Himachal Pradesh High Court
Administrative and Public LawProperty and Real Estate Law

A distribution licensee cannot deny electricity supply for want of consumer-provided Right of Way.

DAYA RAM vs THE HPSEBL AND ANOTHER

Himachal Pradesh High CourtJUDGMENT: September 10, 20263 MIN READSOURCE JUDGMENT
A distribution licensee cannot deny electricity supply for want of consumer-provided Right of Way.. DAYA RAM vs THE HPSEBL AND ANOTHER. Himachal Pradesh High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The petitioner owned land and a double-storey house situated at Village Galot, District Shimla, over which an existing single-phase LT electricity line passed, allegedly endangering his life and property.

Source reference: para. 2

He requested the HP State Electricity Board to shift the line.

Source reference: para. 2

Following a survey, an estimate, and issuance of a Panchayat NOC, the Board laid a new electricity line; however, it neither energized the new line nor removed the old poles and wires.

Source reference: paras. 2–3

The Board opposed the petition, contending that the petitioner was required to provide the necessary Right of Way (RoW), and that objections and pending civil litigation concerning the land prevented completion of the work.

Source reference: para. 4

The petitioner therefore sought directions to energize the new line and remove the old line passing over his house.

Source reference: para. 1
02

Issues

Whether the distribution licensee could refuse or delay energization of the newly laid electricity line on the ground that the petitioner had not provided the requisite RoW.

Source reference: paras. 5–6, 12–13

Whether the Board was obliged to address objections or obstructions to the shifting of the electricity line under the Electricity Act, 2003 and the Works of Licensees Rules, 2006.

Source reference: paras. 8–12

Whether the pending civil litigation and alleged stay justified the Board’s failure to energize the new line and remove the old line passing over the petitioner’s house.

Source reference: para. 15
03

Law Applied

Section 43 of the Electricity Act, 2003 imposes a duty on every distribution licensee to supply electricity to the premises of an owner or occupier upon application and, where required, to provide the necessary electric plant or line.

Source reference: paras. 6–7

Section 67 empowers a licensee to lay, alter, repair, or remove electricity lines and authorizes the appropriate Government to frame rules concerning consent, objections, compensation, and removal of obstructions.

Source reference: para. 8

Rule 3 of the Works of Licensees Rules, 2006 permits a licensee to carry out works and lay electricity lines with the prior consent of the owner or occupier; where an objection is raised, the licensee may obtain written permission from the District Magistrate, Commissioner of Police, or another authorized officer.

Source reference: paras. 9–11

Although Clause 30 of the Electricity Manual refers to the consumer’s obligation to provide RoW, the Court held that this does not relieve the licensee of its statutory duty to deal with obstructions and provide electricity.

Source reference: para. 13

The Court distinguished Power Grid Corporation of India Ltd. v. Century Textiles and Industries Ltd., (2017) 5 SCC 143, Haryana Vidyut Prasaran Nigam Ltd. v. Navin Kumar, (2008) 16 SCC 282, and Madhya Pradesh Electricity Board v. Shri Basantibai, (1988) 1 SCC 23, on the facts.

Source reference: para. 14
04

Reasoning

The Court held that Section 43 places the primary obligation to provide electricity on the distribution licensee and does not make the consumer’s ability to independently secure RoW a precondition for supply.

Source reference: paras. 6–8

Under Rule 3 of the Works of Licensees Rules, any objection or obstruction to laying or shifting the line was required to be addressed by the Board by obtaining appropriate administrative assistance from the competent authorities.

Source reference: paras. 10–13

Since the new line had already been laid, the remaining steps—energization of that line and removal of the old line—could not be avoided merely by referring generally to pending litigation.

Source reference: para. 15

The Board produced no material demonstrating that the operative stay specifically prohibited energization or removal of the old poles and wires.

Source reference: para. 15

Accordingly, the Court concluded that the Board’s reliance on RoW and the pending civil proceedings was insufficient to justify withholding the petitioner’s electricity supply.

Source reference: no citation
05

Holding

The petition was allowed.

The HP State Electricity Board was directed to energize the single-phase LT electricity line laid in Village Galot, as shown in Annexure P-5, and to remove the existing single-phase line passing over the petitioner’s house, preferably within six weeks from the date of judgment.

Source reference: para. 16

The petition and all pending applications were disposed of accordingly.

Source reference: para. 17
06

Acts & Sections Cited

2 provisions across 1 statute referred to in this judgment. Each provision opens on LawLens.

Electricity Act, 20032

Himachal Pradesh High Court

Original Court PDF

DAYA RAMvsTHE HPSEBL AND ANOTHER

Himachal Pradesh High Court · September 10, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment