MRS. URMILA SINGH AND ANR vs C.E.S.C. LIMITED AND ORS
- Court
- Calcutta High Court
IN THE HIGH COURT AT CALCUTTA
CONSTITUTIONAL WRIT JURISDICTION
ORIGINAL SIDE
BEFORE:-
THE HON’BLE JUSTICE SHAMPA SARKAR
&
THE HON’BLE JUSTICE ARJUN RAY MUKHERJEE
APOT No. 127 of 2026
With
IA No. GA/1/2026
Mrs. Urmila Singh & Anr.
Vs.
CESC Limited & Ors.
For the Appellant : Mr. Aniruddha Chatterjee, Sr. Adv.
Mr. Raja Mantosh, Adv.
Ms. Smruti Rekha Das, Adv.
Mr. Parikhit Lakhotia, Adv.
For CESC Limited : Mr. Subir Sanyal, Sr. Adv.
Mr. Debanjan Mukherjee, Adv.
For the Respondent No. 6 : Mr. Joydeep Kar, Sr. Adv.
Ms. Amrita Pandey, Adv.
For the Respondent Nos. 4,5,7 & 8 : Mr. Manju Agarwal, Sr. Adv.
Ms. Amrita Pandey, Adv.
Judgment Reserved on : 15.09.2026
Judgment pronounced on : 08.10.2026
Shampa Sarkar, J. :-
1. The appeal arises out of a judgment and order dated July 14, 2026,
passed in W.P.O. No. 860 of 2025. By the order impugned, the learned
Single Judge dismissed the writ petition, inter alia, holding that, the
contention of the appellants that they had been consuming electricity
through a sub-meter which was later disconnected, was ex-facie false.
His Lordship held that, Hastings chamber was categorized as a high
2
risk building and domestic connection could not be provided to the said
building. The building was being exclusively used for commercial
purpose. According to His Lordship, CESC was State under Article 12
of the Constitution of India, insofar as, the function of distribution of
electricity was concerned and as such, CESC should act in public
interest. His Lordship held that, although Article 21 of the Constitution
of India recognized electricity to be essential to the right to life and right
to shelter, but welfare and safety of the people had a greater legal
perspective than an individual right. The petitioners continued to
encroach the rooftop of a high risk building, on account of which the
fire safety certificate could not be issued. Thus, it would be inequitable
to direct a new domestic connection to be effected at the rooftop. Such
order would be contrary to law, unjust, unfair and hazardous to the
remaining occupants. Upon balancing the equities, His Lordship held
that public interest would supersede private interest in this case. As
the appellants did not take remedial measures to cure the defects
pointed out by the Fire Department by removing the blockage and
access to the roof, the question of granting any discretionary relief by
issuing a high prerogative writ, did not arise.
2. Mr. Aniruddha Chatterjee, learned Senior Advocate for the appellants
submitted that the appellants have been residing in the premises since
long. The predecessor in interest of the appellants was inducted as a
tenant. Thereafter, disputes arose and the rent was being regularly
deposited before the rent controller. The writ court did not have any
authority in law to hold that the appellants were encroachers. In any
3
event, the nature of occupation was irrelevant for the purpose of grant
of electricity. The fact that the appellants were in settled possession of a
part of Hastings Chambers was admitted by all the parties. There was
no dispute with regard to their occupation of the premises in question.
Section 43 of the Electricity Act, 2003 mandated that the distribution
licensee must supply electricity to any premise, upon an application
being made by the owner or occupier. The owners of the building under
whom the appellants were tenants, did not raise any objection. The
other occupants who were sub-lessees in the premises, did not have
any authority under the law to raise any objection with regard to the
connection to be supplied by the CESC authorities. The CESC
authorities had filed a feasibility report, indicating that one meter could
be installed at the common meter space, for supply of electricity to the
appellants.
3. Under such circumstances, the order impugned was perverse and
contrary to the settled position of law with regard to grant of electricity
to an occupant of a premise. He further submitted that the
construction on the rooftop could not be said to be unauthorized, as
the construction was regularized by the Kolkata Municipal Corporation
by disposing of a demolition proceeding. Although, some of the
occupants had challenged such order of regularization, before the
Tribunal, the Tribunal did not grant any order of stay.
4. It was urged that, the portion occupied by the appellants on the rooftop
should be treated to be authorized and having been constructed in
accordance with law. It was further submitted that, although one of the
4
staircases of the building having access to the rooftop had been blocked
by the entrance door to the premises of the appellants, the other
staircase leading to the roof was open and there was no obstruction.
The sub-lessees or other occupants did not face any obstruction to
enter the roof. He placed reliance on the photographs which were filed
pursuant to our direction and submitted that the photographs would
clearly depict the nature of possession of the appellants.
5. Mr. Joydeep Kar and Ms. Manju Agarwal, learned Senior Advocates
appeared on behalf of the private respondents (other occupants) and
submitted that, the predecessor in interest of the appellants was not a
tenant. He was inducted as a caretaker and was allowed to reside in a
temporary asbestos shed when the building was being constructed, in
order to supervise the construction work. The building plan did not
permit residential use by converting a portion of the roof. The
appellants actually encroached upon the common roof and had been
unlawfully occupying the same. The appellants had also erected a
private gate and closed a staircase by blocking one of the two fire exits.
Such obstruction had been condemned by the Fire Department and by
the Special Commissioner of Police. After the tragedy at Stephen court
in 2010, a Joint Inspection had been conducted on March 27, 2010, by
the concerned authorities, including CESC limited. It was opined that,
as the appellants had caused an unauthorized construction on the
rooftop, the fire license could not be renewed.
6. It was submitted that the appeal should be dismissed on the ground of
maintainability, as also on merits. The appellants prayed for a writ in
5
the nature of mandamus, commanding the CESC authorities to provide
new electric connection to the premises being 7C Kiran Shankar Roy
Road, Top floor, Police Station-Hare Street, Kolkata 700001. CESC
authorities filed a report pursuant to the direction of the court of the
learned Single Judge indicating that a single phase meter could be
accommodated to provide electricity to the premises of the appellants.
Such connection should not be provided as the appellants did not
approach the writ court with clean hands.
7. Mr. Subir Sanyal, learned Senior Advocate submitted that, if the court
directs, electricity supply can be granted by installing a new meter in
favour of the appellants.
8. Considered the submissions. Section 43 of the Electricity Act, 2003,
casts a mandatory duty on the licensee to supply electricity to any
premise, on an application being made either by the owner or the
occupier and such supply is to be effected within one month from
receipt of the application requiring such supply. Undoubtedly, the right
of the appellants to get electricity from the licensee has been statutorily
provided. That apart, right to enjoy electricity is a part and parcel of
Article 21 of the Constitution of India. An occupier of a premise must
be a person in settled possession or occupation. In this case
undoubtedly, the appellants have been in possession since long, and it
matters little, whether the nature of the possession is legal or illegal.
Even a trespasser is entitled to electricity. The fact that the appellants
have been in occupation of the premises since long, is not in dispute.
6
9. However, the issue is whether these appellants, who are in occupation
of Hastings Chambers, will be entitled to electric connection in the
peculiar facts and circumstances of the present case.
10. First and foremost, it is an admitted position that the building is a high
risk building. Thus, a fire license is mandatory under the law. The fire
license has expired and has not been renewed. According to the
respondents, the fire license will never be granted because one of the
fire exits, that is, the door connecting one of the staircases to the
rooftop had been permanently blocked by the construction of the
appellants. This fact needs to be clarified by the Fire Department. The
building is used for commercial purpose, thus domestic connection
cannot be granted. In our view, open fire or use of LPG cannot be
allowed in the premises. The photographs which have been filed by the
appellants during the course of hearing clearly indicate that the
construction on the rooftop is being used for residential purpose, and
the family of the appellants are residing there.
11. We refer to the minutes of the joint inspection report which was held in
respect of the premises in question. The report was supplied by the
Special Commissioner of Police, Kolkata and the following shortcomings
were detected. Copy of the said notice is quoted below:-
NOTICE
Mr. PAWAN KUMAR JHUNJHUNWALA, SECRETARY OF
OWNERS’ASSOCIATION OF 7C KIRAN SANKAR ROY ROAD, 5th
FLOOR, KOLKATA- 700001
Owner/Occupier/Tenant/Manager/Caretaker/Representativeof
Owners’Tenants’ Association/Board of Directrs/Reveiver
7
Address: HASTINGS CHAMBERS, 7C KIRAN SNKAR ROY ROAD,
KOLKATA-700001
During the joint inspection held in your premises on 27/03/2010 in
the presence of caretaker/durwan of the building, the following faults
were detected and against each fault the maximum period given for
compliance has been noted. You are hereby directed to take necessary
remedial measures for these faults.
Faults detected by CESC:
Service 1 Service 2
Short Term
Requirement (to
be complied
within 15 days)
(i) Dressing of wires inside
(i) To remove all the
the meter box catering
consumers installation.
(ii) To replace all the main
inflammable goods
away from the
service position.
(ii) Dressing of wires
inside the meter box
catering consumers’
installation.
(iii) To replace all the
switches with MCBs.
(iii) To install fire
extinguishers/sand
bucket adjacent to
meter board.
(iv) To remove
unauthorized load.
main switches with
MCBs.
(iv) To install fire
extinguishers/sand
bucket adjacent to
meter board.
(v) To repair/renew
earthing, measure
earth resistance &
inform CESC Ltd.
(vi) To engage electrical
contractor.
(vii) To remove
unauthorised load.
Long Term
Requirement
To maintain cleanliness of
wiring inside the
consumer’s
To maintain cleanliness
of wiring inside the
Long Term
Requirement (to
be complied
within 6
months)
To maintain cleanliness of
wiring inside the
consumer’s premises and
to check leakage, if any, by
licensed electrical
contractors periodically.
To maintain cleanliness
of wiring inside the
consumer’s premises
and to check leakage, if
any, by licensed
electrical contractors
periodically.
Faults detected by Fire and Emergency Services:
1. All temporary mezzanine floors of wooden ply constructions with
wooden CAT ladders should be dismantled within a fortnight.
8
2. Compartmentalization made of wooden ply construction should be
converted to brick walling after evaluating the structural stability of
the building within thirty days.
th
3. One of the staircases of this building has been encroached on the 5
floor by construction of a room for residential purpose due to which
the staircase could not reach the terrace level. In a fire situation the
occupiers will be trapped inside the building. The encroachment has
to be removed within thirty days such that free access to the terrace
can be secured.
4. Earthing provisions should be checked and certified by competent
authority within fifteen days.
5. Underground Water Reservoir exclusively for fire fighting should be
provided in building, with replenishing arrangement @1000 liters/
min. from two dedicated source of supply within ninety days. In
case, Underground Water Reservoir is not feasible, Overhead Water
Reservoir of capacity 10,000 liters exclusively for fire fighting need to
be provided at terrace level within thirty days.
6. 6. In case of Underground Water Reservoir, it shall be provided with
wet riser of 150mm internal diameter pipe line with provision of
landing valves at the staircase landings / half landings at the rate of
one such riser for every staircase. The system shall be so designed
that shall be kept charged with water all the time under pressure
and capable to discharge 2850 liters/min at the ground level outlet
and minimum 900 liters/min at the top most outlets. In cases, the
running pressure shall not be less that 3.5 Kg/cm2. All other
requirements shall conform to L.S. 3844-1989 within ninety days.
7. Provision of the fire pump shall have to be made to supply water at
the rate designed pressure and discharge into the water based
system, which shall be installed in the building. One such pump
shall always be kept on stand-by mode preferably of diesel driven
type.
8. Provision of Jockey pump shall also have to be made to keep the
water based system under pressurized condition at all the time. All
the pumps shall be incorporated with both manual and auto
starting facilities with in ninety days.
9. MCP (Manual call Points) incorporating with hooters shall be
installed in all floors. Multi-grade detector system should be
provided in all the floors of the business occupancies with in thirty
10. No open flame or use of LPG will be allowed in the business
occupancy building whether it is a eatery house or restaurant with
immediate effect.
11. ‘Exit’ signage to be provided in each for floor level of all
buildings in conspicuous place by fluroscent paint/UPS with floor
numbers within fifteen days.
12. The automatic sprinkler installation shall be provided in
basement of the building as per I. S. 9972. Alarm gong needs to be
incorporated along, with the sprinkler system with in ninety days.
Faults detected by K.M.C:
9
1. Owner/occupier should furnish structural stability report by an
Empanelled Structural Engineer for ensuring the structural
safely and stability of the building within 30 days from the date of
receipt of notice from Kolkata Police. If any action is to be taken
as per the recommendation of Structural Engineer, it has to be
taken forthwith, but not later than sixty days from the date of
receipt of the report of Structural engineer.
2. Owner/occupier is directed to remove all types of obstruction om
Exit and Entry including passage and corridors.
It is noted for the information of all concerned that if such faults
are not rectified within the time limit prescribed, the concerned
agencies will launch proceedings as per law against the
defaulters without any further reference to the parties concerned.
S/d
(B B Basu)
Spl. Commissioner of Police
Kolkata
12. It also appears that a proceeding was initiated in respect of the
construction on the allegation that the same was unauthorized.
Demolition Case No. 19-D/V/18-19 had been initiated by the Kolkata
Municipal Corporation. The High Court directed proceedings to be
initiated in terms of the provisions of the Kolkata Municipal
Corporation Act, 1980 is quoted below:-
“In such situation, since the Corporation is of the prima facie
view that there exist unauthorized construction it will invoke
provision of Section 400(1) of the Kolkata Municipal Corporation
Act, 1980 within a period of fortnight from date. It will be
endeavour to conclude such proceedings within a period of 12
weeks thereafter. The issue as to the nature and extent of the
unauthorized construction is kept open to be decided in such
proceeding. The authority will afford reasonable opportunity of
hearing to the private parties.”
13. The Owners Association of Hastings Chambers contested the
proceeding. Ultimately, the Special Officer (Building), Kolkata Municipal
Corporation, passed an order. The relevant portion thereof is quoted
below:-
10
“Considered the submissions of the person responsible as well
as the complainant. Also considered the inspection report dated
6.8.2019 submitted by the Deputy Chief Engineer (B). From the
inspection report it is evident that the persons responsible have
not removed the wooden door which is hampering access of the
nd
2 stair case to the roof. The persons responsible cannot
nd
obstruct the access to the roof through the 2 stair case, by
installing a door and keep it under lock and key. Hence it is
order that-
th
2) The unauthorized constructions on the roof of the 6 floor
being quite old and having an area of 893.0 Sq. ft. which is
being used as residence by the persons responsible can be
treated as ‘minor unauthorized erection or work’ as Defined in
Rule 3(1) of the KMC (Regularization of Building) Regulation
2015 and these unauthorized constructions are regularized and
retained under Rule 4 of the Regulations 2015 of the KMC Act
1980 subject to the following preconditions:
(a) That the persons responsible must furnish a certificate from
a KMC empanelled structural engineer certifying that the
stability and the foundation of the impugned constructions are
safe and sound and the materials used as well as workmanship
are as per the latest edition of NBC of India, within 30 days of
receipt of this order.
(b) That they must pay the fees for retention of the regularized
construction within 30 days of receipt of the calculation sheet to
be prepared by the respective department of the KMC.
(c) That they must furnish an affidavit declaring on oath that
they will not make any construction whatsoever in the
impugned premises without prior sanction from the KMC
authority.
Non-compliance of any of the conditions stated above will invite
demolition of the unauthorized constructions by the KMC
authority at the cost and at the risk of the person responsible.
Let a copy of this order be served on the concerned parties for
information and necessary action.
Sd./
Munshi Md. Faruque
Special Officer (Building) K.M.C.”
14. The order was passed on August 26, 2019, by the Special Officer
(Building). The appellants prayed for regularization of the unauthorized
construction on the roof of the sixth floor of the premises. It was
submitted that the construction was very old and had been existing for
11
a long time. The objectors who had drawn the attention of the KMC to
the alleged illegal construction submitted before the Special Officer
(Building) that, the appellants and or their predecessors had illegally
and wrongfully obstructed the passage leading to the second staircase
of the said premises, by obstructing free ingress and egress.
15. They further alleged that due to construction of rooms as well as privy
and toilet, the passage to the staircase was blocked up to the roof. The
appellants had raised further constructions by encroaching an area on
the roof measuring more than 400 square feet. They had also
encroached upon the passage. The door was a private door, giving
access only to the appellants to reach their unauthorized construction.
