M/S Hamirpur Byepass Private Ltd & Anr. vs National Highway Authority Of India & Anr.

Court
Delhi High Court

$~62
* IN THE HIGH COURT OF DELHI AT NEW DELHI
th
% Date of Decision: November 27 , 2026
# CNR No. DLHC010564672026
+ W.P.(C) 17423/2026 & CM APPL. 81328/2026, CM APPL.
81329/2026, CM APPL. 81330/2026
M/S HAMIRPUR BYEPASS PRIVATE LTD
& ANR. .....Petitioners
Through: Mr. Sandeep Sethi, Sr. Adv.
with Ms. Aditi, Mr. Kapil
Arora, Mr. Krishna Gambhir,
Ms. Shreya Sethi & Mr. Ritwik
Sharma, Advs.

versus

NATIONAL HIGHWAY AUTHORITY OF INDIA
& ANR. .....Respondents
Through: Ms. Madhu Sweta, Ms. Srishti
Bajpai, Advs. for R-1.
Dr. Abhishek Khanna, Adv. for
SPC with Mr. Garvil Singh, GP
for R-2.
CORAM:
HON'BLE MR. JUSTICE AMIT MAHAJAN
AMIT MAHAJAN, J. (Oral)

1. By the present petition, the petitioner challenges the order dated
17.11.2026 (hereafter ‘ impugned order ’) passed by Respondent No.
1 pursuant to which the petitioners were debarred from participating in
future bids for National Highways projects with MoRTH and its
executing agencies, including NHAI, for a period of 3 years or till the
completion of rectification (whichever is later) and a penalty of
₹3,97,50,000/- has been imposed on Petitioner No. 1.
Signature Not Verified
W.P.(C) 17423/2026 Page 1 of 7

Signed By:HARMINDER
KAUR
Signing Date:28.11.2026
16:49:24

2. Succinctly put, Respondent No. 1 had invited a bid for
construction of New 2-Lane with Paved Shoulder of Hamirpur Bypass
of NH-103 & NH-03 (Design Ch. Km 121+175 to Km 138+295,
Design Length 17.120 Km) in the State of Himachal Pradesh under
NH(O) on Hybrid Annuity Mode in which Petitioner No. 2 was
declared as the selected bidder and Petitioner No. 1 was established as
a SPV. In that regard, a Concession Agreement was executed between
Petitioner No. 1 and Respondent No. 1 on 24.11.2022.
3. On 02.10.2026, when the project was underway, the erection
team was lifting the launching nose at pier with hydraulic jacks in
order to correct a lateral displacement of about 10mm of one of the
sliding shoes of the launching nose. During the course of the
operation, the 90m truss and the launching nose lost stability and
collapsed into the gorge as a result of which one Sh. Ajay Kumar,
Truss Bridge Site Head lost his life. Additionally, three workers also
suffered certain injuries.
4. In the light of the said incident, a show cause notice was issued
to the petitioners on 12.10.2026 calling upon the petitioners to show
cause why debarment for a period of up to 3 years (or till the
completion of the rectification work) from participating in future bids
for National Highways projects with MoRTH and its executing
agencies including NHAI be not imposed for the lapses relating to
safety, equipment fitness and execution of the works. The petitioners
furnished their reply on 27.10.2026. A technical expert committee was
also constituted which furnished its report on 23.10.2026. Upon a
Signature Not Verified
W.P.(C) 17423/2026 Page 2 of 7

Signed By:HARMINDER
KAUR
Signing Date:28.11.2026
16:49:24

consideration of the aforesaid, the impugned order was passed thereby
debarring the petitioners from participating in future bids for National
Highways projects with MoRTH and its executing agencies including
NHAI for a period of 3 years or till the completion of the rectification
work.
5. Aggrieved thereby, the petitioners have filed the present
petition.
6. The learned Senior counsel for the petitioners submits that the
impugned order is perverse and is liable to be set aside on account of
the patent violation of the principles of natural justice. He submits that
the a copy of the Technical Expert Committee Report dated
23.10.2026 which has extensively been relied upon while passing the
impugned order was never furnished to the petitioners. He submits
that the petitioners were deprived of an opportunity to examine the
findings recorded therein and offer their explanation.
7. He submits that the petitioners though in their reply to the show
cause notice had specifically requested for an opportunity of personal
hearing, yet no such opportunity was afforded to them before the
impugned order came to be passed. He submits that in such
circumstances, the impugned order cannot be sustained and is liable to
be set aside.
8. On the other hand, the learned counsel for Respondent No. 1
submits that the present case cannot and ought not to be treated as an
ordinary contractual dispute or a case of routine non-performance. She
submits that the matter concerns a catastrophic failure of a major
Signature Not Verified
W.P.(C) 17423/2026 Page 3 of 7

Signed By:HARMINDER
KAUR
Signing Date:28.11.2026
16:49:24

structure resulting in the unfortunate loss of one human life and
injuries to three other persons. She submits that the findings of the
Technical Expert Committee disclose serious lapses in the execution
of the work.

