Facts
The appellant-plaintiff instituted a partition suit concerning 21 decimals of land described in the “Kha” schedule.
Source reference: paras. 3–5According to the plaint, the appellant occupied approximately 8 decimals, while the respondents occupied the remaining 13 decimals.
Source reference: paras. 3–5Although the property had not been partitioned by metes and bounds, the parties were allegedly in separate possession pursuant to an amicable arrangement.
Source reference: paras. 3–5, 43–45The appellant had obtained an ad interim injunction restraining construction on the suit property.
Source reference: para. 2The respondents applied under Order XXXIX Rule 4 of the Code of Civil Procedure, 1908, for vacation of that injunction, relying on a sanctioned building plan and ongoing construction on their occupied portion.
Source reference: para. 2The Trial Court vacated the injunction, subject to the construction being confined to the respondents’ demarcated portion and being carried out strictly in accordance with the sanctioned plan.
Source reference: paras. 33–34, 50–51The respondents also undertook not to claim the cost of construction if the concerned portion was ultimately allotted to another co-sharer in the final partition decree.
Source reference: paras. 33–34, 50–51Issues
Whether the Trial Court erred in vacating the ad interim injunction and permitting the respondents to continue construction on the disputed joint property?
Source reference: paras. 2, 24, 37–40Whether construction on the respondents’ portion would prejudice the appellant’s co-sharer rights or render the partition proceedings irreversible?
Source reference: paras. 6–17, 40–47Whether the alleged discrepancies in the number of pillars, the nature of the proposed construction, and the alleged suppression by the respondents warranted restoration of the injunction?
Source reference: paras. 18–23, 25–36, 47Law Applied
The Court applied Order XXXIX Rule 4 of the Code of Civil Procedure, 1908, concerning discharge, variation, or setting aside of an injunction, together with the settled principles governing interlocutory injunctions, namely prima facie case, balance of convenience, and irreparable injury.
Source reference: paras. 8–17It considered the principles in Israil v. Shamser Rahman, ILR XLI 436, that a co-owner in possession of part of joint property cannot ordinarily alter its nature or use it to the prejudice of other co-sharers.
Source reference: paras. 8–17It considered Bina Murlidhar Hemdev v. Kanhaiyalal Lokram Hemdev, (1999) 5 SCC 222, and Gangubai Bablya Chaudhary v. Sitaram Bhalchandra Sukhtankar, (1983) 4 SCC 31, concerning the risk of irreversible construction on disputed joint property.
Source reference: paras. 8–17It further applied the principle that a party may be bound by admissions in its pleadings and, in the circumstances, be estopped from denying an agreed arrangement of separate possession.
Source reference: paras. 43–45Reasoning
The Court distinguished the authorities relied upon by the appellant because those cases involved construction by one co-sharer in a manner prejudicial to the rights of other co-sharers over the very portion in dispute.
Source reference: paras. 40–42In the present case, the appellant’s own plaint acknowledged that the parties were in separate possession of approximately 8 and 13 decimals pursuant to an amicable arrangement.
Source reference: paras. 43–45The Court therefore held that the appellant was bound by that position and could not, at the interlocutory stage, contend that construction within the respondents’ occupied 13-decimal portion necessarily invaded his rights.
Source reference: paras. 43–45The sanctioned plan and local inspection report indicated that the proposed construction was confined to the respondents’ portion.
Source reference: para. 46The discrepancy regarding 24 sanctioned pillars and 35 observed pillars was explained by the respondents on the basis that some pillars supported an underground reservoir, and the Court considered the discrepancy immaterial because no substantive right of the appellant over his occupied 8 decimals was shown to be affected.
Source reference: paras. 25, 47The respondents had obtained sanction, invested substantial sums, and commenced construction; consequently, restraining them would cause undue hardship.
Source reference: paras. 48–51The Trial Court’s safeguards—construction strictly according to the sanctioned plan and within the respondents’ entitlement, together with the undertaking regarding future allotment and construction costs—adequately protected the appellant’s interests.
Source reference: paras. 48–51Holding
The Court held that the respondents could continue construction on their separately demarcated and occupied portion, notwithstanding the absence of a formal partition by metes and bounds, because the construction was sanctioned, substantially underway, and subject to adequate safeguards.
The appellant’s apprehension of encroachment or prejudice was found to be unsupported.
Source reference: paras. 52–57The appeal, F.M.A. 1143 of 2026, was dismissed on contest, and the Trial Court’s order dated 28 August 2026 vacating the injunction was affirmed.
Source reference: paras. 52–57CAN 1 of 2026 was consequently disposed of, with no order as to costs.
Source reference: paras. 52–57Original Court PDF
SHAKTI PRASAD PARUAvsMANAS MAITY AND ANR
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
