THE BISWA BHARATI CONSTRUCTION vs STATE OF WEST BENGAL AND ORS.
- Court
- Calcutta High Court
Form No. J(2)
In the High Court at Calcutta
Civil Appellate Jurisdiction
Appellate Side
Present: The Hon’be Justice Sabyasachi Bhattacharyya
And
The Hon’ble Justice Sandip Jumar De
M.A.T 1924 of 2025
IA No: CAN 1 of 2025
The Biswa Bharati Construction
Vs.
The State of West Bengal and others
For the appellants : Mr. Robiul Islam
Mr. Sk. Jayed Hossain
Mr. Sumitra Das
For the State : Mr. Nilanjan Bhattacharjee, SSC
Ms. Jayita Dhar Chakraborty
Mr. Saikat Dey
For the private respondents : Mr. Prosenjit Mukherjee
Mr. Sk. Sahajahan Ali
Mr. Arghya Kamal Das
Heard on : 09.10.2026
Judgment on : 09.10.2026
2
Sabyasachi Bhattacharyya, J.:-
1. Heard learned counsel for the parties.
2. The premise of the lis is an allegation raised by the private
respondents that the appellant, while constructing a road, had
demolished the boundary wall of a property of the private
respondents.
3. Subsequently, in an earlier writ petition, a learned Single Judge
of this court was pleased to direct that a field enquiry was to be
conducted by the authorities upon prior notice to the appellant
and thereafter, upon giving opportunity of hearing to the
appellant and the other interested parties, a reasoned order was
to be passed with regard to the issue.
4. In the said order, it was further recorded that in the event the
respondent no.4 finds that the respondent no.11 (present
appellant) has demolished the boundary wall of the writ
petitioners (present private respondents) without any lawful
authority, the said authority shall direct the present appellant to
pay Rs.10 lakh to the present private respondents by way of
compensation.
5. Subsequently, pursuant to such direction, a field enquiry was
held and a report submitted before the concerned DL & LRO.
6. Upon consideration of the same, giving opportunity of hearing to
the appellant, the matter was disposed of in favour of the private
3
respondents, holding that the appellant had, in an unauthorized
manner, demolished the boundary wall of the private
respondents during the road construction work and accordingly
a direction was given to the appellant to reconstruct the
demolished wall as well as pay compensation of Rs.10 lakh.
7. Learned counsel for the appellant argues that prior to
conducting the field enquiry, no notice was given to the
appellant.
8. Secondly, at the time of hearing before the concerned authority
and/or before that, no copy of the field enquiry report was ever
served on the appellant, thereby depriving the appellant of a
meaningful opportunity of hearing before the authority.
9. It is thus submitted that in the teeth of such patent violation of
principles of natural justice, the present writ petition was
moved, upon which the learned Single Judge came to a finding
that since such issues as to non service of notice were not raised
before the concerned authority, the same cannot be reopened at
this juncture.
10. Learned Senior Standing Counsel appearing for the State
respondents submits that the crux of the dispute which remains
to be considered is only the imposition of Rs.10 lakh
compensation on the appellant, since the appellant has, in the
meantime, already rebuilt the demolished wall, thereby virtually
4
acquiescing to the report to the extent that it was the appellant
which was responsible for the demolition of the said wall.
11. Even insofar as the quantum of compensation is concerned, it is
argued that in the earlier round of litigation, the writ court had
categorically directed the appellant to pay Rs.10 lakh in the
event it was found that the boundary wall of the private
respondents was demolished without any lawful authority.
12. Thus, it is argued that the said chapter cannot be reopened.
13. Learned counsel appearing for the private respondents argues in
tune with the contentions of the State and further submits that
the boundary wall has already been rebuilt by the appellant.
14. Upon a careful consideration of the arguments of the parties and
the materials before us, we find that a plea has been taken by
the appellant to the effect that the boundary wall was
constructed under threat of contempt, as per the directions of
the court taking up the contempt application, and as such, the
said act cannot be construed as acquiescence by the appellant to
the factum of demolition of boundary wall in an unauthorized
manner by the appellant.
15. In support of such contention, learned counsel for the appellant
hands over server copies of two orders, respectively dated
February 27 and April 2, 2026, passed in the contempt
proceeding.
5
16. From the first such order dated February 27, 2026, we find that
the learned Single Judge taking up the contempt application had
recorded that as per the request made by the learned Advocate
for the alleged contemnor no.2, the matter was to be listed for
further consideration on a subsequent date.
17. It was further clarified in the said order that the order passed on
that date and the previous orders as passed by the court in
connection with the contempt application would not “stand in
the way in complying with the judgment and order dated October
28, 2025 as passed by this court in WPA 23735 of 2025 in the
event the alleged contemnor no.2 reconstructs the demolished
boundary wall of the writ petitioners in the meantime”.
18. Thus, we find that the contempt court did not pass any
categorical direction on the appellant which could be construed
as a threat of imposition of penalty for contempt in the event
such reconstruction of boundary wall was not done.
19. Rather, by the aforesaid observations, the contempt court had
left it open to the appellant’s discretion to make the
reconstruction of the demolished boundary wall, merely
clarifying that if such rebuilding was done, the orders of the
court would not come in its way.
20. In the subsequent order dated April 2, 2026, the learned Single
Judge taking up the contempt matter merely recorded that the
learned Advocate appearing on behalf of the alleged contemnor
6
no.2 submitted on instruction that the said contemnor had
already initiated the process of reconstruction of the boundary
wall “as directed by the court” and, also upon instruction, the
said learned Advocate further submitted that it would take two
weeks’ time to reconstruct the said wall to its fullest extent.
21. The learned Advocate also submitted that such time might be
given for compliance of the order as passed by the court.
22. Although the expression “as directed by the court” was used by
learned counsel for the alleged contemnor, nothing has been
placed before us to show that there was any such specific
direction issued by the court taking up the contempt
application.
23. Thus, from the said orders, copies of which are kept on record, it
is evident that there was no occasion of any “threat of contempt”
for the appellant to comply with the order of the court insofar as
reconstruction of the demolished boundary wall was concerned,
and the appellant undertook such reconstruction even during
pendency of the contempt application of its own volition.
24. Having done so, the appellant cannot take the plea that the
reconstruction was not done in acquiescence of the position that
it was the appellant which was responsible for the demolition.
25. Insofar as the quantum of compensation of Rs.10 lakh is
concerned, learned Senior Standing Counsel is perfectly justified
7
in arguing that the said quantum was crystallized vide judgment
dated August 4, 2025 passed in WPA 16213 of 2025.
26. In paragraph no.28 thereof, the concerned learned Single Judge
had observed that it was made clear that in the event the
respondent no.4 found that the respondent no.11 has
demolished the boundary wall of the writ petitioners without any
lawful authority, respondent no.4 shall direct the respondent
no.11/authority to pay Rs.10 lakh to the writ petitioners as and
by way of compensation.
27. Having not challenged the said order at any point of time, the
appellant cannot now resile from such position and assail such
quantum.
28. The imposition of such compensation was only dependent upon
it being found by the authority that the appellant had
demolished the boundary wall.
29. Since the appellant has already reconstructed the boundary
wall, as per our previous observation, no further question
remains regarding the liability of the appellant in that regard.
30. Thus, the question as to whether prior notice of field enquiry
was given or not loses relevance.
31. Even otherwise, we do not find fault with the observation of the
learned Single Judge that nowhere from the records before the
concerned authority is it evident that, at any point of time, any
question or objection was raised by the appellant before such
8
authority as to no notice of the field enquiry having been given
to the appellant and/or no copy of the field enquiry report
having been served on the appellant.
32. We also find that there was no contemporaneous communication
by the appellant to the concerned authority as to such non-
service of notice/copy.
33. Thus, the observation of the learned Single Judge in the
impugned order to the effect that the appellant was not entitled
to raise such point for the first time in the writ petition, having
not raised it before the concerned authority, cannot be faulted.
34. Thus, there is no scope of interference in the appeal.
35. Accordingly, MAT 1924 of 2025 is dismissed on contest, thereby
affirming the impugned order dated October 28, 2025 passed in
WPA 23735 of 2025 and directing the appellant to pay the
amount of compensation to the tune of Rs.10 Lakh to the private
respondents at the earliest, positively by the end of October,
2026.
36. CAN 1 of 2025 is consequentially disposed of as well.
37. It is made clear that upon such payment being made by the
appellant to the private respondents, it will be open to the
appellant to recover in due process of law any such sum, if
deposited on account of such compensation to any authority,
from the said authority, of course, subject to such authority
raising any defence as to any other non-compliance on the part
9
of the appellant for which the said authority was entitled to
retain such amount, fully or partially.
38. There will be no order as to costs.
39. Urgent photostat copies of this judgment, if applied for, be given
to the parties upon compliance of all requisite formalities.
(Sabyasachi Bhattacharyya, J.)
I agree.
(Sandip Kumar De, J.)
AD-30
AK