Shree Samarth Spark Developers Private Limited vs Amardeep Constructions

Court
Bombay High Court

941-carbpl23540-2026-J.doc
AGK
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
IN ITS COMMERCIAL DIVISION
COMM ARBITRATION PETITION (L) NO. 23540 OF 2026
Shree Samarth Spark Developers LLP … Petitioner
V/s.
1. Amardeep Constructions
2. Keshavji Damji Minat
3. Premji Velji Patel
4. Jeram Jetha Gami
5. Govind Jetha Gami
… Respondents
Mr. Mayur Khandeparkar with Mr. Aadil
Parsurampuria, Mr. Malhar Bageshwar, and Mr. Samir
Suryawanshi for the petitioner.
ATUL
GANESH
KULKARNI
Digitally signed by
ATUL GANESH
KULKARNI
Date: 2026.07.28
11:21:47 +0530
Mr. A.R. Gole with Ms. Vishwoli V. Botte for respondent
Nos.2 and 3.
Mr.Rohan Sawant with Mr. Aman Saraf, and Ms. Sakshi
Agarwal i/by Mr. Bipin Joshi for respondent Nos.4 and
5.
CORAM : AMIT BORKAR, J.
RESERVED ON : JULY 24, 2026
PRONOUNCED ON : JULY 28, 2026
JUDGMENT:
1. By this petition filed under Section 9 of the Arbitration and
Conciliation Act, 1996, the petitioner is asking for interim
protection of its rights arising out of the Development Agreement
dated 31 December 2014, the First Supplementary Agreement
1

941-carbpl23540-2026-J.doc
dated 21 April 2016, the Second Supplementary Agreement dated
11 June 2021, the Third Supplementary Agreement dated 14 June
2021 and the Memorandum of Understanding dated 11 September
2023. According to the petitioner, these agreements govern the
rights and obligations of the parties in relation to the
redevelopment project and those rights require protection till the
disputes are decided in arbitration.
2. The facts leading to the filing of the present petition are as
follows. On 31 January 2009, the Slum Rehabilitation Authority
issued a Letter of Intent in favour of the petitioner for
redevelopment of the subject property. This Letter of Intent was
later revised on 14 January 2012 and again on 28 April 2021. On
31 December 2014, the petitioner and respondent No.1 entered
into a Development Agreement for joint development of the
subject property. Under this agreement, respondent No.1 received
development rights over land admeasuring 6,848.55 square metres
together with development potential of 12,655.47 square metres.
In return, respondent No.1 agreed to pay the petitioner Rs.52
crores in stages and also provide the constructed area mentioned
in the agreement. The agreement made respondent No.1
responsible for bearing all expenses connected with the project.
These included payment of premiums, obtaining permissions and
approvals, construction costs, payment of transit rent to slum
dwellers, dues and all other expenses relating to the rehabilitation
buildings and respondent No.1's share of the project. Respondent
No.1 also agreed to complete the SRA scheme, comply with all
conditions imposed by the SRA authorities, engage the required
2

941-carbpl23540-2026-J.doc
workforce, obtain the Completion Certificate and secure the
Occupation Certificate for the rehabilitation buildings at its own
cost. The agreement also contained a clause providing that
disputes between the parties would be resolved through
arbitration. On 21 April 2016, the parties executed the First
Supplementary Agreement. Under this agreement, the free sale
units to be shared between the petitioner and respondent No.1
were identified in Annexure "B". It also recorded the security
furnished by respondent No.1 for payment of the remaining
consideration of Rs.38 crores. By that time, respondent No.1 had
paid Rs.14 crores out of the total agreed consideration of Rs.52
crores. Subsequently, on 28 April 2021, the SRA issued a revised
Letter of Intent permitting utilisation of the Incentive Sale FSI.
3. On 11 June 2021, the parties executed the Second
Supplementary Agreement. Under this agreement, respondent
No.1 again accepted responsibility to bear all expenses for
construction of Rehabilitation Building No.4. Respondent No.1 also
agreed to continue paying transit rent to all slum dwellers until the
building was completed, and the Occupation Certificate was
obtained. On 14 June 2021, the petitioner and respondent No.1
executed the Third Supplementary Agreement. Under this
agreement, respondent No.1 provided security in favour of the
petitioner towards payment of the balance consideration of
Rs.11.04 crores.
4. On 11 September 2023, the parties entered into a
Memorandum of Understanding because Rehabilitation Building
No.4 had still not been completed. By that time, four rehabilitation
3

941-carbpl23540-2026-J.doc
buildings and one sale building had been completed and
Occupation Certificates had been obtained. Rehabilitation Building
No.4 and Sale Building No.2 remained incomplete. The
Memorandum recorded that respondent No.1 would concentrate
on completing Rehabilitation Building No.4. As security for
completion of the remaining work and payment of transit rent,
respondent No.1 offered 6,500 square feet of premises in favour of
the petitioner. It was also agreed that if respondent No.1 failed to
complete the remaining work, the secured premises would stand
released in favour of the petitioner, who would then be free to sell
them. Respondent No.1 assured that these premises were free from
any encumbrance and had neither been sold nor mortgaged. The
Memorandum also required respondent No.1 to all outstanding
transit rent and, after obtaining the Occupation Certificate for
Rehabilitation Building No.4, obtain the full Occupation Certificate
for Sale Building No.2. The Memorandum also contained an
arbitration clause.
5. On 17 September 2025, the Slum Rehabilitation Authority
passed an order on its own under Section 13(2) of the Slum Act
terminating the petitioner's appointment as developer of the
project. The order recorded that a stop work notice had been
issued on 7 March 2025 in respect of the sale building because
transit rent had not been paid. The order recorded that transit rent
of about Rs.3.87 crores was still payable to 73 slum dwellers.
Aggrieved by this order, the petitioner filed Slum Appeal No.382 of
2025 before the Apex Grievance Redressal Committee on 9
October 2025 challenging the termination order passed under
4

941-carbpl23540-2026-J.doc
Section 13(2) of the Slum Act. On 15 May 2026, the Apex
Grievance Redressal Committee stayed the operation of the order
passed under Section 13(2). While granting interim protection, it
directed the petitioner to deposit Rs.50 lakhs towards transit rent
and to complete the project on or before 1 September 2026.
According to the petitioner, this direction was complied with by
depositing Rs.50 lakhs and by making direct payments of Rs.1.5
crores to the slum dwellers towards transit rent. According to the
petitioner, financial obligations in relation to the project are still
outstanding. These include unpaid contractor dues of Rs.4.01
crores, pending LUC charges of Rs.3.76 crores, outstanding transit
rent of Rs.3.37 crores and pro rata charges payable to the
Municipal Corporation amounting to Rs.4.19 crores. The petitioner
has also placed on record the details of the unsold flats which ar
still available in the project.
6. On 13 June 2026, the petitioner issued a notice invoking the
arbitration agreement against the respondents. On 16 July 2026,
the present petition came to be filed before this Court. At the
initial stage, this Court passed an ad interim order in terms of
prayer clause (a), restraining the respondents from creating any
third party rights or otherwise dealing with the unsold flats until
orders.
7. Mr. Khandeparkar, learned Advocate appearing for the
petitioner, submitted that at this stage the petitioner is pressing the
reliefs contained in prayer clauses (a), (b), (e), (f), (g), (h), (i), (j)
and (k) of the petition. He submitted that, considering the facts of
the present case, the petitioner should be appointed as the agent of
5

941-carbpl23540-2026-J.doc
the Court Receiver because the Letter of Intent for the
redevelopment project continues to stand in the name of the
petitioner. Learned Advocate for the petitioner submitted that the
present petition is filed to ensure completion of the rehabilitation
building meant for the slum dwellers. According to him, the
petitioner is not seeking any relief at this stage in relation to
completion of the free sale building.
8. Learned Advocate for the petitioner submitted that the
present claim is founded upon Section 20 of the Specific Relief Act.
According to him, the petitioner is seeking enforcement of the
obligations by adopting the substituted mode of specific
performance contemplated under the said provision.
9. Inviting my attention to the Development Agreement dated
31 December 2014, learned Advocate for the petitioner submitted
that under Clause 2, the petitioner had granted development rights
to respondent No.1 as the co-developer. In return, respondent No.1
had agreed to pay the agreed monetary consideration and also
hand over constructed premises admeasuring 6,594.42 square feet
together with other agreed rights. Referring to Clause 5 of the
agreement, he submitted that respondent No.1 had accepted full
responsibility for bearing all expenses relating to construction of
both the rehabilitation buildings and the free sale component.
According to him, respondent No.1 was also required to comply
with all conditions contained in the Letter of Intent and all
directions and requirements imposed by the concerned authorities
for development of the project. Learned Advocate for the petitioner
then referred to the First Supplementary Agreement dated 21 April
6

941-carbpl23540-2026-J.doc
2016. He submitted that Annexure "B" to the agreement identified
the flats that were to be allotted to the petitioner. According to
him, Annexure "B" contained details of the petitioner's share in
Building No.2. He submitted that by a subsequent agreement
dated 9 February 2021, both parties agreed to modify Annexure
"B" of the Supplementary Agreement by substituting it with
Annexure "B5". The revised annexure included, among other flats,
Flat Nos.23, C-2001 and C-2002, which formed part of the
petitioner's allocation. He also relied upon the Memorandum of
Understanding dated 11 September 2023, which records that
respondent No.1 was required to concentrate on completing the
remaining work of Rehabilitation Building No.4, since completion
of that building was necessary for obtaining the Occupation
Certificate for Sale Building No.2.
10. Learned Advocate for the petitioner next relied upon Clause
5 of the Memorandum of Understanding dated 11 September
2023. He submitted that respondent No.1 had agreed to keep an
area admeasuring about 6,560 square feet carpet area in Building
No.2 as security in favour of the petitioner for completion of the
remaining construction work of Rehabilitation Building No.4.
Referring to Clause 6 of the Memorandum, he submitted that if
respondent No.1 failed to complete the balance construction work
of Rehabilitation Building No.4, the said secured area would stand
released in favour of the petitioner, who would then be entitled to
sell the same in the open market and utilise the sale proceeds for
completing the remaining construction work. Learned Advocate for
the petitioner submitted that Clause 8 of the Memorandum
7

