New Age Fire Fighting Co Ltd vs Nanded Airport Limited

Court
Bombay High Court

CNR No : HCBM020306842026

2026:BHC-OS:20539
carbpl30683-2026-J.doc

AGK
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
IN ITS COMMERCIAL DIVISION
COMM ARBITRATION PETITION (L) NO.30683 OF 2026
New Age Fire Fighting Co. Limited
… Petitioner
Vs.
1. Nanded Airport Limited
2. Union Bank of India
… Respondents
Mr. Rohan Savant with Ms. Aneesa Cheema and Mr.
Harsh Kesharia for the Petitioner.
ATUL
GANESH
KULKARNI
Mr. Tushad Kakalia with Mr. D.J. Kakalia, Mr. Paresh
Patkar and Mr. Ayaan Zariwalla i/by Mulla & Mulla and
Craigie Blunt & Caroe for the Respondents.
Digitally signed by
ATUL GANESH
KULKARNI
Date: 2026.09.18
12:12:47 +0530
CORAM : AMIT BORKAR, J.
RESERVED ON : SEPTEMBER 16, 2026.
PRONOUNCED ON : SEPTEMBER 18, 2026
JUDGMENT:
1. By the present Petition filed under Section 9 of the
Arbitration and Conciliation Act, 1996, the Petitioner seeks
directions against the Respondents to restrain the encashment of
the Performance Bank Guarantee. The Petitioner states that
Respondent No.1 has invoked the Bank Guarantee by its email
dated 1 September 2026. The Petitioner has sought other reliefs
1
Uploaded on - 18/09/2026 Downloaded on - 18/09/2026 13:58:29

carbpl30683-2026-J.doc

connected with the said Bank Guarantee.
2. According to the Petitioner, the facts and circumstances
which led to filing of the present Petition are as follows. On 18
April 2024, the Petitioner submitted its initial offer for supplying
one Airfield Crash Fire Tender, known as ACFT, having a water
tank capacity of 10,000 litres for Nanded Airport. Thereafter, on 10
July 2024, the Petitioner submitted a revised offer pursuant to the
tender issued by Respondent No.1. On 5 August 2024, the
Petitioner confirmed its offer. Respondent No.1 issued Letter of
Award No. NAL/CPG/ADMIN/2024/11 dated 6 August 2024 for a
total contract value of Rs.7,03,00,000/-. On 21 August 2024 and
22 August 2024, Respondent No.1 issued Notice to Proceed, which
was made effective from 22 August 2024. Pursuant to the said
Notice, the Petitioner started the work relating to execution of the
contract, including procurement and manufacture of the ACFT. On
10 September 2024, the Petitioner furnished Advance Bank
Guarantee No. 03352GI3D2403957 for Rs.1,48,94,068/- in favour
of Respondent No.1. The Bank Guarantee was valid up to 6
October 2025 and its claim period was stated to be up to 6 October
2026. On 25 April 2025, Respondent No.1 directed the Petitioner
to stop all engineering, manufacturing, procurement and delivery
activities under the Letter of Award. The Petitioner informed
Respondent No.1 that by that time major components had been
manufactured and other parts and accessories had either been
procured or ordered. Thereafter, on 20 June 2025, Respondent
No.1 terminated the Letter of Award under Article 24, which
provided for termination for convenience. Respondent No.1 stated
2
Uploaded on - 18/09/2026 Downloaded on - 18/09/2026 13:58:29

carbpl30683-2026-J.doc

that the termination was because MIDC had resumed Nanded
Airport. Respondent No.1 asked the Petitioner to refund the
advance amount of Rs.1,48,94,068/-. It was stated that the Bank
Guarantee would be returned after the advance amount was
received.
3. During September and October 2025, the parties exchanged
correspondence regarding settlement of the matter. The
discussions were concerning return of the Bank Guarantee against
refund of the advance amount. However, the proposed settlement
was not concluded by Respondent No.1. On 18 October 2025 and
28 October 2025, the Petitioner submitted its claim for
Rs.4,63,82,051/-. The claim was towards the work carried out,
materials procured and the obligations performed by the Petitioner
up to the date of termination. On 30 March 2026, Respondent
No.1 rejected the Petitioner's claim in its entirety. At that stage,
Respondent No.1, for the first time, relied upon Article 39
concerning Force Majeure. Thereafter, on 1 September 2026, the
Petitioner received information from its banker that Respondent
No.1 had called upon Respondent No.2 to encash the Bank
Guarantee. The Petitioner was informed that payment would be
made after completion of the required formalities. According to the
Petitioner, the encashment of the Bank Guarantee is imminent. It is
in these circumstances that the Petitioner has filed the present
Petition.
4. Mr. Savant, learned Advocate appearing for the Petitioner,
submitted that Respondent No.1 terminated the Letter of Award by
relying upon Article 24 of the GCC, which provides for Termination
3
Uploaded on - 18/09/2026 Downloaded on - 18/09/2026 13:58:29

