K.LATHA vs THE ADDITIONAL CHIEF SECRETARY TO GOVERNMENT

Court
Madras High Court

2026:MHC:4777
WP No. 21000 of 2023
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED: 26-11-2026
CORAM
THE HON'BLE MR.JUSTICE C.KUMARAPPAN
WP No. 21000 of 2023
CNR: {HCMA011247382023}
K.Latha
W/o.C.Ravi,
31, Sagariya Street,
Mela Kamarajapuram,
Nagercoil, Kanyakumari District.
..Petitioner(s)
Vs
1. The Additional Chief Secretary To Government
Municipal Administration And Water Supply,
(ME.4) Department, Secretariat, Chennai- 9.
2. The Commissioner Of Municipal
Administration
Office Of The Commissioner Of Municipal
Administration, Chepauk, Chennai- 5.
3. The Commissioner,
Nagecoil Municipality, Nagercoil,
Kanyakumari District.
4. The Collector
Kanyakumari District.
..Respondent(s)
Writ Petition filed under Article 226 of the Constitution of India, praying
to issue a writ of Certiorarified Mandamus, calling for the records relating to the
first respondent vide G.O. (D) No.134 Municipal Administration and Water
Supply (ME.4) Department, dated 16.3.2023 and to quash the same and
consequently direct the respondents to regularize the services of the Petitioner
with all attendant benefits.
__________
Page1 of 17
https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2026 07:53:39 pm )

2026:MHC:4777
WP No. 21000 of 2023
For Petitioner(s): Mr.S.Vijayakumar
Senior Counsel
for Mr.G.Rajesh
For Respondent(s): Mr.K.K.Ram Siddhartha
Additional Government Pleader

ORDER
The brief facts which are necessary for the disposal of the present writ
petition is that, the petitioner joined in the Municipal Office as Work Inspector
on 27.02.1987 and later, she was promoted to the post of a Junior Engineer on
08.03.2004. During her tenure as a Junior Engineer, the petitioner was in-charge
of the Engineering Section for a period from 01.07.2004 to 09.01.2006.
According to the respondent, there was some delinquency during the above
period. Hence, the petitioner was issued with a charge memorandum on
24.10.2010. Subsequently, though the Enquiry Officer found that charges have
not been proved, the Disciplinary Authority has deviated from the findings and
imposed a punishment of compulsory retirement vide G.O.(D).No.134 dated
16.03.2023. Aggrieved with the same, the present Writ Petition has been filed.
2.Heard the learned Senior Counsel appearing for the petitioner and the
learned Additional Government Pleader appearing for the respondents.
__________
Page2 of 17
https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2026 07:53:39 pm )

2026:MHC:4777
WP No. 21000 of 2023
3(a).The learned Senior Counsel for the petitioner would contend that
there was an enormous delay at every stage of disciplinary proceedings and that,
such delay caused serious prejudice to the petitioner. He would further submit
that the Commissioner of Municipality, instructed the then Municipal Engineer
Mr.Suresh Kumar and the petitioner to complete the Bus Stand work
immediately, as the District Collector, Nagarcoil, has instructed him to
undertake the work urgently. He would further submit that as per the direction
of the superior officer, the petitioner has discharged her duty between 2004-
2006. However, the Department with a delay of nearly five years, issued a
charge memorandum on 24.10.2010. Subsequently, the Enquiry Officer filed the
Enquiry report on 31.07.2014 qua after a lapse of three years discharging the
petitioner from all charges. But, the first respondent deviated from the findings
of the Enquiry Officer and had issued a show cause notice on 16.02.2018 calling
upon the explanation from the petitioner. Though the petitioner submitted her
explanation within a period of three months, the punishment was imposed after
a period of five years. Therefore, the learned Senior Counsel would contend that
at every stage, there was a delay, which seriously prejudiced the petitioner in
defending her case effectively. Furthermore, her entire career was forced to be
under the hanging Damocles sword of disciplinary proceedings, which made her
__________
Page3 of 17
https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2026 07:53:39 pm )

2026:MHC:4777
WP No. 21000 of 2023
career become more worrisome. Therefore, notwithstanding the other grounds,
on account of the delay, the disciplinary proceeding is to be quashed.
(b).Even on merits, it is their submission that though certain allegations
were made with regard to the misappropriation, on the face of it the same is not
a real misappropriation. On the other hand, it was couched in such a way that
the payment to the Contractor through the petitioner as a misappropriation,
since no tender was floated. In fact, it is their submission that according to the
charge memorandum issued to the co-delinquent one Mr.D.Suresh Kumar, it
was who he permitted the petitioner to retain the money and not by the
petitioner voluntarily. Therefore, the very charge by itself would prove that the
petitioner has no power to draw money on her own, so as to charge her for
misappropriation. It is his further contention that the tender could not be floated
at the relevant point of time, as the contractors were went on strike, which stand
taken by the Municipal Commissioner was accepted by the Authority. Having
accepted such defence in favour of the superior officer, the initiation of
disciplinary proceedings against the inferior officer who obeyed the orders of
his superior is biased and illegal. It is his further contention that the punishment
imposed against the co-delinquent Mr.D.Suresh Kumar for compulsory
retirement was set aside. Therefore, the petitioner is also entitled to have a
__________
Page4 of 17
https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2026 07:53:39 pm )

2026:MHC:4777
WP No. 21000 of 2023
similar relief, as the charges are belated and the findings are erroneous and
perverse. Hence, prayed to allow the writ petition.
4. Per contra, the said contention was stoutly objected by the learned
Additional Government Pleader and would contend that there is a serious charge
of violating a specific rule mandating the floating of tenders. The petitioner,
having worked as a Junior Engineer did not bring such illegality to her higher
officials. Furthermore, she has caused huge loss to the exchequer to the tune of
Rs.10,97,505/- and that she received money from Treasury beyond her
entitlement and spent the same for the Government work. However, until the
payment was made to the contractor, she retained the money in her hand, which
is nothing but a misappropriation. Since the charges are serious, the punishment
of compulsory retirement cannot be faulted. It is also his contention that though
Enquiry Officer has given a clean chit to the petitioner, on the basis of a
verifiable material and on proper appreciation of facts, the Disciplinary
Authority has deviated from the findings. Though such deviation order is not
elaborate, the same is to the point which demonstrates the clarity of thought and
the application of mind to it's fullest extent. It is also his contention that, there is
a duty cast upon the petitioner to follow the Tamil Nadu Transparency in
Tenders Act, 1998. Though the petitioner would contend that there is a delay in
__________
Page5 of 17
https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2026 07:53:39 pm )

2026:MHC:4777
WP No. 21000 of 2023
disciplinary proceedings, absolutely there is no delay, as one of the Enquiry
Officer in-between has unfortunately died, and that after following all due
procedures, the disciplinary proceedings was concluded within a reasonable
time. Therefore, would contend that there is no delay. Furthermore, he would
contend that when the petitioner has got an alternative relief of review before
the Government, the very filing of this writ petition is not maintainable and is
liable to be dismissed. Hence, prayed to dismiss the writ petition.
5.I have given my anxious consideration to either side submissions.
6.The petitioner was given a charge memorandum on 24.10.2010 for
following charges:-
“ Charge -1:
That Tmt.K.Latha while working as Junior Engieer,
Nagercoil Municipality during the period from 1.7.2004 to
9.1.2006 in connivance with the Municipal Commissioner,
Municipal Engineer and Work Inspector had executed 28 works
(as listed out in Annexure-IIA), without calling for tenders and
accepted the rates offered by the contractors which were above
the rates approved by PWD Schedule of rates for the year 2004-
2005 and paid exorbitant rate causing loss to the tune of
Rs.19,38,658/- as tabulated in Annexure II-AA and thereby
violated the instructions issued in paragraph 2.5 of Engineering
Manual for Urban Local Bodies in Tamil Nadu, Rule 4 of the
Tamil Nadu Transparency in Tenders Act, 1998, and the Tender
Rules discussed in Chapter II (General), III (Publicity), IV
(Notice Inviting Tender and Tender Documents) of Tamil Nadu
Transparency in Tenders Rules, 2000.
Charge-2:
That Tmt.K.Latha, while working as Junior Engineer,
__________
Page6 of 17
https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2026 07:53:39 pm )

2026:MHC:4777
WP No. 21000 of 2023
Nagercoil Municipality in connivance with Municipal Engineers
obtained huge amount as an advance for execution of 14 works
as shown in Annexure II-B against the rules. The amounts were in
your hands during the course of execution of these works, which
amounts to temporary misappropriation of Municipal funds.
Charge-3:
That Tmt.K.Latha, while working as Junior Engineer in
Nagercoil Municipality in connivance with Municipal
Commissioner, Junior Engineer and Work Inspector had
committed the following irregularities during the course of
execution of the following works referred to in the Annexure IIA
& IIB.
1.Failed to prepare the estimates based on the current schedule
of rates for the year 2004-2005 and as per the prevailing market
rate.
2.Intentionally avoided usage of measurement books and nominal
muster roll forms from the Municipal Stationery for these works
and used unauthorized M.Book and nominal muster roll forms.
3.Intentionally avoided Tender Procedures for purchase of
materials of which value exceeded Rs.5000/-.
4.Failed to recover Income Tax, Sales tax and other taxes from
the Supplier’s bills of payment.
5.Failed to purchase bitumen from authorized suppliers and thus
failed to ensure quality of bitumen purchased and used.
6.Ingenuine quotations have been used and bills have been
prepared based on such quotations.
7.Failed to take photograph before and after execution of works
executed departmentally.
8.Failed to make stock entries for the materials purchased such
as steel, cement, bitumen.”
7.On perusal of the above charge memorandum, the so called
delinquencies were taken place between 2004-2005. However, with a delay of
__________
Page7 of 17
https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2026 07:53:39 pm )

2026:MHC:4777
WP No. 21000 of 2023
four years, the charge memorandum was issued. Admittedly, the Enquiry
Officer has found that all the three charges were not proved, as the petitioner is
the subordinate Officer to the Municipal Commissioner and Municipal
Engineer. The first and foremost charge is that, during 2004-2006, 28 works
were done without floating tender. The Enquiry Officer found that floating
tender is not the duty of the Junior Engineer and she has to only simply comply
the direction of the higher officials. Though such position was not seriously
disputed by the Disciplinary Authority, he deviated from the findings of the
Enquiry Officer on the thin premise that there was a duty cast upon the
petitioner to inform such irregularity to the higher officials.
8.At this juncture, it is relevant to refer the orders passed in respect of the
co-delinquent one Mr.D.Suresh Kumar in WP.No.15360 of 2019 dated
rd
09.01.2020, wherein this Court has considered the specific stand taken by the 3
respondent viz., The Commissioner of Municipality. For ready reference,
paragraph 17 of order made in WP.No.15360 of 2019, which arising in the very
same delinquency is as follows:-
rd
“17 . The specific stand that has been taken by the 3 respondent
rd
also assumes a lot of significance in this case. The 3 respondent,
who is Commissioner of the Municipality has taken a very specific
stand that during the relevant point of time, the contractors were
on strike and the Municipality had to complete certain works
immediately and therefore, a decision was taken not to issue any
__________
Page8 of 17
https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2026 07:53:39 pm )

2026:MHC:4777
WP No. 21000 of 2023
tenders and to allot work to the available Contractors. In view of
rd
this specific stand taken by the 3 respondent, this Court does not
find any apparent moral turpitude involved on the part of the
delinquent officers to have allotted the work to the Contractors.
Merely because the contracts have been allotted at a higher rate,
that by itself cannot be taken as a ground to initiate disciplinary
proceedings unless there is a material to show that the concerned
delinquent officers have acted beyond their powers and caused loss
to the Municipality.”
9.After taking into consideration of such findings, this Court has arrived
at a conclusion that there was no apparent violation of Rule involving moral
turpitude on the part of the delinquent officer in the allotment of works to the
contractors. The above finding is in favour of Municipal Engineer, who is
higher in rank and who has chosen the contractor. Whereas this petitioner is
subordinate to the Municipal Engineer and her duty is only to ascertain whether
the work had been done in accordance with the work order issued by the
Municipal Commissioner and Municipal Engineer. Therefore, in respect of the
first charge for non floating of tender, this Court cannot blame this petitioner.
Therefore, the finding of the Disciplinary Authority with respect to the first
charge is liable to be interfered with.
10.The Second charge is in respect of receipt of certain amount as an
advance towards the execution of 14 works. In order to decide this charge, this
__________
Page9 of 17
https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2026 07:53:39 pm )

