when it comes to setting aside an award <br /> on the ground of patent illegality [ See <b><i>SsangyongEngg. &amp; </i></b><br /> <b><i>Construction Co. Ltd.</i></b> <b> v. </b> <b><i>NHAI</i></b> <b>, (2019) 15 SCC 131</b> ]. Further, it <br /> was observed, reappreciation of evidence is not permissible under <br /> this category of challenge to an arbitral award <br /> [See <b><i>SsangyongEngg. &amp; Construction Co. Ltd.</i></b> <b> v. </b> <b><i>NHAI</i></b> <b>, (2019) </b><br /> <b>15 SCC 131</b> ]. <br /> <b><i>Perversity as a ground of challenge</i></b> <br /> <b>69.</b> Perversity as a ground for setting aside an arbitral award was <br /> recognised in <b><i>ONGC Ltd.</i></b> <b> v. </b> <b><i>Western Geco International Ltd.</i></b> <b>, </b><br /> <b>(2014) 9 SCC 263</b> . Therein it was observed that an arbitral decision <br /> must not be perverse or so irrational that no reasonable person <br /> would have arrived at the same. It was observed that if an award is <br /> perverse, it would be against the public policy of India. <br /> <b>70.</b> In <b><i>Associate Builders</i></b> <b> v. </b> <b><i>DDA</i></b> <b>, (2015) 3 SCC 49</b> certain tests <br /> were laid down to determine whether a decision of an Arbitral <br /> Tribunal could be considered perverse. In this context, it was <br /> observed that where: <br /> ( <i>i</i> ) a finding is based on no evidence; or <br /> ( <i>ii</i> ) an Arbitral Tribunal takes into account something irrelevant to <br /> the decision which it arrives at; or <br /> ( <i>iii</i> ) ignores vital evidence in arriving at its decision, such decision <br /> would necessarily be perverse. <br /> However, by way of a note of caution, it was observed that when a <br /> court applies these tests it does not act as a court of appeal and, <br /> consequently, errors of fact cannot be corrected. Though, a possible <br /> view by the arbitrator on facts has necessarily to pass muster as the <br /> arbitrator is the ultimate master of the quantity and quality of <br /> evidence to be relied upon. It was also observed that an award <br /> based on little evidence or on evidence which does not measure up <br /> in quality to a trained legal mind would not be held to be invalid on <br /> that score. <br /> <b>71.</b> In <b><i>SsangyongEngg. &amp; Construction Co. Ltd.</i></b> <b> v. </b> <b><i>NHAI</i></b> <b>, (2019) </b><br /> <b>15 SCC 131</b> , which dealt with the legal position post the 2015 <br /> Amendment in Section 34 of the 1996 Act, it was observed that a <br /> decision which is perverse, while no longer being a ground for <br /> challenge under “public policy of India”, would certainly amount to <br /> a patent illegality appearing on the face of the award. It was <br /> pointed out that an award based on no evidence, or which ignores <br /> vital evidence, would be perverse and thus patently illegal. It was <br /> Signature Not Verified<br /> Digitally Signed<br /> By:VARNIKA<br /> Signing Date:06.04.2026<br /> 18:20:17<br /> O.M.P. (COMM) 246/2016 Page <b>14</b> of <b>24</b> <br /><br /> <br /></div><table><thead><tr><th>also observed that a finding based on documents taken behind the</th><th></th><th></th></tr></thead><tbody><tr><td>back of the parties by the arbitrator would also qualify as a decision</td><td></td><td></td></tr><tr><td>based on no evidence inasmuch as such decision is not based on</td><td></td><td></td></tr><tr><td>evidence led by the parties, and therefore, would also have to be</td><td></td><td></td></tr><tr><td>characterised as perverse [ See SsangyongEngg. &amp; Construction</td><td></td><td></td></tr><tr><td>Co. Ltd. v. NHAI, (2019) 15 SCC 131].</td><td></td><td></td></tr><tr><td>72. The tests laid down inAssociate Builders v. DDA, (2015) 3</td><td></td><td></td></tr><tr><td>SCC 49 to determine perversity were followed in SsangyongEngg.</td><td></td><td></td></tr><tr><td>&amp; Construction Co. Ltd. v. NHAI, (2019) 15 SCC 131 and later</td><td></td><td></td></tr><tr><td>approved by a three-Judge Bench of this Court inPatel Engg.</td><td></td><td></td></tr><tr><td>Ltd. v. North Eastern Electric Power Corpn. Ltd., (2020) 7 SCC</td><td></td><td></td></tr><tr><td>167.