carbpl30683-2026-J.doc

for Convenience. Article 25 of the GCC, which deals with
Termination for Default, was never invoked against the Petitioner.
The Termination Notice dated 20 June 2025 does not contain any
allegation that the Petitioner had committed any default or breach,
caused any delay, supplied defective goods or failed to perform its
obligations. On the contrary, in paragraph 8 of the said Notice,
Respondent No.1 appreciated the efforts made by the Petitioner,
thanked the Petitioner for its cooperation and expressed its hope of
working with the Petitioner in future projects. Paragraph 6 of the
Notice stated that after termination, no obligations would arise
against either party, except those obligations which were stated to
continue even after termination.
5. According to Mr. Savant, the termination took place only
because MIDC resumed possession of the airport site under its
Resumption Order dated 8 April 2025. As a result, Respondent
No.1 stopped its operations at Nanded Airport. This was an issue
between Respondent No.1 and MIDC, which was a third party. The
Petitioner had no role in that matter and had no control over it. At
all relevant times, the Petitioner was ready and willing to perform
its obligations under the contract. By then, major components of
the ACFT had been manufactured. The other necessary parts and
accessories had been procured or ordered and were available for
being fitted to the ACFT. It was submitted that the rights of the
Petitioner could not be affected because of a dispute or
circumstance between Respondent No.1 and a third party.
6. Mr. Savant submitted that, in any event, Respondent No.1
has till date not alleged that it suffered any loss or damage because
4
Uploaded on - 18/09/2026 Downloaded on - 18/09/2026 13:58:29

carbpl30683-2026-J.doc

of any act or failure on the part of the Petitioner. Respondent No.1
has not stated the amount of any such loss or produced any
material to support it. The contract was terminated by Respondent
No.1 for its own convenience. In such circumstances, according to
the Petitioner, encashing the Bank Guarantee without even
claiming any loss cannot be treated as an ordinary enforcement of
security. It would amount to Respondent No.1 recovering the
amount of the Bank Guarantee on its own and without first
establishing any liability of the Petitioner.
7. Mr. Savant submitted that the facts of the present case show
several special circumstances which justify protection of the
Petitioner. First, the Letter of Award was terminated by Respondent
No.1 for its own convenience and not because of any default by
the Petitioner. The termination was caused only because MIDC
resumed the airport site, which was completely beyond the control
of the Petitioner. Second, Respondent No.1 had stated that the
Bank Guarantee would be returned to the Petitioner, but the
settlement proposed for that purpose was not completed by
Respondent No.1. Third, the Bank Guarantee was given only in
respect of the unadjusted advance. According to the Petitioner, the
advance had been used for performing the obligations and for
procuring customised goods which could not easily be sold to
another purchaser. Fourth, the Petitioner has made a quantified
claim under Article 24.1 of the GCC arising from the same
termination. The claim is more than three times the amount
covered by the Bank Guarantee. Fifth, Respondent No.1 has taken
different stands at different stages. It first terminated the contract
5
Uploaded on - 18/09/2026 Downloaded on - 18/09/2026 13:58:29

carbpl30683-2026-J.doc

under Article 24 and, only after receiving the Petitioner's claim,
relied upon Article 39 relating to Force Majeure. Sixth, the Bank
Guarantee was invoked shortly before expiry of its claim period,
without prior notice to the Petitioner and without stating or
quantifying any loss suffered by Respondent No.1.
8. It was submitted that Respondent No.1 has stopped carrying
on the only business in which it was engaged and has lost the only
asset from which it was earning revenue. In these circumstances,
the Petitioner apprehends that if the Bank Guarantee is encashed
and the amount is taken by Respondent No.1, the Petitioner may
not be able to recover that amount even if it succeeds in the
arbitration proceedings. According to the Petitioner, it may then
have only an award in its favour without any possibility of
recovering the money.
9. Mr. Savant pointed out that during September and October
2025, the parties were in correspondence regarding a settlement
under which the Bank Guarantee was to be returned against
repayment of the advance. By its e-mail dated 25 September 2025,
the Petitioner requested a draft Minutes of Meeting recording this
arrangement. Thereafter, by its e-mail dated 6 October 2025, the
Petitioner forwarded a draft Minutes of Meeting along with a draft
No Due Certificate. According to the Petitioner, it was Respondent
No.1 which did not complete the proposed settlement. It was
submitted that after not completing the arrangement which it had
proposed, Respondent No.1 could not now unilaterally encash the
Bank Guarantee.
6
Uploaded on - 18/09/2026 Downloaded on - 18/09/2026 13:58:29

carbpl30683-2026-J.doc

10. Mr. Savant submitted that Article 24.1 of the GCC provides
that when the contract is terminated for convenience, the Vendor is
entitled to receive, as full compensation, the amount relating to all
obligations performed under the Contract up to the date of
termination, along with the retainage withheld. Relying upon this
provision, the Petitioner, by its letter dated 18 October 2025,
which was forwarded by e-mail dated 28 October 2025, submitted
a quantified claim of Rs.4,63,82,051/-. The claim was supported
by a detailed statement of claim and relevant documents. It was
pointed out that this claim is more than three times the amount
secured by the Bank Guarantee.
11. It was submitted that the advance payment cannot be looked
at separately from the termination of the Letter of Award and the
amounts which may become payable to the Petitioner because of
such termination. According to the Petitioner, it is necessary to
determine whether any amount is payable by the Petitioner
towards the advance and, if so, whether that amount has to be
adjusted against the amount payable to the Petitioner under Article
24.1. These questions can be decided only after the accounts
between the parties are examined. They are part of the disputes
which are required to be decided in arbitration. Respondent No.1
cannot dispute the Petitioner's entire claim on the one hand and,
on the other hand, recover the entire advance amount by
encashing the Bank Guarantee before the accounts between the
parties are determined.
12. Mr. Kakalia, learned Advocate appearing for the
Respondents, submitted that Respondent No.1 issued Letter of
7
Uploaded on - 18/09/2026 Downloaded on - 18/09/2026 13:58:29

