Antriksh Developers And Promoters Pvt. Ltd. Thru. Authorized Signatory Sarafaraz Ahamad vs Shyam Sundar Agrawal

Court
Allahabad High Court

AFR
Reserved on August 10,2026
Pronounced on September 23 ,2026
HIGH COURT OF JUDICATURE AT ALLAHABAD
LUCKNOW
RERA APPEAL No. - 37 of 2026
Antriksh Developers and
Promoters Pvt. Ltd. Thru.
Authorized Signatory Sarafaraz
Ahmad
….Appellant(s)
Versus
Shyam Sundar Agarwal
..Respondents(s)
Counsel for Appellant(s) : Abhishek Khare, Aahuti
Agarwal
Counsel for Respondent(s) : Aditya Tewari
Court No. - 20
HON’BLE PRASHANT KUMAR, J.
1. Heard Mr. Abhishek Khare, learned counsel for the appellant as
well as learned counsel for the respondent.
2. The instant RERA Appeal under Section 58 of the Real Estate
(Regulation & Development) Act, 2016 has been preferred by the
appellant against the judgement dated 13.05.2025 passed by the
Uttar Pradesh Real Estate Appellate Tribunal, at Lucknow
(hereinafter referred as 'Appellate Tribunal') in Appeal bearing
Case no.824 of 2020 ( Shyam Sundar Agarwal v. Antriksh
Developers & Promoters Pvt. Ltd. ).

2
RERA APPEAL No. - 37 of 2026
Factual Matrix -
3. The appellant launched a project namely 'Antriksh Golf View'
in the year 2010 situated at Plot No.GH-005A, Sector-78, Noida,
Uttar Pradesh. On 30.04.2010, the respondent booked a unit in the
said project and paid the booking amount.
4. The booking of the flat was done pre-launch and as per the
allotment letter the total basic price of the unit was Rs.43,53,750/-,
which was paid. The allotment letter was executed in favour of the
respondent on 21.09.2010 by means of which Unit No. 1903,
Floor- 19th Block - L, admeasuring super area approx. 2025 sq.ft.,
Type 3D (hereinafter referred as ‘Unit in Question’).
5. The appellant promised to handover the possession by
December, 2012 (plus-minus 6 months) subject to receipt of
entire basic price, extra charges, lease rent charges, registration
charges and other extra charges as may be intimated by the
appellant company.
6. Demand letter for payment of remaining balance was sent by
the appellant to respondent vide letter dated 08.04.2016 asking for
Rs.13,12,866/- The said payment was made by the respondent
through RTGS on 26.04.2016.
7. The Appellant sent a written offer of possession in the year
2017 vide letter dated 22.05.2017, i.e., nearly four years after the
contractual possession date, and that too without any Occupancy
Certificate and other relevant papers just to comply with clause 30
of the allotment letter. The respondent being homebuyer
compelled to take possession immediately without any Occupancy
Certificate and other relevant papers as per agreement.

3
RERA APPEAL No. - 37 of 2026
8. Later, the Occupancy Certificate was received by the appellant
on 06.06.2018.
9. The complainant/respondent sent an email to the appellant on
21.02.2019, wherein the respondent asked the appellant to issue
possession certificate and pay the delay penalty along with refund
of the amount charged as electrical charges and increase in super
area from 2025 sq.ft. to 2100 sq.ft..
10. Being aggrieved by inaction of appellant, the respondent made
a complaint against the appellant on 04.10.2019 before the
Regulatory Authority praying for refund of Rs.4,06,554/-, and for
issuance of no dues certificate and possession letter and also to
bear all delay charge/penalty levied by Noida Authority for
registration of flat.
11. The complaint of the respondent was disposed of by the Real
Estate Regulatory Authority vide its order dated 22.09.2020
together with another complaint of some other unit/flat owner one
Ms. Tripti Agarwal, whereby the following directions and order
was passed : -
"1. 31.12.2020
विपक्षीकोआदेशितकियाजाताहैकि वहदिनांक

तकशिकायतकर्तागणसेअनुबन्धानुसारउचितधनराशि प्राप्तकरतेहुए
-
उन्हेंनो डयूज़जारीकरेंऔरदेयस्टाम्पशुल्कप्राप्तकरनियमानुसार
"
रजिस्ट्रीकरायें।
2. , 45 ,
विपक्षी शिकायतकर्तागणको दिनोंकेअन्दरबिजली पानी

