Supreme Court

A party cannot unilaterally adjudicate a disputed contractual breach or oust all legal remedies.

M/S. Abs Marine Services vs Andaman And Nicobar Administration

Supreme CourtJUDGMENT: March 23, 20263 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

In December 2008, the Appellant entered into a "Manning Agreement" with the Respondent for 17 vessels

Source reference: para. 3

In July 2009, a vessel was damaged after striking a submerged rock

Source reference: para. 5

In 2014, the Respondent unilaterally recovered Rs. 2,87,84,305/- from the Appellant's pending bills as a penalty for the grounding, citing "negligence" under Clause 3.20 of the agreement

Source reference: para. 6

Clause 3.20 stipulated that the Administration's decision regarding financial loss due to negligence would be final, binding, and could not be challenged in any court or arbitration

Source reference: para. 19

The Appellant disputed liability, leading to the appointment of a sole arbitrator by the Supreme Court

Source reference: para. 7

The Arbitrator held Clause 3.20 void under Section 28 of the Indian Contract Act and awarded the recovered amount to the Appellant

Source reference: paras. 9, 11

While the District Judge upheld the award, the High Court of Calcutta set it aside, ruling that Clause 3.20 created an "excepted matter" over which the arbitrator had no jurisdiction

Source reference: paras. 12-13
02

Issues

Whether the High Court was correct in law to set aside the arbitral award by treating the dispute as an "excepted matter" under Clause 3.20

Source reference: para. 15

Whether a contractual clause can validly authorize one party to be the sole arbiter of a disputed breach and simultaneously bar all legal and arbitral remedies

Source reference: paras. 24-25
03

Law Applied

The Court primarily applied the fundamental principle of the Rule of Law that no person shall be a judge in their own cause (Nemo judex in causa sua)

Source reference: para. 25

It relied on State of Karnataka v. Shree Rameshwara Rice Mills, which established that a party to a contract cannot adjudicate a disputed breach; such power is limited to cases where the breach is admitted

Source reference: para. 26

It further cited J.G. Engineers Private Limited v. Union of India, affirming that the question of breach must be decided by an adjudicatory forum, not the party alleging the breach

Source reference: para. 27

The Court invoked Section 28 of the Indian Contract Act, 1872, which renders agreements in restraint of legal proceedings void

Source reference: para. 31

The maxim Ubi jus ibi remedium (where there is a right, there is a remedy)

Source reference: para. 30

Section 9 of the Code of Civil Procedure and the principles in Sri Vedagiri Lakshmi Narasimha Swami Temple v. Induru Pattabhirami Reddi prevent any interpretation that creates a "vacuum" in legal remedies

Source reference: paras. 31-32
04

Reasoning

The Court reasoned that Clause 3.22 (Arbitration) was widely worded to include "any dispute," while Clause 3.20 sought to grant the Respondent unilateral power to determine "negligence" and "wilful act"

Source reference: paras. 21-23

The Court held that the Administration cannot be the judge of a breach when the other party disputes liability, as this violates the Rule of Law

Source reference: para. 25

Harmoniously construing the contract, the Court clarified that Clause 3.20’s "finality" applies only to the quantification of loss in instances where the breach is admitted

Source reference: paras. 28, 35

Since the Appellant disputed negligence, the issue of liability fell squarely within the arbitrator's jurisdiction under Clause 3.22

Source reference: para. 29

The Court rejected the "excepted matter" argument, noting that "excepting" a matter from arbitration is permissible, but "excluding" justice by barring both courts and arbitration is illegal

Source reference: paras. 37-38

It described the Respondent’s attempt to foreclose all legal remedies while reserving its own right to sue as "grossly discriminatory"

Source reference: para. 38
05

Holding

The Supreme Court allowed the appeals, set aside the High Court’s judgment, and restored the arbitral award dated 08.05.2017

The Court held that one party to a contract cannot unilaterally decide on a disputed breach, and any clause barring a party from challenging such a decision in a court of law or arbitration is contrary to the Rule of Law and Section 28 of the Indian Contract Act

Source reference: paras. 34, 40

The dispute was found to be within the arbitrator's domain as the liability was contested

Source reference: para. 41
Supreme Court

Original Court PDF

M/S. Abs Marine ServicesvsAndaman And Nicobar Administration

Supreme Court · March 23, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment