Gwalior Development Authority Gwalior vs Kalpana Sharma

Court
Madhya Pradesh High Court

NEUTRAL CITATION NO. 2026:MPHC-GWL:22705
1 WA-2541-2026
IN THE HIGH COURT OF MADHYA PRADESH
AT GWALIOR

BEFORE
HON'BLE SHRI JUSTICE G. S. AHLUWALIA
&
HON'BLE SMT. JUSTICE ANURADHA SHUKLA
th
ON THE 29 OF JULY, 2026
WRIT APPEAL No. 2541 of 2026
GWALIOR DEVELOPMENT AUTHORITY GWALIOR AND OTHERS
Versus
KALPANA SHARMA AND OTHERS
Appearance:
Shri Raghvendra Dixit - Advocate for the petitioners.
Shri Prashant Sharma - Advocate for the respondent No.1.
Shri C.P. Singh - Government Advocate for the State.
ORDER
Per: Justice Gurpal Singh Ahluwalia
This writ appeal under Section 2(1) of the Madhya Pradesh Uchcha
Nyayalaya (Khand Nyayapeeth Ko Appeal) Adhiniyam, 2005 has been filed
against the order dated 27.04.2026 passed by Learned Single Judge in Writ
Petition No.33444/2025 by which action of appellants in forfeiting the
security amount of Rs.2,95,750/- has been set aside and the appellants have
been directed to refund the said amount.
2. The facts necessary for disposal of the present appeal, in short, are
that NIC was floated for auction of various plots. Respondent submitted her
bid for plot No.J-143 area 181.5 sq. meter. The offset price fixed by the
appellants was Rs.29,94,750/- and 10% of the said amount i.e. 2,94,750/-
Signature Not Verified
Signed by: RASHID KHAN
Signing time: 8/7/2026
11:04:26 AM

NEUTRAL CITATION NO. 2026:MPHC-GWL:22705
2 WA-2541-2026
was security amount. The respondent submitted her bid of Rs.3,38,05,555/-.

After the bid was opened on 14.02.2025, it was duly accepted on 24.02.2025.
Thereafter, on 28.02.2025 respondent moved an application seeking
permission to withdraw her bid. The application for withdrawal was accepted
but as per the provisions of Rule 6(iv) as well as Form C of the Madhya
Pradesh Vikas Pradhikaron Ki Sampatiyon Ka Prabandhan Tatha Vyayan
Niyam, 2018, the security amount was forfeited.
3 . Challenging the forfeiture of the security amount, the respondent
preferred Writ Petition No.33444/2025 which has been allowed by the
learned Single Judge by holding that on-line bidding mechanism lacked basic
safeguards which could have prevented such an error. The absence of
a feature for entering the bid amount in words, coupled with the lack of any
opportunity to review or correct the submitted bid, reflects a systemic
deficiency. The respondent/authority having designed and implemented such
a system, cannot be permitted to take undue advantage of its own
shortcomings to the detriment of a bidder who has acted in good faith.
Furthermore, it has been held that upon discovering the facts, respondent
acted in promptitude and submitted a request for cancellation and refund of
security amount well before any further steps in the allotment process could
crystallize. It has also been held that impugned order of forfeiture of security
amount suffers from non application of mind as it fails to consider the
explanation furnished by the respondent. It is submitted that as per the Rules,
2018, once the bid is accepted, then the prayer for withdrawal of bid can be
permitted only on forfeiture of bid amount. Learned Single Judge has
Signature Not Verified
Signed by: RASHID KHAN
Signing time: 8/7/2026
11:04:26 AM

NEUTRAL CITATION NO. 2026:MPHC-GWL:22705
3 WA-2541-2026
ignored the fact that the bid was already accepted, and whatever explanation

may be given by bidder, the same cannot be looked into for any purposes.
4 . Furthermore, it was not the case of respondent that immediately
after submitting the on-line application, she realized that by mistake in place
of Rs.38,05,555/-, she has entered Rs.3,38,05,555/- and in absence of any
provision for correction of bid amount, she was compelled to face the bid
process. It is submitted that once it is the case of respondent herself that she
came to know about her mistake only after the bid was opened, then whether
there was any provision for correction of bid amount or not is immaterial
under the facts and circumstances of the case. It is further submitted that after
having participating in the bid process and knowing-fully well that there is
no provision for correction of the bid amount, bidder/respondent cannot be
permitted to challenge the so called shortcoming in the bid process and relied
upon the judgment passed by Supreme Court in the case of National High
Speed Rail Corporation Limited Vs. Montecarlo Limited and another [(2022)
6 SCC 401] and Uflex Limited Vs. Government of Tamil Nadu and others
[(2022) 1 SCC 165].
5. Per contra, it is submitted by counsel for the respondent that it is
true that after the bids are opened, no one can be permitted to change the bid
amount. However, in the present case there was no provision for correction
of bid amount which was erroneously filled up, therefore, the Writ Court did
not commit any mistake by quashing the order of forfeiture of security
amount.
6. Heard the learned counsel for the parties.
Signature Not Verified
Signed by: RASHID KHAN
Signing time: 8/7/2026
11:04:26 AM

NEUTRAL CITATION NO. 2026:MPHC-GWL:22705
4 WA-2541-2026
7 . It is not the case of respondent/petitioner that immediately after

submitting the bid amount or before opening of bids, she had realized that
she had mistakenly entered a figure of Rs.3,38,05,555/- in place of
Rs.38,05,555/-. It is equally true that the bid amount cannot be permitted to
be changed after the bid is open. If the respondent had not realized that she
had mistakenly entered the bid amount and did not make any application to
the respondent to withdraw her bid before opening of bid, then the absence
of provision for correction of bid amount will not make the bid process
vulnerable or bad in law.
8. Since, the basic foundation for addressing the violation of principle
of natural justice on the ground of absence of any provision for correction of
bid amount is missing, this Court is of considered opinion that learned Single
Judge should not have considered the aspects which were never raised by
respondent/petitioner in her application (Annexure P/4).
9. Furthermore, Rule 6 (iv) of Niyam, 2018 reads as under:-
"6. Disposal of properties by inviting bids:-
(iv) The conditions of the bid which shall ordinarily be
mentioned in the bid document shall be such as
mentioned in Form-C."
10. Form C (III)(IV) reads as under: -
"Form-C, Bid Document: III. Validity of Bid, Bid Security and
Forfeiture of Bid Security
1. The bids shall remain valid for a period of 90 days
from the bid due date.
2. The Bidders are required to submit a bid security of
Rs.........(.......% of the reserve price for the property for
which the bid is being submitted).
3. The Bid Security of the other bidders whose bids
have not been accepted shall be returned within 15 days
of opening of the Bid Envelope.
4. The Bid Security for the bidder whose offer has been
accepted by the Authority, who either wishes to
withdraw the offer or who fails to pay the balance
Signature Not Verified
Signed by: RASHID KHAN
Signing time: 8/7/2026
11:04:26 AM

NEUTRAL CITATION NO. 2026:MPHC-GWL:22705
5 WA-2541-2026
amount within the time frame as per the terms and
conditions for payment in the bid document or is found
to have made representation of the facts/information for
the eligibility or otherwise, shall be forfeited.

IV. Information/Documents to be Provided
Envelope A-Eligibility Envelope

1. Demand draft/Pay-order for the Bid Document Fee in
favour of ................ Development Authority (Non-
refundable) in case the form has been downloaded from
the web-site of the Authority or copy of the original
receipt of the cash payment for purchase of bid
document from the Authority.
2. Demand draft/Pay-order for the Bid Security of
Rs................ (...........% of the reserve price for the
property drawn in favour of ............. Development
Authority.
3. Mandatory Supporting Documents to be Submitted."

11. Thus, it is clear that after the bids are opened and accepted,
aspirants/bidders can withdraw their bid only on forfeiture of security
amount.
12. In the present case, it is not disputed by any of the parties that bid
of respondent/petitioner was already accepted much prior to her application
for withdrawal. Learned Single Judge has also held that upon discovering the
mistake, respondent/petitioner acted with promptitude. However, it is suffice
to mention here that no bid amount can be permitted to be changed after the
bids are open and if the respondent had acted after bids were open, then it
cannot be said that she had ever acted with promptitude. Furthermore, once
the bids were opened on 14.02.2025, respondent was well aware of the fact
that her bid is of Rs.3,38,05,555/-, but she made an application for
withdrawal on 28.02.2025 i.e. after 14 days of opening of the bid. In the
meanwhile, bid submitted by the respondent/petitioner was also accepted i.e.
on 24.02.2025. By no stretch of imagination, it can be said that
Signature Not Verified
Signed by: RASHID KHAN
Signing time: 8/7/2026
11:04:26 AM

NEUTRAL CITATION NO. 2026:MPHC-GWL:22705
6 WA-2541-2026
respondent/petitioner had acted with promptitude after discovering her

mistake.
13. It appears that learned Single Judge was convinced with the
arguments made by counsel for respondent/petitioner that since the offset
price itself was only Rs.29,94,750/- then why the respondent/petitioner
would submit her bid for Rs.3,38,05,555/- ?. It is suffice to mention here that
while exercising jurisdiction in contractual matter, this Court has a limited
jurisdiction to interfere. Supreme Court in the case of Tata Cellular Vs.
Union of India reported in (1994) 6 SCC 651 has held that:-

"94. The principles deducible from the above are:

(1) The modern trend points to judicial restraint in administrative
action.

(2) The court does not sit as a court of appeal but merely reviews
the manner in which the decision was made.

(3) The court does not have the expertise to correct the
administrative decision. If a review of the administrative decision
is permitted it will be instituting its own decision, without the
necessary expertise which itself may be fallible.

(4) The terms of the invitation to tender cannot be open to judicial
scrutiny because the invitation to tender is in the realm of contract.
Normally speaking, the decision to accept the tender or award the
contract is reached by process of negotiations through several
tiers. More often than not, such decisions are made qualitatively
by experts.

(5) The Government must have freedom of contract. In other
words, a fair play in the joints is a necessary concomitant for an
administrative body functioning in an administrative sphere or
quasi-administrative sphere. However, the decision must not only
be tested by the application of Wednesbury principle of
reasonableness (including its other facts pointed out above) but
must be free from arbitrariness not affected by bias or actuated by
mala fides.

(6) Quashing decisions may impose heavy administrative burden
on the administration and lead to increased and unbudgeted the
expenditure.
Signature Not Verified
Signed by: RASHID KHAN
Signing time: 8/7/2026
11:04:26 AM

NEUTRAL CITATION NO. 2026:MPHC-GWL:22705
7 WA-2541-2026


Based on these principles we will examine the facts of this case since they
commend to us as the correct principles."


14. The Supreme Court in the case of National High Speed Rail
Corporation Limited Vs. Montecarlo Limited and another reported in (2022)
6 SCC 401 has held as under:-
"28. At this stage, few decisions of this Court on the interference by the
courts in the tender matters are required to be referred to:
28.1. In Afcons Infrastructure Ltd. v. Nagpur Metro Rail Corpn. Ltd.
[Afcons Infrastructure Ltd. v. Nagpur Metro Rail Corpn. Ltd., (2016) 16
SCC 818] , this Court in paras 11 to 13 and 15 has observed and held as
under : (SCC pp. 824-25)
“11. Recently, in Central Coalfields Ltd. v. SLL-SML (Joint
Venture Consortium) [Central Coalfields Ltd. v. SLL-SML (Joint
Venture Consortium), (2016) 8 SCC 622 : (2016) 4 SCC (Civ)
106] , it was held by this Court, relying on a host of decisions that
the decision-making process of the employer or owner of the
project in accepting or rejecting the bid of a tenderer should not be
interfered with. Interference is permissible only if the decision-
making process is mala fide or is intended to favour someone.
Similarly, the decision should not be interfered with unless the
decision is so arbitrary or irrational that the Court could say that
the decision is one which no responsible authority acting
reasonably and in accordance with law could have reached. In
other words, the decision-making process or the decision should
be perverse and not merely faulty or incorrect or erroneous. No
such extreme case was made out by GYT-TPL JV in the High
Court or before us.
12. In Dwarkadas Marfatia & Sons v. Port of Bombay [Dwarkadas
Marfatia & Sons v. Port of Bombay, (1989) 3 SCC 293] , it was
held that the constitutional courts are concerned with the decision-
making process. Tata Cellular v. Union of India [Tata Cellular v.
Signature Not Verified
Signed by: RASHID KHAN
Signing time: 8/7/2026
11:04:26 AM

NEUTRAL CITATION NO. 2026:MPHC-GWL:22705
8 WA-2541-2026
Union of India, (1994) 6 SCC 651] went a step further and held
that a decision if challenged (the decision having been arrived at
through a valid process), the constitutional courts can interfere if
the decision is perverse. However, the constitutional courts are
expected to exercise restraint in interfering with the administrative
decision and ought not to substitute its view for that of the
administrative authority. This was confirmed in Jagdish Mandal v.
State of Orissa [Jagdish Mandal v. State of Orissa, (2007) 14 SCC
517] , as mentioned in Central Coalfields Ltd. v. SLL-SML (Joint
Venture Consortium) [Central Coalfields Ltd. v. SLL-SML (Joint
Venture Consortium), (2016) 8 SCC 622 : (2016) 4 SCC (Civ)
106].