2026:MHC:4777
WP No. 21000 of 2023
Court must go into the charge with reference to one Mr.D.Suresh Kumar, as
discussed in the writ petition referred to hereinabove. The sum and substance of
the charge that was framed against Mr.D.Suresh Kumar was extracted in
paragraph 11 of the aforementioned writ petition and the same is extracted
herein below:-
“11.The 2nd respondent had issued the Charge Memo against the
petitioner by framing six charges. The sum and substance of the
charge is that while the petitioner was working as a Municipal
Engineer in the Nagercoil Municipality during the period
24.11.2003 to 02.08.2005, he in connivance with the Municipal
Commissioner, Junior Engineer and Work Inspector have
executed works without calling for tenders from contractors at
exorbitant rates and thereby caused loss to the tune of
Rs.19.38,658/- to the Municipality. The further charge is that the
petitioner has permitted the Junior Engineer and the Work
Inspector to obtain huge amounts as advance for the execution of
the works and thereby has allowed them to misappropriate the
amounts. The further charge against the petitioner is there were
irregularities in the execution of the works and there were also
procedural lapses and the petitioner as the head of the technical
wing failed to guide the Municipal commissioner in a proper
manner and thereby, he has committed acts of misconduct.”
11.According to the above charge, he was permitted the petitioner to
obtain huge amount as advance for execution of work and such permission is
nothing but misappropriation of the amount. Here again the petitioner has no
authority to draw money directly from the Treasury or it is not the case of the
respondent that the petitioner drew money on her own. On the other hand, it is
__________
Page10 of 17
https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2026 07:53:39 pm )

2026:MHC:4777
WP No. 21000 of 2023
the simple case of the respondent that the petitioner was in possession of
Government money beyond her entitlement. In this regard, the Disciplinary
Authority has relied upon the provisions in paragraph 5.3 under the head of
payment in Engineering Municipal for Urban Local Bodies in Tamil Nadu,
which is extracted hereunder:-
“5.The provision in para 5.3 under the head of payment is
Engineering Municipal for Urban Local Bodies in Tamil Nadu
and it states as follows:-
“5.3 The Engineer may be given a temporary imprest,
commensurate with the requirements of the work or works,
of an amount not exceeding one thousand rupees. Payments
for labour for materials purchased will ordinarily be made
by the Engineer directly from this imprest. Suppliers bills
for materials exceeding Rs.200/- in value being forwarded
to the Commissioner for payment by him direct.
5.3.1 In the case of road metal and gravel, the general
principle of measurement and check-measurement before
spreading shall be followed and a record kept in the
measurement book also, the measurements being taken by
the AE/JE and check-measurement by the Engineer.
5.3.2 All labour employed on departmental works shall be
booked on nominal muster rolls prepared by the Overseer /
AE. The Municipal Engineer shall check them as often as
possible, leaving a note of such check on the nominal
muster rolls itself. The nominal muster roll shall be passed
for payment by the Engineer before payment is made.”
As per the above provision, a sum of minimum amount can
be withdrawn as advance. Whereas, in this case, for all the 28
works, the delinquent officer Tmt.K.Latha, formerly Junior
Engineer, Nagercoil Municipality had received the huge amount of
Rs.24,22,000/- as advance in cash, which is in contrary to the
Government norms and caused loss of Rs.10,97,505/- to the
Government.”
__________
Page11 of 17
https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2026 07:53:39 pm )

2026:MHC:4777
WP No. 21000 of 2023
12. On Perusal of the same, the Engineer may be given a temporary
imprest commensurate with the requirementa of the work, but the same should
not exceed Rs.1000/-. A plain reading of the above provisions would only
mandate the Engineer. In the case in hand, Mr.D.Suresh Kumar. Whereas he
himself had drew money and handed over to the petitioner so as to disburse the
same to the Contractors. It is relevant to mention that the very situation had
arisen on account of the strike by the Contractors, which compelled the
Engineers to do works without floating tender and disburse the amounts to those
who had carried out the work.
13.No doubt, any initiation of work without floating tender would lead to
various undesirable consequences. But, here the Municipal Commissioner as
well as the Municipal Engineer have taken a stand that such situation had arisen
on account of the strike undertaken by the contractors. This position was
accepted by the Enquiry Officer and was also endorsed by this Court in the
connected writ proceedings, wherein it was held that the non floating of tender
cannot be imputed as a violation involving moral turpitude. Based on that, the
punishment of compulsory retirement imposed against the co-delinquent was set
__________
Page12 of 17
https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2026 07:53:39 pm )

