Union Of India vs M/S Anand And Company

Court
Delhi High Court
Case type
Original Misc Petition Commercial
Decided on
04-04-2026
<div> <br /> <br /> <b>* </b> <b>IN THE HIGH COURT OF DELHI AT NEW DELHI </b><br /> % <b>Judgment reserved on: 27.03.2026 </b><br /> <b> </b> <b> Judgment pronounced on: 04.04.2026 </b><br /> + O.M.P. (COMM) 289/2023, I.A. 14392/2023 &amp; I.A. <br /> 14396/2023 <br /> <br /> UNION OF INDIA .....Petitioner <br /> Through: Mr. Rakesh Kumar, SPC with <br /> Mr. Sunil, Adv. <br /> versus <br /> M/S ANAND AND COMPANY .....Respondent <br /> Through: Mr. Kunwar Chandresh, Ms. <br /> Poonam Prasad, Mr. Divyansh <br /> Singh &amp; Mr. George Lincoln, <br /> Advs. <br /> <b>CORAM: </b><br /> <b>HON&#x27;BLE MR. JUSTICE AVNEESH JHINGAN </b><br /> <b>J U D G M E N T </b><br /> 1. This petition is filed under Section 34 of the Arbitration and <br /> Conciliation Act, 1996 (for short „the Act‟) challenging the arbitral <br /> award dated 17.02.2023. <br /> 2. The facts in brief are that the petitioner invited an e-tender for <br /> construction of hundred Family Quarters (Type-II, III &amp; IV) including <br /> internal W/S, S/I and electrical works for ITBP 22nd Bn. Campus at <br /> Chhawla, New Delhi. The bid of the respondent was accepted and a <br /> Letter of Acceptance (for short „LOA‟) dated 20.06.2017 was issued. <br /> An agreement (02/EE/AIMSPD/2017-18) was executed between the <br /> parties to the <i>lis</i> . The stipulated date of commencement was <br /> 11.07.2017 and the time period for completion was twelve months i.e. <br /> Signature Not Verified<br /> O.M.P. (COMM) 289/2023 Page 1 of 17 <br /> Signed By:CHANCHAL<br /> Signing Date:04.04.2026<br /> 17:01:08<br /> <br /><br /> <br /> <br /> 10.07.2018. <br /> 2.1 During execution of the contract, disputes arose between the <br /> parties. The respondent approached the Engineer-in-Charge of CPWD <br /> (hereinafter „EE‟) but the disputes were not resolved. Clause 25 of the <br /> General Conditions of Contract (hereinafter „contract‟) was invoked <br /> for forming a Dispute Resolution Committee (for short „DRC‟). On <br /> failure to do the needful the respondent by notice dated 08.04.2021 <br /> initiated arbitration proceedings which culminated in the impugned <br /> award. <br /> 3. Learned counsel for the petitioner contends that the arbitrator <br /> erred in directing the release of Rs.35,12,328/- withheld for failure of <br /> the respondent to achieve the milestones. The submission is that <br /> extension of time and rescheduling of milestones are two distinct <br /> aspects. Moreover, extension of time is to be granted by the EE <br /> whereas rescheduling of milestones is to be done by the <br /> Superintending Engineer, CPWD (for short „SE‟). The respondent <br /> failed to apply for rescheduling of the milestones under clause 5.3 of <br /> the contract and in case of non-achievement of the milestones the <br /> petitioner was entitled to withhold the amount to the extent of ten <br /> percent of the tender value. Clause 2 of the contract is relied upon to <br /> challenge the award of interest on the withheld amount. <br /> 3.1 It is submitted that there is a clerical error in awarding the <br /> amount of Rs.71,45,578/- on account of release of pending final bills <br /> and while doing so the amount already paid was not deducted. <br /> 3.2 The awarding of three percent difference on account of <br /> Signature Not Verified<br /> O.M.P. (COMM) 289/2023 Page 2 of 17 <br /> Signed By:CHANCHAL<br /> Signing Date:04.04.2026<br /> 17:01:08<br /> <br /><br /> <br /> <br /> difference between the Goods and Services Tax (for short „GST‟) and <br /> Value Added Tax (for short „VAT‟) is canvassed to be based upon <br /> assumed calculation and contrary to clause 38 of the contract where <br /> under the GST paid is to be reimbursed. The arbitrator erred in <br /> awarding the difference of three percent without proof that it was <br /> deposited. <br /> 3.3 The refund of Rs.3,00,000/- penalty imposed for delay in <br /> completing the sample flat is stated to