13. In other words, a mere disagreement with the decision-making
process or the decision of the administrative authority is no reason
for a constitutional court to interfere. The threshold of mala fides,
intention to favour someone or arbitrariness, irrationality or
perversity must be met before the constitutional court interferes
with the decision-making process or the decision.
*
15. We may add that the owner or the employer of a project,
having authored the tender documents, is the best person to
understand and appreciate its requirements and interpret its
documents. The constitutional courts must defer to this
understanding and appreciation of the tender documents, unless
there is mala fide or perversity in the understanding or
appreciation or in the application of the terms of the tender
conditions. It is possible that the owner or employer of a project
may give an interpretation to the tender documents that is not
acceptable to the constitutional courts but that by itself is not a
reason for interfering with the interpretation given.”
28.2. In B.S.N. Joshi & Sons Ltd. v. Nair Coal Services Ltd. [B.S.N. Joshi
& Sons Ltd. v. Nair Coal Services Ltd., (2006) 11 SCC 548] , after
considering the various decisions of this Court on the point enumerated in
para 66, this Court has observed and held as under : (SCC pp. 571-72)
Signature Not Verified
Signed by: RASHID KHAN
Signing time: 8/7/2026
11:04:26 AM

NEUTRAL CITATION NO. 2026:MPHC-GWL:22705
9 WA-2541-2026
“66. We are also not shutting our eyes towards the new principles
of judicial review which are being developed; but the law as it
stands now having regard to the principles laid down in the
aforementioned decisions may be summarised as under:

(i) if there are essential conditions, the same must be
adhered to;
(ii) if there is no power of general relaxation, ordinarily
the same shall not be exercised and the principle of strict
compliance would be applied where it is possible for all
the parties to comply with all such conditions fully;
(iii) if, however, a deviation is made in relation to all the
parties in regard to any of such conditions, ordinarily
again a power of relaxation may be held to be existing;
(iv) the parties who have taken the benefit of such
relaxation should not ordinarily be allowed to take a
different stand in relation to compliance with another part
of tender contract, particularly when he was also not in a
position to comply with all the conditions of tender fully,
unless the court otherwise finds relaxation of a condition
which being essential in nature could not be relaxed and
thus the same was wholly illegal and without jurisdiction;
(v) when a decision is taken by the appropriate authority
upon due consideration of the tender document submitted
by all the tenderers on their own merits and if it is
ultimately found that successful bidders had in fact
substantially complied with the purport and object for
which essential conditions were laid down, the same may
not ordinarily be interfered with;
(vi) the contractors cannot form a cartel. If despite the
same, their bids are considered and they are given an offer
to match with the rates quoted by the lowest tenderer,
public interest would be given priority;
(vii) where a decision has been taken purely on public
Signature Not Verified
Signed by: RASHID KHAN
Signing time: 8/7/2026
11:04:26 AM

NEUTRAL CITATION NO. 2026:MPHC-GWL:22705
10 WA-2541-2026
interest, the court ordinarily should exercise judicial
restraint.”

28.3. In Michigan Rubber (India) Ltd. v. State of Karnataka [Michigan
Rubber (India) Ltd. v. State of Karnataka, (2012) 8 SCC 216] , after
considering various other decisions of this Court on the point, more
particularly, after considering the decisions in Jagdish Mandal [Jagdish
Mandal v. State of Orissa, (2007) 14 SCC 517] and Tejas Constructions &
Infrastructure (P) Ltd. v. Municipal Council, Sendhwa [Tejas
Constructions & Infrastructure (P) Ltd. v. Municipal Council, Sendhwa,
(2012) 6 SCC 464] , in paras 23 and 24, this Court has observed and held
as under : (Michigan Rubber case [Michigan Rubber (India) Ltd. v. State
of Karnataka, (2012) 8 SCC 216] , SCC p. 229)
“23. From the above decisions, the following principles emerge:
(a) The basic requirement of Article 14 is fairness in
action by the State, and non-arbitrariness in essence and
substance is the heartbeat of fair play. These actions are
amenable to the judicial review only to the extent that the
State must act validly for a discernible reason and not
whimsically for any ulterior purpose. If the State acts
within the bounds of reasonableness, it would be
legitimate to take into consideration the national
priorities;
(b) Fixation of a value of the tender is entirely within the
purview of the executive and the courts hardly have any
role to play in this process except for striking down such
action of the executive as is proved to be arbitrary or
unreasonable. If the Government acts in conformity with
certain healthy standards and norms such as awarding of
contracts by inviting tenders, in those circumstances, the
interference by courts is very limited;
(c) In the matter of formulating conditions of a tender
document and awarding a contract, greater latitude is
required to be conceded to the State authorities unless the
action of the tendering authority is found to be malicious
Signature Not Verified
Signed by: RASHID KHAN
Signing time: 8/7/2026
11:04:26 AM

NEUTRAL CITATION NO. 2026:MPHC-GWL:22705
11 WA-2541-2026
and a misuse of its statutory powers, interference by
courts is not warranted;

(d) Certain preconditions or qualifications for tenders
have to be laid down to ensure that the contractor has the
capacity and the resources to successfully execute the
work; and
(e) If the State or its instrumentalities act reasonably,
fairly and in public interest in awarding contract, here
again, interference by court is very restrictive since no
person can claim a fundamental right to carry on business
with the Government.
24. Therefore, a court before interfering in tender or contractual
matters, in exercise of power of judicial review, should pose to
itself the following questions:
(i) Whether the process adopted or decision made by the
authority is mala fide or intended to favour someone; or
whether the process adopted or decision made is so
arbitrary and irrational that the court can say:‘the decision
is such that no responsible authority acting reasonably and
in accordance with relevant law could have reached’? and
(ii) Whether the public interest is affected?
If the answers to the above questions are in the negative, then
there should be no interference under Article 226.”
28.4. In Central Coalfields Ltd. v. SLL-SML (Joint Venture Consortium)
[Central Coalfields Ltd. v. SLL-SML (Joint Venture Consortium), (2016)
8 SCC 622 : (2016) 4 SCC (Civ) 106] , it is specifically observed and
held by this Court that the Court must, as far as possible, avoid a
construction which would render the words used by the author of the
document meaningless and futile or reduce to silence any part of the
document and make it altogether inapplicable. It is further observed that
whether a term of NIT is essential or not is a decision taken by the
employer, which should be respected and soundness of that decision
cannot be questioned by Court. In the case before this Court, the bid was
Signature Not Verified
Signed by: RASHID KHAN
Signing time: 8/7/2026
11:04:26 AM

NEUTRAL CITATION NO. 2026:MPHC-GWL:22705
12 WA-2541-2026
rejected for non-furnishing of bank guarantee in prescribed format. While
submitting EMD by furnishing bank guarantee in format prescribed by
GTC of another tender and the bidder took the plea that bank guarantee
format of present tender was ambiguous.