</td><td></td><td></td></tr><tr><td>73. In a recent three-Judge Bench decision of this Court inDMRC</td><td></td><td></td></tr><tr><td>Ltd. v. Delhi Airport Metro Express (P) Ltd., (2024) 6 SCC 357,</td><td></td><td></td></tr><tr><td>the ground of patent illegality/perversity was delineated in the</td><td></td><td></td></tr><tr><td>following terms: (SCC p. 376, para 39)</td><td></td><td></td></tr><tr><td></td><td>“39. In essence, the ground of patent illegality is available</td><td></td></tr><tr><td></td><td>for setting aside a domestic award, if the decision of the</td><td></td></tr><tr><td></td><td>arbitrator is found to be perverse, or so irrational that no</td><td></td></tr><tr><td></td><td>reasonable person would have arrived at it; or the</td><td></td></tr><tr><td></td><td>construction of the contract is such that no fair or</td><td></td></tr><tr><td></td><td>reasonable person would take; or, that the view of the</td><td></td></tr><tr><td></td><td>arbitrator is not even a possible view. A finding based on</td><td></td></tr><tr><td></td><td>no evidence at all or an award which ignores vital</td><td></td></tr><tr><td></td><td>evidence in arriving at its decision would be perverse and</td><td></td></tr><tr><td></td><td>liable to be set aside under the head of “patent illegality”.</td><td></td></tr><tr><td></td><td>An award without reasons would suffer from patent</td><td></td></tr><tr><td></td><td>illegality. The arbitrator commits a patent illegality by</td><td></td></tr><tr><td></td><td>deciding a matter not within its jurisdiction or violating a</td><td></td></tr><tr><td></td><td>fundamental principle of natural justice.”</td><td></td></tr><tr><td>Scope of interference with an arbitral award</td><td></td><td></td></tr><tr><td>74. The aforesaid judicial precedents make it clear that while</td><td></td><td></td></tr><tr><td>exercising power under Section 34 of the 1996 Act the Court does</td><td></td><td></td></tr><tr><td>not sit in appeal over the arbitral award. Interference with an</td><td></td><td></td></tr><tr><td>arbitral award is only on limited grounds as set out in Section 34 of</td><td></td><td></td></tr><tr><td>the 1996 Act. A possible view by the arbitrator on facts is to be</td><td></td><td></td></tr><tr><td>respected as the arbitrator is the ultimate master of the quantity and</td><td></td><td></td></tr><tr><td>quality of evidence to be relied upon. It is only when an arbitral</td><td></td><td></td></tr><tr><td>award could be categorised as perverse, that on an error of fact an</td><td></td><td></td></tr><tr><td>arbitral award may be set aside. Further, a mere erroneous</td><td></td><td></td></tr><tr><td>application of the law or wrong appreciation of evidence by itself is</td><td></td><td></td></tr><tr><td>not a ground to set aside an award as is clear from the provisions of</td><td></td><td></td></tr><tr><td>sub-section (2-A) of Section 34 of the 1996 Act.</td><td></td><td></td></tr><tr><td>75. InDyna Technologies (P) Ltd. v. Crompton Greaves Ltd.,</td><td></td><td></td></tr><tr><td>(2019) 20 SCC 1, paras 27-43, a three-Judge Bench of this Court</td><td></td><td></td></tr><tr><td>held that courts need to be cognizant of the fact that arbitral awards</td><td></td><td></td></tr><tr><td>are not to be interfered with in a casual and cavalier manner, unless</td><td></td><td></td></tr></tbody></table><div><br /> Signature Not Verified<br /> Digitally Signed<br /> By:VARNIKA<br /> Signing Date:06.04.2026<br /> 18:20:17<br /> O.M.P. (COMM) 246/2016 Page <b>15</b> of <b>24</b> <br /><br /> <br /> the court concludes that the perversity of the award goes to the root <br /> of the matter and there is no possibility of an alternative <br /> interpretation that may sustain the arbitral award. It was observed <br /> that jurisdiction under Section 34 cannot be equated with the <br /> normal appellate jurisdiction. Rather, the approach ought to be to <br /> respect the finality of the arbitral award as well as party&#x27;s autonomy <br /> to get their dispute adjudicated by an alternative forum as provided <br /> under the law. <br /> <b></b>* <br /> <b><i>Scope of interference with the interpretation/construction of a </i></b><br /> <b><i>contract accorded in an arbitral award</i></b> <br /> <b>84.