कनेक्शनएवंकिसानप्रतिकरकेमदमेंमांगीजानीवालीधनराशि के
/
सम्बंधमेंवहसाक्ष्योंसहितसम्बंधितविभाग प्राधिकरणकोअदाकीगयी

धनराशि का विवरण उपलब्ध कराते हुए अनुपातिकं तौर पर

शिकायतकर्तागणसेधनराशि प्राप्तकरें।साक्ष्यउपलब्धकरानेके

उपरान्तशिकायतकर्ताद्वाराअपनी देयधनराशि का भुगतानकिया
जायेगा।
5. ,
विपक्षी शिकायतकर्तागणकोविभिन्नमदोंमेंमांगीजानेवाली
Calculation Sheet
धनराशि का उन्हेंउपलब्धकरायें।

4
RERA APPEAL No. - 37 of 2026
6.
ओपनपार्किंगकेसम्बंधमेंउभयपक्षअनुबन्धकेअनुसारकार्यवाही

करनासुनिश्चितकरें।
7. -
इसआदेशकीएक एकप्रतिसम्बंधितपत्रावलियोंपररखीजाये।
- ( )
इसआदेशका उल्लघंनउ०प्र०भू सम्पदा विनियमनतथा विकास
, 2016 -63
अधिनियम कीधारा तथाअन्यसुसंगतप्राविधानोंकेअन्तर्गत
"
दंडनीयहोगा।आदेशपोर्टलपरअपलोडकियाजाये।
12. Appellant after order passed by the regulatory authority has
again issued a fresh demand letter on 03.10.2020 for
Rs.24,13,940/-. Being aggrieved, the complainant/respondent
challenged the order dated 22.09.2020 passed by the Real Estate
Regulatory Authority before the Real Estate Appellate Tribunal on
the ground that the concerned authority has failed to consider the
plight of the builder and has not granted any relief with respect to
payment of delay interest and also failed to pay any heed to the
fact that the complainant had cleared all dues in accordance with
the terms and conditions of the agreement executed between the
parties. The following relief was sought by the complainant before
the Appellate Tribunal :
"6. Relief(s) sought:
i. As per Clause 27 of the Agreement, disallow charges for
increase in the Super Area and direct builder refund the
amount collected on this account.
ii. As per Clause 9 (III) of Annexure-B of the Agreement,
disallow charges on account of external electrification
and direct builder refund the amount collected on this
account.
iii. As per Annexure-A and Annexure-B of the Agreement,
direct builder to pay interest on early demand of other
charges without completion of the unit.
iv. As the complainants have made all the payments
against the final demand letter, direct builder to issue No
Dues Certificate to enable registry of the flat and bear all
charges if any towards delay in registry.

5
RERA APPEAL No. - 37 of 2026
V. As per Clause 29 of Annexure-B of the Agreement and
Section 18 (1) (a) of RERA, direct builder to pay delay
delivery compensation."
13. The Appellant filed objections before the learned Appellate
Tribunal.
14. After hearing the submissions of the parties and on the basis of
pleadings and records, the Appellate Tribunal framed the
following questions/issues to decide :-
"(i) Whether the project of the respondent is delayed?
(ii) Whether the appellant is entitled for interest for the
delay in possession even after taking physical possession
of the unit?
(iii) Whether the demand raised by the respondent
towards electricity, water connection and farmers'
compensation etc. was justified?
(iv) Whether the appellant is entitled for interest for the
delay in completion of the Project under the scheme of
Act, 2016 and if yes, what rate of interest is required to be
paid by the Promoter to the allottee?"
15. The Appellate Tribunal came to the conclusion that the project
was delayed and the appellant (respondent herein) being
homebuyer does not lose his right to claim compensation and/or
interest for the delay in possession even after taking possession of
the Unit/Apartment/Flat booked by him. It was further concluded
that the demand raised by the respondent (appellant herein)
towards electricity, water connection, farmers' compensation and
delay payment interest was not justified. It is concluded that the
appellant (respondent herein) being homebuyer is entitled to the
interest for the delay in completion of the project for the period
from December, 2012 (after promised date of possession
November, 2012, as per allotment letter) till 03.03.2017 (the date
of handing over physical possession) and the demand letter dated
03.10.2020 is liable to be set aside.