2026:MHC:4777
WP No. 21000 of 2023
aside. When that being the case, the action of payment routed through the Junior
Engineer by the Municipal Engineer also cannot be imputed with any
delinquency involving moral turpitude. Therefore, in respect of the second
charge also, the deviation which referred by the Disciplinary Authority though
to some extent is reasonable, but cannot blame the petitioner solely for such
deviation, as it was the Municipal Engineer one Mr.D.Suresh Kumar who
allowed her to make payment to the Contractor, and now that, he has already
been discharged from all charges by this Court. Therefore, even the second
charge has not been made out against the petitioner.
14.Coming to the third charge, viz., there was a loss to the exchequer to
the tune of Rs.10,97,505/-. The Disciplinary Authority has relied upon the
Technical Committee reports. But, the Enquiry Officer had given a specific
reference that the purchase of material from the open market had arisen when
there were no rate contract for such item with the Public Works Department.
Even this charge falls back on the first charge of absence of floating the tender.
When this Court had accepted, the co-delinquent defence in respect of the
justification for non floating tenders and held that the same does not amount to
moral turpitude, the consequential action taken by the petitioner cannot be
viewed differently.
__________
Page13 of 17
https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2026 07:53:39 pm )

2026:MHC:4777
WP No. 21000 of 2023
15.Even for argument sake, though certain excess amount had been paid,
the Enquiry Officer had given a clear finding that such excess expenditure had
arisen on account of purchase of material from open market, as no rate contracts
were available with the Public Works Department. Though the Disciplinary
Authority has deviated, he has not traverse the very specific finding given by
the Enquiry Officer. Therefore, this Court is of the firm view that the lapses
which are referred cannot be elevated to the extent of a serious misconduct. No
doubt there are lapses. For such lapses not involving any moral turptitude, the
punishment of compulsory retirement is shockingly disproportionate. It is
relevant to refer that the order discharging the co-delinquent Mr.D.Suresh
Kumar in WP.No.15360 of 2019 has already been implemented, which factum
was not seriously disputed by the respondent.
16.At this juncture, it is also relevant to refer an abnormal delay in
conducting the disciplinary proceedings. The so called delinquency that had
taken place between 2004-2006, whereas the punishment was imposed after a
period of almost 20 years viz., on 16.03.2023.
17.The following dates would demonstrate the height of delay committed by the
Disciplinary Authority.
__________
Page14 of 17
https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2026 07:53:39 pm )

2026:MHC:4777
WP No. 21000 of 2023
2004-2005 - the alleged delinquency came to the light of the Department.
●
24.10.2010 - the charge memorandum issued [with delay of six years]
●
The enquiry report submitted on 31.07.2014 [after three years from the
●
date of the charge memorandum].
16.02.2018 - second show cause notice issued [after a period of three
●
years]
● 21.03.2018 - the petitioner submitted her explanation [within three
months]
● 16.03.2023- the impugned punishment imposed [after a period of five
years]
18.Therefore, the very unreasonable delay in imposing of punishment
must also be viewed seriously. While perusing the records, this Court could not
find any stay order or any other bona fide reason on the part of respondent for
such delay. When there are no hurdles, the very conduct of the respondents for
taking almost 20 years to impose the punishment, would definitely vitiate the
entire proceedings, as the petitioner was prejudiced at every stage and was
forced to undergo ordeals of disciplinary proceedings for all her 20 years of
service. Therefore, having this Court had arrived at a conclusion that the
charges are not proved, though certain lapses are there, considering the long
delay in concluding the disciplinary proceedings, this Court is of the firm view
__________
Page15 of 17
https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2026 07:53:39 pm )

2026:MHC:4777
WP No. 21000 of 2023
that the above lapse also would pale into insignificance at this length of time.
Hence, this Court would like to interfere with the impugned order.
19.In view of the above detailed discussions, the present writ petition is
allowed and the punishment imposed against the petitioner is set aside. As a
concomitant, the respondents are directed to regularize the service of the
petitioner with all attendant benefits. The above exercise is directed to be
completed within a period of four(4) weeks from the date of receipt of a copy of
this order. No costs.
26-11-2026
Index: Yes
Speaking order
Neutral Citation: Yes
KMI
To
1. The Additional Chief Secretary To Government
Municipal Administration And Water Supply, (me.4) Department,
Secretariat, Chennai- 9.
2. The Commissioner Of Municipal Administration
Office Of The Commissioner Of Municipal Administration, Chepauk,
Chennai- 5.
3. The Commissioner
Nagercoil Municipality, Nagercoil, Kanyakumari District.
4. The Collector
Kanyakumari District.
__________
Page16 of 17
https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2026 07:53:39 pm )

2026:MHC:4777
WP No. 21000 of 2023
C.KUMARAPPAN, J.
KMI
WP No. 21000 of 2023
26-11-2026
__________
Page17 of 17