</b> An Arbitral Tribunal must decide in accordance with the terms <br /> of the contract. In a case where an Arbitral Tribunal passes an <br /> award against the terms of the contract, the award would be <br /> patently illegal. However, an Arbitral Tribunal has jurisdiction to <br /> interpret a contract having regard to terms and conditions of the <br /> contract, conduct of the parties including correspondences <br /> exchanged, circumstances of the case and pleadings of the parties. <br /> If the conclusion of the arbitrator is based on a possible view of the <br /> matter, the Court should not intefere [See: <b><i>SAIL</i></b> <b> v. </b> <b><i>Gupta Brother </i></b><br /> <b><i>Steel Tubes Ltd.</i></b> <b>, (2009) 10 SCC 63; </b> <b><i>Pure Helium India (P) </i></b><br /> <b><i>Ltd.</i></b> <b> v. </b> <b><i>ONGC</i></b> <b>, (2003) 8 SCC 593; </b> <b><i>McDermott International </i></b><br /> <b><i>Inc.</i></b> <b> v. </b> <b><i>Burn Standard Co. Ltd.</i></b> <b>, (2006) 11 SCC 181; </b> <b><i>MMTC </i></b><br /> <b><i>Ltd.</i></b> <b> v. </b> <b><i>Vedanta Ltd.</i></b> <b>, (2019) 4 SCC 163</b> ]. But where, on a full <br /> reading of the contract, the view of the Arbitral Tribunal on the <br /> terms of a contract is not a possible view, the award would be <br /> considered perverse and as such amenable to interference [ <i>South </i><br /> <b><i>East Asia Marine Engg. &amp; Constructions Ltd.</i></b> <b> v. </b> <b><i>Oil India Ltd.</i></b> <b>, </b><br /> <b>(2020) 5 SCC 164</b> ]. <br /> <b><i>Whether unexpressed term can be read into a contract as an </i></b><br /> <b><i>implied condition</i></b> <br /> <b>85.</b> Ordinarily, terms of the contract are to be understood in the <br /> way the parties wanted and intended them to be. In agreements of <br /> arbitration, where party autonomy is the <i>grund norm</i> , how the <br /> parties worked out the agreement, is one of the indicators to <br /> decipher the intention, apart from the plain or grammatical meaning <br /> of the expressions used [ <b><i>B</i></b> <b><i>ALCO</i></b> <b> v. </b> <b><i>Kaiser Aluminium Technical </i></b><br /> <b><i>Services Inc.</i></b> <b>, (2016) 4 SCC 126</b> ]. <br /> <b>86.</b> However, reading an unexpressed term in an agreement would <br /> be justified on the basis that such a term was always and obviously <br /> intended by the parties thereto. An unexpressed term can be <br /> implied if, and only if, the court finds that the parties must have <br /> intended that term to form part of their contract. It is not enough for <br /> the court to find that such a term would have been adopted by the <br /> parties as reasonable men if it had been suggested to them. Rather, <br /> it must have been a term that went without saying, a term necessary <br /> to give business efficacy to the contract, a term which, although <br /> Signature Not Verified<br /> Digitally Signed<br /> By:VARNIKA<br /> Signing Date:06.04.2026<br /> 18:20:17<br /> O.M.P. (COMM) 246/2016 Page <b>16</b> of <b>24</b> <br /><br /> <br /> tacit, forms part of the contract [ <b><i>Adani Power (Mundra) </i></b><br /> <b><i>Ltd.</i></b> <b> v. </b> <b><i>Gujarat ERC</i></b> <b>, (2019) 19 SCC 9</b> ]. <br /> <b>87.</b> But before an implied condition, not expressly found in the <br /> contract, is read into a contract, by invoking the business efficacy <br /> doctrine, it must satisfy the following five conditions: <br /> ( <i>a</i> ) it must be reasonable and equitable; <br /> ( <i>b</i> ) it must be necessary to give business efficacy to the contract, <br /> that is, a term will not be implied if the contract is effective <br /> without it; <br /> ( <i>c</i> ) it must be obvious that “it goes without saying”; <br /> ( <i>d</i> ) it must be capable of clear expression; <br /> ( <i>e</i> ) it must not contradict any terms of the contract [ <b><i>Nabha Power </i></b><br /> <b><i>Ltd.