Sri Pranab Pathak vs The State Of Assam And 5 Ors

Court
Gauhati High Court

Page No.# 1/13
GAHC010024832026

2026:GAU-AS:16938
THE GAUHATI HIGH COURT
(HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH)
Case No. : WP(C)/807/2026
SRI PRANAB PATHAK
SON OF PRAMOD PATHAK, RESIDENT OF VILLAGE- DUMURIA, P.O.-
BHOUKAMARI, P.S.- BAJALI, DIST.- BARPETA, ASSAM.PIN-781325.
VERSUS
THE STATE OF ASSAM AND 5 ORS
REPRESENTED BY THE COMMISSIONER AND SPECIAL SECRETARY TO
THE GOVERNMENT OF ASSAM, PUBLIC WORKS DEPARTMENT (BUILDING
AND NH), DISPUR, GUWAHATI- 6
2:THE CHIEF ENGINEER
PWD (BUILDING)
ASSAM
CHANDMARI
GUWAHATI- 3
3:BODOLAND TERRITORIAL COUNCIL
REPRESENTED BY THE PRINCIPAL SECRETARY TO THE BODOLAND
TERRITORIAL COUNCIL
KOKRAJHAR.
4:SECRETARY DEPARTMENT OF INFRASTRUCTURE DEVELOPMENT AND
BUILDING ACTIVITY (IBA)
BODOLAND TERRITORIAL COUNCIL
KOKRAJHAR.
5:THE ADDITIONAL CHIEF ENGINEER -CUM -DIRECTOR
PWD
BODOLAND TERRITORIAL COUNCIL
KOKRAJHAR.

Page No.# 2/13
6:THE EXECUTIVE ENGINEER

PWD
(BLDG AND NH)
UDALGURI DISTRICT AND BAKSA DISTRICT
TERRITORIAL BUILDING DIVISION
UDALGURI

BEFORE
HONOURABLE MR. JUSTICE DEVASHIS BARUAH
For the Petitioner(s) : Mr. U.K. Das, Advocate

For the Respondent(s) : Ms. N. Choudhury, Standing Counsel
Mr. M. Bhuyan, Standing Counsel


· Date on which Judgment was reserved : NA
· Date of Pronouncement of Judgment : 17.11.2026
· Whether the pronouncement is of
the Operative Part of the Judgment : NA

· Whether the full Judgment has been
Pronounced : Yes
JUDGMENT AND ORDER (ORAL)
Heard Mr. U.K. Das, the learned counsel for the Petitioner. Ms.
N. Choudhury, the learned Standing Counsel, appears on behalf of
the BTC and Mr. M. Bhuyan, the learned Standing Counsel, appears
on behalf of the PWD.
2. The present writ petition has been filed assailing the

Page No.# 3/13
communication dated 17.01.2026 issued by the Respondent No. 6
cancelling the work awarded to the Petitioner for construction of
the Community Hall at DakhsinBijni Degree College, Ananda Bazar,
Baksa, TN_18_12.
BRIEF FACTS
3. The brief facts of the instant case as they emerge from a
perusal of the materials on record are that the Respondent No. 5
had issued a Notice Inviting Tender dated 23.07.2025, inviting
fresh bids on behalf of the Governor of Assam for 14 Nos. of works
under various Executive Engineers.
4. Amongst the various works mentioned in the Notice Inviting
Tender, one of such works was for construction of the Community
Hall at DakhsinBijni Degree College, Ananda Bazar, Baksa
(hereinafter referred to as the “contractual work in question”).
5. The Petitioner, being interested, submitted his bid and was
issued the Letter of Acceptance on 22.08.2025 at a contract price
of Rs. 94,99,870.37p. The Petitioner was asked to submit the
performance security in terms of Para 34.1 of the Instructions to
the Bidders for an amount of Rs. 1,90,000/- within 21 days of the
receipt of the Letter of Acceptance, valid up to 28 days from the

Page No.# 4/13
date of expiry of the defect liability period, i.e., up to 22.03.2027,
and to sign the contract.
6. The Petitioner accordingly submitted the performance security
and was issued the Notice to Proceed with the work on
26.08.2025. The Petitioner also entered into a contractual
agreement with the Respondent No. 5.
7. Clause 1 of the General Conditions of the Contract defined the
term "Employer" to be the Additional Chief Engineer-cum-Director,
PWD, BTC, Kokrajhar. The term "Engineer" was also defined to be
the concerned Executive Engineer, PWD, Udalguri District &Baksa
District Territorial Building Division, Udalguri, Assam, who is
responsible for supervising the contractor, administering the
contract, certifying payments due to the contractor, issuing and
valuing variations to the contract, awarding extensions of time and
valuing the compensation events.
8. Clause 60 of the General Conditions of the Contract is the
termination Clause. In terms of Clause 60.1, the Employer or the
Contractor was given the liberty to terminate the contract if the
other party causes a fundamental breach of the contract.
9. It is alleged by the Petitioner that all of a sudden, while the

