STATE OF WEST BENGAL vs RAJPATH CONTRACTORS AND ENGINEERS LTD

Court
Calcutta High Court

IN THE HIGH COURT AT CALCUTTA
CIVIL APPELLATE JURISDICTION
COMMERCIAL DIVISION
Before:
The Hon’ble Justice Debangsu Basak
And
The Hon’ble Justice Aryak Dutt

FAT 180 Of 2022
State of West Bengal
Vs.
Rajpath Contractors and Engineers Limited

For the Appellant : Mr. Dibashis Basu, Ld. A.G.P.,
Ms. Sneha Datta,
Ld. Junior Gvt. Adv.,
Mr. Purnendu Das, Adv.,
Mr. Chandrachur Lahiri, Adv.,

For the Respondent : Mr. Sakya Sen, Ld. Sr. Adv.,
Mr. Priyankar Saha, Adv.,
Ms. Srijani Mukherjee, Adv.,
Mr. Ritinkar Bhattacharjee, Adv.

Heard On : 27.08.2026, 07.09.2026,
17.09.2026, 28.09.2026

Hearing Concluded On : 28.09.2026
Judgment Delivered On : 12.10.2026

2


Aryak Dutt, J.:
1. This appeal under Section 37(1)(c) of the Arbitration
and Conciliation Act, 1996 (hereinafter referred to as “the Act”) is
st
directed against the judgment dated 31 March, 2022, passed by
the learned Judge, Commercial Court at Alipore in Misc. Case
(Arbitration) No. 35 of 2019. By the judgment, the learned
Commercial Court rejected the application of the State of West
Bengal under Section 34 of the Act and declined to set aside the
th
Arbitral Award dated 29 September, 2014, as corrected by the
th
corrigendum dated 16 October, 2014, passed by a three-
member Arbitral Tribunal in favour of Rajpath Contractors and
Engineers Limited.

2. The State was the respondent before the Arbitral
Tribunal and the petitioner before the Commercial Court and it is
the appellant here. Rajpath Contractors and Engineers Limited
(hereinafter referred to as “the contractor”) was the claimant and
is the respondent here.

3. Following Tender Notice No. 14 of 1994-95 (2nd Call) of
the Superintending Engineer, State Highway Circle No. 1, P.W.

3

(Roads) Directorate, the contractor was awarded the work of
“Design and construction of proposed High Level R.C. or P.S.C.
Bridge over River Hogol at Sonakhali on Calcutta-Basanti Road in
the district of South 24-Parganas under 24-Parganas Highway
Division” being Agreement No.32 of 1996-97 was executed
between the parties.

4. The work was completed about six years (2191 days)
after the scheduled date. The contractor applied for extension of
th th
time by letters dated 29 December, 1999 and 5 October, 2004.
No formal extension was granted. The State, however, accepted
th th
the work, paid the 13 R/A and Final Bill and the 12 escalation
th
bill, and recorded the date of completion as 30 December, 2005.

5. The contractor attributed the delay to the State. Its
case was that the State failed to hand over free and unobstructed
possession of the site, delayed the mobilisation advance, failed to
make proper and timely on-account payments, failed to prevent
obstruction by local pressure groups at the site, and delayed
approval of drawings. The State's case was that the delay was
caused by the contractor's own slow progress, its want of
readiness and its failure to mobilise resources.

4


6. Disputes having arisen, a three-member Arbitral
Tribunal was constituted. Its members were engineers with long
th
experience. The first sitting was held on 24 April, 2009. The
th
contractor filed its statement of claim on 5 June, 2009, the
th
State filed its statement of defence on 7 September, 2009, and
th
the contractor filed its rejoinder on 4 February, 2010. The
Tribunal in total held 36 sittings.


7. The Award runs into 189 pages. The Tribunal found
st
that out of the total delay of 2191 days which is from 1 January,
th
2000 to 30 December, 2005, 197 days were attributable to the
nd
contractor. These were 24 days between 22 February, 1997 and
th
17 March, 1997, when the contractor failed to submit drawings
st rd
and designs, and 173 days between 1 February, 2002 and 23
July, 2002, when it was negligent in submitting drawings. The
balance of 1994 days was held attributable to the State.

th
8. The Tribunal made and published its award on 29
September, 2014 and awarded a principal sum of Rs.
3,65,87,951/-, along with interest pendente lite for a sum of Rs.
th th
2,38,77,396/- for the period from 24 April, 2009 to 29
September, 2014, and costs of Rs. 5,41,500/-. By a corrigendum

5

th
dated 16 October, 2014, the Tribunal corrected certain clerical
and typographical errors.

