Facts
The Petitioner, a joint venture, was awarded a contract by the Respondent on 05.09.2013 for the construction of railway bridges
Source reference: para. 3Following disputes, the contract was terminated on 08.08.2017, and arbitration was invoked on 06.02.2019
Source reference: para. 4On 04.02.2021, the High Court appointed Justice Tapan Kumar Dutt (Retd.) as the Sole Arbitrator
Source reference: para. 5Due to financial constraints, the Petitioner did not communicate the appointment order to the Arbitrator for over four years
Source reference: paras. 6, 9When finally notified on 11.06.2025, the Arbitrator withdrew from the proceedings on 19.06.2025
Source reference: para. 7The Petitioner subsequently filed the present petition seeking termination of the original mandate and appointment of a substitute arbitrator
Source reference: para. 8Issues
1. Whether the Petitioner’s inordinate delay of four years in prosecuting the arbitration amounts to an implied abandonment of the arbitral proceedings
Source reference: para. 242. Whether the petition for substitution of an arbitrator under Sections 14 and 15 is barred by limitation under Article 137 of the Limitation Act, 1963
Source reference: para. 26Law Applied
The court primarily applied Sections 14 and 15 of the Arbitration and Conciliation Act, 1996, regarding the termination of an arbitrator's mandate and the appointment of a substitute
Source reference: para. 8It relied on Section 43 of the Act, which makes the Limitation Act, 1963, applicable to arbitrations
Source reference: para. 26Regarding abandonment, the court applied the principle from Dani Wooltex Corporation v. Sheil Properties Pvt. Ltd. (2024), which establishes that abandonment cannot be readily inferred and requires convincing circumstances showing a clear, unequivocal intention to relinquish a claim
Source reference: para. 24It also considered Article 137 of the Limitation Act, which provides a three-year period for applications not otherwise provided for
Source reference: para. 16Reasoning
The court reasoned that while the four-year delay was substantial and the explanation of "financial constraints" was not entirely satisfactory, it did not constitute abandonment
Source reference: paras. 22, 25Applying the Dani Wooltex test, the court found the Petitioner's attempts to file a petition in 2025 and the eventual communication to the Arbitrator demonstrated a "continuing intention" to pursue the remedy
Source reference: para. 25On the issue of limitation, the court rejected the Respondent's argument that the clock started in 2021. It held that for a petition under Sections 14 and 15, the right to apply arises only when the mandate becomes incapable of performance—in this case, on 19.06.2025, when the Arbitrator withdrew
Source reference: para. 26The court emphasized a "pro-arbitration approach," stating that procedural lapses should not technicality defeat substantive rights or the continuity of the arbitral process
Source reference: paras. 28-29Holding
The Court allowed the petition, holding that the mandate of the previous arbitrator stood terminated due to his withdrawal
It ruled that the claim was neither abandoned nor barred by limitation, as the cause of action for substitution arose only upon the arbitrator’s formal withdrawal
Source reference: para. 26The Court appointed Justice Pranab Kumar Chattopadhyay (Retd.) as the substitute Sole Arbitrator to adjudicate the disputes, directing him to file a disclosure under Section 12(1) and proceed according to law
Source reference: paras. 31, 32Original Court PDF
MIPL DRAIPL JVvsEASTERN RAILWAY
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in