Facts
The petitioner, a registered contractor, was awarded the work of strengthening and widening the Beldaur–Sakrohar Road under the NABARD Scheme pursuant to Agreement No. 26-F2/2006-07. The agreement was executed in March 2007, with completion stipulated by 28 February 2008. The work was completed on 24 May 2011 after an extension of time granted by the respondents, and the contractual dues were otherwise paid.
Source reference: p.2; para. 2; p.5, para. 9The petitioner claimed reimbursement of the increased cost of bitumen under the departmental Bitumen Price Neutralization Policy dated 24 September 2009. His claim, quantified at Rs.14,58,297/-, was verified and recorded in the Measurement Book in 2015.
Source reference: p.2–3; para. 3The Executive Engineer thereafter requested allotment of the said amount for payment to the petitioner by letter dated 15 July 2017, but payment was not made despite representations and legal notices.
Source reference: p.3; p.5–6, para. 10The respondents resisted the claim on the grounds that the policy was introduced after execution of the agreement and that the extension of time had been granted subject to a condition barring additional claims.
Source reference: p.4, paras. 5–7Issues
Whether the petitioner was entitled to payment of Rs.14,58,297/- under the Bitumen Price Neutralization Policy dated 24 September 2009, notwithstanding that the contract had been executed before the policy was introduced.
Source reference: p.4, paras. 5–7; p.6, para. 11Whether the condition attached to the extension of time, barring additional claims, defeated the petitioner’s otherwise substantiated claim for bitumen price escalation.
Source reference: p.4, para. 6; p.5, para. 9Whether the respondents could withhold the amount despite departmental verification and a specific request for allocation of funds.
Source reference: p.5–6, paras. 10–12Law Applied
The Court applied the terms of the parties’ contract together with the departmental Bitumen Price Neutralization Policy dated 24 September 2009.
Source reference: p.5, para. 9; p.6, para. 11The governing principle was that a contractual claim otherwise payable under an applicable departmental policy could not be rejected merely because the original agreement preceded the policy, particularly where the department had subsequently examined, verified, and acted upon the claim.
Source reference: p.5, para. 9; p.6, para. 11The Court further held that an extension-of-time condition could not, by itself, defeat a claim found payable under the departmental policy.
Source reference: p.5, para. 9; p.6, para. 11No statutory provision or judicial precedent was expressly relied upon in the judgment.
Source reference: no citationReasoning
The Court found that the petitioner’s work had been completed after a departmental extension granted upon consideration of the relevant circumstances, and that the extension did not automatically extinguish an otherwise valid claim under the departmental policy.
Source reference: p.5, para. 9Although the respondents argued that the 2009 policy could not apply to a 2007 agreement, the Court placed substantial reliance on the subsequent departmental conduct: the petitioner’s claim had been recorded in the Measurement Book, and the Executive Engineer had specifically sought allotment of Rs.14,58,297/- for payment in accordance with the policy.
Source reference: p.3; p.5–6, para. 10In the absence of any satisfactory justification for withholding the verified amount for several years, the Court concluded that the respondents’ objections were insufficient and that the petitioner had established his entitlement.
Source reference: p.6–7, paras. 11–13Holding
The High Court allowed the writ petition and held that the petitioner was entitled to Rs.14,58,297/- towards Bitumen Price Neutralization under the departmental policy.
The judgment did not expressly grant the separate claim for interest or prescribe a specific time limit for payment.
Source reference: p.7, paras. 14–15Any interlocutory applications were disposed of.
Source reference: p.7, paras. 14–15Original Court PDF
Sri Rajendra SharmavsThe State Of Bihar and Ors
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