941-carbpl23540-2026-J.doc
required respondent No.1 to pay the road pro rata charges before
applying for the full Occupation Certificate of Building No.2. He
submitted that under Clause 9, respondent No.1 was required to
all outstanding transit rent payable to the slum dwellers through
the petitioner before execution of the Memorandum. He submitted
that Clause 11 required respondent No.1 to complete the balance
construction work of Rehabilitation Building No.4. Referring to
Clause 16, he submitted that all disputes arising out of the
Memorandum, including disputes relating to interpretation of its
terms, rights, and obligations of the parties and any acts or
omissions connected with the agreement, were required to be
referred to arbitration. According to him, Clause 16 supersedes the
arbitration clause contained in Clause 31 of the Development
Agreement and, therefore, the present disputes are governed by
Clause 16 of the Memorandum of Understanding.
11. Learned Advocate for the petitioner also relied upon the
order dated 17 September 2025 passed by the Slum Rehabilitation
Authority under Section 13(2) of the Slum Act. He submitted that
while terminating the petitioner's appointment as developer, the
Authority recorded that the petitioner had failed to comply with
the directions for payment of provisional transit rent to the slum
dwellers. The Authority also relied upon the Auditor's Report dated
21 February 2025, which recorded that transit rent amounting to
Rs.3,87,54,325 remained unpaid and that 73 slum dwellers had
not received transit rent, which according to the Authority
amounted to breach of Circular No.153. He submitted that, in the
appeal preferred by the petitioner, the Apex Grievance Redressal
8

941-carbpl23540-2026-J.doc
Committee granted interim protection and directed the petitioner
to deposit 50% of the amount together with Rs.50 lakhs towards
transit rent before the SRA, which direction was subsequently
modified by the Committee.
12. Learned Advocate for the petitioner submitted that although
prayer clause (j) seeks recoup Rs.61.15 crores, the petitioner is, at
this stage, restricting its monetary claim to Rs.15.33 crores.
13. Mr. Sawant, learned Advocate appearing for respondent
Nos.4 and 5, invited my attention to Clause 31 of the registered
Development Agreement dated 31 December 2014. He submitted
that the arbitration clause provides that the Arbitrator has no
power to pass any order or award terminating or cancelling the
agreement or directing stoppage, suspension, or postponement of
the development work. According to him, when the Arbitrator
himself has no such power, this Court, while exercising jurisdiction
under Section 9 of the Arbitration and Conciliation Act, cannot
grant a relief which the Arbitrator is not competent to grant.
Learned Advocate for respondent Nos.4 and 5 submitted that the
petitioner has suppressed important facts from this Court. He
pointed out that on 6 May 2026 the petitioner had applied for a
full Occupation Certificate in respect of Rehabilitation Building
No.4, which according to him shows that the building was
complete. He also relied upon the appeal filed by the petitioner
before the Apex Grievance Redressal Committee challenging the
order passed under Section 13(2) of the Slum Act. He submitted
that in paragraph (p) of the appeal, the petitioner had stated that
the work of the building was 99% complete and that all slum
9

941-carbpl23540-2026-J.doc
dwellers would shortly be rehabilitated. He pointed out that in
paragraph (q) of the same appeal, the petitioner had stated that
transit rent had been paid to all slum dwellers up to November
2025. According to him, after April 2025 the petitioner never
issued any notice calling upon the respondents to pay any transit
rent. He also relied upon Exhibit D to the affidavit in reply, which
according to him shows that respondent No.1 had paid a total
amount of Rs.6,55,64,169 to the petitioner up to 19 March 2024
and that the said amount was paid towards transit rent for the
slum dwellers.
14. Referring to Clause 6 of the Memorandum of Understanding
dated 11 September 2023, learned Advocate submitted that both
parties had agreed that the security area would be released
proportionately to respondent No.1 as and when the remaining
construction work of Rehabilitation Building No.4 was completed.
According to him, the area admeasuring 6,560 square feet in
Building No.2, which formed part of respondent No.1's allocation,
was kept as security for meeting third party liabilities. He relied
upon Annexure C to the Memorandum and submitted that this
area of 6,560 square feet represents the maximum security
available to the petitioner and no larger claim can be made against
it. He submitted that Annexure D provides for proportionate
release of the respondents' flats after compliance with Clause 6 of
the Memorandum. According to him, an area of 435 square feet
remained to be released after completion of Rehabilitation
Building No.4. He therefore submitted that the real dispute
concerns 435 square feet, whereas the petitioner is seeking relief
10

941-carbpl23540-2026-J.doc
in respect of a much larger area measuring 13,627 square feet.
15. In reply to the petitioner's reliance on Section 20 of the
Specific Relief Act, learned Advocate submitted that the said
provision has no application to the facts of the present case.
According to him, Section 20 makes its operation subject to the
terms of the contract. Since the rights and obligations of the
parties are governed by their agreements, the petitioner cannot
invoke Section 20 to claim any independent right. He submitted
that the petitioner had not issued any written notice calling upon
respondent No.1 to perform its obligations before seeking
substituted performance.
16. Dealing with the petitioner's contention that Clause 16 of the
Memorandum of Understanding supersedes Clause 31 of the
registered Development Agreement, learned Advocate submitted
that this contention is contrary to the petitioner's own case. He
pointed out that both in the notice invoking arbitration and in the
present petition, the petitioner has relied upon the arbitration
clause contained in the registered Development Agreement. He
submitted that an arbitration clause contained in an unregistered
Memorandum of Understanding cannot replace or modify the
arbitration clause contained in a registered Development
Agreement. According to him, the disputes between the parties are
therefore governed by Clause 31 of the registered Development
Agreement.
17. Learned Advocate also invited my attention to paragraph 24
of the affidavit in reply. He submitted that the respondents have
11

941-carbpl23540-2026-J.doc
stated therein that minor works such as painting and polishing
remain to be completed and that about 99% of the construction
has been completed, including all structural work and slabs.
According to him, this demonstrates the willingness and ability of
the respondents to complete the project. He submitted that the
value of the remaining work is about Rs.4,01,37,788. As regards
the alleged outstanding property tax payable to the Municipal
Corporation, he submitted that such liability does not relate to
Rehabilitation Building No.4 but also concerns other portions of
the project being developed by the petitioner. Learned Advocate
relied upon Clause 19 of the Development Agreement. He
submitted that under the said clause, respondent No.1, as co-
developer, is prohibited from assigning its rights, title, interest, or
obligations under the agreement to any other person.
18. Learned Advocate then referred to the reliefs sought in the
petition. He submitted that the relief claimed in prayer clause (a)
is much wider than what the petitioner is entitled to seek. In so far
as prayer clause (b) is concerned, he submitted that the said relief
could operate till completion of the building. According to the
respondents, the building stands completed. He submitted that
prayer clause (c), which seeks a direction to the respondents to
complete the building, is inconsistent with the petitioner's own
statement made before the Apex Grievance Redressal Committee
that the construction was 99% complete. Lastly, learned Advocate
referred to Clause M of the petition, which contains the list of the
respondents' alleged pending financial obligations. He submitted
that the figures mentioned therein are unsupported by any
12

941-carbpl23540-2026-J.doc
documentary material and have no factual basis. On these
grounds, he submitted that the petition deserves to be dismissed.
19. In rejoinder, Mr. Khandeparkar, learned Advocate for the
petitioner, relied upon Clause 16 of the Memorandum of
Understanding dated 11 September 2023. He submitted that this
clause has replaced Clause 31 of the Development Agreement and,
therefore, there is no restriction on the powers of the Arbitrator.
According to him, Clause 16 authorises the Arbitrator to decide all
disputes relating to the rights and obligations of the parties. He
submitted that even if Clause 31 of the Development Agreement is
considered, it prevents the Arbitrator from passing an award
terminating the agreement or directing stoppage of the
development work. According to him, this restriction does not limit
the powers of this Court while exercising jurisdiction under
Section 9 of the Arbitration and Conciliation Act, 1996. He
therefore submitted that the reliefs sought in the present petition
are not barred by Clause 31 of the Development Agreement.
20. Learned Advocate for the petitioner then relied upon the
notice invoking arbitration dated 13 June 2026. He submitted that
paragraphs 9 and 14 of the notice called upon the respondents to
perform their obligations and, therefore, the notice satisfies the
requirement contemplated under Section 20 of the Specific Relief
Act. According to him, unless the respondents perform their part of
the contract, the redevelopment project cannot be completed. He
submitted that the photographs placed on record show that the
respondents' contention that the building is complete is incorrect.
According to him, though the structural work may have been
13

941-carbpl23540-2026-J.doc
completed, internal work still remains unfinished. He also
submitted that from the year 2019 till October 2024, the
respondents failed to pay transit rent to the slum dwellers and that
transit rent payable to 73 slum dwellers still remains unpaid. He
contended that three flats, which were allotted to the petitioner
and kept as security under the Memorandum of Understanding,
have been sold by the respondents. According to him, this conduct
shows an intention on the part of the respondents to dispose of the
secured assets.
21. Learned Advocate for the petitioner submitted that under the
Memorandum of Understanding, ten flats and one shop were kept
as security for performance of the respondents' obligations.
According to him, out of these secured properties, two flats have
been sold by the respondents. He submitted that completion of
Rehabilitation Building No.4 is necessary in the interest of the
slum dwellers who are still awaiting rehabilitation. He reiterated
that the petitioner is not seeking any relief at this stage in relation
to the free sale component of the project. The object of the present
petition is to ensure completion of the rehabilitation building so
that the slum dwellers receive possession of their premises. On
these grounds, he prayed that the petition be allowed in terms of
prayer clauses (a), (b), (e), (f), (h), (i), (j) and (k).
REASONS AND ANALYSIS:
22. I have heard the learned Advocate for the petitioner and the
learned Advocate appearing for respondent Nos.4 and 5 at length.
I have also carefully perused the Development Agreement dated 31
14

941-carbpl23540-2026-J.doc
December 2014, the three Supplementary Agreements, the
Memorandum of Understanding dated 11 September 2023, the
order passed by the Slum Rehabilitation Authority under Section
13(2) of the Slum Act, the order passed by the Apex Grievance
Redressal Committee, the correspondence exchanged between the
parties, the notice invoking arbitration and the pleadings filed
before this Court.
I. Whether Clause 16 of the Memorandum of Understanding
dated 11 September 2023 supersedes Clause 31 of the
Development Agreement dated 31 December 2014:
23. The first issue which arises for consideration is whether
Clause 16 of the Memorandum of Understanding dated 11
September 2023 supersedes Clause 31 of the Development
Agreement dated 31 December 2014.
24. Before considering the rival submissions, it is necessary to
examine the language used in the two arbitration clauses. Clause
31 of the Development Agreement provides that if any difference
arises between the parties in respect of the development of the
property, interpretation of any clause, any act or omission
connected with the agreement or any matter relating to the
project, such dispute shall be referred to arbitration. However, the
clause provides as follows:
"The Arbitrators shall not have any power or authority to
pass any order, direction or award for
termination/cancellation of these presents and/or to direct
discontinuance, postponement, stoppage of continuance of
the development work by the Co-Developer."
15

941-carbpl23540-2026-J.doc
25. The clause records that:
"Pending adjudication of the dispute by the arbitrator, the
construction and development work of the Project... shall
continue in accordance with these presents…"
26. Clause 16 of the Memorandum of Understanding, on which
reliance is placed by the petitioner, provides that disputes relating
to interpretation of the agreement, legal effect of its terms and
conditions, rights and liabilities of the parties and acts or omissions
connected with the agreement shall be referred to arbitration.
Unlike Clause 31, Clause 16 does not prohibit the Arbitrator from
granting any relief.
27. In my view, the submission of the petitioner that Clause 16
supersedes Clause 31 cannot be accepted in the manner in which
it is canvassed. The Memorandum of Understanding nowhere
states that Clause 31 of the Development Agreement stands
cancelled, deleted or substituted. There is no clause declaring that
the earlier arbitration agreement shall cease to operate. Had the
parties intended to extinguish the earlier arbitration clause ,
nothing prevented them from recording such intention in
language. The absence of such words assumes significance
because the Development Agreement constitutes the principal
contract governing the redevelopment project.
28. At the same time, the submission of the respondents that
Clause 31 governs the dispute also cannot be accepted without
qualification. The Memorandum of Understanding is executed
between the same parties. It creates additional rights and
obligations. It earmarks fresh security. It regulates completion of
16

941-carbpl23540-2026-J.doc
Rehabilitation Building No.4. It provides obligations regarding
transit rent, property taxes, road pro rata charges and release of
security area. It also records an agreement for reference of
disputes to arbitration. Therefore, the Memorandum of
Understanding cannot be ignored while determining the scope of
the arbitral reference.
29. In my opinion, the proper approach is to read both
documents harmoniously. Courts lean in favour of giving effect to
the clause of a contract rather than rendering one provision
redundant. Unless there is an inconsistency making operation
impossible, provisions executed between the same parties should
be construed in a manner which allows both to operate.
30. When so construed, Clause 31 continues to regulate disputes
arising under the Development Agreement. Clause 16, on the other
hand, extends the arbitration mechanism to disputes arising out of
the rights and obligations created under the Memorandum of
Understanding. Since the Memorandum supplements the
Development Agreement rather than replacing it, both clauses can
coexist. Even assuming for the sake of argument that Clause 31
governs the present disputes, the restriction incorporated therein
requires examination. The prohibition is against an award
directing termination or cancellation of the agreement or directing
discontinuance, postponement, or stoppage of the development
work. The clause does not state that the Arbitrator cannot grant
form of interim or protective relief. It does not prohibit directions
intended to preserve the subject-matter of arbitration or secure
performance of obligations. Significantly, the second part of Clause
17

941-carbpl23540-2026-J.doc
31 declares that pending adjudication of disputes, the construction
and development work shall continue. Thus, the object of the
clause appears to be continuity of the redevelopment project.
Prima facie, therefore, the clause is intended to prevent either
party from using arbitration as a means of stopping
redevelopment.
31. The petitioner is correct to the extent that the reliefs pressed
are founded upon the case that Rehabilitation Building No.4
should be completed and transit rent should continue to be paid.
These reliefs, on their face, do not seek termination of the
Development Agreement or stoppage of redevelopment. Whether
individual prayer falls within permissible limits is a question which
will require examination while dealing with each prayer. However,
because Clause 31 contains a limited restriction upon the
Arbitrator's powers, it cannot be said at this stage that relief
claimed in the petition is barred. The respondents are justified in
contending that the restriction contained in Clause 31 cannot be
ignored. If any relief results in termination of the arrangement or
displacement of respondent No.1 from execution of the project, the
Court would have to examine whether such relief travels beyond
the framework accepted by the parties.
32. Thus, the rival submissions are accepted in part. The
contention of the petitioner that Clause 16 replaces Clause 31 is
not borne out from the documents. The contention of the
respondents that Clause 31 alone governs the dispute irrespective
of subsequent Memorandum of Understanding also cannot be
accepted.
18

941-carbpl23540-2026-J.doc
33. The prima facie conclusion, therefore, is that the
Development Agreement and the Memorandum of Understanding
must be read together. Clause 31 continues to operate in respect of
the Development Agreement, while Clause 16 governs disputes
arising under the Memorandum of Understanding. Neither clause
renders the other redundant. The restrictions contained in Clause
31 remain relevant, but their applicability has to be tested with
reference to the nature of each relief sought by the petitioner. The
question, whether those restrictions curtail the powers of this
Court under Section 9 of the Arbitration and Conciliation Act, is a
different issue and is required to be examined independently.
II. Whether the restriction contained in Clause 31 of the
Development Agreement limits the jurisdiction of this Court under
Section 9 of the Arbitration and Conciliation Act, 1996:
34. The next question which arises for consideration is whether
the restriction contained in Clause 31 of the Development
Agreement, that the Arbitrator shall not pass any order or award
terminating the agreement or directing discontinuance of the
development work, also restricts the jurisdiction of this Court
while exercising powers under Section 9 of the Arbitration and
Conciliation Act, 1996.
35. Mr. Sawant submitted that the jurisdiction of this Court
under Section 9 is ancillary to the arbitral proceedings. According
to him, Section 9 is intended to preserve the efficacy of the arbitral
process and not to enlarge the powers of the Arbitrator. He
submitted that where the parties have agreed that the Arbitrator
19

941-carbpl23540-2026-J.doc
shall have no authority to terminate the agreement or interfere
with continuation of the development work, the Court cannot
grant indirectly what the Arbitrator cannot grant directly.
According to him, permitting such a course would rewrite the
contract between the parties.
36. Learned counsel submitted that several of the reliefs claimed
by the petitioner, particularly appointment of the Court Receiver,
permission to sell the respondents' unsold flats, transfer of sale
proceeds and authorising the petitioner to complete the remaining
work, displace respondent No.1 from execution of the project.
According to him, although the petitioner has not prayed for
termination of the Development Agreement, the consequence of
such reliefs would be exactly the same. He therefore submitted
that such reliefs fall within the prohibition contained in Clause 31.
37. Mr. Khandeparkar, on the other hand, submitted that the
argument proceeds on an incorrect understanding of Section 9.
According to him, the jurisdiction of this Court under Section 9
flows from the Arbitration and Conciliation Act and not from the
arbitration agreement executed between the parties. He submitted
that Clause 31 limits the powers of the Arbitrator while deciding
the disputes. It does not curtail the powers conferred upon the
Court by Parliament under Section 9.
38. Learned counsel submitted that none of the reliefs pressed
seeks cancellation of the Development Agreement or stoppage of
the redevelopment project. On the contrary, the relief is intended
to facilitate completion of Rehabilitation Building No.4 and
20

941-carbpl23540-2026-J.doc
payment of transit rent. According to him, continuation of the
project is the object of the petition and, therefore, the respondents
cannot rely upon Clause 31 to oppose interim measures which are
intended to secure completion of the obligations.
39. Before considering these rival submissions, it is necessary to
notice the scope of Section 9. The provision empowers the Court to
grant interim measures before commencement of arbitration,
during pendency of arbitration or after passing of the award but
before its enforcement. The object of the provision is to preserve
the subject matter of arbitration, secure the amount in dispute,
protect property, maintain status quo where necessary and grant
such interim measures as appear just and convenient in the facts of
the case.
40. The jurisdiction under Section 9 is discretionary. The Court
does not exercise ordinary civil jurisdiction while deciding a
Section 9 petition. At the same time, it originates from the
Arbitration and Conciliation Act. Therefore, while exercising
powers under Section 9, the Court is required to give due regard to
the rights of the parties, but it cannot ignore the scheme governing
interim protection pending arbitration. It is well settled that
Section 9 cannot be invoked to rewrite the contract between the
parties. Interim relief cannot be granted because it appears
equitable. The relief must remain consistent with the framework
accepted by the parties. The Court cannot create new rights or
impose obligations which the parties never agreed to undertake.
21