6
RERA APPEAL No. - 37 of 2026
16. The Appellate Tribunal partly allowed the appeal vide its order
dated 13.05.2024 with the following directions :-
"(A) The respondent is directed to pay delay interest to the
appellant on the deposited amount at the rate of
MCLR+1% from December 2012 till 22.05.2017.
(B) The demand letter dated 03.10.2020 is set aside. The
respondent is directed to issue fresh demand letter keeping
in view the observations made in para 17.1 above read
with the provisions of Allotment Letter/Agreement dated
21.09.2010 including its Annexure-В.
(C) The aforesaid directions as well as the directions of
the Regulatory Authority by the respondent within 45 days
from the date of upload of this judgement/order.
(D) In case of non-compliance of this order the appellant
will be at liberty to approach UPRERA for execution of
this order."
17. The Appellant being aggrieved by the order dated 13.05.2025
passed by the Appellate Tribunal assailed the same by preferring
the instant appeal.
18. The following substantial questions of law were framed in the
present appeal for adjudication :-
A. Whether the order passed by the Tribunal is coram non
judice as per the provisions of RERA Act, 2016?
B. Whether the claims of an allottee regarding the 'interest
for every month of delay till handing over of the
possession' made under the proviso to Section 18(1) of
RERA Act, 2016 should be considered in absence of a
"demand" contemplated under the main proviso of Section
18(1) which was not made within a reasonable period of
time and whether such an entitlement to lodge a claim can
be kept open for an indefinite/infinite time period?
C. Whether the appellant can be saddled with liability for
the delay in obtaining No Objection Certificates from the
competent authorities, particularly when the issuance of
the Occupancy Certificate/Completion Certificate was
stayed by order of the National Green Tribunal?

7
RERA APPEAL No. - 37 of 2026
D. Whether the appellant can be held liable to pay delay
interest under the Real Estate (Regulation and
Development) Act, 2016, for the period during which the
performance of its obligations was rendered legally
impossible due to the stay order passed by the National
Green Tribunal and the inaction of the competent
authority?
Submissions of learned counsel for the Appellant:
19. Mr. Abhishek Khare, learned counsel for the appellant firstly
submitted that the impugned order passed by the Tribunal is coram
non judice. To buttress his argument he placed reliance upon
section 43(3) read with section 55 of the Real Estate (Regulation
& Development) Act, 2016.
20. He further submitted that the Tribunal while deciding issue
no.1 has failed to consider the fact that the project could not be
delivered to the allottee by the month of June, 2013 only because
of unforeseen circumstances. He further submitted that the project
was completed in the year 2014 and the appellant had duly applied
for the Occupancy Certificate / Completion Certificate from the
competent authority. The delay was only on the part of authority
in issuing the Occupancy Certificate / Completion Certificate and
therefore the liability to pay the interest on the delay should not be
fastened on the appellant.
21. While the construction work was going on in full swing, the
National Green Tribunal (hereinafter referred as 'NGT') vide its
orders dated 14.08.2013, 17.09.2013 and 28.10.2013 (in respect to
proximity of projects related to the Okhla Bird Sanctuary) had
stayed the promoters from carrying out any development activity
within 10 Kms radius of the Okhla Bird Sanctuary. The said order
was later modified by the NGT on 28.10.2013, which prohibited
the concern authority from issuing any Occupancy Certificate /
Completion Certificate in respect of the projects which were