have been allowed without <br /> recording reasons and ignoring the terms and conditions of the <br /> contract. Neither there was a provision for extending the time for <br /> completion of the sample flat nor the time was extended. <br /> 3.4 The grant of loss of on-site and off-site expenses for the <br /> prolongation period is stated to be against Section 73 of the Indian <br /> Contract Act, 1872 (for short „Contract Act‟) and the law laid by the <br /> Supreme Court in <b>Kailash Nath Associates v. DDA, </b> (2015) 4 SCC <br /> 136 <b> </b> and <b> Unibros vs. All India Radio, </b> 2023 SCC OnLine SC 1366. <br /> The argument is that there was no proof of actual loss or damage <br /> suffered and the arbitrator without any basis apportioned the expenses <br /> depicted in the certificate issued by the Chartered Accountant (for <br /> short „CA‟) and awarded the damages. <br /> 3.5 The interest awarded at the rate of nine percent is contended to <br /> be on the higher side. The costs awarded of Rs.8,00,000/- to the <br /> respondent are assailed being on the higher side and contrary to the <br /> terms of the contract providing that the arbitration costs shall be <br /> equally borne by both the parties. <br /> Signature Not Verified<br /> O.M.P. (COMM) 289/2023 Page 3 of 17 <br /> Signed By:CHANCHAL<br /> Signing Date:04.04.2026<br /> 17:01:08<br /> <br /><br /> <br /> <br /> 4. <i>Per contra</i> the delay in achieving the milestones was <br /> attributable to the petitioner and for this reason the time was <br /> repeatedly extended, yet the amount was withheld for non-<br /> achievement of the milestones. The contention is that under clause 5.4 <br /> of the contract the milestones should have been rescheduled without <br /> filing of an application by the respondent. The award of interest on the <br /> refund of the withheld amount is defended by stating that clause 2 of <br /> the contract is not applicable to the facts of the case. <br /> <br /> 4.1 It is argued that from 01.07.2017, GST was levied and service <br /> tax thereafter is included in GST. Submission is that clauses 37 and 38 <br /> of the contract provided that service tax shall be reimbursed and the <br /> arbitrator rightly awarded the service tax portion of the contract <br /> covered by GST. <br /> 4.2 The contention is that the sample flat was to be completed after <br /> two months of casting of first floor slab and the delay in completion <br /> was due to repeated revisions suggested by the petitioner. Moreover, <br /> the petitioner failed to prove the actual loss or injury suffered due to <br /> delay in completion of the sample flat and the arbitrator rightly relied <br /> upon the decisions of the Supreme Court in <b>Kailash Nath Associates</b> <br /> (supra) and <b> Fateh Chand v. Balkishan Dass</b> , 1963 SCC OnLine SC <br /> 49 to allow the claim. <br /> 4.3 The grant of damages for prolongation of the contract is <br /> defended as having been granted relying upon a certificate issued by <br /> the CA. Contention is that it is admitted position that the work which <br /> was to be completed by 10.07.2018 was actually completed on <br /> Signature Not Verified<br /> O.M.P. (COMM) 289/2023 Page 4 of 17 <br /> Signed By:CHANCHAL<br /> Signing Date:04.04.2026<br /> 17:01:08<br /> <br /><br /> <br /> <br /> 05.10.2019 i.e. after delay of 452 days. The submission is that a <br /> reasonable amount in accordance with the settled principles of law <br /> was awarded by the arbitrator. <br /> 4.4 The rate of interest and litigation costs awarded is supported by <br /> stating that the discretion exercised by the arbitrator is on a sound <br /> basis and no interference can be made within the restricted scope <br /> under Section 34 of the Act. <br /> 5. Heard learned counsel for the parties at length and perused the <br /> relevant record with their able assistance. No other issue than those <br /> noted above was pressed. <br /> 6. The terms of the contract between the parties provide the time <br /> stipulated for completion of the work and the milestones to be <br /> achieved periodically. Clause 5 of the contract deals with the <br /> extension of time and rescheduling of milestones. Clauses 5.3 and 5.4 <br /> of the contract are reproduced below: <br /> <b>“CLAUSE 5 </b><br /> 5.3 Request for rescheduling of Mile stones and <br /> extension of time, to be eligible for consideration, shall <br /> be made by the Contractor (As per Appendix XVI) in <br /> writing with supporting documents within fourteen <br /> days of the happening of the event causing delay on the <br /> prescribed form to the authority as indicated in <br /> Schedule &#x27;F&#x27;. <br /> 5.4 In any such case the authority as indicated in <br /> Schedule &#x27;F&#x27; may give a fair and reasonable extension <br /> of time and reschedule the mile stones for completion <br /> of work. Such extension or rescheduling of the <br /> milestones shall be communicated to the Contractor by <br /> the authority as Indicated in Schedule &#x27;F&#x27; in writing, <br /> Signature Not Verified<br /> O.M.P. (COMM) 289/2023 Page 5 of 17 <br /> Signed By:CHANCHAL<br /> Signing Date:04.04.2026<br /> 17:01:08<br /> <br /><br /> <br /> <br /> within 3 months or 4 weeks of the date of receipt of <br /> such request with all supporting documents <br /> respectively failing which it will be deemed that <br /> rescheduling of milestones have been approved. <br /> Non application by the contractor for extension of <br /> time/ rescheduling of the milestones shall not be a bar <br /> for giving a fair and reasonable extension/ rescheduling <br /> of the milestones by the authority as indicated in <br /> Schedule „F‟ and this shall be binding on the <br /> contractor.” <br /> <br /> 7. It is an admitted fact that the time for completion of the project <br /> was extended from time to time and delay in completion of the work <br /> was not attributed to the respondent. The last extension was granted <br /> up to 15.10.2019 vide letter dated 24.09.2019 and almost after one <br /> year of the last extension of time, the penalty for non-achievement of <br /> the milestones was apportioned from the withheld amount. The <br /> contention of learned counsel for the petitioner that the respondent had <br /> not applied for rescheduling of milestones is factually wrong. The <br /> respondent vide letter dated 23.03.2018 applied for rescheduling of the <br /> milestones to the EE and this letter was forwarded to the SE but was <br /> not decided. Be that as it may, clause 5.4 of the contract provides that <br /> non-filing of an application by the contractor for rescheduling of <br /> milestones shall not be a bar for rescheduling the milestones. The <br /> view taken by the arbitrator that once time was extended from time to <br /> time, the milestones should have been rescheduled is a plausible and <br /> calls for no interference. <br /> 8. So far as the grant of interest on the amount withheld for non-<br /> achievement of the milestones is concerned there is no discussion in <br /> Signature Not Verified<br /> O.M.P. (COMM) 289/2023 Page 6 of 17 <br /> Signed By:CHANCHAL<br /> Signing Date:04.04.2026<br /> 17:01:08<br /> <br /><br /> <br /> <br /> the award and is bereft of reasons. Clause 2 of the contract provides <br /> for withholding of amount on failure of the contractor to achieve <br /> milestones mentioned in schedule „F‟ or the rescheduled milestones in <br /> terms of clause 5.4 of the contract. This amount is to be adjusted <br /> against compensation levied at the time of final grant of extension of <br /> time. The withholding is automatic without notice and in case the <br /> contractor catches up with the progress the amount withheld has to be <br /> released. On failure of the contractor to make up the delay the <br /> amounts mentioned against the subsequent missed milestones shall <br /> also be withheld. Clause 2 of the contract provides that no interest <br /> whatsoever shall be paid on the withheld amount and the condition of <br /> non-payment of interest on the withheld amount has no exceptions. <br /> The granting of interest on the withheld