</i></b> <b> v. </b> <b><i>Punjab SPCL</i></b> <b>, (2018) 11 SCC 508</b> , followed in <b><i>Adani </i></b><br /> <b><i>Power case</i></b> <b>, (2019) 19 SCC 9</b> ]. <br /> <b><i>(emphasis supplied) </i></b><br /> <b><i> </i></b><br /> 16. This Court now proceeds to examine the considerations and <br /> findings returned by the learned Arbitrator on the anvil of the limited <br /> and circumscribed jurisdiction available under Section 34 of the Act, <br /> and in the light of the principles authoritatively laid down by the <br /> Hon’ble Supreme Court in <b><i>OPG Power Generation</i></b> ( <i>supra</i> ). <br /> 17. At the outset, upon a careful and holistic perusal of the <br /> Impugned Award, this Court finds that the same suffers from a <br /> fundamental infirmity, <i>namely</i> , the absence of discernible reasoning. <br /> The paragraphs relied upon by learned counsel for the Respondent <br /> herein, as constituting the reasoning of the learned Arbitrator, reveal <br /> that they are, in substance, a mere reproduction or reiteration of the <br /> submissions and factual assertions advanced on behalf of the <br /> Claimant/Respondent herein, rather than an independent adjudicatory <br /> analysis. The Award, thus, reflects a mechanical acceptance of one <br /> party’s case without any demonstrable application of mind. <br /> 18. Although the issue as to whether the contractual procedure for <br /> extension of time, as envisaged under the GCC, was duly followed, <br /> finds a passing reference in Paragraph No. 13 of the Impugned Award, <br /> Signature Not Verified<br /> Digitally Signed<br /> By:VARNIKA<br /> Signing Date:06.04.2026<br /> 18:20:17<br /> O.M.P. (COMM) 246/2016 Page <b>17</b> of <b>24</b> <br /><br /> <br /> the said observation remains conclusory in nature and is not <br /> meaningfully integrated into the final determination. There is no <br /> analytical linkage between the said observation and the ultimate <br /> conclusions reached by the learned Arbitrator. <br /> 19. In fact, the conclusions of the learned Arbitrator are traceable, if <br /> at all, only to Paragraph Nos. 18 and 19 of the Impugned Award, <br /> which merely summarise the pleadings and record the ultimate <br /> findings. A plain reading of these paragraphs makes it evident that <br /> they do not disclose the reasoning process which led the learned <br /> Arbitrator to reject the Petitioner’s defence and allow the <br /> Respondent’s claim. The observations contained therein are <br /> conclusory and devoid of any analytical reasoning. For ready <br /> reference, Paragraph Nos. 18 and 19 of the Impugned Award are <br /> reproduced hereunder: <br /> “ <b>18.</b> To summarise the pleadings of the Claimant, the provision in <br /> the contract that every hindrance will be reported within ten days, a <br /> decision given by the Engr in charge, and an appeal allowed by the <br /> GM have not been followed. As can be seen, the argument by the <br /> Respondents that the price discount is simple as in case of Basmati <br /> rice and computer provision is not valid, as construction contracts <br /> are much more complicated and claims like delays have to be <br /> evaluated on the basis of data provided. The conclusion that the <br /> norms laid down by the apex Court have not been followed cannot <br /> be avoided. <br /> <b>19.</b> After considering all the facts and pleadings and arguments of <br /> both the parties, I have come to the conclusion that the imposition <br /> of &quot;price discount&quot; for a period of 69 days amounting to <br /> Rs91,59,654 is not admissible. Accordingly, I accept the Claim of <br /> the Claimant that a refund of the price discount already made (Rs <br /> 91.59.654) is justified.” <br /> <br /> 20. The Impugned Award, therefore, suffers from what may <br /> appropriately be characterised as an “ <i>acute reasoning deficit</i> ”. It is a <br /> well-settled and fundamental principle of law that reasons constitute <br /> Signature Not Verified<br /> Digitally Signed<br /> By:VARNIKA<br /> Signing Date:06.04.2026<br /> 18:20:17<br /> O.M.P. (COMM) 246/2016 Page <b>18</b> of <b>24</b> <br /><br /> <br /> the soul of any judicial or quasi-judicial determination. The <br /> requirement of recording reasons is not an empty formality, rather, it <br /> serves to demonstrate that the decision-maker has applied its mind to <br /> the material on record, has duly considered the rival submissions, and <br /> has arrived at its conclusions through a rational and logical process. In <br /> the absence of such reasoning, the decision becomes inherently <br /> opaque and arbitrary, depriving the parties of the ability to understand <br /> the basis of the conclusions reached and rendering the same <br /> vulnerable