941-carbpl23540-2026-J.doc
41. Applying these principles, the first part of the respondents'
submission deserves acceptance to the extent that this Court
cannot, under the guise of interim protection, alter the relationship
between the parties or grant a relief which amounts to final
determination of the disputes. If an interim order removes
respondent No.1 from execution of the project or renders the
arbitral proceedings meaningless, such relief would require close
scrutiny. However, I am unable to accept the proposition canvassed
by the respondents that restriction imposed upon the Arbitrator
limits the powers of the Court under Section 9. Clause 31 is
addressed to the powers of the Arbitrator. The language employed
is significant. It states that:
"The Arbitrators shall not have any power or authority to
pass any order, direction, or award for
termination/cancellation of these presents and/or to direct
discontinuance, postponement, stoppage of continuance of
the development work by the Co-Developer."
42. The clause does not state that the Court exercising
jurisdiction under Section 9 shall also be deprived of its powers.
Had the parties intended to restrict the jurisdiction of the Court,
language to that effect would have been expected.
43. More importantly, the present petition cannot be examined
by looking at the nomenclature of the reliefs. The true nature and
effect of individual prayer must be analysed. A prayer seeking
preservation of security, disclosure of assets or protection against
alienation may stand on a different footing from a prayer
authorising sale of the respondents' properties or appointment of a
Receiver with authority to execute the remaining work. Whether
22

941-carbpl23540-2026-J.doc
any prayer crosses the limitation cannot be decided in the abstract.
It has to be examined prayer wise.
44. I also find substance in the submission of the petitioner that
the reliefs pressed proceed on the basis that Rehabilitation
Building No.4 should be completed. Prima facie, completion of the
rehabilitation building advances rather than obstructs the object
underlying Clause 31, continuation of the redevelopment project.
45. The present case also possesses a feature which cannot be
ignored. The dispute does not concern an ordinary contract alone.
The redevelopment project is undertaken under the Slum
Rehabilitation Scheme. Delay in completion directly affects
rehabilitation of slum dwellers, payment of transit rent and
compliance with obligations under the scheme. Therefore, while
exercising jurisdiction under Section 9, the Court is required to
balance not the rights of the parties but also the larger objective of
ensuring that the redevelopment project is not frustrated. This
Court must therefore adopt a balanced approach. The restriction
contained in Clause 31 cannot be rendered meaningless. The
jurisdiction under Section 9 cannot be treated as having
disappeared because the parties agreed to impose certain
limitations upon the Arbitrator.
46. In my prima facie view, the correct principle is that the
Court, while exercising powers under Section 9, must respect the
allocation of rights and obligations and should avoid granting an
interim measure which defeats the prohibition accepted by the
parties. At the same time, the Court retains jurisdiction to pass
23

941-carbpl23540-2026-J.doc
such protective and preservative orders as may be necessary to
safeguard the subject matter of arbitration, provided such orders
do not amount to termination of the arrangement or displacement
of the rights of either party before adjudication by the Arbitral
Tribunal. Accordingly, I hold, prima facie, that Clause 31 does not
exclude the jurisdiction of this Court under Section 9 of the
Arbitration and Conciliation Act. The restriction contained therein
is relevant while moulding the relief, but it is not by decisive of the
petition. Each interim relief claimed by the petitioner must,
therefore, be examined to ascertain whether it preserves the
subject matter of arbitration or whether, in substance, it travels
beyond the limitations accepted by the parties.
III. Whether the documents prima facie cast upon respondent
No.1 the obligations asserted by the petitioner:
47. The next question which requires consideration is whether,
on a prima facie reading of the Development Agreement dated 31
December 2014, the three Supplementary Agreements and the
Memorandum of Understanding dated 11 September 2023,
respondent No.1 had undertaken the obligations now asserted by
the petitioner. This issue assumes significance because relief sought
in the present petition is founded upon the allegation that
respondent No.1 committed breach of those obligations.
48. Mr. Khandeparkar submitted that the documents leave no
room for ambiguity. According to him, after execution of the
Development Agreement, respondent No.1 assumed complete
responsibility for financing and executing the redevelopment
24

941-carbpl23540-2026-J.doc
project. He submitted that respondent No.1 undertook to bear
expenditure relating to construction of the rehabilitation buildings
and the free sale buildings, payment of transit rent, charges, taxes,
premiums, consultant's fees, obtaining permissions, obtaining the
Occupation Certificates and other obligation necessary for
successful completion of the project. According to him, the
subsequent Supplementary Agreements and the Memorandum of
Understanding reaffirm these obligations and, therefore,
respondent No.1 cannot now dispute its liability.
49. Mr. Sawant did not dispute that the agreements cast
obligations upon respondent No.1. His principal submission is that
respondent No.1 has performed those obligations and that
insignificant finishing work remains. According to him, the
petitioner seeks to magnify minor pending work into a complete
failure of performance. He also submitted that some of the alleged
liabilities mentioned by the petitioner have no documentary basis
and cannot be accepted because they are stated in Exhibit "N" to
the petition.
50. Having considered the rival submissions, it becomes
necessary to examine the documents. In matters arising out of
agreements, the primary source of the parties' rights and
obligations is the contract executed by them. Unless the language
employed is ambiguous, the Court must give effect to the terms as
agreed between the parties. Clause 5 of the Development
Agreement is the principal provision dealing with the obligations
of respondent No.1. The language employed in Clause 5 is
comprehensive. It uses expressions such as "to bear and pay", "shall
25

941-carbpl23540-2026-J.doc
obtain", "shall complete", "shall comply" and "shall be liable". These
expressions are mandatory in nature and do not indicate that the
obligations are dependent upon future negotiations. Under Clause
5(i), respondent No.1 agreed to bear and pay all costs, charges,
and expenses until receipt of the Occupation Certificates of both
the rehabilitation buildings and the free sale buildings. The clause
includes expenditure relating to approvals, sanctions, construction
costs, premiums, payments, professional fees and the cost of
construction of the rehabilitation buildings as well as the
petitioner's allocated premises. Prima facie, therefore, the
obligation to finance and execute the construction work stands
assumed by respondent No.1. Clause 5(ii) obliges respondent No.1
to obtain permission, approval, revised layout, commencement
certificate, Occupation Certificate and other clearance necessary
for implementation of the Slum Rehabilitation Scheme. The clause
also requires respondent No.1 to keep those permissions valid until
completion of the project. This obligation again leaves little scope
for dispute. Clause 5(iii) assumes importance in the facts of the
present case. The clause provides that respondent No.1 shall bear
and pay all costs relating to development of the property, including
amended LOI charges, premiums, infrastructure charges, transit
rent, shifting charges, road pro rata charges, consultant's fees,
maintenance deposits, water charges, electricity charges,
compensation payable to and non-slum dwellers and other
incidental expenditure necessary for completion of the
redevelopment project. The clause records that respondent No.1
shall not be entitled to claim reimbursement of such expenditure
26

941-carbpl23540-2026-J.doc
from the petitioner. Therefore, the obligation to pay transit rent is
not an implied obligation sought to be introduced by the
petitioner. It forms part of the undertaking accepted by respondent
No.1 under the Development Agreement. Whether the obligation
has in fact been performed is a matter of evidence. However, the
existence of the obligation is beyond dispute on a plain reading of
Clause 5(iii). Clauses 5(v) and 5(vi) require respondent No.1 to
comply with condition imposed by the Slum Rehabilitation
Authority and other authorities and to complete implementation of
the Slum Rehabilitation Scheme at its own cost. These clauses also
record that respondent No.1 shall ensure that breaches committed
by it do not prejudice the petitioner's rights or interrupt the
development of the project. Clause 5(vii) requires respondent No.1
to engage contractors, labourers and other agencies and to carry
out construction in accordance with the sanctioned plans. Clause
5(xiii) obliges respondent No.1 to obtain the Occupation
Certificates of the rehabilitation buildings and call upon the
petitioner to take possession of its allocated premises. These
clauses collectively indicate that responsibility for actual execution
of construction work was also accepted by respondent No.1.
51. The obligations undertaken under the Development
Agreement are reaffirmed in the subsequent agreements. The First
Supplementary Agreement records that all costs relating to the
proposed additional development, approvals, sanctions,
construction and obtaining the Occupation Certificate shall be
borne and paid by respondent No.1. Clause 5 thereof again
provides that respondent No.1 shall bear all costs relating to
27

941-carbpl23540-2026-J.doc
construction of Rehabilitation Building No.4, payment of
premiums, pro rata charges, LUC charges, consultant's fees and
payment of transit rent to all slum dwellers until possession of the
rehabilitation premises is handed over. The Second Supplementary
Agreement reinforces the same arrangement. While creating
additional security for payment of the balance consideration, it
does not dilute any of the obligations undertaken by respondent
No.1. On the contrary, the security arrangement proceeds on the
assumption that respondent No.1 remains liable to perform the
obligations and that the petitioner requires adequate security in
case of default.
52. The Memorandum of Understanding dated 11 September
2023 assumes significance because it was executed after the
parties had acquired knowledge of the delay in completion of
Rehabilitation Building No.4. Recital "E" records that respondent
No.1 had completed Sale Building No.2, Rehabilitation Building
No.3 and part of Rehabilitation Building No.4 and that it was then
focusing on completion of the remaining portion of Rehabilitation
Building No.4. Thus, even respondent No.1 acknowledged under
the Memorandum that Rehabilitation Building No.4 was yet to be
completed. Clause 5 of the Memorandum provides that respondent
No.1 agreed to earmark a security area admeasuring 6,560 square
feet from its allocation in Sale Building No.2 for completion of the
remaining construction work of Rehabilitation Building No.4 and
payment of transit rent, property taxes, road pro rata charges and
all expenses necessary for obtaining the Occupation Certificate.
This clause links the security area with performance of the
28