9. The State challenged the award under Section 34 by
th
an application filed on 27 July, 2015. The case was received on
th
transfer by the Commercial Court at Alipore on 7 November,
2019 and registered as Misc. Case (Arbitration) No. 35 of 2019.

10. The learned Commercial Court noted the State's
objections that the contractor did not submit monthly bills. The
delay in payment of bills is not a repudiatory breach. Claim 4 was
barred by acceptance of the final bill. The contractor's own slow
progress caused the delay. The claim for idle establishment was
inconsistent with the plea that the contractor could not mobilise
its resources. The finding of 1994 days of delay rested on
overlapping charts. Claims 5 and 6 were allowed without reasons.

11. The learned Court held that the Tribunal had dealt
with each claim and objection “with precise and sufficient
reasons”. It held that the attribution of 1994 days of delay to the
State was a finding of fact reached “after careful consideration of
all documents as submitted by both sides” and could not be
revisited by re-appreciating evidence. There was no breach of

6

natural justice, no non-application of mind and no patent
illegality. The Section 34 application was rejected without costs.

12. Learned counsel for the State, relying on the written
notes of argument, submitted that the award is contrary to the
terms of the contract and to the public policy of India, and that
the learned Commercial Court failed to examine the points
raised.


13. The claims made by the claimant and allowed by the
Arbitral Tribunal are contrary to the Special Terms and
Conditions of the contract. The contract provided that the
contractor shall not be entitled to any extra cost unless he gives
notice of his claim in writing. The contractor never gave such
notice. This point was urged before the Commercial Court but not
dealt with.

14. Profit is always built into the contractor's rates, and
contract does not permit a separate claim for loss of profit. The
contractor was also paid escalation of Rs. 4,26,00,598/- in gross.
Allowing loss of profit on top of this results in double payment.

7

15. The Measurement Books maintained by the contractor
showed slow progress. From the outset the contractor
complained of hindrances at the Basanti end while the State
insisted that it start at the Sonakhali end. The contractor began
th
work at Sonakhali only on 18 December, 1997, almost a year
after the work order was issued. Neither the Tribunal nor the
Commercial Court dealt with this.

16. On delayed payment of bills the Tribunal awarded
interest at 15% per annum simple. This is contrary to the
contract and to natural justice.

17. The full contract value of Rs. 8,29,00,000/- was paid
th
through the 13 and Final Bill and accepted by the contractor
without objection. Having accepted final payment, the contractor
was estopped from raising further claim.

18. Claim on account of escalation is contrary to contract,
under which escalation is payable only after one year from the
date of dropping of tenders Claims for escalation and refund of
security deposit were allowed in full without reasons.

8

19. The Tribunal has awarded interest at several stages on
the same sums, pre-reference, interest pendente lite , and interest
st
at 18% per annum from 1 February, 2006 till payment. The
Tribunal acted arbitrarily and beyond its jurisdiction and ignored
the contract.

20. Bharat
The State in their written submission relied on
Coking Coal Ltd. v. Annapurna Construction , reported in
(2003) 8 SCC 154 , for the proposition that an arbitrator cannot
act arbitrarily, irrationally, capriciously or independently of the
contract, and cannot travel beyond its parameters. It relied on
Oil and Natural Gas Corporation Ltd. v. Saw Pipes Ltd. ,
reported in (2003) 5 SCC 705 , for the proposition that the terms
of the contract must be considered before deciding whether a
party claiming damages is entitled to them. Finally, reliance was
placed on Executive Engineer (R and B) v. Gokul Chandra
Kanungo , reported in 2022 SCC OnLine SC 1336 , on the
discretion of the Arbitrator under Section 31(7)(a) of the Act and
the duty to give reasons for the rate and period of interest.

21. Learned counsel for the contractor, relying on its notes
of argument, supported the award and the impugned judgment.

9


22. It was argued by the respondent that the scope of
review under Section 34 is narrow, and under Section 37 it is still
narrower. The Court does not sit in appeal over the award,
cannot re-appreciate evidence, and cannot substitute its own
view for that of the Tribunal.

23. The award is a detailed, speaking award. The Tribunal
considered the pleadings, every exhibit relied on by both sides
and every contractual clause placed before it. It recorded specific
findings on delay in approval of drawings, delay in handing over a
hindrance-free site, and the history of payments, and then dealt
with each claim separately. The Tribunal appreciated the
evidence placed before it and reappreciation of such evidence
under Section 34 or Section 37 is not permissible.

24. The finding that delay was attributable to the State is a
pure finding of fact. It was reached by a Tribunal of three
experienced engineers, after analysis of the contemporaneous
record. The State's challenge is an invitation to re-weigh that
evidence.

10

25. It was argued that the grounds concern the
construction of the contract of which the Tribunal is the final
judge. Escalation, delayed payment, and whether acceptance of
the final bill operated as a waiver, has been answered by the
Tribunal. The Tribunal's view on each is a plausible reading of
the contract as a whole and conduct of the parties. It did not
rewrite the contract.

26. The State has raised grounds, almost all of which
attack findings of fact and interpretation by the Tribunal. The
Commercial Court refused to conduct a roving re-appraisal of
evidence looked into by the Tribunal. That refusal was correct in
law. The award is not patently illegal, not contrary to the
fundamental policy of Indian law, and not against justice or
morality.

27. The respondent in the written notes relied on the
following judgments Madhya Pradesh Road Development
Corporation Ltd. v. Jabalpur Corridor P. Ltd. , reported in
2026 SCC OnLine SC 1001 , Jan De Nul Dredging India (P)
Ltd. v. Tuticorin Port Trust , reported in (2026) 3 SCC 186 ,
Punjab State Civil Supplies Corporation Ltd. v. Sanman Rice

11

Mills , reported in 2024 SCC OnLine SC 2632 , Ramesh Kumar
Jain v. Bharat Aluminium Company Ltd. , 2025
reported in
SCC OnLine SC 2857 , MMTC Ltd. v. Vedanta Ltd. , reported in
(2019) 4 SCC 163 , Konkan Railway Corporation Ltd. v.
Chenab Bridge Project Undertaking , reported in (2023) 9 SCC
85 and Larsen Air Conditioning and Refrigeration Co. v.
Union of India , reported in (2023) 15 SCC 472 for the
proposition of scope of Section 37 of the Act of 1996. The learned
advocate for respondent had further relied on Associate
Builders v. Delhi Development Authority , reported in (2015) 3
SCC 49 for the proposition that the Tribunal is the master of the
quantity and quality of evidence produced before it.


28. The test applicable is Section 34 as explained in Saw
Pipes (supra) and Associate Builders (supra) is that, an award
is open to challenge if it is contrary to the fundamental policy of
Indian law, the interest of India, justice or morality, or if it is
patently illegal.

29. In Associate Builders (supra) the Supreme Court
cautioned that when a court applies the public policy test it does
not act as a court of appeal, errors of fact cannot be corrected,

12

and the arbitrator is “the ultimate master of the quantity and
quality of evidence”. An award based on little evidence, or on
evidence that does not measure up in quality to a trained legal
mind, is not invalid on that score.

30. The Appellate Court's role under Section 37 is
narrower. In MMTC Ltd. (supra) , the Supreme Court held that
interference under Section 37 “cannot travel beyond the
restrictions laid down under Section 34”. In Punjab State Civil
Supplies Corporation Ltd. (supra) , the Court said that the
Section 37 power “is exercisable only to find out if the court,
exercising power under Section 34 of the Act, has acted within its
limits as prescribed thereunder or has exceeded or failed to
exercise the power so conferred”.

31. Most recently, in Madhya Pradesh Road
Development Corporation Ltd. (supra) , the Supreme Court
described the jurisdiction to upset an award as “a narrowing
pyramid”, in which each higher layer must be “increasingly
hands-off”. It was held that interference under Section 37 is
permissible only where the Section 34 court exceeded its
jurisdiction or failed to exercise it. To the same effect are Konkan

13

Railway Corporation Ltd. (supra) wherein the Supreme Court
restored an award because there was "at least some evidence and
logical rationale for each award element" and the arbitrator's
approach "was certainly a possible view a reasonable man might
take".

32.
The authorities relied on by the State do not enlarge
this jurisdiction. Bharat Coking Coal Ltd. v. Annapurna
Construction reported in (2003) 8 SCC 154 arose under the
Arbitration Act, 1940. It held that an arbitrator who wanders
outside the contract commits a jurisdictional error, but it
reaffirms, that an error in the construction of the contract is an
error within jurisdiction. Saw Pipes Ltd. (supra) holds that the
terms of the contract must be considered before awarding
damages. Neither decision permits a court to re-weigh evidence or
prefer its own reading of the contract to a plausible reading by
the Tribunal.


33. The State's submissions on this issue invite a fresh
appraisal of the evidence. The record on an earlier, unrelated
contract says nothing about who delayed this one. Whether the
contractor ought to have started the work, and whether the delay

14

in the mobilisation advance is excused by the absence of a bank
guarantee, are questions of fact on which the Tribunal of three
experienced engineers were the final judges.

