Bombay High Court
Arbitration and MediationContract Law

A clear adoption of governing general conditions incorporates their arbitration clause by reference.

Shivkumar Enterprises vs Tata Projects Ltd

Bombay High CourtJUDGMENT: September 07, 20262 MIN READSOURCE JUDGMENT
A clear adoption of governing general conditions incorporates their arbitration clause by reference.. Shivkumar Enterprises vs Tata Projects Ltd. Bombay High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

Tata Projects issued Shivkumar Enterprises four Work Orders in 2021 and 2023, stated to be governed by the General Conditions for Contract Services (GCC), reference no. TPL/SCM/GCC/C4-HV/R3.

Source reference: para. 1–5

After carrying out the work, submitting running-account bills and receiving Virtual Completion Certificates, the Applicant claimed that amounts remained unpaid.

Source reference: para. 1–5

Following demand notices and the Respondent’s denial of liability, the Applicant invoked Clause 41 of the GCC.

Source reference: para. 1–5

The Respondent rejected the invocation, and the Applicant applied under Section 11 of the Arbitration and Conciliation Act, 1996 for appointment of an arbitrator.

Source reference: para. 1–5
02

Issues

1. Whether the Work Orders incorporated the GCC, including its arbitration clause, so as to establish a prima facie arbitration agreement under Section 7 of the Act

Source reference: para. 11–15

2. Whether the Respondent’s objections concerning amicable settlement, outstanding GST documents and the Applicant’s invocation of arbitration across four Work Orders precluded appointment of an arbitrator

Source reference: para. 23–26
03

Law Applied

Section 7(5) of the Arbitration and Conciliation Act, 1996 permits an arbitration clause to be incorporated by reference where the contractual reference demonstrates an intention to make that clause part of the contract.

Source reference: no citation

M. R. Engineers and Contractors Pvt. Ltd. v. Som Datt Builders Ltd., (2009) 7 SCC 696, distinguishes a reference to another document for a limited purpose from incorporation of that document into the contract.

Source reference: para. 12

The Court also considered Inox Wind Ltd. v. Thermocables Ltd., (2018) 2 SCC 519, on incorporation of standard-form terms, and NBCC (India) Ltd. v. Zillion Infraprojects Pvt. Ltd., (2024) 7 SCC 174, and Maharashtra State Electricity Distribution Co. Ltd. v. R. Z. Malpani, 2026 SCC OnLine SC 553, on the insufficiency of a mere general reference in appropriate circumstances.

Source reference: para. 18, 28

An arbitration agreement must rest on consent; at the Section 11 stage, the Court must be satisfied at least prima facie that such an agreement exists.

Source reference: para. 11, 21, 30–32
04

Reasoning

The Court treated the question as one of the Work Orders’ wording and the parties’ intention, rather than whether the arbitration clause was reproduced or separately signed.

Source reference: para. 14–17, 21–22, 28–30

It found that the GCC was identified as governing the Work Orders and was not shown to have been referenced solely for a limited technical or performance purpose; the Respondent also relied on GCC conditions in its defence. Read together, the Work Orders and GCC therefore disclosed prima facie incorporation of Clause 41.

Source reference: para. 14–17, 21–22, 28–30

The alleged failure to pursue amicable settlement and the outstanding GST documents concerned compliance and the merits of the payment claim, not the existence of the arbitration agreement.

Source reference: para. 23–24

Although each Work Order could require separate examination, all four relied on the same GCC and involved the same parties; the tribunal could determine the claims under each Work Order separately.

Source reference: para. 25–26
05

Holding

The Court held that a prima facie arbitration agreement existed between the parties under Section 7 of the Act and appointed Mr. Shadab Jan as sole arbitrator to adjudicate disputes and claims arising from the four Work Orders.

The application was disposed of on the stated terms, with all issues on the merits left open to the tribunal and no order as to costs.

Source reference: para. 35, 37–38
06

Acts & Sections Cited

3 provisions across 1 statute referred to in this judgment. Each provision opens on LawLens.

Arbitration and Conciliation Act, 19963

Bombay High Court

Original Court PDF

Shivkumar EnterprisesvsTata Projects Ltd

Bombay High Court · September 07, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment