01Facts
The Petitioner, a joint venture, was awarded a contract by the Respondent on 05.09.2013 for the construction of railway bridges
¶ 3Following disputes, the contract was terminated on 08.08.2017, and arbitration was invoked on 06.02.2019
¶ 4On 04.02.2021, the High Court appointed Justice Tapan Kumar Dutt (Retd.) as the Sole Arbitrator
¶ 5Due to financial constraints, the Petitioner did not communicate the appointment order to the Arbitrator for over four years
¶ 6, 9When finally notified on 11.06.2025, the Arbitrator withdrew from the proceedings on 19.06.2025
¶ 7The Petitioner subsequently filed the present petition seeking termination of the original mandate and appointment of a substitute arbitrator
¶ 802Issues
i.1. Whether the Petitioner’s inordinate delay of four years in prosecuting the arbitration amounts to an implied abandonment of the arbitral proceedings
¶ 24ii.2. Whether the petition for substitution of an arbitrator under Sections 14 and 15 is barred by limitation under Article 137 of the Limitation Act, 1963
¶ 2603Law Applied
The court primarily applied Sections 14 and 15 of the Arbitration and Conciliation Act, 1996, regarding the termination of an arbitrator's mandate and the appointment of a substitute
¶ 8It relied on Section 43 of the Act, which makes the Limitation Act, 1963, applicable to arbitrations
¶ 26Regarding abandonment, the court applied the principle from Dani Wooltex Corporation v. Sheil Properties Pvt. Ltd. (2024), which establishes that abandonment cannot be readily inferred and requires convincing circumstances showing a clear, unequivocal intention to relinquish a claim
¶ 24It also considered Article 137 of the Limitation Act, which provides a three-year period for applications not otherwise provided for
¶ 16Provisions in the judgment · 8 · Linked ones open on LawLens
Arbitration and Conciliation Act, 1996 Section 12Section 14Section 15Section 21Section 43Section 5Section 7
Limitation Act, 1963 Section 137
04Reasoning
The court reasoned that while the four-year delay was substantial and the explanation of "financial constraints" was not entirely satisfactory, it did not constitute abandonment
¶ 22, 25Applying the Dani Wooltex test, the court found the Petitioner's attempts to file a petition in 2025 and the eventual communication to the Arbitrator demonstrated a "continuing intention" to pursue the remedy
¶ 25On the issue of limitation, the court rejected the Respondent's argument that the clock started in 2021. It held that for a petition under Sections 14 and 15, the right to apply arises only when the mandate becomes incapable of performance—in this case, on 19.06.2025, when the Arbitrator withdrew
¶ 26The court emphasized a "pro-arbitration approach," stating that procedural lapses should not technicality defeat substantive rights or the continuity of the arbitral process
¶ 28-2905Holding
The Court allowed the petition, holding that the mandate of the previous arbitrator stood terminated due to his withdrawal
¶ 30It ruled that the claim was neither abandoned nor barred by limitation, as the cause of action for substitution arose only upon the arbitrator’s formal withdrawal
¶ 26The Court appointed Justice Pranab Kumar Chattopadhyay (Retd.) as the substitute Sole Arbitrator to adjudicate the disputes, directing him to file a disclosure under Section 12(1) and proceed according to law
¶ 31, 32Original Court PDF
MIPL DRAIPL JVvsEASTERN RAILWAY
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