34. A Tribunal is not obliged to refer to every document on
record. The learned Commercial Court correctly held so.

35. The finding that delay was attributable to the State is
based on evidence and is a possible view. It has been affirmed
under Section 34. It is not open to this Court to disturb it.

36. The State contends that Claims are barred by the
Special Terms and Conditions, because the contractor did not
give notice within 7 days. Failure to hand over an unencumbered
site, delay in approving drawings, and delay in payment is a
question of construction of a contract. Under Associate Builders
(supra) construction of the term of contract is for the Tribunal to
determine and cannot be displaced unless no fair-minded person
could adopt it.

37. The State has not identified any period within the 1994
days that falls in another excluded category. Further, the
th
contractor sought extension of time by letters dated 29

15

th
December, 1999 and 5 October, 2004. The State neither
rejected those requests nor declined to accept the work. It paid
th
the Final Bill recording completion on 30 December, 2005. The
State was thus on notice throughout.

38. If this Court differs from the view taken by the Arbitral
Tribunal such view of this court cannot be substituted in the
award. Unless such award portrays perversity. No such
perversity is shown in the present case.

39. The State has argued that the contract bars a separate
claim for profit, and that escalation already paid compensates the
contractor. The Tribunal has held that for having its men,
machinery and capital locked into one project for six years
beyond the contract period. Loss of profit-earning capacity during
a prolongation caused by the employer is a recognized head of
damages. The Supreme Court upheld an award on that basis in
McDermott International Inc. v. Burn Standard Co. Ltd. ,
reported in (2006) 11 SCC 181 as cited by the respondent.

40. The State has argued that the contractor, having
accepted the final bill, was estopped from raising further claim.
Whether acceptance of a final bill amounts to accord and

16

satisfaction or waiver is a question of fact, depending on the
parties' conduct and the circumstances of payment. The Tribunal
accepted that case in part. This is a finding on evidence which is
not shocking to us.

41. Refund of the security deposit of Rs. 5,00,000/- was
not in dispute. The work was completed and accepted. No ground
is shown to withhold it.


42. The State's own Executive Engineer computed and
paid escalation on March 1995 base. The later Report of the
Committee on Public Accounts took a different view. The Tribunal
declined to act on the Committee's report and held that no
recovery was due. That is a construction of the contract which a
reasonable person could adopt. The State may prefer the
Committee's reading which was rejected by the Tribunal, but that
precisely holds no ground for interference by us.

43. The State's complaint is that the Tribunal awarded
interest several times over on the same sums. The Award
compensates the contractor for the State holding back admitted
amounts under its own bills beyond the due date. It is not
interest on the sums awarded. The State has not pointed to any

17

clause of the contract that bars compensation for delayed
payment. In the absence of such an agreement, the statute
empowers the Tribunal to award interest.

44. The Tribunal awarded interest pendente lite only from
the first sitting. There is no duplication of interest, no
contravention of Section 31(7) of the Act, and no ground to
interfere with the award of interest which is within the domain of
the Arbitrators.

45. The learned Commercial Court held that the Tribunal
had dealt with each claim with sufficient reasons, and refused to
re-appreciate evidence. No ground under Section 34 is made out
that would justify setting aside the award. The learned Court
neither exceeded nor failed to exercise its jurisdiction.

46. The Supreme Court observed in MMTC (supra) and
Jan De Nul Dredging India (P) Ltd. (supra) , if an award is not
liable to be disturbed under Section 34, it should not be
interfered with under Section 37.

th
47. The award dated 29 September, 2014 is a detailed,
reasoned award of 189 pages by a Tribunal of experienced

18

engineers. Its findings on the attribution of delay are findings of
fact based on evidence. Its reading of the contract, and of the
effect on the final bill, is a plausible one. Its award of interest is
within Section 31(7) of the Act. It is not in conflict with the public
policy of India. The learned Commercial Court rightly declined to
set aside the Award.

48. In view of our discussion F.A.T. No. 180 of 2022 is
st
dismissed . The judgment dated 31 March, 2022 passed by the
learned Judge, Commercial Court at Alipore in Misc. Case
(Arbitration) No. 35 of 2019 is affirmed. The Arbitral Award dated
th
29 September, 2014, as corrected by the corrigendum dated
th
16 October, 2014, is upheld.

49. There shall be no order as to costs.

(Aryak Dutt, J.)

42. I agree
(Debangsu Basak, J.)