8
RERA APPEAL No. - 37 of 2026
within 10 Kms radius of the Okhla Bird Sanctuary. The appellant
received a letter from the police authority to stop the construction
vide letter dated 15.09.2013.
22. He further submitted that the delay was caused due to stay
order passed by the learned National Green Tribunal, Principle
Bench, New Delhi. Hence, the liability of delay on this ground
should not be fastened on the appellant.
23. He also submitted that the same issue with regards to the
interest of compensation during this period of NGT stay order was
dealt by the Hon'ble Supreme Court in the matter of Griha
Pravesh Build Teck Pvt. Ltd. vs. Suresh Chander Sharma,
bearing Civil Appeal No. 33 of 2024, vide order dated 03.12.2024,
reported in MANU/SCOR/137652/2024, whereby the Hon'ble
Supreme Court clearly held that respondents will not be entitled to
claim interest on the compensation for the period commencing
from 14.08.2013 to 19.08.2015
24. Mr. Khare further submitted that the respondent has already
taken possession and thereafter filed a frivolous compliant before
the Real Estate Regulatory Authority.
25. He further placed reliance on provisions Section 18 of The
Real Estate (Regulation and Development) Act, 2016 and
submitted that the liability to pay interest for the delay period
ceases to exist with the handing over possession. In the present
case the respondent has already taken the possession before filing
the complaint.
26. After arguing at length, learned counsel for the appellant
confined his prayer to the benefit as granted by the Hon'ble
Supreme Court in the matter of Suresh Chander Sharma (supra),
wherein the home buyer will not be entitled to claim interest on

9
RERA APPEAL No. - 37 of 2026
compensation for the period commencing from 14.08.2013 to
19.08.2015
27. Per contra , learned counsel for the respondent vociferously
opposed the instant appeal and submitted that argument of the
learned counsel for the appellant with regards to coram non judice
is unsustainable as the same is not raised before the Tribunal and
the Tribunal itself in the impugned judgement has dealt with the
same in its very first para.
28. He further submitted that the benefit of Suresh Chander
Sharma (supra), cannot be extended to the appellant as the said
project in question has to be completed and possession has to be
given by November 2012. To buttress his argument he places
reliance on annexure-B of the builder-buyer agreement.
29. He further submitted that the Tribunal has rightly decided the
issues in favour of Homebuyer. The present appeal is an attempt to
avoid liability as imposed upon the appellant-builder and the same
is liable to be dismissed with cost.
Analysis :
30. Heard learned counsel for the appellant as well as learned
counsel for the respondent and perused the records.
31. The substantial questions of law raised in the present appeal
are answered here in seriatim.
32. The first substantial question of law is as to whether the order
passed by the Tribunal is coram non-judice as per the provisions of
RERA Act, 2016.
33. On a bare perusal of the impugned judgment, it is evident that
the appellant had never raised such an objection before the

10
RERA APPEAL No. - 37 of 2026
Tribunal. Apart from the same, before proceeding to adjudicate the
matter, the Tribunal had duly considered the issue regarding its
constitution and recorded its reasons for exercising jurisdiction in
the matter. The relevant paragraph is extracted hereunder :
“1. Before we proceed to examine the instant
matter/issue, we deem it proper to place on record that
on demitting office by Technical Member from
26.09.2023 the judicial functioning of the Tribunal had
come to stand still with effect from 27.09.2023. On
receipt of the notification dated 28.11.2023 with
respect to appointment of Judicial Member, in the
larger interest as well as to resume the judicial
functioning of the Tribunal and to achieve the mandate
of Section 44(5) of the Real Estate (Regulation &
Development) Act 2016 read with Regulation 22 and
25 a Bench consisting of Chairman and Judicial
Member was constituted vide order dated 01.12.2023.
The Registry was directed to issue cause list of fresh
appeals and re-schedule the cause list of pending
appeals from 27.09.2023 on joining of the Judicial
Member. Accordingly an office order dated 02.12.2023
was issued by the Registrar, which reads as under:--
OFFICE ORDER
It is hereby informed to all the
concerned that the Tribunal was working
with single Bench consisting of Hon'ble
Chairman and Hon'ble Technical Member
after demitting office by the Hon'ble
Judicial Member on 31.12.2022. Hon'ble
Technical Member also demitted office on
26.09.2023 and Hon'ble Administrative
Member being on unauthorized leave from
30.09.2022 (who finally resigned on
29.10.2023) resulting the judicial
functioning of the Tribunal to tune to
standstill with effect from 27.09.2023.
The State Government vide
Notification dated 28.11.2023 has
appointed Hon'ble Judicial Member and
as such presently, Hon'ble Chairman and
Hon'ble Judicial Member having judicial
back ground are available.

11
RERA APPEAL No. - 37 of 2026
As per Section 43(3) of the Act 2016
every Bench of the Appellate Tribunal is to
consist of at least one Judicial Member
and one Administrative or Technical
Member. The Appellate Tribunal is
required to scrutinize judicially the
appeals against the order of Regulatory
Authority or Adjudicating Officer. Rule 30
of the Rules 2016 empowers the Appellate
Tribunal to call upon such experts or
consultants from the fields of economics,
commerce, accountancy, real estate,
competition, construction, architecture or
engineering or from any other discipline
as it deems necessary, to assist the
Appellate Tribunal in the conduct of any
enquiry or proceedings before it.
Section 55 of the Act 2016 protects
the acts and proceedings of the Appellate
Tribunal from being invalid merely for the
reason of any vacancy in, or any defect in
the constitution of the Appellate Tribunal
or any defect in the appointment of a
person acting as a Member of the
Appellate Tribunal or any irregularity in
the procedure of the Appellate Tribunal
not affecting the merits of the case.
Accordingly in the larger interest
and expeditious disposal of appeals as per
mandate of Section 44(5) of the Act 2016
the Bench for hearing of appeals is
constituted with Hon'ble Chairman &
Hon'ble Judicial Member for judicial
scrutiny of the appeals and in case any
expert opinion/assistance is required the
same will be taken as per provisions of
Rule 30 of the Rules 2016 in appropriate
cases or such cases will be deferred till
availability of Administrative/Technical
Member.
On joining of Hon'ble Judicial
Member, the Registry is directed to issue
cause list of fresh appeals and re-schedule
the cause list of pending appeals from

12
RERA APPEAL No. - 37 of 2026
27.09.2023 and upload the same on the
website of the Tribunal and also inform all
the parties/legal representatives about the
same.
This order is issued with the
approval of Hon'ble Chairman.
The judicial functioning of the Tribunal resumed with
effect from 18.12.2023 after joining of the Judicial
Member and the said Bench is still continuing on
account of non-appointment of Technical and
Administrative Members.”
34. Section 55 of the Real Estate (Regulation and Development)
Act, 2016, clearly provides that no act or proceeding of the
Appellate Tribunal shall be invalid merely by reason of any
vacancy in, or any defect in the constitution of, the Appellate
Tribunal. The provisions of Section 55 of the Real Estate
(Regulation and Development) Act, 2016, read as under:
Section 55: Vacancies, etc., not to invalidate
proceeding of Appellate Tribunal. - No act or
proceeding of the Appellate Tribunal shall be
invalid merely by reason of—
(a) any vacancy in, or any defect in the
constitution of, the Appellate Tribunal, or
(b) any defect in the appointment of a person
acting as a Member of the Appellate
Tribunal; or
(c) Any irregularity in the procedure of the
Appellate Tribunal not affecting the merits of
the case.
35. In view of the aforesaid, this Court finds that the arguments
with regard to the coram of the Tribunal was not raised by the
appellant before the Tribunal. Further, the Tribunal had itself
considered and recorded its reasons regarding its constitution and

13
RERA APPEAL No. - 37 of 2026
jurisdiction before proceeding to adjudicate the matter. In these
circumstances, and having regard to the provisions of section 55
of the Act, this Court finds no ground to interfere with the
impugned order merely on the ground that the Tribunal was not
duly constituted.
36. Accordingly, the first substantial question of law is answered
against the appellant.
37. The second substantial question of law is as to whether the
claim of an allottee regarding interest for every month of delay till
handing over possession under the proviso to Section 18(1) of the
Real Estate (Regulation and Development) Act, 2016 can be
entertained in the absence of a "demand" contemplated under the
main provision of Section 18(1), and whether such claim can be
maintained after a reasonable period of time.
38. The project was launched in the year 2010. The Respondent
booked the unit on 30.04.2010, and an Allotment Letter was
issued on 21.09.2010 whereby Unit No. 1903, Floor- 19th Block -
L, admeasuring super area approx. 2025 sq.ft., Type 3D was
allotted to the Respondent. The Respondent duly paid the basic
consideration as stipulated under the Allotment Letter, and later, a
demand letter dated 08.04.2016 was raised by the appellant, and
respondent paid remaining extra demand of Rs.13,12,866/-
through RTGS on 26.04.2016.
39. On bare perusal of the agreement shows that there is a
contradiction between the date of completion of Project. The
Allotment agreement shows that the possession has to be given by
December 2012 plus minus 6 months, however, the Annexure B
states that the possession has to be given by November 2012.

14
RERA APPEAL No. - 37 of 2026
40. The related extract of Annexure-B clarifies this position, the
relevant portion of extract is quoted hereinbelow:
Annexure-B to allotment letter
This annexure is in addition to the allotment letter.
Various clarification given here against respective clauses
of allotment letter shall govern and be binding on both
the parties. In case of contradiction in clarification and
respective clause of allotment letter, the clarifications
given below shall govern.
Cl. /Page No. of
Clarification
allotment letter
Second Page Possession of unit shall be given by
November, 2012. Date of demand for
other charges payment shall be after
completion of unit. Other charges
shall be paid within one month from
date of possession intimation letter.
41. The admitted facts reveals that under the Allotment Agreement
dated 21.09.2010, read with Annexure-B thereof, possession of the
allotted unit was contractually required to be delivered by
November, 2012 as it is specifically provided that in the event of
any inconsistency between the clauses of the Agreement and
Annexure-B, the provisions of Annexure-B shall prevail. Thus, the
contractual date for handing over possession was November,
2012.
42. Section 18(1) of the Real Estate (Regulation and
Development) Act, 2016 provides two distinct remedies to an
allottee in case of delay by the promoter. Firstly, the allottee may
withdraw from the project and seek refund with interest and

15
RERA APPEAL No. - 37 of 2026
compensation. Secondly, where the allottee chooses not to
withdraw, he is entitled to interest for every month of delay until
possession is handed over. The provisions of Section 18(1) of the
Real Estate (Regulation and Development) Act, 2016 is extracted
as under:
" 18. Return of amount and compensation. - (1) If the
promoter fails to complete or is unable to give possession
of an apartment, plot or building,--
(a) in accordance with the terms of the agreement
for sale or, as the case may be, duly completed by
the date specified therein; or
(b) due to discontinuance of his business as a
developer on account of suspension or revocation
of the registration under this Act or for any other
reason,
he shall be liable on demand to the allottees, in case the
allottee wishes to withdraw from the project, without
prejudice to any other remedy available, to return the
amount received by him in respect of that apartment, plot,
building, as the case may be, with interest at such rate as
may be prescribed in this behalf including compensation
in the manner as provided under this Act:
Provided that where an allottee does not intend to
withdraw from the project, he shall be paid, by the
promoter, interest for every month of delay, till the
handing over of the possession, at such rate as may be
prescribed."
43. A plain reading of Section 18(1) shows that no limitation or
prescribed time frame has been provided by the legislature for
raising a claim for delay interest where the allottee continues with
the project. The expression "demand" occurring in the provision
cannot be interpreted to defeat the substantive statutory right
conferred upon an allottee to receive compensation for delayed
possession.

16
RERA APPEAL No. - 37 of 2026
44. The record further demonstrates continuous correspondence
and representations exchanged between the parties regarding
delayed possession. Such correspondence clearly establishes that
the Respondent never acquiesced in the delay nor abandoned the
statutory claim for interest.
45. The object of the second proviso to Section 18(1) is to
compensate an allottee who chooses to retain the allotment despite
delayed delivery of possession. Such beneficial legislation
deserves liberal interpretation so as to advance its object rather
than defeat it.
46. Accordingly, this Court is of the considered opinion that the
Respondent's claim for interest for every month of delay till
handing over possession is fully maintainable under the proviso to
Section 18(1) of the Act. The second substantial question of law is
answered accordingly in favour of the Respondent/homebuyer.
47. The third substantial question of law, is as to whether the
Appellant can be saddled with liability for delay in obtaining the
Occupancy Certificate/Completion Certificate when the issuance
thereof was allegedly affected by the stay order passed by the
Hon'ble National Green Tribunal.
48. The fourth substantial question of law is as to whether the
Appellant can be held liable to pay delay interest under the Real
Estate (Regulation and Development) Act, 2016 for the period
during which performance of its obligations was allegedly
rendered impossible because of the stay order passed by the
Hon'ble National Green Tribunal and the inaction of the
competent authority.