amount is contrary to clause 2 <br /> of the contract and cannot be sustained. <br /> 9. The clerical error while directing the release of the amount <br /> pending from the final bill is conceded by the respondent and it is <br /> admitted that the due amount was Rs.54,44,112/-. As there is no <br /> modification of the award involved and it is only a clerical error to be <br /> rectified, claim 2 awarded is corrected to Rs.54,44,112/- <br /> 10. Clauses 37 and 38 of the contract dealing with the levy of taxes <br /> and the conditions for reimbursement are reproduced below: <br /> <b>“CLAUSE 37 </b><br /> <b>Levy/Taxes payable by Contractor</b> <br /> (i) Sales Tax/VAT (except Service Tax), Building and <br /> other Construction Workers Welfare Cess or any other <br /> tax or Cess in respect of this contract shall be payable <br /> Signature Not Verified<br /> O.M.P. (COMM) 289/2023 Page 7 of 17 <br /> Signed By:CHANCHAL<br /> Signing Date:04.04.2026<br /> 17:01:08<br /> <br /><br /> <br /> <br /> by the contractor and Government shall not entertain <br /> any claim whatsoever in this respect. However, in <br /> respect of service tax, same shall be paid by the <br /> contractor to the concerned department on demand and <br /> it will be reimbursed to him by the Engineer-in-Charge <br /> after satisfying that it has been actually and genuinely <br /> paid by the contractor. <br /> (ii) The contractor shall deposit royalty and obtain <br /> necessary permit for supply of the red bajri, stone, <br /> kankar, etc. from local authorities. <br /> If pursuant to or under any law, notification or order <br /> any royalty, cess or the like becomes payable by the <br /> Government of India and does not any time become <br /> payable by the contractor to the State Government, <br /> Local authorities in respect of any material used by the <br /> contractor in the works, then in such a case, it shall be <br /> lawful to the Government of India and it will have the <br /> right and be entitled to recover the amount paid in the <br /> circumstances as aforesaid from dues of the <br /> contractor.” <br /> <b>“CLAUSE 38 </b><br /> <b>Conditions for reimbursement of levy/taxes if levied </b><br /> <b>after receipt of tenders </b><br /> (i) All tendered rates shall be inclusive of all taxes and <br /> levies (except Service Tax) payable under respective <br /> statutes. However, if any further tax or levy or cess is <br /> imposed by Statute, after the last stipulated date for the <br /> receipt of tender including extensions if any and the <br /> contractor thereupon necessarily and properly pays <br /> such taxes/levies/cess, the contractor shall be <br /> reimbursed the amount so paid, provided such <br /> payments, if any, is not, in the opinion of the <br /> Superintending engineer (whose decision shall be final <br /> and binding on the contractor) attributable to delay in <br /> execution of work within the control of the contractor. <br /> (ii) The contractor shall keep necessary books of <br /> Signature Not Verified<br /> O.M.P. (COMM) 289/2023 Page 8 of 17 <br /> Signed By:CHANCHAL<br /> Signing Date:04.04.2026<br /> 17:01:08<br /> <br /><br /> <br /> <br /> accounts and other documents for the purpose of this <br /> condition as may be necessary and shall allow <br /> inspection of the same by a duly authorized <br /> representative of the Government and/or the Engineer-<br /> in-Charge and shall also furnish such other <br /> information/document as the Engineer-in-Charge may <br /> require from time to time. <br /> (iii) The contractor shall within a period of 30 days of <br /> the imposition of any such further tax or levy or cess, <br /> give a written notice thereof to the Engineer-in-Charge <br /> that the same is given pursuant to this condition, <br /> together with all necessary information relating <br /> thereto.” <br /> <br /> 11. Clause 37 of the contract provided that sales tax/VAT shall be <br /> payable by the contractor but service tax paid by the contractor shall <br /> be reimbursed on satisfaction of actual and genuine payment. As