941-carbpl23540-2026-J.doc
obligations contained in Clauses 5(i) to 5(xv) of the Development
Agreement. Clause 6 is significant. It provides that if respondent
No.1 is unable to complete the remaining construction work or
discharge the necessary liabilities, the security area would stand
released in favour of the petitioner for sale in the open market so
that the petitioner may recover the expenditure required for
completion of the pending work. Thus, the parties contemplated
the possibility of default and agreed upon a mechanism intended
to protect completion of the rehabilitation building. Clause 7
records an assurance by respondent No.1 that the security area
had not been sold or mortgaged. Clause 8 obliges respondent No.1
to bear the road pro rata charges. Clause 9 once again obliges
respondent No.1 to all outstanding transit rent before execution of
the Memorandum and continue payment of transit rent until
possession of Rehabilitation Building No.4 is handed over to the
slum dwellers. Therefore, when all the documents are read
together, a consistent pattern emerges. Agreement executed
between the parties proceeds on the basis that respondent No.1
bears the primary responsibility for financing, executing and
completing Rehabilitation Building No.4, obtaining the necessary
permissions and Occupation Certificate, paying transit rent and
discharging the liabilities connected with the redevelopment
project. The subsequent agreements do not substitute these
obligations. They reaffirm them while strengthening the security
available to the petitioner in the event of default.
53. The submission of the respondents that the project is
complete may have relevance while considering whether breach
29

941-carbpl23540-2026-J.doc
has in fact occurred or whether the reliefs claimed are
proportionate. However, such submission does not dilute the
obligations. Completion of ninety-nine percent work, assuming the
statement to be correct, does not obliterate the obligation to
complete the remaining one percent if such balance work is
necessary for obtaining the Occupation Certificate or handing over
possession to the slum dwellers. Likewise, the respondents'
contention that certain financial liabilities are disputed cannot by
negate the undertaking to bear those liabilities. The exact quantum
of the outstanding dues may require evidence and adjudication
before the Arbitral Tribunal. Nevertheless, the agreements cast
responsibility upon respondent No.1 to bear such expenditure.
54. I therefore hold, prima facie, that the documents relied upon
by the petitioner impose upon respondent No.1 the obligations of
completing Rehabilitation Building No.4, obtaining the requisite
Occupation Certificate, paying transit rent to the slum dwellers,
discharging dues and complying with the conditions imposed by
the competent authorities. The foundation of the petition is
therefore prima facie established.
IV. Whether the petitioner has established, prima facie, that
respondent No.1 committed breach of its obligations:
55. Having held that the documents, prima facie, cast upon
respondent No.1 the obligation to finance, execute and complete
Rehabilitation Building No.4, pay transit rent and discharge the
other liabilities, the next question which arises is whether the
material placed before this Court prima facie establishes that
30

941-carbpl23540-2026-J.doc
respondent No.1 has failed to perform those obligations. It is upon
an affirmative answer to this question that the petitioner can claim
interim protection under Section 9 of the Arbitration and
Conciliation Act.
56. Having considered the rival submissions, it is necessary to
bear in mind the limited scope of the present enquiry. At this stage,
the Court is not required to record a final finding that respondent
No.1 has committed breach of the contract. Such a determination
can be made by the Arbitral Tribunal after recording evidence. The
Court is concerned with the existence of a prima facie case based
upon the documents and the contemporaneous material placed on
record. In my prima facie opinion, the execution of the
Memorandum of Understanding dated 11 September 2023
constitutes a significant circumstance. Parties do not create fresh
security or redefine obligations where the original contract has
been performed. The Memorandum records that Rehabilitation
Building No.4 remained incomplete and creates a mechanism for
ensuring its completion together with payment of transit rent and
discharge of dues. This contemporaneous document lends support
to the petitioner's contention that the obligations had not been
fully performed as on that date. Significant is the fact that Clause 5
of the Memorandum earmarks specific security for completion of
the remaining work. If no obligation remained outstanding,
creation of such elaborate security would appear unnecessary.
Though this circumstance is not conclusive of breach, it prima facie
indicates that both parties recognised the existence of pending
obligations requiring protection.
31

941-carbpl23540-2026-J.doc
57. The respondents' submission that ninety-nine percent of the
work stands completed cannot be rejected outright. It is possible
that the remaining work is comparatively limited in quantity.
However, completion of a redevelopment project cannot be
measured by percentage of physical construction. The obligation is
not to raise a structure. It extends to obtaining the Occupation
Certificate, clearing dues, paying transit rent till possession is
handed over and fulfilling condition necessary for occupation by
the slum dwellers. A building may be physically complete, yet if
the Occupation Certificate cannot be obtained because
compliances remain unfulfilled, the obligation cannot be said to
have been fully discharged. Similarly, continued liability towards
transit rent survives until possession is handed over in accordance
with the terms. Therefore, the respondents' reliance upon the
alleged stage of physical construction, by, does not answer the
petitioner's allegations.
58. The proceedings initiated under Section 13(2) of the Slum
Act also deserve consideration. I am unable to accept the
petitioner's submission that the order passed by the Slum
Rehabilitation Authority establishes breach. , I am unable to accept
the respondents' submission that the order should be ignored
because its operation has been stayed by the Apex Grievance
Redressal Committee. The stay granted by the appellate authority
suspends the operative consequences of the order; it does not
erase the fact that proceedings were initiated or that findings were
recorded by the Competent Authority. At this stage, the
proceedings under Section 13(2) constitute one relevant
32

941-carbpl23540-2026-J.doc
circumstance among several others. They cannot be treated either
as conclusive proof of breach or as irrelevant. The dispute
regarding the precise quantum of transit rent and other
outstanding liabilities also cannot be resolved in the present
proceedings. The respondents are correct in submitting that those
figures may require accounting before the Arbitral Tribunal.
Nevertheless, the obligation to pay transit rent is not disputed. The
controversy is confined to the amount remaining unpaid. Such
dispute regarding quantum does not, at this stage, negate the
petitioner's prima facie case that the obligation continues.
59. As regards the alleged dealing with the security premises, the
material placed by the petitioner raises an issue requiring
adjudication before the Arbitral Tribunal. Since the respondents
dispute the factual allegations, this Court refrains from recording
any final conclusion. However, the allegation cannot be brushed
aside as without substance, particularly when the documents
emphasise preservation of the security area until performance of
the obligations.
60. Viewed cumulatively, the contemporaneous documents, the
execution of the Memorandum of Understanding, the creation of
additional security, the admitted non-obtaining of the Occupation
Certificate for Rehabilitation Building No.4, the controversy
regarding transit rent and the proceedings initiated under Section
13(2) collectively disclose a prima facie dispute regarding
performance of respondent No.1's obligations.
33

941-carbpl23540-2026-J.doc
61. Accordingly, I hold, prima facie, that the petitioner has
succeeded in demonstrating that respondent No.1 has not shown
complete performance of all the obligations undertaken under the
Development Agreement, the Supplementary Agreements and the
Memorandum of Understanding. Whether such non-performance
constitutes a breach attracting the consequences claimed by the
petitioner is a matter which must be determined by the Arbitral
Tribunal upon appreciation of evidence.
V. Whether the petitioner has made out a prima facie case for
protection of the security created under the documents and
whether there exists a real apprehension that the subject matter of
arbitration may be defeated:
62. The next question which requires consideration is whether
the petitioner has established a prima facie case for protection of
the security created under the contract and whether the material
placed before this Court discloses a reasonable apprehension that,
unless interim protection is granted, the subject matter of the
arbitration may be rendered ineffective.
63. Mr. Khandeparkar submitted that the security created under
the Memorandum of Understanding dated 11 September 2023 is a
specific portion of the free-sale component admeasuring
approximately 6,560 square feet as security to ensure completion
of Rehabilitation Building No.4, payment of transit rent and
discharge of the remaining obligations undertaken by respondent
No.1. He submitted that the security constitutes a part of the
arrangement and was created because the parties recognised that
34

941-carbpl23540-2026-J.doc
completion of the rehabilitation project remained uncertain.
Learned counsel contended that out of the security area of 6,560
square feet, respondent No.1 has sold two flats without obtaining
the consent of the petitioner, although the Memorandum of
Understanding contemplated preservation of the security for the
purposes agreed between the parties. According to him, such
conduct demonstrates that respondent No.1 is dealing with the
security contrary to the contract. Learned counsel further
submitted that this allegation has not been denied in the affidavit-
in-reply. Per contra, Mr. Sawant submitted that the petitioner has
exaggerated the situation. According to him, respondent No.1
continues to be the owner of the free-sale component and is
entitled to deal with its property.
64. It is necessary to appreciate the nature of the security
created under the contract. The security contemplated under
Clause 5 of the Memorandum of Understanding is different from
an ordinary asset. A defined portion of the free-sale component
measuring approximately 6,560 square feet is identified. Such
identification indicates that the parties intended that a particular
asset should remain available for securing performance of the
contract. The contract indicate that the security was intended to
ensure completion of Rehabilitation Building No.4, payment of
transit rent, discharge of statutory liabilities and fulfillment of the
remaining obligations undertaken by respondent No.1. Therefore,
preservation of the security is directly connected with preservation
of the arrangement.
35

941-carbpl23540-2026-J.doc
65. The petitioner has made an assertion that two flats forming
part of the security area have been sold without obtaining its
consent. Upon examining the affidavit-in-reply, I find that there is
no specific denial of this factual allegation.
66. At this stage of the proceedings, for the limited purpose of
deciding the present application under Section 9, the petitioner's
allegation that two flats forming part of the identified security area
have been dealt with without its consent constitutes a prima facie
circumstance which cannot be brushed aside. If that allegation
proves to be correct, it indicates that the security created by the
parties has begun to diminish. Once an identified security is
alienated, restoration of the original position may become difficult.
Even if the petitioner succeeds in arbitration, the contractual
arrangement between the parties may cease to exist in its original
form.
67. It is important that the petitioner has invoked arbitration
alleging defaults in completion of Rehabilitation Building No.4,
payment of transit rent and discharge of statutory liabilities.
Whether those allegations succeed is a matter for the Arbitral
Tribunal. Nevertheless, when those allegations are read together
with the prima facie material regarding the security, the
apprehension expressed by the petitioner to be justified. The object
of Section 9 is to ensure that the subject matter of arbitration is
not defeated before the Arbitral Tribunal has an opportunity to
adjudicate the disputes. If the identified security, which forms
component of the arrangement between the parties, is permitted to
be alienated during pendency of arbitration, there exists a real
36

941-carbpl23540-2026-J.doc
possibility that the eventual arbitral award may become incapable
of enforcement.
68. Upon an overall assessment of the pleadings, the contractual
documents and the rival submissions, I am satisfied that the
petitioner has established a prima facie case for protection of the
security created under the Memorandum of Understanding. I
further hold that the allegation regarding sale of two flats forming
part of the security area gives rise to a reasonable apprehension
that, unless appropriate interim protection is granted, the
remaining security may be dealt with in a manner capable of
frustrating the subject matter of the arbitral proceedings.
Consequently, the security deserves preservation by appropriate
interim orders.
VI. Whether the petitioner is entitled to invoke Section 20 of the
Specific Relief Act, 1963 and whether the requirements for
substituted performance stand satisfied:
69. I have given anxious consideration to the rival submissions
advanced by the learned counsel appearing for the parties on the
applicability of Section 20 of the Specific Relief Act, 1963. The
controversy is not whether respondent No.1 has committed breach
of its obligations. The real question is whether, assuming such
breach exists, the petitioner has acquired the statutory right to
undertake substituted performance through another agency and
recover the expenditure from respondent No.1. This issue has to be
answered not only by referring to the documents executed
between the parties but also by examining the conditions
37

941-carbpl23540-2026-J.doc
incorporated by Parliament in Section 20 of the Specific Relief Act.
70. Mr. Khandeparkar submitted that the documents leave no
manner of doubt that respondent No.1 alone accepted
responsibility for completion of Rehabilitation Building No.4. He
submitted that the Development Agreement, the Supplementary
Agreements as well as the Memorandum of Understanding cast the
obligation of financing, constructing and completing the
rehabilitation building upon respondent No.1. According to him,
despite execution of the Memorandum of Understanding in
September 2023 and despite several assurances thereafter,
respondent No.1 neither completed the rehabilitation building nor
paid the transit rent nor discharged the statutory liabilities.
Learned counsel submitted that the petitioner cannot be compelled
to wait while the rehabilitation project remains incomplete and the
burden towards the slum dwellers continues to increase every
month. Learned counsel argued that the parties anticipated the
possibility of such default while executing the Memorandum of
Understanding. He invited attention to Clause 5 thereof and
submitted that the security area was earmarked so that, in the
event respondent No.1 failed to perform its obligations, the
petitioner would have sufficient security available for completing
the remaining construction work. According to him, the security
was not created to secure repayment of money. It was intended to
ensure completion of the rehabilitation project. Therefore,
according to the learned counsel, permitting respondent No.1 to
continue in breach would defeat the object for which the security
arrangement was incorporated by the parties. Learned counsel
38

941-carbpl23540-2026-J.doc
submitted that the petitioner has invoked the arbitration
agreement and called upon respondent No.1 to perform its
obligations. According to him, respondent No.1 has failed to
honour those obligations despite opportunities. It was therefore
contended that further insistence upon performance by respondent
No.1 would be formality and would prolong the hardship suffered
by the slum dwellers awaiting possession of their rehabilitation
premises. He submitted that the Court should, therefore, permit
the petitioner to resort to substituted performance.
71. Per contra, Mr. Sawant submitted that Section 20 makes its
operation subject to the terms of the contract. Since the rights and
obligations of the parties are governed by their agreements, the
petitioner cannot invoke Section 20 to claim any independent
right. He submitted that the petitioner had not issued any written
notice calling upon respondent No.1 to perform its obligations
before seeking substituted performance.
72. Having considered the rival submissions, it becomes
necessary to first examine the scheme and object of Section 20.
Prior to the amendment of the Specific Relief Act in the year 2018,
an aggrieved party was ordinarily required to approach the Court
for specific performance or damages. The amendment introduced
the concept of substituted performance with the apparent
legislative intention that contracts should not remain unperformed
merely because litigation is pending. Parliament recognised that in
appropriate cases the injured party should be permitted to have
the work completed through another agency and thereafter
recover the expenditure from the party committing breach.
39

941-carbpl23540-2026-J.doc
However, while creating this remedy, Parliament incorporated
safeguards. The Legislature did not confer an unrestricted right
upon every aggrieved party to immediately remove the defaulting
contractor and substitute another agency. Instead, it prescribed
conditions which are required to be fulfilled before such drastic
consequences follow.
73. The first safeguard appears in sub-section (2) of Section 20
which provides:
"No substituted performance of contract under sub-section
(1) shall be undertaken unless the party who suffers such
breach has given a notice in writing, of not less than thirty
days, to the party in breach calling upon him to perform the
contract within such time as specified in the notice, and on
his refusal or failure to do so, he may get the same
performed by a third party or by his own agency." .
74. The Legislature has employed negative language by
providing that "No substituted performance... shall be undertaken
unless..." a written notice of not less than thirty days is first issued.
The use of negative words in a statute indicates that the condition
is mandatory unless a contrary intention is apparent from the
legislative scheme. I find nothing in Section 20 suggesting that
Parliament intended the Court to waive or dispense with this
statutory requirement. The object behind the statutory notice
serves a substantive purpose. It grants the party alleged to be in
breach one final opportunity to perform the contract. Commercial
disputes often arise because of delays, misunderstandings or
temporary difficulties. Parliament appears to have considered that
before the relationship is altered by substituted performance, the
40

941-carbpl23540-2026-J.doc
party alleged to be in breach should receive a statutory notice
informing it that failure to perform within the specified period
would result in substitution by another agency.
75. The notice dated 13 June 2026 records several allegations of
breach. It calls upon respondent No.1 to complete the project and
remedy the defaults. It invokes arbitration and records that the
petitioner reserves its right to seek specific performance, damages,
interim protection under Section 9, completion of the project and
other consequential reliefs. The notice states that the respondents
should remedy the breaches and complete the pending obligations.
However, a careful reading of the notice discloses that it cannot be
equated with the statutory notice contemplated by Section 20(2).
The Legislature has prescribed specific requirements. The notice
must be "of not less than thirty days" and must call upon the
defaulting party to perform the contract within the time specified
therein before substituted performance is undertaken.
76. In the present case, paragraph 17 of the notice calls upon the
respondents to communicate their concurrence for appointment of
an Arbitrator and remedy the breaches "within seven days from the
receipt of this notice." Thus, instead of granting the statutory
minimum period of thirty days, the petitioner granted only seven
days. Where Parliament prescribes a minimum statutory period,
the Court cannot reduce that period by invoking the doctrine of
substantial compliance. The Legislature has consciously chosen
thirty days. Had Parliament intended to permit shorter periods
depending upon the facts of each case, it would have used
different language. Judicial interpretation cannot rewrite the
41

941-carbpl23540-2026-J.doc
statute.
77. Section 20 does not create an exception based upon previous
breaches. Even where repeated defaults have occurred, the
Legislature still requires written notice of not less than thirty days
before substituted performance is undertaken. The Court cannot
introduce an exception which Parliament has not enacted.
78. The petitioner relied upon the provisions contained in the
Memorandum of Understanding, particularly Clause 5 and Clause
6, to contend that the parties contemplated utilisation of the
security for completion of the remaining work. There can be no
dispute that the contractual documents recognise such eventuality.
But contractual provisions cannot override statutory requirement.
If the Legislature prescribes a mandatory procedure before
substituted performance can be undertaken, the parties cannot
dispense with that procedure by contract.
79. Another circumstance also deserves consideration. The
invocation notice simultaneously reserves the petitioner's right to
seek specific performance and also reserves its right of completing
the project. At this stage, no final election of remedies has been
made. This is also evident from the present petition, wherein the
petitioner has prayed for directions compelling respondent No.1 to
perform its contractual obligations while simultaneously seeking
liberty to complete the project. Such alternative pleading is
permissible at the stage of litigation. However, once Section 20 is
actually invoked and substituted performance is undertaken, sub-
section (3) declares that the aggrieved party "shall not be entitled
42