Page No.# 5/13
Petitioner was carrying out the work, the Respondent No. 6 issued
the impugned order dated 17.01.2026 whereby the contract in
question was cancelled and the Petitioner was asked to leave the
site safe and secure. It is the further case of the Petitioner that
immediately thereafter, a Notice Inviting Tender was issued in
respect of the said work on 02.02.2026. The Petitioner, being
aggrieved by the cancellation of the contract as well as issuance of
the Notice Inviting Tender, has approached this Court by filing the
present writ petition.
10. The record reveals that the learned Coordinate Bench of this
Court vide order dated 27.02.2026 issued notice and in the interim
stayed the bidding process initiated in respect of the same
contractual work, directing that the tender process shall not be
finalized without the leave of the Court.
11. The records reveal that an affidavit-in-opposition was filed by
the Respondent No. 6 wherein it was alleged that the Petitioner
committed a fundamental breach of the contract by executing sub-
standard work without following the proper specifications and
drawings. It mentioned that the Petitioner was duly reminded by
the Assistant Executive Engineer, Baksa vide communications dated
06.11.2025 and 22.12.2025. In spite of that, the Petitioner did not

Page No.# 6/13
rectify the defects and continued to progress further. The
Respondent No. 6 further stated in the said affidavit that the
Respondent No. 5 had duly authorized the Respondent No. 6 to
cancel the contract and it is under such circumstances that the
contract in question was cancelled on 17.01.2026 vide the
impugned communication.
12. An affidavit-in-reply was also filed by the Petitioner wherein it
was contended that the communications referred to in the
affidavit-in-opposition dated 06.11.2025 and 22.12.2025 allegedly
issued by the Assistant Executive Engineer, Baksa District Territorial
Building Sub-Division, Barama were never served upon the
Petitioner. It was only after the filing of the present writ petition
that the Petitioner was asked to collect those two communications.
13. This Court heard the present writ petition on 09.10.2026 and,
on that date, taking into consideration the respective pleadings,
enquired with the learned counsel appearing on behalf of the
Petitioner as to whether the Petitioner would be able to carry out
the work in question at the same rate at which he had quoted.
Paragraph Nos. 2, 3, and 4 of the order dated 09.10.2026, being
relevant, are reproduced hereunder:
“ 2. Mr. BC Musahary, the learned Standing Counsel BTC has produced two

Page No.# 7/13
documents dated 06.11.2025 and 22.12.2025 and it is stated by the learned
Standing Counsel that these documents were received by the Petitioner on
07.11.2025 and 23.12.2025 respectively and have put the initials as his signatures.
3. The learned counsel appearing on behalf of the Petitioner referring to the
affidavit-in-reply submitted that these documents were served only after the writ
petition has been filed. However, during the course of the hearing, this Court
enquired with the learned counsel for the Petitioner as to whether it is feasible for
the Petitioner now to carry out the work at the same rate, taking into account that
the period of the contract was for 6(six) months and originally when the notice to
proceed was issued i.e. on 26.08.2025, the period of 6(six) months would have
elapsed sometime in the month of February, 2026 and as on date when the matter
is being taken up for disposal, it is more than a year from the date of initial
issuance of notice to proceed.
4. Further to that, this Court also enquired with the learned counsel for the parties
as to whether the writ petition would be maintainable in the present facts and
circumstances or a suit for breach of contract would be the proper remedy.”
SUBMISSIONS MADE BY THE LEARNED COUNSEL FOR THE
PARTIES
14. Mr. U.K. Das, the learned counsel appearing on behalf of the
Petitioner submitted that pursuant to the order passed by this
Court on 09.10.2026, he had made necessary enquiries with the
Petitioner, who had duly instructed him to apprise this Court that
the Petitioner was still willing to carry out the work at the same
rate at which the contract was awarded to him.

Page No.# 8/13
15. The learned counsel appearing on behalf of the Petitioner
submitted and contended that the impugned communication dated
17.01.2026 was issued by an authority who had no jurisdiction.
The learned counsel drew the attention of this Court to the
definition Clause contained in the General Conditions of the
Contract, wherein the "Employer" has been defined to be the
Additional Chief Engineer-cum-Director, whereas the "Engineer"
has been defined to be the Executive Engineer of the concerned
Territorial Division. The learned counsel, further referring to Clause
60.1 of the General Conditions of the Contract, submitted that the
power to terminate in terms of Clause 60.1 of the General
Conditions of the Contract was only available to the Employer as
well as to the Contractor. The Engineer had no authority to cancel
or terminate the contract.
16. The learned counsel for the Petitioner submitted that the
Petitioner was duly carrying out the work in terms of the drawings
and the specifications and as such, the action on the part of the
Respondent Authorities to cancel the contract is nothing but a case
of malice in law and malice in fact.
17. Per contra, Ms. N. Choudhury, the learned Standing Counsel
for the BTC submitted that the contract in question was for a

Page No.# 9/13
period of six months from the date of issuance of the letter to
proceed with the work. The letter to proceed with the work was
issued on 26.08.2025. However, the work which was carried out by
the Petitioner was minimal. In addition to that, the learned
Standing Counsel for the BTC submitted that drawings and
specifications were provided to the Petitioner. However, the
Petitioner not only did not carry out the work in accordance with
the drawings and specifications, but also did not take effective
steps to rectify the deficiencies pointed out in the two
communications issued by the Assistant Executive Engineer.
18. The learned Standing Counsel for the BTC submitted that the
records would clearly show that the Additional Chief Engineer-cum-
Director, i.e., the Respondent No. 5, had delegated the authority to
the Respondent No. 6 to cancel the contract for committing a
fundamental breach of the terms of the contract.
19. Rejoining to his earlier submissions, the learned counsel for
the Petitioner, however, submitted that these communications
dated 06.11.2025 and 22.12.2025 said to have been issued by the
Assistant Executive Engineer are documents which came into
existence post the filing of the writ petition, inasmuch as the
Petitioner was asked to collect these documents after the issuance

Page No.# 10/13
of the impugned communication dated 17.01.2026. The learned
counsel further submitted that in the instant case, the question of
delegation of the power, as contended by the learned Standing
Counsel for the BTC, does not arise, inasmuch as the General
Conditions of Contract categorically stipulate delegation in Clause
5. However, such power of delegation is conferred only upon the
Engineer, who may, after notifying the Contractor, delegate his
duties and responsibilities to other people, except to the
Adjudicator, and may cancel any delegation after notifying the
Contractor. The learned counsel, therefore, submitted that when
the contractual terms categorically contain a Clause for delegation
and do not mention that the Employer can delegate his powers to
the Engineer, there cannot be any such delegation.
ANALYSIS AND DETERMINATION
20. This Court has heard the learned counsel appearing on behalf
of the parties and has given anxious consideration to the
respective submissions.
21. The materials on record, upon being perused, categorically
show that a contract was entered into by and between the
Petitioner and the Respondent No. 5 as the “Contractor” and

Page No.# 11/13
“Employer” respectively.
22. The General Conditions of the Contract, more particularly
Clause 1, defines the terms "Employer" as well as the "Engineer."
Clause 60.1 of the General Conditions of the Contract only
empowers the Employer or the Contractor to terminate the
contract, if the other party commits a fundamental breach of the
terms and conditions of the contract.
23. In the backdrop of the above, a perusal of the impugned
communication dated 17.01.2026 would show that the Respondent
No. 6 has cancelled the contract in question.
24. The concept of cancelling a contract does not arise once the
contract was validly entered into. Cancellation of a contract in the
legal sense means annulling the contract. On the other hand, when
a contract was validly entered into and any of the parties commits
a breach, the contract can be terminated. In the instant case, from
a perusal of the records and even the pleadings of the
Respondents, it is apparent that the contract in question was
always construed to be valid. Under such circumstances, to end the
contract, the contract had to be terminated.
25. Under such circumstances, even though the impugned

Page No.# 12/13
communication stipulates that the contract in question was
cancelled, in actuality, the contract in question was terminated.
26. Clause 60.1 of the General Conditions of the Contract only
empowered the Employer or the Contractor to terminate the
contract. The Engineer was not authorized to terminate the
contract. Under such circumstances, the communication dated
17.01.2026 issued by the Respondent No. 6, who was the Engineer,
thereby cancelling (actually terminating) the contract, is without
authority and jurisdiction. Consequently, the impugned
communication dated 17.01.2026 cannot be sustained in law.
27. It is the further opinion of this Court that if the impugned
communication dated 17.01.2026 cannot be sustained in law, the
consequential action of issuance of the fresh Notice Inviting Tender
dated 02.02.2026 is also required to be interfered with inasmuch
as the interference with the impugned communication dated
17.01.2026 results in reviving the contract between the Petitioner
and the Respondents.
28. Accordingly, the instant writ petition stands disposed of with
the following observations and directions:
(i) The impugned communication dated 17.01.2026 issued

Page No.# 13/13
by the Respondent No. 6 is without jurisdiction and authority.
Accordingly, the same is set aside and quashed.
(ii) The impugned Notice Inviting Tender dated 02.02.2026
issued by the Respondent No. 5 in respect of the same
contractual work is set aside and quashed.
(iii) It is observed that the setting aside of the impugned
communication dated 17.01.2026 shall not affect the powers
of the Employer to take such course of action as is permissible
as per the terms and conditions of the contractual agreement.
(iv) No costs.

JUDGE