9. She submits that certain documents and records sought from the
petitioners were not furnished, and the competent authority, therefore,
proceeded to take a decision on the basis of the material available on
record. She submits that the issue in the present case raises serious
concerns and ramifications for public safety and the same cannot be
viewed merely from the perspective of an inter se dispute between the
parties.
10. I have heard the rival contentions of the parties and considered
the material placed on record.
11. At the outset, it is pertinent to note that certain aspects of the
matter are not in dispute. Undisputedly, a copy of the Technical
Expert Committee Report was not furnished to the petitioners before
the impugned order was passed. Further, as contended on behalf of the
respondents, though it is stated that since certain documents were not
furnished by the petitioners, the impugned order was passed on the
basis of the material on record, it is not disputed by the respondents
that an opportunity of hearing was not afforded to the petitioners.
12. Having taken note of the stance of the respondents, this Court is
of the view that the explanation that certain documents called for from
the petitioners had not been furnished for which personal hearing
could not be granted to the petitioners is unsatisfactory and the same,
Signature Not Verified
W.P.(C) 17423/2026 Page 4 of 7

Signed By:HARMINDER
KAUR
Signing Date:28.11.2026
16:49:24

cannot, by itself, render the request for personal hearing redundant.
The authority could have identified the documents that were required
and could have called upon the petitioners to furnish the same and
thereafter afforded them an opportunity to explain their position
before taking a final decision. Significantly, the Technical Expert
Committee Report also ought to have been supplied to the petitioners
before the impugned order was passed.
13. The procedural deficiencies thus pointed out on behalf of the
petitioners are not without substance. An order entailing consequences
as serious as debarment must necessarily be founded upon a process
that affords meaningful opportunity to the affected party to meet the
case against it.
14. Having noted so, this Court still cannot lose sight of the
extraordinary circumstances in which the impugned order was passed.
The incident in question involved the collapse of a 90 m steel truss
thereby claiming the life of one person and injuries to three others.
The impugned order refers to serious observations of the Technical
Expert Committee regarding the absence of an effective inspection
and clearance mechanism for critical launching operation, absence of
an engineer at the site, alleged absence of mechanical locking
arrangements etcetera .
15. As pointed out by the learned Senior Counsel for the
petitioners, it is true that the Technical Expert Committee has not
conclusively determined the precise trigger or mechanism that led to
the incident, however, the impugned order does record several serious
Signature Not Verified
W.P.(C) 17423/2026 Page 5 of 7

Signed By:HARMINDER
KAUR
Signing Date:28.11.2026
16:49:24

observations concerning the manner in which the construction work
was executed. The impugned order further records that safety
protocols were allegedly not followed by the petitioners. These
aspects ought not to be disregarded especially when the incident has
resulted in loss of human life.
16. In these circumstances, while the procedural deficiencies in the
decision making process cannot be countenanced, this Court is also
not inclined, at this stage, to set aside the impugned order or interdict
its operation altogether.
17. Having regard to the seriousness of the incident and the nature
of the allegations, this Court considers it appropriate to permit the
authority to undertake a fresh consideration of the matter after
affording the petitioners an effective opportunity of hearing and
supplying them the material relied upon, including the Technical
Expert Committee Report.
18. Accordingly, in the peculiar facts and circumstances of this
case, Respondent No.1 is directed to furnish a copy of the Technical
Expert Committee Report together with any other material proposed
to be relied upon to the petitioners within a period of one week.
Respondent No. 1 is thereafter directed to afford the petitioners a
reasonable opportunity to submit their response and also grant an
effective opportunity of personal hearing to explain their position.
19. Thereafter, Respondent No. 1 is directed to reconsider the
matter independently, uninfluenced by the conclusions recorded in the
impugned order and pass a fresh and reasoned order.
Signature Not Verified
W.P.(C) 17423/2026 Page 6 of 7

Signed By:HARMINDER
KAUR
Signing Date:28.11.2026
16:49:24

20. The aforesaid exercise shall be completed and a fresh order
shall be passed by the competent within a period of four weeks.
21. While this Court, considering the severity of the allegations has
not suspended the operation of the impugned order, it is made clear
that if Respondent No. 1 fails to pass a fresh order within a period of
four weeks, the impugned order, insofar as it operates against the
petitioners, shall automatically stand vacated.
22. The present petition is accordingly disposed of in the aforesaid
terms.
23. It is however made clear that this Court has not expressed any
opinion on the merits of the allegations or the defence of the
petitioners and the same shall independently be considered at the time
of passing the final order.
24. Pending applications also stand disposed of.

AMIT MAHAJAN, J
NOVEMBER 27, 2026
“SK”


Signature Not Verified
W.P.(C) 17423/2026 Page 7 of 7

Signed By:HARMINDER
KAUR
Signing Date:28.11.2026
16:49:24