941-carbpl23540-2026-J.doc
to claim relief of specific performance." Therefore, the
consequence contemplated by Section 20(3) has not yet arisen
because substituted performance has not been undertaken.
80. The proviso to sub-section (2), reads thus:
"Provided that the party who suffers such breach shall not be
entitled to recover the expenses and costs under sub-section
(1) unless he has got the contract performed through a third
party or by his own agency." .
81. The proviso to sub-section (2) also supports the above
conclusion. It declares that recovery of expenditure is permissible
after the contract has been performed through a third party or by
the aggrieved party. Admittedly, no such substituted performance
has yet taken place. Consequently, the stage contemplated by the
proviso has also not yet arrived.
82. Thus, although I find substance in the petitioner's submission
that respondent No.1 has prima facie failed to perform several
obligations and that the documents contemplate utilisation of the
security in the event of default, those circumstances do not confer
the statutory right of substituted performance under Section 20.
The statutory right under Section 20 arises after compliance with
the statutory conditions. Those conditions include issuance of a
notice of not less than thirty days, failure, or refusal of the
defaulting party to perform within that period and thereafter
actual substituted performance through another agency or by the
aggrieved party. These stages have not yet been completed in the
present case.
43

941-carbpl23540-2026-J.doc
83. Consequently, I hold that the petitioner has established a
prima facie breach requiring adjudication by the Arbitral Tribunal.
The petitioner has also established that the contract envisage a
mechanism for protecting completion of the project. However, the
petitioner has not, as on the date of filing of the present petition
on 7 July 2026, satisfied the statutory requirements prescribed
under Section 20(2) of the Specific Relief Act, 1963 for invoking
substituted performance, inasmuch as the notice dated 13 June
2026 granted only seven days' time and not the minimum period
of thirty days contemplated by the provision. I therefore hold that
the petitioner is presently not entitled to invoke substituted
performance under Section 20 of the Specific Relief Act.
84. However, the matter does not conclude there. The
respondents proceeded on the assumption that once Section 20 is
held to be inapplicable, every form of interim arrangement
enabling completion of the rehabilitation project becomes
impermissible. It is necessary to bear in mind that the present
proceedings are under Section 9 of the Arbitration and
Conciliation Act. The source of jurisdiction exercised by this Court
is different. Section 9 empowers the Court to grant interim
measures for preservation, protection and securing the subject
matter of arbitration pending adjudication before the Arbitral
Tribunal. The jurisdiction exercised under Section 9 originates
from the statute. While exercising such jurisdiction, the Court
respects the contract rights agreed between the parties, but the
power flows from the Arbitration and Conciliation Act. The
immediate concern before the Court is of a different nature. The
44

941-carbpl23540-2026-J.doc
rehabilitation building remains incomplete. Transit rent liabilities
continue. Contractor dues, statutory charges and municipal dues
are outstanding. Simultaneously, there exists security in the form
of the unsold free-sale premises which the parties earmarked
under the Memorandum of Understanding. If the Court merely
records that Section 20 has not been complied with and declines
interim arrangement, the consequence may be that the
rehabilitation building will remain incomplete until conclusion of
arbitration. Arbitration proceedings involving disputes of this
nature may require evidence. During that period the slum dwellers
would continue to remain deprived of rehabilitation. The transit
rent liability may increase. The security may gradually lose its
utility. Section 9 has been enacted to prevent such situations where
the arbitral award may become ineffective because the subject
matter requiring protection has deteriorated beyond utility.
85. The distinction is important. Where substituted performance
is undertaken under Section 20, the party acts in assertion of its
own rights and seeks recovery of expenditure from the defaulting
party. In contrast, where the Court appoints a Receiver and
authorises an Agent to act on behalf of the Receiver, the authority
flows from the order. The Agent does not derive any right by virtue
of such appointment. A person, while acting as Agent of the Court
Receiver, would execute the directions issued under the authority
of the Court. Such appointment neither transfers ownership of the
free-sale premises nor confers development rights upon the
petitioner. The legal possession remains with the Court Receiver.
Every receipt and every expenditure remain accountable. Every
45

941-carbpl23540-2026-J.doc
decision remains subject to supervision of the Receiver and, after
constitution, to further directions of the Arbitral Tribunal. Thus,
the interim arrangement contemplated by this Court cannot be
equated with recognition of the petitioner's right under Section 20.
The requirements prescribed under Section 20 remain relevant and
will require consideration by the Arbitral Tribunal. However, those
provisions do not extinguish the jurisdiction in this Court under
Section 9 to evolve interim arrangement for preservation of the
redevelopment project.
86. I, therefore, hold that this Court exercising its jurisdiction
under Section 9 of the Arbitration and Conciliation Act is
competent devise an interim arrangement through the Court
Receiver for preservation and completion of the rehabilitation
component and to safeguard the interests of the slum dwellers,
providing that such arrangement does not confer proprietary rights
upon the petitioner, does not amount to adjudication of the
disputes and remains subject to the decision of the Arbitral
Tribunal.
VII. Whether the petitioner deserves to be appointed as Agent of
the Court Receiver for completion of Rehabilitation Building No.4:
87. Having held that the petitioner has not, at this stage,
acquired a right to substituted performance under Section 20 of
the Specific Relief Act, the next question which arises is whether
this Court, while exercising jurisdiction under Section 9 of the
Arbitration and Conciliation Act, should merely preserve the
security by an order of injunction or whether the facts of the
46

941-carbpl23540-2026-J.doc
present case require an interim arrangement so that the
rehabilitation project does not remain incomplete.
88. Ordinarily, a Court exercising jurisdiction under Section 9
should be slow in passing an order which has the effect of
displacing one party from performance of the contract merely
because breach is alleged. Interim jurisdiction is intended to
preserve rights pending adjudication. The redevelopment in
question forms part of a Slum Rehabilitation Scheme. The object of
such scheme is not merely construction of buildings for
commercial purpose. Its object is rehabilitation of eligible slum
dwellers by providing them permanent alternate accommodation.
Delay in completion of such project therefore has consequences
extending beyond the rights of the petitioner and respondent No.1.
Every month of delay results in displacement of slum dwellers.
Transit rent liability accumulates. Contractor dues remain unpaid.
Municipal and statutory liabilities continue to remain outstanding.
Consequently, the dispute acquires a public element which cannot
be ignored while moulding relief under Section 9. The Court
cannot lose sight of the realities. According to the petitioner,
unpaid contractor dues amount to approximately Rs.4.01 crores.
LUC charges remain payable to the extent of approximately
Rs.3.76 crores. Outstanding transit rent is stated to be
approximately Rs.3.37 crores. Pro-rata charges payable to the
Municipal Corporation are stated to be approximately Rs.4.19
crores. Whether every figure is proved or not is a matter which
shall be examined before the Arbitral Tribunal. Nevertheless, the
existence of liabilities prima facie indicates that the project cannot
47

941-carbpl23540-2026-J.doc
be treated as having reached closure.
89. The respondents have submitted that the project is ninety-
nine percent complete and only minor finishing work remains. At
this stage, this Court is not required to record any conclusive
finding on the percentage of completion. The rival versions
disclose that the extent of the remaining work constitutes a
disputed question requiring evidence. Consequently, no final
conclusion can be recorded upon affidavits.
90. One circumstance assumes considerable importance. The
Apex Grievance Redressal Committee, while passing the order
dated 15 May 2026, stayed the order made under Section 13(2).
Simultaneously, it directed the petitioner to deposit Rs.50 lakhs
towards transit rent and further directed the petitioner to complete
the project on or before 1 September 2026. This Court is
independently required to examine the issues arising before it.
However, the order cannot be treated as irrelevant. It shows that
the authority entrusted with supervision of the Slum Rehabilitation
Scheme considered early completion of the rehabilitation project
to be the immediate concern. It shows that, at least for the purpose
of protecting the rehabilitation scheme, the authority considered it
appropriate to call upon the petitioner to facilitate completion of
the project. The petitioner has placed material indicating that it
complied with the said order by depositing Rs.50 lakhs and
making payments aggregating Rs.1.50 crores towards transit rent
payable to slum dwellers. At this stage, this Court is not recording
any final finding regarding the consequences of such payments.
Nevertheless, such conduct prima facie indicates that the petitioner
48

941-carbpl23540-2026-J.doc
has assumed financial responsibility in relation to the
rehabilitation component pursuant to the directions of authority.
91. Another aspect deserves notice. The petitioner has produced
particulars of unsold flats available in the free-sale component.
Thus, the present case is not one where the Court is required to
create new security. The parties had earmarked assets under the
contract. The Court is therefore concerned with regulating the use
and preservation of an existing security and not with creating fresh
rights.
92. In the facts of the present case, I am not persuaded that a
order of injunction restraining alienation would protect the subject
matter of arbitration. Such an order may preserve the identified
flats, but it does not ensure completion of Rehabilitation Building
No.4. If the rehabilitation building continues to remain incomplete,
the object behind creation of the security may stand frustrated.
Section 9 does not confine the Court merely to granting orders of
preservation. The provision confers wide powers to mould an
interim arrangement appropriate to the peculiar facts of each case,
provided such arrangement remains temporary. The question
therefore is not whether respondent No.1 should be replaced by
the petitioner. The real question is whether an arrangement can be
evolved so that the rehabilitation component is completed without
finally deciding the contractual disputes.
93. In my opinion, appointment of the Court Receiver furnishes
such arrangement. Once the Court Receiver is appointed, the
security comes into the custody of an officer of the Court. Neither
49