per <br /> clause 38 of the contract, the tender rates are inclusive of all taxes <br /> except service tax and in case of any future tax or levy or cess <br /> imposed after the last stipulated date of receipt of tender i.e. <br /> 08.05.2017, the tax or levy or cess shall be reimbursed to the extent of <br /> the amount paid. GST would fall within future tax levied after the last <br /> date stipulated for receipt of tender and is to be reimbursed. No <br /> evidence was produced to show that the amount of three percent <br /> difference claimed was actually paid by the respondent. Service tax <br /> was not leviable after the implementation of GST on 01.07.2017. The <br /> arbitrator without any basis made a split of taxes levied under GST <br /> and held that fifteen percent of the forty percent of the work <br /> constituted a component of service tax. The finding is against public <br /> policy as the service tax under Chapter V of the Finance Act, 1994 <br /> Signature Not Verified<br /> O.M.P. (COMM) 289/2023 Page 9 of 17 <br /> Signed By:CHANCHAL<br /> Signing Date:04.04.2026<br /> 17:01:08<br /> <br /><br /> <br /> <br /> was repealed upon the introduction of GST with effect from <br /> 01.07.2017 and there was no question of service tax being levied <br /> thereafter. The award of claim of Rs.35,12,329/- claimed as a <br /> difference of three percent between the post-GST and pre-GST period <br /> is unsustainable. <br /> 12. The chart forming part of the contract provided for a penalty of <br /> Rs.50,000/- per fortnight for delay in completion of the sample flat. It <br /> is an admitted position that the sample flat was to be completed within <br /> two months of casting of first floor slab and there was delay in <br /> completing the sample flat. The arbitrator considered that the <br /> hindrances causing delay between casting of first floor slab and <br /> construction of the sample flat were not considered by the petitioner <br /> and the respondent was not even given an opportunity to explain the <br /> delay. The reliance was placed upon the decisions of the Supreme <br /> Court in <b>Kailash Nath Associates</b> (supra) and <b>Fateh Chand </b> (supra) <br /> to hold that in the absence of loss due to breach of contract the <br /> imposition of penalty for delay in completion of sample flat cannot be <br /> sustained. It is not a case set up even now that the petitioner had <br /> substantiated the loss due to breach of contract. The view taken by the <br /> arbitrator is plausible and calls for no interference. <br /> 13. The respondent under Section 73 of the Contract Act claimed <br /> loss of on-site and off-site expenses incurred due to prolongation of <br /> the contract period. The law is well settled that for claiming damages <br /> under Section 73 of the Contract Act the claimant has to prove the <br /> actual loss suffered and in case it is not possible to prove loss, a <br /> Signature Not Verified<br /> O.M.P. (COMM) 289/2023 Page 10 of 17 <br /> Signed By:CHANCHAL<br /> Signing Date:04.04.2026<br /> 17:01:08<br /> <br /><br /> <br /> <br /> reasonable amount of damages is to be assessed. Reference is made to <br /> the following judgments: <br /> 13.1 The Supreme Court in <b>Unibros</b> (supra) <b> </b> while dealing with a <br /> claim for redressal of loss of profit made under Section 73 of the CA <br /> arising from prolongation of the contract held: <br /> “19. The law, as it should stand thus, is that for claims <br /> related to loss of profit, profitability or opportunities to <br /> succeed, one would be required to establish the <br /> following conditions : first, there was a delay in the <br /> completion of the contract; second, such delay is not <br /> attributable to the claimant; third, the claimant&#x27;s status <br /> as an established contractor, handling substantial <br /> projects; and fourth, credible evidence to substantiate <br /> the claim of loss of profitability. On perusal of the <br /> records, we are satisfied that the fourth condition, <br /> namely, the evidence to substantiate the