Facts
The petitioner claimed possession of agricultural land measuring 38 bighas and 18 biswas at Rampur Kalan, Mohali.
Source reference: no citationIn the context of a dispute pending before a sole arbitrator, the Court had ordered the parties to maintain status quo regarding possession and directed the local SHO to ensure compliance
Source reference: p.3, paras 8–10The petitioner later alleged attempted trespass and non-compliance, and filed a contempt petition; that application was withdrawn with liberty to refile if circumstances arose
Source reference: pp.1, 3–4, paras 1–3, 11–12In the present petition, the petitioner sought continuation of the interim protection.
Source reference: no citationRespondents 1 and 2 did not appear, and the Court recorded that there was no rebuttal to the petitioner’s case
Source reference: p.4, paras 4–6, 13Issues
Whether the Court should continue the interim protection granted under Section 9 of the Arbitration and Conciliation Act, 1996, pending consideration of the dispute by the arbitral tribunal.
Source reference: pp.3–5, paras 9–10, 14–20Whether the Section 9 petition could be treated as an application under Section 17 and placed before the arbitral tribunal for appropriate orders.
Source reference: p.4, paras 14–16Law Applied
Section 9 of the Arbitration and Conciliation Act, 1996 empowers courts to grant protective interim measures to safeguard the subject matter of arbitration; it does not permit final adjudication of the underlying disputes.
Source reference: p.4, para 14Once the arbitral tribunal is available, interim relief may be considered by it under Section 17.
Source reference: p.4, para 14The Court relied on Arcelor Mittal Nippon Steel India Ltd. v. Essar Bulk Terminated Ltd., (2022) 1 SCC 712, and Ariat International Inc. v. Sunglass Palace India Pvt. Ltd., 2025 SCC OnLine Del 9488, for the protective and non-final nature of Section 9 relief
Source reference: p.4, para 14Reasoning
The Court had previously granted status quo protection in light of the alleged risk of dispossession, and the petitioner subsequently alleged that the order had not been complied with.
Source reference: pp.3–5, paras 9–19With no appearance or rebuttal from the relevant respondents, the Court continued interim protection, but did not finally determine the parties’ rights or make the interim relief absolute.
Source reference: pp.3–5, paras 9–19Instead, applying the limited, protective scope of Section 9, it treated the petition as an application under Section 17 for the arbitral tribunal’s independent consideration
Source reference: pp.3–5, paras 9–19Holding
The petition was disposed of with the Section 9 petition to be treated as an application under Section 17 and placed before the learned arbitrator.
The existing interim protection will continue until the arbitrator considers the application and passes appropriate orders.
Source reference: pp.4–5, paras 15–21The petitioner must take steps to appoint the arbitrator within 45 days, failing which the protection will automatically stand vacated.
Source reference: pp.4–5, paras 15–21The arbitrator may continue, modify, vary, or vacate the protection and must decide the application independently, uninfluenced by the Court’s observations
Source reference: pp.4–5, paras 15–21Acts & Sections Cited
2 provisions across 1 statute referred to in this judgment. Each provision opens on LawLens.
Arbitration and Conciliation Act, 19962
Original Court PDF
Renaissance Buildcon Co Pvt LtdvsMr. Gurvinder Singh And Ors.
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