carbpl30683-2026-J.doc

Award No. NAL/CPG/ADMIN/2024/11 dated 6 August 2024 in
favour of the Petitioner for supply of one Airfield Crash Fire
Tender, or ACFT, having a water tank capacity of 10,000 litres for
use at Nanded Airport. The total contract value was
Rs.7,03,00,000/-, including GST. The General Conditions of
Contract, or GCC, formed part of the Letter of Award. Under the
Letter of Award read with the GCC, Respondent No.1 paid an
advance of Rs.1,48,94,068/- to the Petitioner on 27 September
2024. This amount was 25% of the contract value and was paid
against the Bank Guarantee furnished by the Petitioner through
Respondent No.2. Article 20.1 of the GCC required the Petitioner
to furnish an “unconditional” Bank Guarantee in the prescribed
format. The Bank Guarantee in question was issued in that format.
Article 20.10 of the GCC provides that the Purchaser, namely
Respondent No.1, “at its sole option may invoke the part or full
value of the Bank Guarantee(s) unconditionally under terms of this
Contract”. Article 20.11 provides that any claim or demand made
by the Purchaser within one year from the expiry of the Bank
Guarantee would fall within the claim period. It provides that
interest on the advance would be recovered along with the
advance amount.
13. As stated by the Petitioner, the lease under which
Respondent No.1 was operating Nanded Airport was terminated by
the Maharashtra Industrial Development Corporation, or MIDC, by
its Resumption Order dated 8 April 2025. MIDC took possession of
Nanded Airport and Respondent No.1 stopped its operations there.
In these circumstances, which were beyond the control of
8
Uploaded on - 18/09/2026 Downloaded on - 18/09/2026 13:58:29

carbpl30683-2026-J.doc

Respondent No.1, Respondent No.1 by its email dated 25 April
2025 asked the Petitioner to stop work under the Letter of Award.
Thereafter, by Termination Notice bearing Ref. No.
NAL/CAO/2025/25 dated 20 June 2025, Respondent No.1
terminated the Letter of Award under Article 24 of the GCC.
14. Mr. Kakalia submitted that paragraph 7 of the Termination
Notice called upon the Petitioner to refund the advance amount of
Rs.1,48,94,068/-. The Notice stated that after receiving the said
amount, the Bank Guarantee would be returned to the Petitioner.
Thus, according to the Respondents, the return of the Bank
Guarantee was subject to the Petitioner first refunding the advance
amount. The Petitioner has, even till now, and for more than
fourteen months after the Termination Notice, not refunded the
advance amount or any part of it. It has continued to use the
money of Respondent No.1 without making any payment for the
same.
15. Mr. Kakalia submitted that the correspondence exchanged
between the parties, which has been produced by the Petitioner,
shows that the Petitioner had accepted its obligation to refund the
advance against return of the Bank Guarantee. First, by its email
dated 23 June 2025, the Petitioner's Director did not dispute the
demand for refund. Instead, the Petitioner stated that “we are
working with our finance team in regard to the advance payment”.
The Petitioner only requested release of its standby fire tender
vehicle. Respondent No.1 facilitated the release and the Petitioner
collected the vehicle in June 2025. Second, by its email dated 25
September 2025, the Petitioner stated: “As discussed over our call,
9
Uploaded on - 18/09/2026 Downloaded on - 18/09/2026 13:58:29

carbpl30683-2026-J.doc

we kindly request you to share the draft MOM regarding the
returning our Bank Guarantee, as we intend to return your
advance payment.” Thus, the Petitioner stated that it intended to
refund the advance and requested Respondent No.1 to prepare a
draft Minutes of Meeting recording the arrangement for refund of
the advance against return of the Bank Guarantee. Third, a
meeting was held between the authorised representatives of both
parties by way of conference call on 3 October 2025. The meeting
was attended, among others, by Mr. Manoj Barnwal, Mr. Ajay
Kapur and Mr. Pradeep Harsora on behalf of Respondent No.1 and
Mr. Hemant Shah and Mr. Nayan Solanki on behalf of the
Petitioner. According to Respondent No.1, the parties agreed upon
the manner in which the matter was to be closed. Pursuant to that
understanding and the Petitioner's own request dated 25
September 2025, Respondent No.1 sent the Petitioner a draft
Minutes of Meeting along with the format of a No Dues Certificate.
The Minutes of Meeting recorded under the heading “Agreed Way
Forward” that the parties had mutually discussed the matter and
agreed to the following course. First, NFFCL would refund the
entire advance amount of Rs.1,48,94,068/- to the designated bank
account of NAL within two working days from the signing of the
Minutes of Meeting. Second, NFFCL would give a signed “No Due
Claim” certificate in the format of NAL. Third, after receiving the
refund and the signed No Due Claim certificate, NAL would return
the Advance Bank Guarantee to NFFCL within two working days.
Fourth, after completion of these steps, the contract would be
treated as closed.
10
Uploaded on - 18/09/2026 Downloaded on - 18/09/2026 13:58:29

carbpl30683-2026-J.doc

16. Mr. Kakalia submitted that the Petitioner's own email dated 6
October 2025 is important. By that email, the Petitioner forwarded
to Respondent No.1 what it described as the “final draft” of the
same Minutes of Meeting, along with a draft No Dues Certificate.
The Petitioner stated: “As discussed, please find the attached final
draft along with no due certificate in draft format. Kindly check
and revert prior to signature from our management.” The
document sent by the Petitioner was named “Draft-MOM-NAL-
NewAge (1).docx”. This was the same draft which had earlier been
sent by Respondent No.1 and which the Petitioner then returned as
the final draft. According to Respondent No.1, this correspondence
shows that the parties had agreed that the Petitioner would refund
the advance amount and, after receiving that amount, Respondent
No.1 would return the Bank Guarantee.
17. However, Mr. Kakalia submitted that on the very next day,
namely 7 October 2025, the Petitioner changed its position. By an
email sent through its Director, the Petitioner stated: “Since the
order is cancelled and no transaction has taken place, No Due
Certificate from our side is not required.” According to Respondent
No.1, this email shows two things. First, the Petitioner's objection
to the draft Minutes of Meeting was because it required a No Dues
Certificate. Second, the reason given by the Petitioner for not
giving such certificate was that “no transaction has taken place”
under the Letter of Award. Respondent No.1 submits that this
statement shows that the Petitioner accepted that the resumption
of the Airport was a force majeure event and that the contract had
consequently come to an end. Respondent No.1 contends that the
11
Uploaded on - 18/09/2026 Downloaded on - 18/09/2026 13:58:29

carbpl30683-2026-J.doc

Petitioner had accepted that the advance had not been adjusted
and that the entire advance continued to be payable to Respondent
No.1. By its email dated 9 October 2025, Respondent No.1
informed the Petitioner that Article 68 of the GCC, dealing with
Contract Closure, required the Vendor to provide a No Demand
Certificate in the Purchaser's prescribed format.
18. Thereafter, according to Mr. Kakalia, the Petitioner
completely changed its stand. By its letter dated 18 October 2025,
sent under cover of its email dated 28 October 2025, the Petitioner
for the first time raised a claim of Rs.4,63,82,051/- against
Respondent No.1. Respondent No.1 submits that this claim was
raised only later as an attempt to avoid repayment of the advance.
It is submitted that this was contrary to the Petitioner's own earlier
conduct and its statement that “no transaction has taken place”.
Respondent No.1 contends that the claim was an afterthought and
is wholly denied and disputed.
19. Mr. Kakalia submitted that even Respondent No.1 continued
to act bona fide and tried to resolve the dispute. By its email dated
16 December 2025, Respondent No.1 invited the Petitioner for a
meeting and proposed 19 December 2025 as the date. Respondent
No.1 sent reminders on 23 December 2025, 9 January 2026 and
16 January 2026. According to Respondent No.1, the Petitioner did
not respond promptly. A meeting was held through video
conference on 4 February 2026. Respondent No.1 sent a detailed
reply dated 30 March 2026 dealing with and rejecting the
Petitioner's claim. Even after more than fourteen months from the
date of termination, the Petitioner had not refunded the advance
12
Uploaded on - 18/09/2026 Downloaded on - 18/09/2026 13:58:29

carbpl30683-2026-J.doc

amount. The claim period of the Bank Guarantee was to expire on
6 October 2026. In these circumstances, Respondent No.1
submitted that it exercised its rights and took steps to invoke the
Bank Guarantee. According to Respondent No.1, the invocation
was within the terms of the Bank Guarantee and within the claim
period expressly provided in the Bank Guarantee and Article 20.11
of the GCC. It was submitted that the purpose of the invocation
was to recover Respondent No.1's own money, namely the advance
amount which, according to Respondent No.1, remained
unadjusted.
REASONS AND FINDINGS:
20. I have considered the submissions made by Mr. Savant,
learned Advocate for the Petitioner, and Mr. Kakalia, learned
Advocate for the Respondents. I have considered the Letter of
Award, the General Conditions of Contract, the Bank Guarantee,
the correspondence exchanged between the parties and the other
material placed before the Court. The principles laid down by the
Supreme Court in Jindal Steel & Power Ltd. v. Bansal Infra Projects
(P) Ltd., (2025) 10 SCC 176 and Himadri Chemicals Industries
Ltd. v. Coal Tar Refining Co., (2007) 8 SCC 110 are required to be
kept in mind while considering the present Petition.
21. The Bank Guarantee which is relied upon by both sides is an
Advance Bank Guarantee for Rs.1,48,94,068/-. This Bank
Guarantee was given for securing the advance amount paid by
Respondent No.1. The Petition states that the Bank Guarantee was
given for securing an advance equal to 25% of the contract value.
13
Uploaded on - 18/09/2026 Downloaded on - 18/09/2026 13:58:29

carbpl30683-2026-J.doc

Therefore, the question before the Court is whether Respondent
No.1 can invoke this Advance Bank Guarantee for recovering the
advance amount which has not been repaid.
22. The legal position on this issue is fairly settled. In Jindal
Steel & Power Ltd. , the Supreme Court in paragraph 22 has held as
under:
“22. We are aware of the established legal principle that the
Courts should refrain from interfering with the invocation of
a bank guarantee except in cases of fraud of an egregious
nature or in cases where allowing encashment would result
in irretrievable injustice.”
23. The Supreme Court considered the judgment in Hindustan
Construction Co. Ltd. v. State of Bihar (1999) 8 SCC 436 and
reproduced paragraphs 8 and 9 thereof. The principle stated there
is that a Bank Guarantee is an independent contract between the
bank and the beneficiary. Therefore, the Court should not stop its
encashment merely because some dispute has arisen between the
parties under the main contract.
24. The same position has been explained in more detail by the
Supreme Court in Himadri Chemicals Industries Ltd. In paragraph
10, the Supreme Court held that the bank has to honour the Bank
Guarantee according to its terms even if there is a dispute between
its customer and the beneficiary. Thus, merely because there is a
dispute under the main contract, that fact by is not sufficient to
stop enforcement of the Bank Guarantee. The exceptions are
limited. One exception is where there is fraud which goes to the
very foundation of the Bank Guarantee. The other is where
14
Uploaded on - 18/09/2026 Downloaded on - 18/09/2026 13:58:29