claim of loss <br /> of profitability remains unfulfilled in the present case.” <br /> <br /> 13.2 The Supreme Court in <b>Kailash Nath Associates</b> (supra) held: <b> </b><br /> “43.6. The expression “whether or not actual damage <br /> or loss is proved to have been caused thereby” means <br /> that where it is possible to prove actual damage or loss, <br /> such proof is not dispensed with. It is only in cases <br /> where damage or loss is difficult or impossible to <br /> prove that the liquidated amount named in the contract, <br /> if a genuine pre-estimate of damage or loss, can be <br /> awarded.” <br /> <br /> 13.3 The Supreme Court in <b>State of Rajasthan v. Ferro Concrete </b><br /> <b>Construction (P) Ltd., (2009) 12 SCC 1 </b> held: <b> </b><br /> “55.While the quantum of evidence required to accept <br /> a claim may be a matter within the exclusive <br /> jurisdiction of the arbitrator to decide, if there was no <br /> evidence at all and if the arbitrator makes an award of <br /> Signature Not Verified<br /> O.M.P. (COMM) 289/2023 Page 11 of 17 <br /> Signed By:CHANCHAL<br /> Signing Date:04.04.2026<br /> 17:01:08<br /> <br /><br /> <br /> <br /> the amount claimed in the claim statement, merely on <br /> the basis of the claim statement without anything more, <br /> it has to be held that the award on that account would <br /> be invalid. Suffice it to say that the entire award under <br /> this head is wholly illegal and beyond the jurisdiction <br /> of the arbitrator, and wholly unsustainable.” <br /> <br /> 13.4 The Division Bench of this court in <b>Tower Vision India (P) </b><br /> <b>Ltd. v. Procall (P) Ltd., </b> 2012 SCC OnLine Del 4396 <b> </b> held: <b> </b><br /> “16. Consequence for breach of the contract are <br /> provided in Chapter VI of the Indian Contract Act, <br /> 1872, which contains three sections, namely, section 73 <br /> to section 75. As per section 73 of the Indian Contract <br /> Act, the party who suffers by the breach of contract is <br /> entitled to receive from the defaulting party, <br /> compensation for any loss or damage caused to him by <br /> such breach, which naturally arose in usual course of <br /> things from such breach, or which the two parties knew <br /> when they make the contract to be likely the result of <br /> the breach of contract. This provision makes it clear <br /> that such compensation is not to be given for any <br /> remote or indirect loss or damage sustained by reason <br /> of the breach. The underlying principle enshrined in <br /> this section is that a mere breach of contract by a <br /> defaulting party would not entitle the other side to <br /> claim damages unless the said party has in fact suffered <br /> damages because of such breach. Loss or damage <br /> which is actually suffered as a result of breach has to <br /> be proved and the plaintiff is to be compensated to the <br /> extent of actual loss or damage suffered. When there is <br /> a breach of contract, the party who commits the breach <br /> does not eo instanti, i.e., at the instant incur any <br /> pecuniary obligation, nor does the party complaining of <br /> the breach becomes entitled to a debt due from the <br /> other party. The only right which the party aggrieved <br /> by the breach of the contract has is the right to sue for <br /> damages. No pecuniary liability thus arises till the <br /> Signature Not Verified<br /> O.M.P. (COMM) 289/2023 Page 12 of 17 <br /> Signed By:CHANCHAL<br /> Signing Date:04.04.2026<br /> 17:01:08<br /> <br /><br /> <br /> <br /> court has determined that the party complaining of the <br /> breach is entitled to damages. The court in the first <br /> place must decide that the defendant is liable and then <br /> it should proceed to assess what the liability is. But, till <br /> that determination, there is no liability at all upon the <br /> defendant. The courts will give damages for breach of <br /> contract only by way of compensation for loss suffered <br /> and not by way of punishment. The rule applicable for <br /> determining the amount of