28.5. Rejecting the claim of the bidder and upholding the decision of the
employer of rejection of bid for non-compliance of submitting the bank
guarantee in prescribed format, this Court in paras 31 to 38, 42 to 44, 47
to 49, 52, 55 and 56 has observed and held as under : (Central Coalfields
case [Central Coalfields Ltd. v. SLL-SML (Joint Venture Consortium),
(2016) 8 SCC 622 : (2016) 4 SCC (Civ) 106] , SCC pp. 632-36 & 638-
40)
“31. We were informed by the learned Attorney General that 9 of
the 11 bidders furnished a bank guarantee in the prescribed and
correct format. Under these circumstances, even after stretching
our credulity, it is extremely difficult to understand why JVC was
unable to access the prescribed format for the bank guarantee or
furnish a bank guarantee in the prescribed format when every
other bidder could do so or why it could not seek a clarification or
why it could not represent against any perceived ambiguity. The
objection and the conduct of JVC regarding the prescribed format
of the bank guarantee or a supposed ambiguity in NIT does not
appear to be fully above board.
32. The core issue in these appeals is not of judicial review of the
administrative action of CCL in adhering to the terms of NIT and
the GTC prescribed by it while dealing with bids furnished by
participants in the bidding process. The core issue is whether CCL
acted perversely enough in rejecting the bank guarantee of JVC on
the ground that it was not in the prescribed format, thereby calling
for judicial review by a constitutional court and interfering with
CCL's decision.
33. In Ramana Dayaram Shetty v. International Airport Authority
of India [Ramana Dayaram Shetty v. International Airport
Authority of India, (1979) 3 SCC 489] , this Court held that the
words used in a document are not superfluous or redundant but
must be given some meaning and weightage : (SCC p. 500, para 7)
Signature Not Verified
Signed by: RASHID KHAN
Signing time: 8/7/2026
11:04:26 AM

NEUTRAL CITATION NO. 2026:MPHC-GWL:22705
13 WA-2541-2026
‘7. … It is a well-settled rule of interpretation applicable

alike to documents as to statutes that, save for compelling
necessity, the Court should not be prompt to ascribe
superfluity to the language of a document ‘and should be
rather at the outset inclined to suppose every word
intended to have some effect or be of some use’. To reject
words as insensible should be the last resort of judicial
interpretation, for it is an elementary rule based on
common sense that no author of a formal document
intended to be acted upon by the others should be
presumed to use words without a meaning. The court
must, as far as possible, avoid a construction which would
render the words used by the author of the document
meaningless and futile or reduce to silence any part of the
document and make it altogether inapplicable.'
34. In Ramana Dayaram Shetty case [Ramana Dayaram Shetty v.
International Airport Authority of India, (1979) 3 SCC 489] , the
expression “registered IInd Class hotelier” was recognised as
being inapt and perhaps ungrammatical; nevertheless common
sense was not offended in describing a person running a registered
IInd grade hotel as a registered IInd class hotelier. Despite this
construction in its favour, Respondent 4 in that case were held to
be factually ineligible to participate in the bidding process.
35. It was further held that if others (such as the appellant in
Ramana Dayaram Shetty case [Ramana Dayaram Shetty v.
International Airport Authority of India, (1979) 3 SCC 489] ) were
aware that non-fulfilment of the eligibility condition of being a
registered IInd class hotelier would not be a bar for consideration,
they too would have submitted a tender, but were prevented from
doing so due to the eligibility condition, which was relaxed in the
case of Respondent 4. This resulted in unequal treatment in favour
of Respondent 4 — treatment that was constitutionally
impermissible. Expounding on this, it was held : (SCC p. 504,
para 10)
‘10. … It is indeed unthinkable that in a democracy
governed by the rule of law the executive Government or
Signature Not Verified
Signed by: RASHID KHAN
Signing time: 8/7/2026
11:04:26 AM

NEUTRAL CITATION NO. 2026:MPHC-GWL:22705
14 WA-2541-2026
any of its officers should possess arbitrary power over the
interests of the individual. Every action of the executive

Government must be informed with reason and should be
free from arbitrariness. That is the very essence of the rule
of law and its bare minimal requirement. And to the
application of this principle it makes no difference
whether the exercise of the power involves affectation of
some right or denial of some privilege.'
36. Applying this principle to the present appeals, other bidders
and those who had not bid could very well contend that if they had
known that the prescribed format of the bank guarantee was not
mandatory or that some other term(s) of NIT or GTC were not
mandatory for compliance, they too would have meaningfully
participated in the bidding process. In other words, by rearranging
the goalposts, they were denied the “privilege” of participation.
37. For JVC to say that its bank guarantee was in terms stricter
than the prescribed format is neither here nor there. It is not for
the employer or this Court to scrutinise every bank guarantee to
determine whether it is stricter than the prescribed format or less
rigorous. The fact is that a format was prescribed and there was no
reason not to adhere to it. The goalposts cannot be rearranged or
asked to be rearranged during the bidding process to affect the
right of some or deny a privilege to some.
38. In G.J. Fernandez v. State of Karnataka [G.J. Fernandez v.
State of Karnataka, (1990) 2 SCC 488] , both the principles laid
down in Ramana Dayaram Shetty [Ramana Dayaram Shetty v.
International Airport Authority of India, (1979) 3 SCC 489] were
reaffirmed. It was reaffirmed that the party issuing the tender (the
employer) “has the right to punctiliously and rigidly” enforce the
terms of the tender. If a party approaches a court for an order
restraining the employer from strict enforcement of the terms of
the tender, the court would decline to do so. It was also reaffirmed
that the employer could deviate from the terms and conditions of
the tender if the “changes affected all intending applicants alike
and were not objectionable”. Therefore, deviation from the terms
and conditions is permissible so long as the level playing field is
Signature Not Verified
Signed by: RASHID KHAN
Signing time: 8/7/2026
11:04:26 AM

NEUTRAL CITATION NO. 2026:MPHC-GWL:22705
15 WA-2541-2026
maintained and it does not result in any arbitrariness or
discrimination in Ramana Dayaram Shetty [Ramana Dayaram
Shetty v. International Airport Authority of India, (1979) 3 SCC
489] sense.