carbpl30683-2026-J.doc

encashment would result in irretrievable injury or injustice and the
amount cannot be recovered.
25. In paragraph 11 of Himadri Chemicals, the Supreme Court
explained the first exception and observed:
“The fraud must be of an egregious nature such as to vitiate
the entire underlying transaction.”
26. The Court has accepted that the material relating to fraud
must be clear and must show the knowledge of the bank regarding
such fraud. Therefore, merely stating that the beneficiary has acted
wrongly in the contractual dispute is not sufficient. The fraud
required for this purpose has to be of a much more serious nature.
It must affect the foundation of the transaction and the Bank
Guarantee.
27. The second exception is that of irretrievable injury or
injustice. In paragraph 13 of Himadri Chemicals , while considering
U.P. State Sugar Corpn. v. Sumac International Ltd., (1997) 1 SCC
568, the Supreme Court has made this position clear. Before the
Court can stop encashment on this ground, exceptional
circumstances have to be established. The Supreme Court has
observed:
“Clearly, a mere apprehension that the other party will not
be able to pay, is not enough.”
28. Therefore, it is not sufficient for the Petitioner to say that it
may face financial difficulty if the Bank Guarantee is encashed.
The Petitioner has to place material before the Court to show that
even if it succeeds in arbitration, recovery of the amount from
15
Uploaded on - 18/09/2026 Downloaded on - 18/09/2026 13:58:29

carbpl30683-2026-J.doc

Respondent No.1 would become impossible.
29. Paragraph 14 of Himadri Chemicals summarises the
principles. The following part is relevant:
“(i) While dealing with an application for injunction in the
course of commercial dealings, and when an unconditional
bank guarantee or letter of credit is given or accepted, the
beneficiary is entitled to realise such a bank guarantee or a
letter of credit in terms thereof irrespective of any pending
disputes relating to the terms of the contract.”
30. The Supreme Court states:
“(iii) The courts should be slow in granting an order of
injunction to restrain the realisation of a bank guarantee or a
letter of credit.”
31. Paragraph 14(iv) states:
“Since a bank guarantee or a letter of credit is an
independent and a separate contract and is absolute in
nature, the existence of any dispute between the parties to
the contract is not a ground for issuing an order of injunction
to restrain enforcement of bank guarantees or letters of
credit.”
32. These principles have to be applied while considering the
facts and circumstances of the present case. The terms of the Bank
Guarantee in the present case are important. Clause 5 describes
the Bank Guarantee as unconditional, irrevocable and payable on
demand. The Bank has agreed to pay the Purchaser, upon receiving
a written demand, an amount up to Rs.1,48,94,068/- “without any
demur, reservation, contest or protest and/or without reference to
the Supplier and without the Purchaser needing to provide or
show to the Bank grounds or reasons or give any justification for
16
Uploaded on - 18/09/2026 Downloaded on - 18/09/2026 13:58:29

carbpl30683-2026-J.doc

such demand”. Clause 6 provides that the decision of the
Purchaser to invoke the Bank Guarantee would be binding upon
the Bank even if there is a dispute between the Purchaser and the
Supplier or such dispute is pending before a Court, Tribunal or
Arbitrator. Clauses 7 and 8 make the Bank liable as a principal
debtor. They do not require the Purchaser to first proceed against
the Supplier. In view of this language, it is difficult to accept the
submission of the Petitioner that Respondent No.1 must first prove
default, breach, loss or damage before the Bank Guarantee can be
invoked. There is no such condition in the Bank Guarantee. On the
contrary, the Bank Guarantee states that the Purchaser need not
give any reason or justification for making the demand. These are
the terms which the parties had agreed. While exercising
jurisdiction under Section 9, the Court cannot alter these terms
merely because a dispute has arisen between the parties.
33. The Petitioner has relied upon the fact that the LOA was
terminated under Article 24, namely Termination for Convenience,
and not under Article 25 relating to default. It is correct that the
Termination Notice dated 20 June 2025 invoked Article 24. The
Notice records that Respondent No.1 had stopped its operations at
Nanded Airport because of the Resumption Order issued by MIDC.
It records appreciation of the efforts made by the Petitioner. The
Notice does not allege default, defective supply, delay or non-
performance by the Petitioner. Therefore, the Petitioner does have
a dispute regarding the effect of the termination and its
entitlement under Article 24.1. However, this fact by does not
answer the question, which arises in the present Petition. Article
17
Uploaded on - 18/09/2026 Downloaded on - 18/09/2026 13:58:29

carbpl30683-2026-J.doc

24.1 deals with the entitlement of the Petitioner arising from
termination for convenience. The Bank Guarantee deals with the
advance amount of Rs.1,48,94,068/- paid by Respondent No.1.
Article 24.1, as reproduced in the Petition, provides for
compensation to the Vendor for obligations performed before
termination. Whether the Petitioner is entitled to Rs.4,63,82,051/-
or to any other amount, and whether any amount is required to be
adjusted against the advance, are questions which have to be
decided under the contract. It is not necessary to give any final
finding on the Petitioner's substantive claim in the present
proceedings. But the existence of such a dispute cannot stop the
encashment of an unconditional Bank Guarantee.
34. The same position applies to the Petitioner's submission
regarding Article 39 concerning Force Majeure. The record shows
that Respondent No.1 initially terminated the LOA by invoking
Article 24 in the Termination Notice dated 20 June 2025.
Thereafter, while rejecting the Petitioner's claim by letter dated 30
March 2026, Respondent No.1 relied upon Article 39 and stated
that because of the resumption of the airport, it had become
impossible to continue the performance. Whether Articles 24 and
39 are inconsistent, whether Article 39 was properly invoked,
whether notice under Article 39.3 was necessary and whether the
Petitioner is entitled to compensation under Article 24.1 are all
questions arising from the main contract. These questions may
have to be decided in arbitration. But they do not change the
separate and independent terms of the Bank Guarantee.
18
Uploaded on - 18/09/2026 Downloaded on - 18/09/2026 13:58:29

carbpl30683-2026-J.doc

35. There is substance in the submission of the Respondents that
the invocation is connected with the purpose for which the
Advance Bank Guarantee was given. The amount demanded by
Respondent No.1 is the amount of advance secured by the Bank
Guarantee. The Termination Notice demanded refund of
Rs.1,48,94,068/- and stated that after receiving that amount, the
Bank Guarantee would be returned. The material shows that
Respondent No.1 has not invoked the Bank Guarantee for some
new claim. It is seeking the very advance amount which was
secured by the Bank Guarantee.The Petitioner has submitted that
the advance amount was used for manufacturing a highly
customised ACFT. According to the Petitioner, major components
had been manufactured and other parts and accessories had been
procured or ordered. Respondent No.1 disputes the effect of this
expenditure and states that the Petitioner continues to have
possession and ownership of the ACFT, its components and
materials, and that their value can be considered while deciding
the Petitioner's monetary claim. At this stage, it is not necessary to
decide which version is correct. The important point is that
spending the advance amount is not the same as repayment or
adjustment of the advance. The Petitioner's claim for
reimbursement or compensation can be considered in arbitration.
Such expenditure by does not bring the security given for the
advance to an end.
36. The conduct of the parties regarding refund of the advance is
required to be considered. On 23 June 2025, the Petitioner
informed Respondent No.1 that the issue of refund was being
19
Uploaded on - 18/09/2026 Downloaded on - 18/09/2026 13:58:29

carbpl30683-2026-J.doc

taken up with its finance team. Thereafter, by email dated 25
September 2025, the Petitioner stated: “we intend to return your
advance payment”. The Petitioner asked Respondent No.1 to
provide a draft Minutes of Meeting regarding return of the Bank
Guarantee against refund of the advance. The parties had a
meeting on 3 October 2025. Respondent No.1 forwarded a draft
Minutes of Meeting providing for refund of the full advance and
return of the Bank Guarantee after such refund. By email dated 6
October 2025, the Petitioner forwarded what it described as the
“final draft”. It is not necessary, for deciding the present Petition, to
hold that the draft Minutes of Meeting became a final and binding
settlement. The draft appears to have required signatures of the
managements of the parties. The Petitioner may contend in
arbitration that no final settlement was completed. However, the
correspondence does show one important fact. At the relevant
time, the Petitioner was considering refund of the advance against
return of the Bank Guarantee. This conduct has a bearing upon the
present submission that the encashment has no connection with
the purpose for which the Bank Guarantee was given.
37. Thereafter, the Petitioner raised its quantified claim of
Rs.4,63,82,051/- under Article 24.1. The claim was made on 18
October 2025 and forwarded on 28 October 2025. Respondent
No.1 rejected the claim on 30 March 2026. The fact that the
Petitioner's claim is more than three times the amount of the Bank
Guarantee does not by create a right to stop its encashment. The
claim is disputed and has not yet been decided. The Bank
Guarantee cannot be treated as a security which automatically gets
20
Uploaded on - 18/09/2026 Downloaded on - 18/09/2026 13:58:29

carbpl30683-2026-J.doc

adjusted against an unadjudicated claim of the Petitioner. Any
question regarding adjustment can be considered by the competent
forum.
38. The Petitioner has submitted that Respondent No.1 did not
give notice before invoking the Bank Guarantee and that the
Petitioner came to know about the invocation only through its
banker. The Petition records that the Petitioner's banker informed
it on 1 September 2026 that Respondent No.1 had called upon
Respondent No.2 to encash the Bank Guarantee and that payment
would follow after completion of the required formalities. The
Respondents dispute the requirement of a notice and point out that
the demand for refund of the same amount had been made on 20
June 2025. The Bank Guarantee does not make prior notice to the
Petitioner a condition for payment by the Bank. Clause 5 requires a
written demand upon the Bank and says that the demand can be
made without reference to the Supplier. Therefore, the absence of
a separate notice before invocation cannot by make the invocation
invalid.
39. The fact that the invocation was made near the end of the
claim period does not make the invocation unlawful. The material
shows that the Bank Guarantee was valid up to 6 October 2025
and that the claim period extended up to 6 October 2026. The
invocation was initiated on 1 September 2026. Therefore, the
demand was made within the claim period. Merely because
Respondent No.1 invoked the Bank Guarantee near the end of that
period, it cannot be said that the invocation was for that reason
impermissible.
21
Uploaded on - 18/09/2026 Downloaded on - 18/09/2026 13:58:29

