Calcutta High CourtArbitration and MediationCivil Procedure and Evidence

Absence of Intent to Relinquish Claim and Subsequent Arbitrator Withdrawal Preclude Finding of Abandonment Under Section 14

MIPL DRAIPL JVv.EASTERN RAILWAY

Absence of Intent to Relinquish Claim and Subsequent Arbitrator Withdrawal Preclude Finding of Abandonment Under Section 14. MIPL DRAIPL JV vs EASTERN RAILWAY. Calcutta High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the Petitioner’s inordinate delay of four years in prosecuting the arbitration amounts to an implied abandonment of the arbitral proceedings

The court held

The Court allowed the petition, holding that the mandate of the previous arbitrator stood terminated due to his withdrawal

It also directed

It ruled that the claim was neither abandoned nor barred by limitation, as the cause of action for substitution arose only upon the arbitrator’s formal withdrawal

The Court appointed Justice Pranab Kumar Chattopadhyay (Retd.) as the substitute Sole Arbitrator to adjudicate the disputes, directing him to file a disclosure under Section 12(1) and proceed according to law

01Facts

The Petitioner, a joint venture, was awarded a contract by the Respondent on 05.09.2013 for the construction of railway bridges

¶ 3

Following disputes, the contract was terminated on 08.08.2017, and arbitration was invoked on 06.02.2019

¶ 4

On 04.02.2021, the High Court appointed Justice Tapan Kumar Dutt (Retd.) as the Sole Arbitrator

¶ 5

Due to financial constraints, the Petitioner did not communicate the appointment order to the Arbitrator for over four years

¶ 6, 9

When finally notified on 11.06.2025, the Arbitrator withdrew from the proceedings on 19.06.2025

¶ 7

The Petitioner subsequently filed the present petition seeking termination of the original mandate and appointment of a substitute arbitrator

¶ 8

02Issues

i.1. Whether the Petitioner’s inordinate delay of four years in prosecuting the arbitration amounts to an implied abandonment of the arbitral proceedings

¶ 24

ii.2. Whether the petition for substitution of an arbitrator under Sections 14 and 15 is barred by limitation under Article 137 of the Limitation Act, 1963

¶ 26

03Law Applied

The court primarily applied Sections 14 and 15 of the Arbitration and Conciliation Act, 1996, regarding the termination of an arbitrator's mandate and the appointment of a substitute

¶ 8

It relied on Section 43 of the Act, which makes the Limitation Act, 1963, applicable to arbitrations

¶ 26

Regarding abandonment, the court applied the principle from Dani Wooltex Corporation v. Sheil Properties Pvt. Ltd. (2024), which establishes that abandonment cannot be readily inferred and requires convincing circumstances showing a clear, unequivocal intention to relinquish a claim

¶ 24

It also considered Article 137 of the Limitation Act, which provides a three-year period for applications not otherwise provided for

¶ 16

Provisions in the judgment · 8 · Linked ones open on LawLens

Arbitration and Conciliation Act, 1996 Section 12Section 14Section 15Section 21Section 43Section 5Section 7

Limitation Act, 1963 Section 137

04Reasoning

The court reasoned that while the four-year delay was substantial and the explanation of "financial constraints" was not entirely satisfactory, it did not constitute abandonment

¶ 22, 25

Applying the Dani Wooltex test, the court found the Petitioner's attempts to file a petition in 2025 and the eventual communication to the Arbitrator demonstrated a "continuing intention" to pursue the remedy

¶ 25

On the issue of limitation, the court rejected the Respondent's argument that the clock started in 2021. It held that for a petition under Sections 14 and 15, the right to apply arises only when the mandate becomes incapable of performance—in this case, on 19.06.2025, when the Arbitrator withdrew

¶ 26

The court emphasized a "pro-arbitration approach," stating that procedural lapses should not technicality defeat substantive rights or the continuity of the arbitral process

¶ 28-29

05Holding

The Court allowed the petition, holding that the mandate of the previous arbitrator stood terminated due to his withdrawal

¶ 30

It ruled that the claim was neither abandoned nor barred by limitation, as the cause of action for substitution arose only upon the arbitrator’s formal withdrawal

¶ 26

The Court appointed Justice Pranab Kumar Chattopadhyay (Retd.) as the substitute Sole Arbitrator to adjudicate the disputes, directing him to file a disclosure under Section 12(1) and proceed according to law

¶ 31, 32
Calcutta High Court

Original Court PDF

MIPL DRAIPL JVvsEASTERN RAILWAY

Calcutta High Court · April 27, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment