M/S AROHI ELEVATORS PVT. LTD., THROUGH ITS DIRECTOR, BAJRANG BAHADUR SINGH vs THE STEEL AUTHORITY OF INDIA LTD., THROUGH ITS CHAIRMAN-CUM-MANAGING DIRECTOR
- Court
- Jharkhand High Court
- Case type
- WRIT PETITIONS
- Decided on
- 07-04-2026
<div> <br /> <br /> <br /> ( 2026:JHHC:9725-DB ) <br /> <br /> <b>IN THE HIGH COURT OF JHARKHAND AT RANCHI</b> <br /> <b>W.P. (C) No. 2253 of 2026 </b><br /> M/s. Arohi Elevators Pvt. Ltd., Ashok Kunj, Ashok Nagar, No. 3, P.O. & P.S. <br /> Argora, District - Ranchi through its Director Bajrang Bahadur Singh, aged <br /> about 60 years, son of Late Surya Bhan Singh, resident of C-1670, Okhala <br /> Industrial Area Phase-I, P.O. & P.S. Okhala Industrial Estate, District - South <br /> Delhi. <br /> …. …. Petitioner <br /> Versus <br /> 1. The Steel Authority of India Ltd., a Company registered under Companies <br /> Act, 1956 through its Chairman- cum-Managing Director, having its office <br /> Ispat Bhawan, Lodhi Road, P.O. & P.S. Delhi Lodhi Road, New Delhi. <br /> 2. Bokaro Steel Plant through its Managing Director, having its office at <br /> Bokaro Steel City, P.O. & P.S. Bokaro Steel City, District Bokaro, <br /> Jharkhand. <br /> 3. The Chief General Manager (Mechanical Maintenance), Bokaro Steel <br /> Plant, having its office at Bokaro Steel City, P.O. & P.S. Bokaro Steel City, <br /> District Bokaro, Jharkhand. <br /> 4. The General Manager (Contract Cell), SAIL, Bokaro Steel Plant, having <br /> its office at Bokaro Steel City, P.O. & P.S. Bokaro Steel City, District <br /> Bokaro, Jharkhand. <br /> 5. The Assistant Manager (L&A), Bokaro Steel Plant, having its office at <br /> Bokaro Steel City, P.O. & P.S. Bokaro Steel City, District Bokaro, <br /> Jharkhand <br /> …. …. Respondents <br /> ------ <br /> <b>CORAM : HON’BLE THE CHIEF JUSTICE </b><br /> <b> HON’BLE MR. JUSTICE RAJESH SHANKAR </b><br /> <b> </b> <b> </b> <b> </b> <b> </b> ------ <br /> For the Petitioner : Mr Rahul Kumar, Advocate <br /> For the Respondents : Mr Indrajit Sinha, Advocate <br /> Mr Ankit Vishal, Advocate <br /> ----- <b> </b><br /> <b>02 /Dated: 07.04.2026 </b><br /> 1. Heard the learned counsel for the parties. <br /> 2. The petitioner challenges the order dated 24.02.2026, by which the Steel <br /> Authority of India Limited (SAIL) has banned future business dealings with the <br /> petitioner for a period of two years, starting from 03.10.2025 and ending on <br /> 02.10.2027. <br /> 3. Mr Rahul Kumar, learned counsel for the petitioner, submits that the <br /> impugned order is non-speaking and demonstrates a complete lack of <br /> consideration. He contends that even the petitioner's response to the show cause <br /> 1 <br /> <br /><br /> <br /> <br /> <br /> ( 2026:JHHC:9725-DB ) <br /> <br /> notice has not been properly considered. He argues that issuing non-speaking <br /> orders or those which fail to consider the cause shown by the petitioner violates <br /> the principles of natural justice and fair play and, therefore, must be regarded as <br /> void. On these grounds, Mr Rahul Kumar submits that the impugned order dated <br /> 24.02.2026 should be quashed. <br /> 4. Mr Indrajit Sinha, learned counsel for SAIL, submits that the charge <br /> against the petitioner was non-compliance with the provisions of the Payment of <br /> Wages Act and denial of execution of any further work orders. He pointed out <br /> that no less than two show-cause notices were issued to the petitioner, and after <br /> due consideration of the petitioner's response, the impugned order was made. Mr <br /> Sinha submitted that the petitioner’s response did not deny the allegations; on <br /> the contrary, the petitioner expressed an inability to comply with the provisions <br /> of the Payment of Wages Act. He made particular reference to the petitioner's e-<br /> th<br /> mail dated 16 August 2025, in which the petitioner requested the foreclosure <br /> of the contract and even offered to continue services until SAIL made alternate <br /> arrangements to terminate the contract. <br /> 5. Accordingly, Mr Sinha submitted that there was no failure of natural <br /> justice and the impugned order was entirely consistent with the contractual terms <br /> and the petitioner's request. <br /> 6. The rival contentions now fall for our determination. <br /> 7. The record shows that the petitioner was engaged by SAIL under a <br /> comprehensive maintenance contract for three Goods-cum-passengers’ lifts <br /> outside the Bokaro Steel Plant on a STE basis. <br /> 8. Upon realising that the petitioner was not complying with the provisions <br /> of the Payment of Wages Act, even though the work orders had clearly stipulated <br /> such compliance, a notice was issued to the petitioner, proposing the banning of <br /> 2 <br /> <br /><br /> <br /> <br /> <br /> ( 2026:JHHC:9725-DB ) <br /> <br /> th<br /> future business dealings. The petitioner, by communication dated 16 August <br /> 2025, wrote to SAIL that their wage payment system is in sync with the labour <br /> laws and the company's policy. The CLC’s BSL requirement may not align with <br /> the petitioner’s established norms. Therefore, the petitioner expressed an <br /> inability to modify the whole wage payment system for a single contract. By this <br /> communication, the petitioner also requested foreclosure of the contract but <br /> agreed to continue with their services until SAIL makes alternative arrangements <br /> or terminates the contract. <br /> th<br /> 9. The contents of the e-mail dated 16 August 2025 addressed by the <br /> petitioner to the SAIL are transcribed below for the convenience of reference: - <br /> <i>“Arohi Elevators </i> <i>[email protected]</i> <i> Sat, Aug 16, 2025 at 11:24. </i><br /> <i>To: MTB Eqpt Inspn </i> <i>[email protected]</i> <i> </i><br /> <i>Cc: MAHESHKUMAR LAL <[email protected]>, KRISHNA [email protected], </i><br /> <i>manoranjan </i> <i>[email protected]</i> <i> </i><br /> <i>Dear Sir, </i><br /> <i>Our wage payment system is in sync with labour laws and company's policy. </i><br /> <i>The CLC requirement of BSL may not be in line with our established norms. </i><br /> <i>We express our inability to modify the whole wage payment system for a </i><br /> <i>single contract. </i><br /> <i>Hence we would request you to foreclose the contract. We agree to continue </i><br /> <i>our services till you make alternate arrangements or terminate the contract. </i><br /> <i>[Quoted text hidden) </i><br /> <i>Regards” </i><br /> <i> </i><br /> 10. Despite the above response, in which the petitioner requested foreclosure <br /> of the contract after expressing inability to modify its wage payment system, no <br /> less than two show-cause notices were issued to the petitioner regarding the ban <br /> on future business dealings. <br /> 11. In the response furnished to the show cause notices, the petitioner <br /> nowhere denied non-compliance or non-adherence but sought to raise the issue <br /> of delayed payments by SAIL and other such issues. However, what is important <br /> is the fact that there was no denial about the non-adherence to the requirements <br /> of the Payment of Wages Act and disinclination to comply with such statutory <br /> 3 <br /> <br /><br /> <br /> <br /> <br /> ( 2026:JHHC:9725-DB ) <br /> <br /> provisions on the ground that the petitioner was unwilling “ <i>to modify the whole </i><br /> <i>wage payment system for a single contract</i> ”. <br /> <br /> 12. Therefore, considering the materials on record, including the response to <br /> flatly comply with even the statutory provisions, we do not think that there was <br /> any failure of natural justice, non-application of mind or even unfairness on the <br /> part of SAIL, issuing the impugned order, banning the petitioner from future <br /> business dealings for a period of two years. <br /> 13. The claim that the impugned order is non-speaking is quite misconceived. <br /> The reason for the ban is clearly outlined in the impugned order, supported by <br /> the email and response to the show cause notices sent by the petitioner. The <br /> impugned order was made after giving the petitioner due opportunity for <br /> rectification and after careful consideration of their response. <br /> <br /> 14. Accordingly, we are satisfied that there is no illegality, procedural <br /> impropriety, or unfairness involved in the decision-making process leading to <br /> the issuance of the impugned order. This petition is, accordingly, meritless and <br /> dismissed without any order for costs. <br /> 15. Let a copy of this order be sent to the Payment of Wages Authority at <br /> Bokaro / Dhanbad, so that the Authority can inquire into the payment structure <br /> being offered by the petitioner to its workmen. <br /> 16. The Registry to do the needful. <b> </b><br /> <b> </b><br /> <b>(M.S. Sonak, C.J.) </b><br /> <b> </b><br /> <b> </b> <b> </b> <b> </b> <b> </b> <b> </b> <b> </b> <b> </b> <b> </b> <b> (Rajesh Shankar, J.) </b><br /> April 07, 2026 <br /> Ranjeet / R.Kr. <br /> NAFR <br /> Uploaded on 09.04.2026 <br /> <br /> 4 <br /> </div>