carbpl30683-2026-J.doc

40. I now come to the allegation of fraud. The Petition does not
place before the Court any material to show that the Bank
Guarantee was obtained by fraud, that the underlying transaction
was fraudulent or that the Bank had knowledge of any such fraud.
The case of the Petitioner is that Respondent No.1 wrongly
terminated the LOA, wrongly rejected the Petitioner's claim and is
now seeking to recover the advance through the Bank Guarantee.
Even if this case is taken at its highest, it remains a dispute under
the contract. It is not the kind of fraud which is required in law for
stopping encashment of a Bank Guarantee. As stated by the
Supreme Court in paragraph 11 of Himadri Chemicals :
“The fraud must be of an egregious nature such as to vitiate
the entire underlying transaction.”
41. That requirement is not established from the material placed
before the Court.
42. The next question is regarding irretrievable injury or
injustice. The Petitioner says that Respondent No.1 has stopped its
operations at Nanded Airport, has lost its source of revenue and
may not have sufficient financial capacity to repay the amount if
the Petitioner succeeds in arbitration. The Petition describes this as
a “serious and well-founded apprehension” and states that the
Petitioner may otherwise be left with only a paper award. This
submission has been considered.
43. Respondent No.1 has placed material showing a different
financial position. It relies upon its audited financial statements for
the financial year 2025-26. According to Respondent No.1, these
22
Uploaded on - 18/09/2026 Downloaded on - 18/09/2026 13:58:29

carbpl30683-2026-J.doc

financial statements show that it continues as a going concern. It
relies upon continuing support from the Reliance group, trade
receivables of Rs.2.24 crore and balances with Government
authorities of Rs.2.63 crore. It relies upon the auditors' report
regarding repayment of borrowings and statutory dues. These
financial statements are not required to be treated as a guarantee
that the Petitioner will certainly recover the money in future. That
is not the test which has to be applied. The question is whether the
Petitioner has shown that restitution would be impossible. On the
material before the Court, this has not been shown. The Petitioner
has shown that Respondent No.1 lost possession of Nanded
Airport. But that fact alone does not establish that Respondent
No.1 will be unable to satisfy an arbitral award. Respondent No.1
has placed financial material showing that it continues to exist and
has assets and receivables. The case of the Petitioner remains an
apprehension. As paragraph 13 of Himadri Chemicals states:
“a mere apprehension that the other party will not be able to
pay, is not enough.”
44. I cannot accept that irretrievable injury will arise merely
because the Petitioner's bank account will be debited after
encashment. Such financial effect is normally the consequence
when an on-demand Bank Guarantee is encashed. Every
encashment of such a Bank Guarantee has financial effect upon the
party which furnished it. If this consequence is treated as
irretrievable injustice, an unconditional Bank Guarantee would
become difficult to enforce in almost every case. The Respondents
have submitted that if the Petitioner succeeds in arbitration, its
23
Uploaded on - 18/09/2026 Downloaded on - 18/09/2026 13:58:29

carbpl30683-2026-J.doc

monetary claim can be decided and an award with interest can be
passed.
45. The plea of “special equities” does not provide a ground to
interfere with the Bank Guarantee. The circumstances relied upon
by the Petitioner are the same matters which have been
considered. The termination under Article 24, the Petitioner's claim
under Article 24.1, the subsequent reliance upon Article 39, the
expenditure allegedly incurred on the customised ACFT and the
absence of immediate notice are all matters connected with the
underlying contract. These matters may be important when the
rights of the parties are decided. But in the facts of the present
case, they do not amount to such exceptional circumstances by
which the Court can disregard the unconditional Bank Guarantee.
46. The allegation regarding suppression of the Minutes of
Meeting requires consideration. The Respondents have pointed out
that the Petition relies upon the correspondence dated 25
September 2025 and 6 October 2025, but the attachment to the
email dated 6 October 2025, namely the draft Minutes of Meeting
and No Dues Certificate, was not annexed. According to
Respondent No.1, this was an important document because it
recorded the proposed refund of the entire advance against return
of the Bank Guarantee. The Petitioner's own case accepts that
correspondence regarding the proposed settlement had taken
place. It is not necessary for this Court to record any finding
regarding the intention of the Petitioner in not annexing the
attachment. Such a finding is not required for deciding the
Petition. However, the omission is material. The email dated 6
24
Uploaded on - 18/09/2026 Downloaded on - 18/09/2026 13:58:29

carbpl30683-2026-J.doc

October 2025 becomes clearer when the document sent with it is
seen. The document relied upon by Respondent No.1 records a
proposed course under which the entire advance was to be
refunded and the Bank Guarantee was to be returned. This was
relevant to the Petitioner's plea of special equities and to its
contention that Respondent No.1 was acting contrary to its earlier
stand. Therefore, the omission has a bearing upon the Petitioner's
prayer for equitable and discretionary relief under Section 9.
47. I do not accept the submission that Respondent No.1 is
improperly bypassing Article 27 of the GCC by invoking the Bank
Guarantee. Article 27 provides the procedure for resolution of
disputes and arbitration. The Bank Guarantee is separately
worded. It provides that the Purchaser may invoke it
unconditionally and that the Bank's obligation to pay is not
affected by any dispute between the Purchaser and the Supplier.
Article 20.10 of the GCC and Clause 6 of the Bank Guarantee are
relied upon by Respondent No.1 for this purpose. Therefore,
exercising a right under the independent Bank Guarantee cannot
be treated as defeating the dispute resolution procedure under the
main contract.
48. The submission of the Petitioner that encashment would
allow Respondent No.1 to obtain through “self-help” the amount
which forms part of the disputed claim cannot be accepted. At
present, the amount sought through the Bank Guarantee is not the
Petitioner's claim of Rs.4,63,82,051/-. It is the amount of the
advance originally paid by Respondent No.1 and secured by the
Advance Bank Guarantee. Whether Respondent No.1 will be
25
Uploaded on - 18/09/2026 Downloaded on - 18/09/2026 13:58:29