941-carbpl23540-2026-J.doc
party obtains exclusive control over the property. Every step
remains subject to supervision of the Receiver and to further
orders of the Court or, after constitution, of the Arbitral Tribunal.
Appointment of a Receiver therefore protects both sides. The
petitioner is assured that the security will not disappear during
pendency of arbitration. Equally, respondent No.1 is protected
because the property is not handed over absolutely to the
petitioner. The Receiver acts as officer of the Court and remains
accountable to the Court.
94. The next question is whether some person should be
authorised to execute the work necessary for completion of the
rehabilitation building. In the facts of the present case, I find no
compelling reason to appoint third party unconnected with the
project. LOI is in the name of petitioner. The petitioner has
participated in the proceedings before the Apex Grievance
Redressal Committee. Pursuant to the directions issued, the
petitioner has prima facie deposited Rs.50 lakhs and made direct
payments of approximately Rs.1.50 crores towards transit rent.
The petitioner has expressed willingness to facilitate completion of
Rehabilitation Building No.4. In these circumstances, appointment
of the petitioner as Agent of the Court Receiver appears to be a
practical arrangement.
95. Such appointment requires strict limitations. The petitioner
cannot be permitted to contend that appointment as Agent of the
Court Receiver creates any rights in its favour. The authority of the
petitioner must flow from the order of this Court. The petitioner is
proposed to be appointed only because the Court Receiver, being
50

941-carbpl23540-2026-J.doc
an officer of the Court, requires an executing agency for
implementation of the interim arrangement. The petitioner, while
acting as Agent of the Court Receiver, functions under the
authority of the Court. The source of such authority is the order
passed under Section 9 of the Arbitration and Conciliation Act.
96. Equally, the rights of respondent No.1 remain protected.
Respondent No.1 continues to retain ownership of the free-sale
component, subject to the custody of the Court Receiver.
Appointment of the Receiver does not divest title. Appointment of
the petitioner as Receiver's Agent does not create ownership,
possession in an independent capacity, in favour of the petitioner
over the free-sale building or the unsold flats. Every amount
realised, every expenditure incurred, pursuant to this
arrangement shall remain subject to scrutiny before the Arbitral
Tribunal. The Tribunal shall finally determine the respective rights
and liabilities of the parties, including the entitlement of either
party to reimbursement or any other monetary consequence
arising from this arrangement.
97. Having regard to the cumulative effect of the contract, the
public element involved in the rehabilitation scheme, the order
dated 15 May 2026 passed by the Apex Grievance Redressal
Committee, the payments prima facie made by the petitioner, the
financial liabilities placed on record, the existence of unsold flats
constituting security and the necessity of preserving the efficacy of
the arbitral proceedings, I am satisfied that the ends of justice
would be served by appointing the Court Receiver over the security
and by appointing the petitioner only as Agent of the Court
51

941-carbpl23540-2026-J.doc
Receiver for the limited purpose of completing Rehabilitation
Building No.4.
98. In view of the foregoing discussion and for the reasons
recorded hereinabove, the following order is passed:
(i) The Arbitration Petition is partly allowed;
(ii) Pending commencement and conclusion of the arbitral
proceedings, the Court Receiver, High Court, Bombay is
appointed as Receiver, with all powers under Order XL Rule
1 of the Code of Civil Procedure, 1908, in respect of the
Security Area admeasuring approximately 6,560 sq.ft. carpet
area, more particularly described Annexure "C" to the
Memorandum of Understanding dated 11 September 2023;
(iii) The Court Receiver shall take symbolic possession of
the aforesaid premises. The Receiver shall not dispossess any
lawful occupant already in possession unless further orders
are passed by this Court or by the Arbitral Tribunal;
(iv) The petitioner is appointed as Agent of the Court
Receiver, without security or on such security and terms as
the Court Receiver may consider appropriate, solely for the
limited purpose of facilitating completion of Rehabilitation
Building No.4, obtaining the Occupation Certificate and
discharging the statutory obligations directly connected
therewith;
(v) The appointment of the petitioner as Agent of the
Court Receiver is an interim arrangement evolved by this
52

941-carbpl23540-2026-J.doc
Court in exercise of powers under Section 9 of the
Arbitration and Conciliation Act, 1996 and shall not be
construed—
(a) as recognition of any right of substituted
performance under Section 20 of the Specific Relief
Act, 1963;
(b) as displacement of respondent No.1 as developer
under the Development Agreement;
(c) as conferring any equitable rights upon the
petitioner in respect of the free-sale component of the
project; or
(d) as adjudicating the rights and liabilities of the
parties.
(vi) The Court Receiver shall supervise implementation of
this order. The petitioner shall act under the directions of the
Court Receiver and shall not undertake any act inconsistent
with the directions issued by the Court Receiver;
(vii) The Court Receiver is authorised, if satisfied that the
same is necessary for completion of Rehabilitation Building
No.4 and after hearing both parties, to permit sale of such
unsold free-sale flats as may be reasonably required for
generation of funds for—
(a) completion of Rehabilitation Building No.4;
(b) obtaining Completion Certificate and Occupation
Certificate;
53

941-carbpl23540-2026-J.doc
(c) payment of legitimate contractor dues directly
relatable to the rehabilitation component;
(d) payment of transit rent payable to eligible slum
dwellers;
(e) payment of LUC charges;
(f) payment of pro-rata premium and other statutory
dues payable to statutory authorities; and
(g) meeting other expenditure directly necessary for
lawful completion of the rehabilitation component.
(viii) No sale shall be effected by the petitioner in its
independent capacity. Every sale shall be undertaken only
with the prior written approval of the Court Receiver and
upon such terms and conditions as the Court Receiver may
determine. The Court Receiver shall ensure that the sale
consideration broadly reflects prevailing market value and
shall maintain complete records of every transaction;
(ix) All monies realised from sale of the aforesaid flats shall
be deposited into a separate escrow account to be opened
and operated under the control and supervision of the Court
Receiver. No withdrawal shall be permitted except in
accordance with the written directions of the Court Receiver
and solely for the purposes specified in clause (vii);
(x) The petitioner shall maintain complete books of
account of all receipts and expenditure and shall submit
quarterly statements of accounts together with progress
54

941-carbpl23540-2026-J.doc
reports regarding completion of Rehabilitation Building No.4
to the Court Receiver, with copies simultaneously furnished
to respondent No.1;
(xi) Respondent No.1 shall, within two weeks, hand over to
the Court Receiver and the petitioner all sanctioned plans,
approvals, permissions, architectural and structural
drawings, licences, NOCs, correspondence with statutory
authorities and all documents reasonably necessary for
completion of Rehabilitation Building No.4;
(xii) Pending the arbitral proceedings, respondent No.1, its
partners, servants, agents, representatives or any person
claiming through or under it are restrained from selling,
transferring, alienating, assigning, creating third-party rights,
mortgaging, charging, encumbering or otherwise dealing
with the remaining unsold flats forming part of Free Sale
Building No.2 except with the prior written permission of the
Court Receiver or further orders of the Arbitral Tribunal;
(xiii) Prayer clause (h) is partly allowed. Respondent No.1
shall, within three weeks, file an affidavit before the Court
Receiver, with a copy to the petitioner, disclosing—
(a) complete particulars of every unit forming part of
the Security Area;
(b) present status of each unit;
(c) allotment details;
(d) agreements executed, if any;
55

941-carbpl23540-2026-J.doc
(e) consideration received;
(f) encumbrances created;
(g) particulars of third-party rights, if any; and
(h) all unsold inventory remaining in Free Sale
Building No.2.
(xiv) Respondent No.1, its partners, servants, agents or any
person claiming through or under it are restrained from
selling, transferring, alienating, assigning, mortgaging,
creating third-party rights, parting with possession or
otherwise dealing with the remaining Security Area or any
unsold flats forming part thereof without the prior written
permission of the Court Receiver and, after constitution,
subject to such further directions as may be issued by the
Arbitral Tribunal;
(xv) The reliefs sought in prayer clauses (e), (f), (g), (i) and
(j), seeking immediate reimbursement, payment of transit
rent, deposit of sale consideration and deposit of security
amount of 61.15 crores are not granted at this stage. Those ₹
claims involve disputed questions relating to liability and
quantum and shall be adjudicated by the Arbitral Tribunal.
However, the petitioner shall be at liberty to seek
reimbursement of all expenditure incurred pursuant to this
order before the Arbitral Tribunal, which shall decide the
same on its own merits;
56

941-carbpl23540-2026-J.doc
(xvi) It is clarified that any amount spent by the petitioner
pursuant to the present order shall not entitle the petitioner
to reimbursement. The entitlement, quantum, priority and
adjustment of such expenditure shall be determined by the
Arbitral Tribunal;
(xvii) The petitioner shall not claim any ownership, lien,
possessory right, development right, beneficial interest or
equity in the free-sale component merely because it has been
appointed as Agent of the Court Receiver or because
expenditure has been incurred pursuant to this order;
(xviii) The Court has refrained from granting substituted
performance under Section 20 of the Specific Relief Act. The
arrangement directed herein is an interim protective
mechanism evolved under Section 9 of the Arbitration and
Conciliation Act for preserving the subject matter of
arbitration and facilitating completion of the rehabilitation
component in the larger interest of the rehabilitation scheme
and the eligible slum dwellers;
(xix) All findings contained in this judgment are prima facie
in nature and shall not bind the Arbitral Tribunal. All
disputes relating to breach, substituted performance,
damages, reimbursement, accounting, contractual
interpretation and adjustment of rights and liabilities are
expressly kept open for adjudication by the Arbitral Tribunal;
(xx) Upon constitution of the Arbitral Tribunal, either party
shall be at liberty to apply under Section 17 of the
57

941-carbpl23540-2026-J.doc
Arbitration and Conciliation Act, 1996 for continuation,
modification, variation or vacation of the interim
arrangement created by this order. The Arbitral Tribunal
shall consider such application independently and
uninfluenced by the prima facie observations contained
herein;
(xxi) There shall be no order as to costs.
(xxii) Parties to act upon an authenticated copy of this order.
[
(AMIT BORKAR, J.)
58