to judicial scrutiny and interference. An arbitral award that <br /> merely sets out the final conclusions, without disclosing the mental <br /> process or analytical pathway leading thereto, fails to satisfy the <br /> minimum statutory mandate. <br /> 21. Significantly, although the learned Arbitrator in the present case <br /> makes a cursory reference to the necessity of rendering a reasoned <br /> decision in accordance with settled legal principles, the Impugned <br /> Award itself falls conspicuously short of that very standard. The <br /> findings recorded therein are unsupported by any cogent reasoning or <br /> legal analysis and do not reflect a meaningful consideration of the <br /> pleadings, evidence, or submissions advanced by both parties. Such a <br /> perfunctory approach strikes at the very root of the adjudicatory <br /> process and renders the Award unsustainable in law. <br /> 22. The Hon’ble Supreme Court, in a catena of decisions, including <br /> <b><i>8</i></b><br /> <b><i>Dyna Technologies (P) Ltd. v. Crompton Greaves Ltd.</i></b> , has <br /> consistently held that Section 31(3) of the Act mandates that an <br /> arbitral award must contain reasons that are intelligible and adequate, <br /> though not necessarily elaborate. While arbitrators are not required to <br /> <br /> 8<br /> (2019) 20 SCC 1 <br /> Signature Not Verified<br /> Digitally Signed<br /> By:VARNIKA<br /> Signing Date:06.04.2026<br /> 18:20:17<br /> O.M.P. (COMM) 246/2016 Page <b>19</b> of <b>24</b> <br /><br /> <br /> render judgments akin to courts, the reasoning must nonetheless <br /> reflect a rational nexus between the material on record and the <br /> conclusions arrived at. A reasoned award must satisfy three essential <br /> attributes, <i>namely</i> , that it is proper, intelligible, and adequate. Where <br /> the reasoning is improper, it discloses a flaw in the decision-making <br /> process and may render the award vulnerable to challenge under <br /> Section 34 of the Act on grounds of perversity. <br /> 23. The Apex Court, in <b><i>Dyna Technologies </i></b> <i>(supra)</i> , has clarified <br /> that where the reasoning is unintelligible, it is tantamount to no <br /> reasons at all, and such awards are ordinarily liable to be set aside. <br /> While the adequacy of reasons may vary depending upon the <br /> complexity of the issues involved, and minor gaps in reasoning may <br /> not by themselves warrant interference, an award that is <br /> fundamentally bereft of intelligible reasoning cannot be sustained. <br /> Courts must, therefore, carefully distinguish between a case of mere <br /> inadequacy of reasons and one of complete absence or unintelligibility <br /> of reasoning. The former may not justify interference, whereas the <br /> latter strikes at the very root of the award. The relevant paragraphs of <br /> the said judgment read as follows: <br /> “ <b>1.</b> <b> </b> The question involved herein revolves around the requirement <br /> of reasoned award and the cautionary tale for the parties and <br /> arbitrators to have a clear award, rather than to have an award <br /> which is muddled in form and implied in its content, which <br /> inevitably leads to wastage of time and resources of the parties to <br /> get clarity, and in some cases, frustrate the very reason for going <br /> for an arbitration. <br /> <b><i></i></b><i> </i>*<br /> <b>24.</b> There is no dispute that Section 34 of the Arbitration Act limits <br /> a challenge to an award only on the grounds provided therein or as <br /> interpreted by various courts. We need to be cognizant of the fact <br /> that arbitral awards should not be interfered with in a casual and <br /> cavalier manner, unless the court comes to a conclusion that the <br /> perversity of the award goes to the root of the matter without there <br /> Signature Not Verified<br /> Digitally Signed<br /> By:VARNIKA<br /> Signing Date:06.04.2026<br /> 18:20:17<br /> O.M.P. (COMM) 246/2016 Page <b>20</b> of <b>24</b> <br /><br /> <br /></div><table><thead><tr><th>being a possibility of alternative interpretation which may sustain</th><th></th><th></th></tr></thead><tbody><tr><td>the arbitral award. Section 34 is different in its approach and cannot</td><td></td><td></td></tr><tr><td>be equated with a normal appellate jurisdiction. The mandate under</td><td></td><td></td></tr><tr><td>Section 34 is to respect the finality of the arbitral award and the</td><td></td><td></td></tr><tr><td>party autonomy to get their dispute adjudicated by an alternative</td><td></td><td></td></tr><tr><td>forum as provided under the law. If the courts were to interfere</td><td></td><td></td></tr><tr><td>with the arbitral award in the usual course on factual aspects, then</td><td></td><td></td></tr><tr><td>the commercial wisdom behind opting for alternate dispute</td><td></td><td></td></tr><tr><td>resolution would stand frustrated.</td><td></td><td></td></tr><tr><td>25. Moreover, umpteen number of judgments of this Court have</td><td></td><td></td></tr><tr><td>categorically held that the courts should not interfere with an award</td><td></td><td></td></tr><tr><td>merely because an alternative view on facts and interpretation of</td><td></td><td></td></tr><tr><td>contract exists. The courts need to be cautious and should defer to</td><td></td><td></td></tr><tr><td>the view taken by the Arbitral Tribunal even if the reasoning</td><td></td><td></td></tr><tr><td>provided in the award is implied unless such award portrays</td><td></td><td></td></tr><tr><td>perversity unpardonable under Section 34 of the Arbitration Act.</td><td></td><td></td></tr><tr><td>*****</td><td></td><td></td></tr><tr><td>28. Similar to the position under the Model Law, India also adopts</td><td></td><td></td></tr><tr><td>a default rule to provide for reasons unless the parties agree</td><td></td><td></td></tr><tr><td>otherwise. As with most countries like England, America and</td><td></td><td></td></tr><tr><td>Model Law, Indian law recognises enforcement of the reasonless</td><td></td><td></td></tr><tr><td>award if it has been so agreed between the parties.</td><td></td><td></td></tr><tr><td>29. There is no gainsaying that arbitration proceedings are not per</td><td></td><td></td></tr><tr><td>se comparable to judicial proceedings before the Court. A party</td><td></td><td></td></tr><tr><td>under Indian Arbitration Law can opt for an arbitration before any</td><td></td><td></td></tr><tr><td>person, even those who do not have prior legal experience as well.</td><td></td><td></td></tr><tr><td>In this regard, we need to understand that the intention of the</td><td></td><td></td></tr><tr><td>legislature to provide for a default rule, should be given rational</td><td></td><td></td></tr><tr><td>meaning in light of commercial wisdom inherent in the choice of</td><td></td><td></td></tr><tr><td>arbitration.</td><td></td><td></td></tr><tr><td>30. A five-Judge Constitution Bench of this Court in Raipur</td><td></td><td></td></tr><tr><td>Development Authority v. Chokhamal Contractors, (1989) 2 SCC</td><td></td><td></td></tr><tr><td>721, considered the scope of Section 30 of the Arbitration Act,</td><td></td><td></td></tr><tr><td>1940 and held as under: (SCC p. 736, para 19)</td><td></td><td></td></tr><tr><td></td><td>“19. It is now well settled that an award can neither be</td><td></td></tr><tr><td></td><td>remitted nor set aside merely on the ground that it does not</td><td></td></tr><tr><td></td><td>contain reasons in support of the conclusion or decisions</td><td></td></tr><tr><td></td><td>reached in it except where the arbitration agreement or the</td><td></td></tr><tr><td></td><td>deed of submission requires him to give reasons. The</td><td></td></tr><tr><td></td><td>arbitrator or umpire is under no obligation to give reasons</td><td></td></tr><tr><td></td><td>in support of the decision reached by him unless under the</td><td></td></tr><tr><td></td><td>arbitration agreement or in the deed of submission he is</td><td></td></tr><tr><td></td><td>required to give such reasons and if the arbitrator or</td><td></td></tr><tr><td></td><td>umpire chooses to give reasons in support of his decision</td><td></td></tr><tr><td></td><td>it is open to the court to set aside the award if it finds that</td><td></td></tr><tr><td></td><td>an error of law has been committed by the arbitrator or</td><td></td></tr></tbody></table><div><br /> Signature Not Verified<br /> Digitally Signed<br /> By:VARNIKA<br /> Signing Date:06.04.2026<br /> 18:20:17<br /> O.M.P. (COMM) 246/2016 Page <b>21</b> of <b>24</b> <br /><br /> <br /></div><table><thead><tr><th></th><th>umpire on the face of the record on going through such</th><th></th></tr></thead><tbody><tr><td></td><td>reasons. The arbitrator or umpire shall have to give</td><td></td></tr><tr><td></td><td>reasons also where the court has directed in any order such</td><td></td></tr><tr><td></td><td>as the one made under Section 20 or Section 21 or Section</td><td></td></tr><tr><td></td><td>34 of the Act that reasons should be given or where the</td><td></td></tr><tr><td></td><td>statute which governs an arbitration requires him to do</td><td></td></tr><tr><td></td><td>so.”