17
RERA APPEAL No. - 37 of 2026
49. Since, the third and fourth substantial questions of law are
intrinsically connected and, therefore, they are considered and
decided together.
50. At the outset, it is evident that the Appellant has taken
mutually destructive and inconsistent stands in the present appeal.
On the one hand, the Appellant has sought to justify the delay in
handing over possession by contending that the project was
affected by the stay order passed by the Hon'ble National Green
Tribunal, Principal Bench, New Delhi, relating to projects falling
within the radius of 10 kilometres of the Okhla Bird Sanctuary. On
the other hand, the Appellant has categorically admitted in the
memorandum of appeal (Para 30) that the construction of the
project stood completed in the year 2014 and the Occupancy
Certificate was also applied year 2014 before the authority
concern.
51. These two pleas cannot stand together. If the project had in
fact been completed in the year 2014 and the Appellant had
applied for the Occupancy Certificate during the subsistence of the
alleged stay, the Appellant cannot simultaneously contend that the
very same stay prevented completion of the project and caused the
delay in handing over possession. Such contradictory pleas strike
at the root of the Appellant's case.
52. It is a settled principle of law that 'a person cannot approbate
and reprobate simultaneously or blow hot and cold in the same
breath. A party cannot be permitted to adopt inconsistent stands in
the same proceedings merely to suit its convenience.
Consequently, the plea of the Appellant attributing the delay
entirely to the NGT stay order deserves to be rejected.
53. The project in question was stayed by the National Green
Tribunal, New Delhi as the said project falls within radius of 10

18
RERA APPEAL No. - 37 of 2026
Kms of the Okhla Bird Sanctuary. The issue with respect to the
interest on compensation for the period between 14.08.2013 to
19.08.2015 which was recognised as 'Zero Period' was raised
before the Hon'ble Supreme Court in the matter of Suresh
Chander Sharma (supra), whereby it has been clearly held that
the appellant being a real estate developers can not be made
entitled to pay interest on compensation for the period from
14.08.2013 to 19.08.2015. The relevant para is extracted herein-
below:-
"9. Having considered the matter in detail, we will restrict
the consideration in the present appeal to grant of interest
for the period between 14.08.2023 to 19.08.2015. In view
of the orders passed by the (i) National Green Tribunal,
(ii) Standing Committee of the National Board for
Wildlife, (iii) Report of the Committee constituted by the
Ministry of Housing and Urban Affair (MoHUA) and (iv)
certain orders passed by the National Commission, we
direct that the respondents will not be entitled to claim
interest on compensation for the period commencing from
14.08.2013 to 19.08.2015."
(emphasis supplied)
54. The contractual obligation of the Appellant was to complete
the project and deliver possession by November, 2012.
Significantly, the stay order of the Hon'ble National Green
Tribunal came into effect only in August, 2013, which was well
after the contractual date for delivery of possession. Therefore, the
Appellant had already defaulted in performing its contractual
obligation before the stay order came into existence.
55. Further, the Appellant itself admits that the Occupancy
Certificate was applied for only on 27.08.2014. The relevant para
of the appeal is extracted hereinbelow:
"30. That while dealing with the issue no.1 the Learned
Tribunal has failed to considered the fact that due to
unforeseen circumstance the project could not be

19
RERA APPEAL No. - 37 of 2026
delivered to the allottee in the month of December. 2016.
Further the Learned Tribunal has failed to considered
the fact that the project was completed in the year 2014,
and the appellant has duly applied for the OC/CC from
the competent authority. The delay was on the part of the
authority in issuing the OC/CC and therefore the
appellant should not be liable to pay the delay interest.”
56. The benefit of the said Zero Period has been recognized in
favour of the developers for the limited purpose of excluding the
said period while computing delay. This benefit of zero period
would have been granted only to those projects which are
completely stopped because of the stay order passed by the NGT.
However, in this case the project ought to have been completed
much prior to the said stay order. The Appellant, in his pleadings,
has stated that he completed the project in the year 2014 and
thereafter applied for the Occupancy Certificate. If the entire
project was subject to a ban imposed by the NGT order, how could
the project be completed during the said period. This clearly
shows that they continued with the construction work contrary to
the stay order passed by the NGT. The appellant cannot blow hot
and cold at the same time, on one side they say that they have
completed their project in the year 2014 and on other side they
wants to take advantage of the stay order passed by the NGT,
wherein all the construction work was stopped.
57. If, according to the appellant, the project had already been
completed, there was no explanation whatsoever for not applying
for the Occupancy Certificate within the contractual timeline or
immediately upon completion. The delay in seeking the
Occupancy Certificate is attributable solely to the Appellant and
the same also clearly shows that the project was not completed as
per agreement.
58. Clause 30 of the Agreement provides that the allottee shall
take possession within ninety days of the written offer of