damages for the breach of <br /> contract to perform a specified work is that the <br /> damages are to be assessed at the pecuniary amount of <br /> difference between the state of the plaintiff upon the <br /> breach of the contract and what it would have been if <br /> the contract had been performed and not the sum which <br /> it would cost to perform the contract, though in <br /> particular cases the result of either mode of calculation <br /> may be the same. The measure of compensation <br /> depends upon the circumstances of the case. The <br /> complained loss or claimed damage must be fairly <br /> attributed to the breach as a natural result or <br /> consequence of the same. The loss must be a real loss <br /> or actual damage and not merely a probable or a <br /> possible one. When it is not possible to calculate <br /> accurately or in a reasonable manner, the actual <br /> amount of loss incurred or when the plaintiff has not <br /> been able to prove the actual loss suffered, he will be, <br /> all the same, entitled to recover nominal damages for <br /> breach of contract. Where nominal damages only are to <br /> be awarded, the extent of the same should be estimated <br /> with reference to the facts and circumstances involved. <br /> The general principle to be borne in mind is that the <br /> injured party may be put in the same position as that he <br /> would have been if he had not sustained the wrong.” <br /> <br /> (emphasis supplied) <br /> <br /> 14. The only evidence produced by the respondent to support the <br /> claim for damages was a certificate of expenses issued by the CA. <br /> Signature Not Verified<br /> O.M.P. (COMM) 289/2023 Page 13 of 17 <br /> Signed By:CHANCHAL<br /> Signing Date:04.04.2026<br /> 17:01:08<br /> <br /><br /> <br /> <br /> There was no evidence of actual loss suffered due to prolongation of <br /> the contract. The certificate issued by the CA provides year-wise <br /> expenses and head office expenses incurred but there is no <br /> certification as to the quantification of loss suffered if any, due to the <br /> extension of time period of the contract. In other words, there was no <br /> proof of actual loss suffered by incurring additional expenses due to <br /> extension of period of the contract. The expenses incurred after the <br /> stipulated date of completion of the contract in itself are not evidence <br /> of actual loss or damage suffered. It is not the case set up that the <br /> actual loss or damage suffered cannot be quantified. The <br /> quantification of damages by the arbitrator is based on assumptions <br /> and is without any foundation. The compensation awarded is in <br /> violation of Section 73 of the Contract Act and the law laid down by <br /> the Supreme Court and cannot be sustained being against public <br /> policy. <br /> 15. The simple interest awarded at the rate of nine percent by the <br /> arbitrator calls for no interference within the limited scope of <br /> jurisdiction under Section 34 of the Act. No case is made out that the <br /> interest awarded is excessive. <br /> 16. Section 31A(3) of the Act bestows discretion upon the arbitrator <br /> to determine costs considering the facts and circumstances of the case. <br /> A reasonable figure has been quantified by the arbitrator taking into <br /> consideration the various factors calling for no interference. <br /> 17. The Supreme Court in <b>Gayatri Balasamy v. ISG Novasoft </b><br /> <b>Technologies Ltd.