*
42. Unfortunately, this Court in Poddar Steel Corpn. v. Ganesh
Engg. Works [Poddar Steel Corpn. v. Ganesh Engg. Works, (1991)
3 SCC 273] did not at all advert to the privilege-of-participation
principle laid down in Ramana Dayaram Shetty [Ramana Dayaram
Shetty v. International Airport Authority of India, (1979) 3 SCC
489] and accepted in G.J. Fernandez [G.J. Fernandez v. State of
Karnataka, (1990) 2 SCC 488] . In other words, this Court did not
consider whether, as a result of the deviation, others could also
have become eligible to participate in the bidding process. This
principle was ignored in Poddar Steel [Poddar Steel Corpn. v.
Ganesh Engg. Works, (1991) 3 SCC 273] .
43. Continuing in the vein of accepting the inherent authority of an
employer to deviate from the terms and conditions of an NIT, and
reintroducing the privilege-of-participation principle and the level
playing field concept, this Court laid emphasis on the decision-
making process, particularly in respect of a commercial contract.
One of the more significant cases on the subject is the three-Judge
decision in Tata Cellular v. Union of India [Tata Cellular v. Union
of India, (1994) 6 SCC 651] which gave importance to the
lawfulness of a decision and not its soundness. If an administrative
decision, such as a deviation in the terms of NIT is not arbitrary,
irrational, unreasonable, mala fide or biased, the courts will not
judicially review the decision taken. Similarly, the courts will not
countenance interference with the decision at the behest of an
unsuccessful bidder in respect of a technical or procedural
violation. This was quite clearly stated by this Court (following
Tata Cellular [Tata Cellular v. Union of India, (1994) 6 SCC 651] )
in Jagdish Mandal v. State of Orissa [Jagdish Mandal v. State of
Orissa, (2007) 14 SCC 517] ] in the following words : (Jagdish
Mandal case [Jagdish Mandal v. State of Orissa, (2007) 14 SCC
517] , SCC p. 531, para 22)
Signature Not Verified
Signed by: RASHID KHAN
Signing time: 8/7/2026
11:04:26 AM

NEUTRAL CITATION NO. 2026:MPHC-GWL:22705
16 WA-2541-2026
‘22. Judicial review of administrative action is intended to

prevent arbitrariness, irrationality, unreasonableness, bias
and mala fides. Its purpose is to check whether choice or
decision is made “lawfully” and not to check whether
choice or decision is “sound”. When the power of judicial
review is invoked in matters relating to tenders or award
of contracts, certain special features should be borne in
mind. A contract is a commercial transaction. Evaluating
tenders and awarding contracts are essentially commercial
functions. Principles of equity and natural justice stay at a
distance. If the decision relating to award of contract is
bona fide and is in public interest, courts will not, in
exercise of power of judicial review, interfere even if a
procedural aberration or error in assessment or prejudice
to a tenderer, is made out. The power of judicial review
will not be permitted to be invoked to protect private
interest at the cost of public interest, or to decide
contractual disputes. The tenderer or contractor with a
grievance can always seek damages in a civil court.
Attempts by unsuccessful tenderers with imaginary
grievances, wounded pride and business rivalry, to make
mountains out of molehills of some technical/procedural
violation or some prejudice to self, and persuade courts to
interfere by exercising power of judicial review, should be
resisted. Such interferences, either interim or final, may
hold up public works for years, or delay relief and succour
to thousands and millions and may increase the project
cost manifold.’
This Court then laid down the questions that ought to be asked in
such a situation. It was said : (Jagdish Mandal case [Jagdish
Mandal v. State of Orissa, (2007) 14 SCC 517] , SCC p. 531, para
22)
‘22. … Therefore, a court before interfering in tender or
contractual matters in exercise of power of judicial
review, should pose to itself the following questions:
(i) Whether the process adopted or decision made by the
Signature Not Verified
Signed by: RASHID KHAN
Signing time: 8/7/2026
11:04:26 AM

NEUTRAL CITATION NO. 2026:MPHC-GWL:22705
17 WA-2541-2026
authority is mala fide or intended to favour someone;

or
Whether the process adopted or decision made is so
arbitrary and irrational that the court can say:‘the decision
is such that no responsible authority acting reasonably and
in accordance with relevant law could have reached’;
(ii) Whether public interest is affected.
If the answers are in the negative, there should be no
interference under Article 226.’
44. On asking these questions in the present appeals, it is more
than apparent that the decision taken by CCL to adhere to the
terms and conditions of NIT and the GTC was certainly not
irrational in any manner whatsoever or intended to favour anyone.
The decision was lawful and not unsound.
*
47. The result of this discussion is that the issue of the acceptance
or rejection of a bid or a bidder should be looked at not only from
the point of view of the unsuccessful party but also from the point
of view of the employer. As held in Ramana Dayaram Shetty
[Ramana Dayaram Shetty v. International Airport Authority of
India, (1979) 3 SCC 489] the terms of NIT cannot be ignored as
being redundant or superfluous. They must be given a meaning
and the necessary significance. As pointed out in Tata Cellular
[Tata Cellular v. Union of India, (1994) 6 SCC 651] there must be
judicial restraint in interfering with administrative action.
Ordinarily, the soundness of the decision taken by the employer
ought not to be questioned but the decision-making process can
certainly be subject to judicial review. The soundness of the
decision may be questioned if it is irrational or mala fide or
intended to favour someone or a decision ‘that no responsible
authority acting reasonably and in accordance with relevant law
could have reached’ as held in Jagdish Mandal [Jagdish Mandal v.
State of Orissa, (2007) 14 SCC 517] followed in Michigan Rubber
Signature Not Verified
Signed by: RASHID KHAN
Signing time: 8/7/2026
11:04:26 AM

NEUTRAL CITATION NO. 2026:MPHC-GWL:22705
18 WA-2541-2026
[Michigan Rubber (India) Ltd. v. State of Karnataka, (2012) 8
SCC 216] .

48. Therefore, whether a term of NIT is essential or not is a
decision taken by the employer which should be respected. Even if
the term is essential, the employer has the inherent authority to
deviate from it provided the deviation is made applicable to all
bidders and potential bidders as held in Ramana Dayaram Shetty
[Ramana Dayaram Shetty v. International Airport Authority of
India, (1979) 3 SCC 489]. However, if the term is held by the
employer to be ancillary or subsidiary, even that decision should
be respected. The lawfulness of that decision can be questioned on
very limited grounds, as mentioned in the various decisions
discussed above, but the soundness of the decision cannot be
questioned, otherwise this Court would be taking over the function
of the tender issuing authority, which it cannot.
49. Again, looked at from the point of view of the employer if the
courts take over the decision-making function of the employer and
make a distinction between essential and non-essential terms
contrary to the intention of the employer and thereby rewrite the
arrangement, it could lead to all sorts of problems including the
one that we are grappling with. For example, the GTC that we are
concerned with specifically states in Clause 15.2 that ‘Any bid not
accompanied by an acceptable bid Security/EMD shall be rejected
by the employer as non-responsive’. Surely, CCL ex facie intended
this term to be mandatory, yet the High Court held [SLL-SML
(Joint Venture Consortium) v. Central Coalfields Ltd., 2015 SCC
OnLine Jhar 4819] that the bank guarantee in a format not
prescribed by it ought to be accepted since that requirement was a
non-essential term of the GTC. From the point of view of CCL,
the GTC has been impermissibly rewritten by the High Court.
*
52. There is a wholesome principle that the courts have been
following for a very long time and which was articulated in Nazir
Ahmad v. King Emperor [Nazir Ahmad v. King Emperor, 1936
SCC OnLine PC 41 : AIR 1936 PC 253 (2)] , namely : (SCC
Signature Not Verified
Signed by: RASHID KHAN
Signing time: 8/7/2026
11:04:26 AM

NEUTRAL CITATION NO. 2026:MPHC-GWL:22705
19 WA-2541-2026
OnLine PC)

‘… where a power is given to do a certain thing in a
certain way the thing must be done in that way or not at
all. Other methods of performance are necessarily
forbidden.'
There is no valid reason to give up this salutary principle or not to
apply it mutatis mutandis to bid documents. This principle
deserves to be applied in contractual disputes, particularly in
commercial contracts or bids leading up to commercial contracts,
where there is stiff competition. It must follow from the
application of the principle laid down in Nazir Ahmad [Nazir
Ahmad v. King Emperor, 1936 SCC OnLine PC 41 : AIR 1936 PC
253 (2)] that if the employer prescribes a particular format of the
bank guarantee to be furnished, then a bidder ought to submit the
bank guarantee in that particular format only and not in any other
format. However, as mentioned above, there is no inflexibility in
this regard and an employer could deviate from the terms of the
bid document but only within the parameters mentioned above.
*
55. On the basis of the available case law, we are of the view that
since CCL had not relaxed or deviated from the requirement of
furnishing a bank guarantee in the prescribed format, insofar as the
present appeals are concerned every bidder was obliged to adhere
to the prescribed format of the bank guarantee. Consequently, the
failure of JVC to furnish the bank guarantee in the prescribed
format was sufficient reason for CCL to reject its bid.
56. There is nothing to indicate that the process by which the
decision was taken by CCL that the bank guarantee furnished by
JVC ought to be rejected was flawed in any manner whatsoever.
Similarly, there is nothing to indicate that the decision taken by
CCL to reject the bank guarantee furnished by JVC and to adhere
to the requirements of NIT and the GTC was arbitrary or
unreasonable or perverse in any manner whatsoever.”
(emphasis in original)
Signature Not Verified
Signed by: RASHID KHAN
Signing time: 8/7/2026
11:04:26 AM

NEUTRAL CITATION NO. 2026:MPHC-GWL:22705
20 WA-2541-2026
28.6. In Maa Binda Express Carrier v. North-East Frontier Railway [Maa
Binda Express Carrier v. North-East Frontier Railway, (2014) 3 SCC 760]
, this Court had an occasion to consider the scope of judicial review in the
matters relating to award of contracts by the State and its
instrumentalities. In paras 8 to 10 this Court has observed and held as
under : (SCC pp. 764-65)

“8. The scope of judicial review in matters relating to award of
contracts by the State and its instrumentalities is settled by a long
line of decisions of this Court. While these decisions clearly
recognise that power exercised by the Government and its
instrumentalities in regard to allotment of contract is subject to
judicial review at the instance of an aggrieved party, submission of
a tender in response to a notice inviting such tenders is no more
than making an offer which the State or its agencies are under no
obligation to accept. The bidders participating in the tender
process cannot, therefore, insist that their tenders should be
accepted simply because a given tender is the highest or lowest
depending upon whether the contract is for sale of public property
or for execution of works on behalf of the Government. All that
participating bidders are entitled to is a fair, equal and non-
discriminatory treatment in the matter of evaluation of their
tenders. It is also fairly well settled that award of a contract is
essentially a commercial transaction which must be determined on
the basis of consideration that are relevant to such commercial
decision. This implies that terms subject to which tenders are
invited are not open to the judicial scrutiny unless it is found that
the same have been tailor-made to benefit any particular tenderer
or class of tenderers. So also, the authority inviting tenders can
enter into negotiations or grant relaxation for bona fide and cogent
reasons provided such relaxation is permissible under the terms
governing the tender process.
9. Suffice it to say that in the matter of award of contracts the
Government and its agencies have to act reasonably and fairly at
all points of time. To that extent the tenderer has an enforceable
right in the court which is competent to examine whether the
aggrieved party has been treated unfairly or discriminated against
to the detriment of public interest. (See Meerut Development
Signature Not Verified
Signed by: RASHID KHAN
Signing time: 8/7/2026
11:04:26 AM

NEUTRAL CITATION NO. 2026:MPHC-GWL:22705
21 WA-2541-2026
Authority v. Assn. of Management Studies [Meerut Development
Authority v. Assn. of Management Studies, (2009) 6 SCC 171 :
(2009) 2 SCC (Civ) 803] and Air India Ltd. v. Cochin
International Airport Ltd. [Air India Ltd. v. Cochin International
Airport Ltd., (2000) 2 SCC 617] )

10. The scope of judicial review in contractual matters was further
examined by this Court in Tata Cellular v. Union of India [Tata
Cellular v. Union of India, (1994) 6 SCC 651] , Raunaq
International Ltd. case [Raunaq International Ltd. v. I.V.R.
Construction Ltd., (1999) 1 SCC 492] and in Jagdish Mandal v.
State of Orissa [Jagdish Mandal v. State of Orissa, (2007) 14 SCC
517] besides several other decisions to which we need not refer.”
29. Thus, from the aforesaid decisions, it can be seen that a court before
interfering in a contract matter in exercise of powers of judicial review
should pose to itself the following questions:
(i) Whether the process adopted or decision made by the authority
is mala fide or intended to favour someone; or whether the process
adopted or decision made is so arbitrary and irrational that the
court can say:“the decision is such that no responsible authority
acting reasonably and in accordance with relevant law could have
reached”? And
(ii) Whether the public interest is affected?
If the answers to the above questions are in the negative, then there
should be no interference under Article 226."
15. The Supreme Court in the case of Uflex Limited Vs. Government
of Tamil Nadu and others reported in (2022) 1 SCC 165 has held as under:-
"6. The burgeoning litigation in this field and the same being carried to
this Court in most matters was the cause we set forth an epilogue in
Caretel Infotech Ltd. v. Hindustan Petroleum Corpn. Ltd. [Caretel Infotech
Ltd. v. Hindustan Petroleum Corpn. Ltd., (2019) 14 SCC 81] Even if it
amounts to repetition, we believe that it needs to be emphasised in view
Signature Not Verified
Signed by: RASHID KHAN
Signing time: 8/7/2026
11:04:26 AM