</td><td></td></tr><tr><td>31. A three-Judge Bench of this Court in another case of S.</td><td></td><td></td></tr><tr><td>Harcharan Singh v. Union of India [S. Harcharan Singh v. Union</td><td></td><td></td></tr><tr><td>of India, (1990) 4 SCC 647] , reiterated its earlier view that the</td><td></td><td></td></tr><tr><td>arbitrator&#x27;s adjudication is generally considered binding between</td><td></td><td></td></tr><tr><td>the parties for he is a Tribunal selected by the parties and the power</td><td></td><td></td></tr><tr><td>of the Court to set aside the award is restricted to cases set out in</td><td></td><td></td></tr><tr><td>Section 30 of the Arbitration Act, 1940.</td><td></td><td></td></tr><tr><td>32. However, the ratio of Chokhamal case has not found favour of</td><td></td><td></td></tr><tr><td>the legislature, and accordingly Section 31(3) has been enacted in</td><td></td><td></td></tr><tr><td>the Arbitration Act. This Court in Som Datt Builders Ltd. v. State</td><td></td><td></td></tr><tr><td>of Kerala, (2009) 10 SCC 259, a Division Bench of this Court has</td><td></td><td></td></tr><tr><td>indicated that passing of a reasoned award is not an empty</td><td></td><td></td></tr><tr><td>formulation under the Arbitration Act.</td><td></td><td></td></tr><tr><td>33. It may be relevant to note Russell on Arbitration, 23rd Edn.</td><td></td><td></td></tr><tr><td>(2007), wherein he notes that:</td><td></td><td></td></tr><tr><td></td><td>“If the Court can deduce from the award and the materials</td><td></td></tr><tr><td></td><td>before it, which may include extracts from evidence and</td><td></td></tr><tr><td></td><td>the transcript of hearing, the thrust of the tribunal&#x27;s</td><td></td></tr><tr><td></td><td>reasoning then no irregularity will be found….Equally, the</td><td></td></tr><tr><td></td><td>court should bear in mind that when considering awards</td><td></td></tr><tr><td></td><td>produced by non-lawyer arbitrators, the court should look</td><td></td></tr><tr><td></td><td>at the substance of such findings, rather than their form,</td><td></td></tr><tr><td></td><td>and that one should approach a reading of the award in a</td><td></td></tr><tr><td></td><td>fair, and not in an unduly literal way.”</td><td></td></tr><tr><td></td><td>(emphasis supplied)</td><td></td></tr><tr><td>34. The mandate under Section 31(3) of the Arbitration Act is to</td><td></td><td></td></tr><tr><td>have reasoning which is intelligible and adequate and, which can in</td><td></td><td></td></tr><tr><td>appropriate cases be even implied by the courts from a fair reading</td><td></td><td></td></tr><tr><td>of the award and documents referred to thereunder, if the need be.</td><td></td><td></td></tr><tr><td>The aforesaid provision does not require an elaborate judgment to</td><td></td><td></td></tr><tr><td>be passed by the arbitrators having regard to the speedy resolution</td><td></td><td></td></tr><tr><td>of dispute.</td><td></td><td></td></tr><tr><td>35. When we consider the requirement of a reasoned order, three</td><td></td><td></td></tr><tr><td>characteristics of a reasoned order can be fathomed. They are:</td><td></td><td></td></tr><tr><td>proper, intelligible and adequate. If the reasonings in the order are</td><td></td><td></td></tr><tr><td>improper, they reveal a flaw in the decision-making process. If the</td><td></td><td></td></tr><tr><td>challenge to an award is based on impropriety or perversity in the</td><td></td><td></td></tr><tr><td>reasoning, then it can be challenged strictly on the grounds</td><td></td><td></td></tr><tr><td>provided under Section 34 of the Arbitration Act. If the challenge</td><td></td><td></td></tr></tbody></table><div><br /> Signature Not Verified<br /> Digitally Signed<br /> By:VARNIKA<br /> Signing Date:06.04.2026<br /> 18:20:17<br /> O.M.P. (COMM) 246/2016 Page <b>22</b> of <b>24</b> <br /><br /> <br /></div><table><thead><tr><th>to an award is based on the ground that the same is unintelligible,</th><th></th></tr></thead><tbody><tr><td>the same would be equivalent of providing no reasons at all.</td><td></td></tr><tr><td>Coming to the last aspect concerning the challenge on adequacy of</td><td></td></tr><tr><td>reasons, the Court while exercising jurisdiction under Section 34</td><td></td></tr><tr><td>has to adjudicate the validity of such an award based on the degree</td><td></td></tr><tr><td>of particularity of reasoning required having regard to the nature of</td><td></td></tr><tr><td>issues falling for consideration. The degree of particularity cannot</td><td></td></tr><tr><td>be stated in a precise manner as the same would depend on the</td><td></td></tr><tr><td>complexity of the issue. Even if the Court comes to a conclusion</td><td></td></tr><tr><td>that there were gaps in the reasoning for the conclusions reached by</td><td></td></tr><tr><td>the Tribunal, the Court needs to have regard to the documents</td><td></td></tr><tr><td>submitted by the parties and the contentions raised before the</td><td></td></tr><tr><td>Tribunal so that awards with inadequate reasons are not set aside in</td><td></td></tr><tr><td>casual and cavalier manner. On the other hand, ordinarily</td><td></td></tr><tr><td>unintelligible awards are to be set aside, subject to party autonomy</td><td></td></tr><tr><td>to do away with the reasoned award. Therefore, the courts are</td><td></td></tr><tr><td>required to be careful while distinguishing between inadequacy of</td><td></td></tr><tr><td>reasons in an award and unintelligible awards.”</td><td></td></tr></tbody></table><div><br /> <b>(</b> <b><i>emphasis supplied</i></b> <b>) </b><br /> <br /> 24. In the considered opinion of this Court, the Impugned Award, <br /> when tested on the anvil of settled legal principles, squarely falls <br /> within the category of awards vitiated by unintelligibility of reasoning. <br /> This is not a case of mere inadequacy or insufficiency of reasons, <br /> where, despite certain gaps or brevity, the underlying thought process <br /> of the Arbitrator may still be gathered from the record. <br /> <br /> 25. On the contrary, the present case discloses a far more <br /> fundamental infirmity. The conclusions recorded therein are bald, <br /> conclusory, and unsupported by any discernible analytical process. <br /> Such an Award, which merely announces the result without revealing <br /> the complete mental process leading to it, cannot be sustained in law. <br /> 26. As noted earlier, the Impugned Award fails to disclose any <br /> coherent or logical adjudicatory pathway linking the factual assertions <br /> and the ultimate conclusions arrived at by the learned Arbitrator. The <br /> absence of such a reasoning framework renders it impossible for this <br /> Court to meaningfully examine or scrutinize the basis of the findings <br /> Signature Not Verified<br /> Digitally Signed<br /> By:VARNIKA<br /> Signing Date:06.04.2026<br /> 18:20:17<br /> O.M.P. (COMM) 246/2016 Page <b>23</b> of <b>24</b> <br /><br /> <br /> returned. This deficiency strikes at the very root of the statutory <br /> mandate embodied in Section 31(3) of the Act. <br /> 27. Furthermore, in the absence of intelligible reasoning, the <br /> contentions raised by the Petitioner herein cannot be effectively <br /> examined on the merits. On this ground alone, the Impugned Award is <br /> rendered unsustainable. <br /> <br /> 28. Accordingly, the present Petition is allowed, and the Impugned <br /> Award dated 20.11.2014 is set aside. <br /> 29. The present Petition, along with pending Application(s), if any, <br /> stands disposed of in the aforesaid terms. <br /> 30. There shall be no order as to costs. <br /> <br /> <b>HARISH VAIDYANATHAN SHANKAR, J. </b><br /> <b>APRIL 02, 2026/tk/ DJ</b> <br /> Signature Not Verified<br /> Digitally Signed<br /> By:VARNIKA<br /> Signing Date:06.04.2026<br /> 18:20:17<br /> O.M.P. (COMM) 246/2016 Page <b>24</b> of <b>24</b> </div>