</b> , (2025) 7 SCC 1 held that while an arbitral award <br /> Signature Not Verified<br /> O.M.P. (COMM) 289/2023 Page 14 of 17 <br /> Signed By:CHANCHAL<br /> Signing Date:04.04.2026<br /> 17:01:08<br /> <br /><br /> <br /> <br /> cannot be modified under Section 34 of the Act, a severable part of the <br /> award may be set aside. The relevant paragraphs are quoted below: <br /> “32. In the present controversy, the proviso to Section <br /> 34(2)(a)(iv) is particularly relevant. It states that if the <br /> decisions on matters submitted to arbitration can be <br /> separated from those not submitted, only that part of <br /> the arbitral award which contains decisions on matters <br /> non-submitted may be set aside. The proviso, therefore, <br /> permits courts to sever the non-arbitrable portions of an <br /> award from arbitrable ones. This serves a twofold <br /> purpose. First, it aligns with Section 16 of the 1996 <br /> Act, which affirms the principle of kompetenz-<br /> kompetenz, that is, the arbitrators&#x27; competence to <br /> determine their own jurisdiction. Secondly, it enables <br /> the Court to sever and preserve the “valid” part(s) of <br /> the award while setting aside the “invalid” ones. [The <br /> “validity” and “invalidity”, as used here, does not refer <br /> to legal validity or merits examination, but validity in <br /> terms of the proviso to Section 34(2)(a)(iv) of the 1996 <br /> Act.] Indeed, before us, none of the parties have argued <br /> that the Court is not empowered to undertake such a <br /> segregation. <br /> 33. We hold that the power conferred under the proviso <br /> to Section 34(2)(a)(iv) is clarificatory in nature. The <br /> authority to sever the “invalid” portion of an arbitral <br /> award from the “valid” portion, while remaining within <br /> the narrow confines of Section 34, is inherent in the <br /> Court&#x27;s jurisdiction when setting aside an award. <br /> 34. To this extent, the doctrine of omne majus continet <br /> in se minus—the greater power includes the lesser—<br /> applies squarely. The authority to set aside an arbitral <br /> award necessarily encompasses the power to set it <br /> aside in part, rather than in its entirety. This <br /> interpretation is practical and pragmatic. It would be <br /> incongruous to hold that power to set aside would only <br /> mean power to set aside the award in its entirety and <br /> not in part. A contrary interpretation would not only be <br /> Signature Not Verified<br /> O.M.P. (COMM) 289/2023 Page 15 of 17 <br /> Signed By:CHANCHAL<br /> Signing Date:04.04.2026<br /> 17:01:08<br /> <br /><br /> <br /> <br /> inconsistent with the statutory framework but may also <br /> result in valid determinations being unnecessarily <br /> nullified. <br /> (emphasis supplied) <br /> <br /> 18. The non-awarding of interest on refund of the withheld amount <br /> for non-achievement of the milestones; the rectification of the amount <br /> due for settlement of the final bill; the denial of three percent <br /> difference in post-GST and pre-GST period; and the quashing of <br /> awarding of damages under Section 73 of the Contract Act are <br /> separable, not dependant on other claims awarded and are not <br /> intricately connected with each other. <br /> 19. In view of the above discussion, it is concluded as under: <br /> A. The award directing release of the amount withheld for non-<br /> achievement of milestones is upheld. <br /> B. The award of interest on the amount withheld for non-<br /> achievement of milestones is set aside. <br /> C. The amount awarded towards the final bill is corrected to <br /> Rs.54,44,112/-. <br /> D. The award of three percent difference between the post-GST <br /> and pre-GST period is set aside. <br /> E. The grant of refund of penalty for delay in completion of the <br /> sample flat is upheld. <br /> <br /> F. The award of damages under Section 73 of the Contract Act on <br /> account of prolongation of the contract is set aside. <br /> G. The interest granted except on the amount withheld for non-<br /> achievement of milestones and the costs awarded are upheld. <br /> Signature Not Verified<br /> O.M.P. (COMM) 289/2023 Page 16 of 17 <br /> Signed By:CHANCHAL<br /> Signing Date:04.04.2026<br /> 17:01:08<br /> <br /><br /> <br /> <br /> 20. The petition is partly allowed. Pending applications stand <br /> disposed of. <br /> <br /> <br /> <b>AVNEESH JHINGAN, J</b> <br /> <b>APRIL 04, 2026 </b><br /> <b>‘ha’ </b><br /> Reportable:- <b>Yes</b> <br /> Signature Not Verified<br /> O.M.P. (COMM) 289/2023 Page 17 of 17 <br /> Signed By:CHANCHAL<br /> Signing Date:04.04.2026<br /> 17:01:08<br /> </div>