NEUTRAL CITATION NO. 2026:MPHC-GWL:22705
22 WA-2541-2026
of the controversy arising in the present case to appreciate the contours
within which the factual matrix of the present case has to be analysed and
tested : (SCC pp. 92-95, paras 37-43)

“37. We consider it appropriate to make certain observations in the
context of the nature of dispute which is before us. Normally
parties would be governed by their contracts and the tender terms,
and really no writ would be maintainable under Article 226 of the
Constitution of India. In view of Government and public sector
enterprises venturing into economic activities, this Court found it
appropriate to build in certain checks and balances of fairness in
procedure. It is this approach which has given rise to scrutiny of
tenders in writ proceedings under Article 226 of the Constitution of
India. It, however, appears that the window has been opened too
wide as almost every small or big tender is now sought to be
challenged in writ proceedings almost as a matter of routine. This
in turn, affects the efficacy of commercial activities of the public
sectors, which may be in competition with the private sector. This
could hardly have been the objective in mind. An unnecessary,
close scrutiny of minute details, contrary to the view of the
tendering authority, makes awarding of contracts by Government
and Public Sectors a cumbersome exercise, with long-drawn out
litigation at the threshold. The private sector is competing often in
the same field. Promptness and efficiency levels in private
contracts, thus, often tend to make the tenders of the public sector
a non-competitive exercise. This works to a great disadvantage to
the Government and the public sector.
38. In Afcons Infrastructure Ltd. v. Nagpur Metro Rail Corpn. Ltd.
[Afcons Infrastructure Ltd. v. Nagpur Metro Rail Corpn. Ltd.,
(2016) 16 SCC 818] , this Court has expounded further on this
aspect, while observing that the decision-making process in
accepting or rejecting the bid should not be interfered with.
Interference is permissible only if the decision-making process is
arbitrary or irrational to an extent that no responsible authority,
acting reasonably and in accordance with law, could have reached
such a decision. It has been cautioned that constitutional courts are
expected to exercise restraint in interfering with the administrative
decision and ought not to substitute their view for that of the
Signature Not Verified
Signed by: RASHID KHAN
Signing time: 8/7/2026
11:04:26 AM

NEUTRAL CITATION NO. 2026:MPHC-GWL:22705
23 WA-2541-2026
administrative authority. Mere disagreement with the decision-
making process would not suffice.

39. Another aspect emphasised is that the author of the document
is the best person to understand and appreciate its requirements. In
the facts of the present case, the view, on interpreting the tender
documents, of Respondent 1 must prevail. Respondent 1 itself,
appreciative of the wording of Clause 20 and the format, has taken
a considered view. Respondent 3 cannot compel its own
interpretation of the contract to be thrust on Respondent 1, or ask
the Court to compel Respondent 1 to accept that interpretation. In
fact, the Court went on to observe in the aforesaid judgment that it
is possible that the author of the tender may give an interpretation
that is not acceptable to the constitutional court, but that itself
would not be a reason for interfering with the interpretation given.
We reproduce the observations in this behalf as under : (Afcons
Infrastructure case [Afcons Infrastructure Ltd. v. Nagpur Metro
Rail Corpn. Ltd., (2016) 16 SCC 818] , SCC p. 825, para 15)
‘15. We may add that the owner or the employer of a
project, having authored the tender documents, is the best
person to understand and appreciate its requirements and
interpret its documents. The constitutional courts must
defer to this understanding and appreciation of the tender
documents, unless there are mala fides or perversity in the
understanding or appreciation or in the application of the
terms of the tender conditions. It is possible that the
owner or employer of a project may give an interpretation
to the tender documents that is not acceptable to the
constitutional courts but that by itself is not a reason for
interfering with the interpretation given.'
40. We may also refer to the judgment of this Court in Nabha
Power Ltd. v. Punjab State Power Corpn. Ltd. [Nabha Power Ltd.
v. Punjab State Power Corpn. Ltd., (2018) 11 SCC 508 : (2018) 5
SCC (Civ) 1] authored by one of us (Sanjay Kishan Kaul, J.). The
legal principles for interpretation of commercial contracts have
been discussed. In the said judgment, a reference was made to the
observations of the Privy Council in Attorney General of Belize v.
Signature Not Verified
Signed by: RASHID KHAN
Signing time: 8/7/2026
11:04:26 AM

NEUTRAL CITATION NO. 2026:MPHC-GWL:22705
24 WA-2541-2026
Belize Telecom Ltd. [Attorney General of Belize v. Belize
Telecom Ltd., 2009 Bus LR 1316 : (2009) 1 WLR 1988 (PC)] as
under : (Nabha Power case [Nabha Power Ltd. v. Punjab State
Power Corpn. Ltd., (2018) 11 SCC 508 : (2018) 5 SCC (Civ) 1] ,
SCC pp. 534-36, para 45)

‘45. … “16. Before discussing in greater detail the
reasoning of the Court of Appeal, the Board will make
some general observations about the process of
implication. The court has no power to improve upon the
instrument which it is called upon to construe, whether it
be a contract, a statute or articles of association. It cannot
introduce terms to make it fairer or more reasonable. It is
concerned only to discover what the instrument means.
However, that meaning is not necessarily or always what
the authors or parties to the document would have
intended. …
*
19. … In Trollope & Colls Ltd. v. North West
Metropolitan Regl. Hospital Board [Trollope & Colls Ltd.
v. North West Metropolitan Regl. Hospital Board, (1973)
1 WLR 601 (HL)] Lord Pearson, with whom Lord Guest
and Lord Diplock agreed, said : (WLR p. 609)
‘… the court does not make a contract for the
parties. The court will not even improve the
contract which the parties have made for
themselves, however desirable the improvement
might be. The court's function is to interpret and
apply the contract which the parties have made
for themselves. If the express terms are perfectly
clear and free from ambiguity, there is no choice
to be made between different possible meanings
: the clear terms must be applied even if the
court thinks some other terms would have been
more suitable. An unexpressed term can be
implied if and only if the court finds that the
parties must have intended that term to form part
Signature Not Verified
Signed by: RASHID KHAN
Signing time: 8/7/2026
11:04:26 AM

NEUTRAL CITATION NO. 2026:MPHC-GWL:22705
25 WA-2541-2026
of their contract : it is not enough for the court to

find that such a term would have been adopted
by the parties as reasonable men if it had been
suggested to them : it must have been a term that
went without saying, a term necessary to give
business efficacy to the contract, a term which,
though tacit, formed part of the contract which
the parties made for themselves.’ ” (Attorney
General of Belize case [Attorney General of
Belize v. Belize Telecom Ltd., 2009 Bus LR
1316 : (2009) 1 WLR 1988 (PC)] , WLR pp.
1993-94, paras 16 & 19)’
(emphasis in original)
41. Nabha Power Ltd. [Nabha Power Ltd. v. Punjab State Power
Corpn. Ltd., (2018) 11 SCC 508 : (2018) 5 SCC (Civ) 1] also took
note of the earlier judgment of this Court in Satya Jain v. Anis
Ahmed Rushdie [Satya Jain v. Anis Ahmed Rushdie, (2013) 8
SCC 131 : (2013) 3 SCC (Civ) 738] , which discussed the
principle of business efficacy as proposed by Bowen, L.J. in
Moorcock [Moorcock, (1889) LR 14 PD 64 (CA)] . It has been
elucidated that this test requires that terms can be implied only if it
is necessary to give business efficacy to the contract to avoid
failure of the contract and only the bare minimum of implication is
to be there to achieve this goal. Thus, if the contract makes
business sense without the implication of terms, the courts will not
imply the same.
42. The judgment in Nabha Power Ltd. [Nabha Power Ltd. v.
Punjab State Power Corpn. Ltd., (2018) 11 SCC 508 : (2018) 5
SCC (Civ) 1] concluded with the following observations in para
72 : (SCC p. 546)
‘72. We may, however, in the end, extend a word of
caution. It should certainly not be an endeavour of
commercial courts to look to implied terms of contract. In
the current day and age, making of contracts is a matter of
high technical expertise with legal brains from all sides
Signature Not Verified
Signed by: RASHID KHAN
Signing time: 8/7/2026
11:04:26 AM

NEUTRAL CITATION NO. 2026:MPHC-GWL:22705
26 WA-2541-2026
involved in the process of drafting a contract. It is even
preceded by opportunities of seeking clarifications and

doubts so that the parties know what they are getting into.
Thus, normally a contract should be read as it reads, as per
its express terms. The implied terms is a concept, which is
necessitated only when the Penta test referred to aforesaid
comes into play. There has to be a strict necessity for it. In
the present case, we have really only read the contract in
the manner it reads. We have not really read into it any
“implied term” but from the collection of clauses, come to
a conclusion as to what the contract says. The formula for
energy charges, to our mind, was quite clear. We have
only expounded it in accordance to its natural grammatical
contour, keeping in mind the nature of the contract.’
43. We have considered it appropriate to, once again, emphasise
the aforesaid aspects, especially in the context of endeavours of
courts to give their own interpretation to contracts, more
specifically tender terms, at the behest of a third party competing
for the tender, rather than what is propounded by the party framing
the tender. The object cannot be that in every contract, where some
parties would lose out, they should get the opportunity to
somehow pick holes, to disqualify the successful parties, on
grounds on which even the party floating the tender finds no
merit.”
7. It may also be pertinent to note the principles elucidated in Tata
Cellular v. Union of India [Tata Cellular v. Union of India, (1994) 6 SCC
651] : (SCC pp. 687-88, para 94)
“94. The principles deducible from the above are:
(1) The modern trend points to judicial restraint in administrative
action.
(2) The court does not sit as a court of appeal but merely reviews
the manner in which the decision was made.
(3) The court does not have the expertise to correct the
Signature Not Verified
Signed by: RASHID KHAN
Signing time: 8/7/2026
11:04:26 AM

NEUTRAL CITATION NO. 2026:MPHC-GWL:22705
27 WA-2541-2026
administrative decision. If a review of the administrative decision
is permitted it will be substituting its own decision, without the
necessary expertise which itself may be fallible.

(4) The terms of the invitation to tender cannot be open to judicial
scrutiny because the invitation to tender is in the realm of contract.
Normally speaking, the decision to accept the tender or award the
contract is reached by process of negotiations through several
tiers. More often than not, such decisions are made qualitatively
by experts.
(5) The Government must have freedom of contract. In other
words, a fair play in the joints is a necessary concomitant for an
administrative body functioning in an administrative sphere or
quasi-administrative sphere. However, the decision must not only
be tested by the application of Wednesbury principle of
reasonableness (including its other facts pointed out above) but
must be free from arbitrariness not affected by bias or actuated by
mala fides.
(6) Quashing decisions may impose heavy administrative burden
on the administration and lead to increased and unbudgeted
expenditure.”
(emphasis in original)
16. This Court can only look into the decision making process and
cannot look into the merits of the case.
1 7 . Once the respondent/petitioner herself submitted her bid of
Rs.3,38,5,555/- and she never made any application for withdrawal of her bid
prior to the opening of bid, then this Court cannot interfere with the amount
which was submitted by respondent/petitioner as her bid. It falls within the
exclusive jurisdiction of employer or the institution inviting tenders and does
not fall within with the jurisdiction of the Courts. Furthermore, in order to
maintain uniformity amongst all bidders, the principle of strict compliance
Signature Not Verified
Signed by: RASHID KHAN
Signing time: 8/7/2026
11:04:26 AM

NEUTRAL CITATION NO. 2026:MPHC-GWL:22705
28 WA-2541-2026
must be allowed and Rules of Game cannot be changed in the midway.

18. So far as the observation made in the paragraph 12 of impugned
order are concerned, it is suffice to mention here that the appellant shall take
it as a suggestion and would think as to whether in future they should make a
provision for correction of mistake(s) prior to the opening of the bid or not,
because, in various advertisements, primarily for recruitment, two dates are
given i.e. last date for submission of application and last date for correction
of mistake which might have crept in the online applications.
19. Since the learned Single Judge has exceeded his jurisdiction in a
contractual matter by holding that excuse given by respondent/petitioner was
bonafide and she had committed a mistake in a good faith, the said order
cannot be given the strength of judicial approval.
20. Accordingly, order dated 27.04.2026 passed by Learned Single
Judge in Writ Petition No.33444/2025 is hereby set aside. Writ Appeal
succeeds and is hereby allowed.
No order as to costs.
(G. S. AHLUWALIA)
(ANURADHA SHUKLA)
JUDGE
JUDGE
Rashid

Signature Not Verified
Signed by: RASHID KHAN
Signing time: 8/7/2026
11:04:26 AM