16. According to the report, the area of unauthorized construction was
about 893.0 square feet. The order recorded that the persons
responsible for the construction had not removed the wooden door. The
said door obstructed access to the second staircase to the roof. The
persons responsible could not obstruct the access to the roof through
the second staircase, by installing a door and keeping it under lock and
key.
17. However, the Special Officer Building held that, as the unauthorized
construction on the roof was quite old, the same shall be regularized.
The unauthorized construction should be treated as minor erection and
the same should be retained in terms of Rule 4 of Regulations of 2015
of the KMC Act. However, such regularization was made subject to
fulfilment of certain conditions. The persons responsible were directed
to furnish a certificate from an empanelled structural engineer of the
12
KMC, certifying the stability and foundation of the construction within
30 days from receipt of the order. They were to pay fees for retention
and they were directed to furnish an affidavit declaring on oath that
they would not make any further construction. The order also provided
that, non-compliance of any of the conditions would invite demolition of
the unauthorized construction.
18. The Hon’ble Apex Court in the matter of Rajendra Kumar Barjatya &
Anr. Vs. U.P. Avas Evam Vikas Parishad & Ors. reported in 2024 INSC
990, held as follows:-
“(iii) Upon conducting personal inspection and being satisfied
that the building is constructed in accordance with the building
planning permission given and there is no deviation in such
construction in any manner, the completion/occupation
certificate in respect of residential / commercial building, be
issued by the authority concerned to the parties concerned,
without causing undue delay. If any deviation is noticed, action
must be taken in accordance with the Act and the process of
issuance of completion/occupation certificate should be
deferred, unless and until the deviations pointed out are
completely rectified.
(iv) All the necessary service connections, such as, Electricity,
water supply, sewerage connection, etc., shall be given by the
service provider / Board to the buildings only after the
production of the completion/occupation certificate.
(v) Even after issuance of completion certificate, deviation /
violation if any contrary to the planning permission brought to
the notice of the authority immediate steps be taken by the said
authority concerned, in accordance with law, against the builder
/ owner / occupant; and the official, who is responsible for
issuance of wrongful completion /occupation certificate shall be
proceeded departmentally forthwith.
(vi) No permission /licence to conduct any business/trade must
be given by any authorities including local bodies of
States/Union Territories in any unauthorized building
irrespective of it being residential or commercial building. (vii)
The development must be in conformity with the zonal plan and
usage. Any modification to such zonal plan and usage must be
taken by strictly following the rules in place and in
consideration of the larger public interest and the impact on the
environment.”
13
19. The Hon’ble Apex Court had directed that electricity connection or any
other essential services should not be provided to constructions which
were unauthorized. We are not clear as to whether the compliances as
directed by the Special Officer (Building) which were conditions
precedent to regularization, had been fulfilled or not. Secondly, we find
from the documents before us that the Fire Department had raised
objection with regard to closure of one of the doors leading to the roof
sometime in 2010. It appears from a communication dated February 3,
2025 made by the owners association to the Director, West Bengal Fire
and Emergency Services that one of the grounds for rejection of the
application for renewal of the fire license was occupation over a portion
of the roof.
20. Under such circumstances, we are neither sure of the legality of the
construction nor about the safety of the building and its vulnerability in
case of fire hazards. However, we cannot ignore the appellants’ right to
enjoy electricity and we hold that the appellants will be entitled to
electric connection from CESC Limited which shall not be domestic but
commercial, provided CESC is satisfied that the conditions as per the
order of regularization had been actually fulfilled or not and to
ascertain such issue, CESC will obtain a report from the KMC as to
whether the records of KMC depict such compliance. The Executive
Engineer, KMC of the concerned bureau shall inform CESC whether,
the construction stood regularized upon the appellants fulfilling those
conditions. In the event supply is granted, operation of the kitchen or
14
use of LPG or any other equipment giving rise to open flame, shall not
be permitted. The connection cannot be used for residential purpose.
CESC will also obtain a report from the Fire Department as the said
department had objected to blockage of one of the entrances to the roof
and did not grant renewal of licence in view of such closed door.
21. With the above direction, the order impugned is modified.
22. The appeal and connected applications are disposed of.
23. Urgent Photostat certified copies of this judgment, if applied for, be
supplied to the parties upon fulfilment of requisite formalities.
(Shampa Sarkar, J.)
I Agree.
(Arjun Ray Mukherjee, J.)