carbpl30683-2026-J.doc

entitled to retain the entire amount, or whether some adjustment
is required after considering the Petitioner's claim, is a separate
question. Encashment of the Bank Guarantee does not decide that
question.
49. The Petitioner's submission that Respondent No.1 had
undertaken to return the Bank Guarantee has to be understood
from the words used. Paragraph 7 of the Termination Notice stated
that Respondent No.1 requested refund of the advance and that:
“Upon the receipt of the said advance Payment amount” the
Bank Guarantee would be returned. These words do not
show an unconditional promise that the Bank Guarantee
would be returned even if the advance was not refunded.
The words used make the return of the Bank Guarantee
dependent upon receipt of the advance. Therefore, when the
advance was not refunded, the Petitioner's reliance upon
paragraph 7 as creating an absolute bar against subsequent
invocation cannot be accepted.
50. The present case is different from a case where a beneficiary
seeks to encash an unconditional Bank Guarantee for an amount
which has no connection with the purpose for which the guarantee
was given. It is different from a case where clear material of
egregious fraud is shown or where it is proved that restitution after
encashment would be impossible. Here, the Bank Guarantee was
furnished for securing the very advance which Respondent No.1
seeks to recover. The amount demanded corresponds with the
guaranteed amount. The advance has not been returned by the
Petitioner. The Bank Guarantee permits unconditional invocation.
The disputes between the parties can still be decided in arbitration.
26
Uploaded on - 18/09/2026 Downloaded on - 18/09/2026 13:58:29

carbpl30683-2026-J.doc

51. I have considered the submission of the Petitioner that the
specialised ACFT had been manufactured and that the Petitioner
would suffer loss if the Bank Guarantee is encashed. This question
may have relevance to the Petitioner's monetary claim. But in the
facts of this case, it cannot change the normal consequence of
encashment into irretrievable injustice as understood in the
judgments of the Supreme Court. Respondent No.1 states that the
Petitioner continues to have the manufactured ACFT and its
components and that their value can be considered while deciding
the Petitioner's claim. There is no sufficient material to hold that
the Petitioner's monetary rights will disappear only because the
Bank Guarantee is encashed.
52. On considering the entire matter, I find that the grievance of
the Petitioner against Respondent No.1 may give rise to disputes
under Article 24, Article 39 and other provisions of the GCC. Those
disputes are not being decided in the present proceedings. At the
same time, such disputes cannot be used to stop an unconditional
Advance Bank Guarantee. The Supreme Court in Himadri
Chemicals has held :
“the existence of any dispute between the parties to the
contract is not a ground for issuing an order of injunction to
restrain enforcement of bank guarantees or letters of credit.”
53. The Petitioner has not established the recognised grounds on
which the Court can interfere with the Bank Guarantee. There is
no established fraud of an egregious nature. There is no sufficient
material showing irretrievable injury or injustice. The plea of
special equities is based upon disputes under the main contract.
27
Uploaded on - 18/09/2026 Downloaded on - 18/09/2026 13:58:29

carbpl30683-2026-J.doc

The Bank Guarantee is unconditional and payable on demand. On
the material before the Court, the invocation has been made
within the claim period and for the amount of the advance secured
by the Bank Guarantee. Merely because the Petitioner may succeed
in arbitration, the position regarding the Bank Guarantee does not
change. If the arbitral tribunal finds that the Petitioner is entitled
to payment under Article 24.1 or any other provision of the
contract, the Petitioner's substantive claim can be decided in those
proceedings and appropriate monetary relief can be granted. The
present Section 9 proceedings cannot be converted into a complete
trial of the claim only for the purpose of stopping encashment of
an independent Bank Guarantee.
54. For all these reasons, I find that there is no sufficient ground
to restrain Respondent No.1 from invoking or encashing the
Advance Bank Guarantee bearing No. 03352GI3D2403957 for
Rs.1,48,94,068/-. The Petition, to the extent it seeks an injunction
against invocation and encashment of the said Bank Guarantee,
cannot succeed. The claims and defences of the Petitioner are kept
open for consideration and decision in accordance with the dispute
resolution mechanism contained in the GCC.
55. In view of the foregoing discussion and for the reasons
recorded hereinabove, the following order is passed:
(i) The Petition is dismissed;
(ii) The interim relief, if any, granted in favour of the
Petitioner restraining Respondent No.1 from invoking or
encashing Advance Bank Guarantee bearing No.
28
Uploaded on - 18/09/2026 Downloaded on - 18/09/2026 13:58:29

carbpl30683-2026-J.doc

03352GI3D2403957 for an amount of Rs.1,48,94,068/-,
stands vacated;
(iii) All rights and contentions of the Petitioner and
Respondent No.1 in respect of the claims and counterclaims
are kept open to be considered by the appropriate forum in
accordance with the dispute resolution mechanism contained
in the GCC;
(iv) The observations made in the present order are
confined to the question of invocation and encashment of the
Advance Bank Guarantee and shall not be construed as a
final adjudication of the substantive claims of either party;
(v) The Petition stands disposed of in the above terms.
There shall be no order as to costs.
56. At this stage, Mr. Savant, learned Advocate for the Petitioner
seeks continuation of the interim relief. However, for the reasons
recorded in this Judgment, the request for continuation of interim
relief stands rejected.
(AMIT BORKAR, J.)