20
RERA APPEAL No. - 37 of 2026
possession after payment of the balance consideration.
Clarification of that clause is given in Annexure-B of the
allotment letter. The relevant extract is as under :
Annexure-B to allotment letter
.........
Cl. /Page No.
of allotment
letter
Clarification
..... .....
Page No. 9
The allottee/s has to make payment of
the balance amount and take
possession of the unit within 90 days
of the written offer of possession from
the company falling which the
allottee/s shall be liable to pay holding
charges, at Rs. 51- per square feet, in
addition to his proportionate share of
all the other charges to the company
for the period of delay in taking over
actual possession of the unit after the
expiry of the said period of 90 days.
Cl. No. 30
59. However, the Appellant admittedly issued the written offer of
possession in the year 2017, i.e., on 22.05.2017 nearly more than
four years after the contractual possession date, and that too
without any Occupancy Certificate and other relevant papers. The
respondent being homebuyer who had invested a huge amount
was compelled to take possession immediately without any
Occupancy Certificate and other relevant papers as per agreement.
This offer of possession was made just to comply with clause 30
of the allotment letter and to avoid extra burden of additional
charges which had arisen only due to the failure of Appellants for
not getting Occupancy Certificate / Completion Certificate and
other relevant papers on time.

21
RERA APPEAL No. - 37 of 2026
60. The conduct of the Appellant clearly establishes that it neither
completed the project within the agreed period nor diligently
pursued the statutory approvals. Consequently, the delay cannot be
attributed entirely to the NGT stay.
61. Moreover, the Appellant cannot simultaneously contend that
the project stood completed in 2014 while also claiming that the
NGT stay prevented completion of the project. These inconsistent
pleas are mutually destructive and cannot be accepted.
62. The benefit of the "Zero Period" granted by the Hon'ble
Supreme Court in the matter of Suresh Chander Sharma (supra),
extends only to the period from 14.08.2013 to 19.08.2015. The
contractual obligation to deliver possession had already arisen in
November, 2012, much before the commencement of the said
Zero Period.
63. The Appellant's initial default had already occurred before the
NGT stay order came into operation. Consequently, the Appellant
cannot seek to extend the benefit of the Zero Period so as to
obliterate the delay which had already accrued prior to August,
2013.
64. Even after excluding the Zero Period granted by the Hon'ble
Supreme Court in Suresh Chander Sharma (supra) , there
remains substantial and unexplained delay attributable exclusively
to the Appellant. The subsequent inaction of the competent
authority during the Zero Period cannot absolve the Appellant of
its contractual and statutory obligations which had already been
breached.
65. The Tribunal has rightly appreciated the facts and correctly
held that the Appellant is liable to compensate the Respondent by

22
RERA APPEAL No. - 37 of 2026
payment of delay interest in accordance with Section 18 of the
Real Estate (Regulation and Development) Act, 2016.
66. Accordingly, the third and fourth substantial question of law is
also answered against the Appellant and in favour of the
Respondent.
67. In view of the foregoing discussion, all the substantial
questions of law are answered in favour of the Respondent and
against the Appellant.
68. In view of the aforesaid, the instant RERA appeal sans merit,
is accordingly dismissed .
69. Office is directed to send the lower court record to the court
concerned along with a copy of this order, forthwith.
70. Before parting with this case, this Court places on record its deep
appreciation for the remarkable assistance rendered by Mr. Utkarsh
Shukla, Research Associate.
(Prashant Kumar , J.)
September 23, 2026
Arjun/-
Digitally signed by :-
ARJUN PRASAD
High Court of Judicature at Allahabad,
Lucknow Bench