Facts
The Petitioner (Developer) and Respondent entered into a Memorandum of Understanding (MoU) on 18.05.2018 for the operation of service apartments/hotels in a mall
Source reference: p. 1-2Under Clause 14, the Petitioner paid ₹1,18,00,000 as advance fees for brand collaboration and technical support
Source reference: p. 2, 5Disputes arose when the Respondent demanded additional space not included in the MoU, leading to a stalemate where neither party performed their obligations
Source reference: p. 2, 6The Petitioner sought a refund of the advance, while the Respondent claimed further payments
Source reference: p. 2-3An Arbitrator was appointed who rejected both the Respondent’s claim for additional money and the Petitioner’s counter-claim for refund, holding that the MoU lacked a specific refund clause
Source reference: p. 3, 7The Petitioner challenged this dismissal under Section 34 of the Arbitration and Conciliation Act, 1996
Source reference: p. 1Issues
1. Whether the arbitral award is "non-speaking" and violates Section 31(3) of the Act by failing to provide reasons for dismissing the counter-claim
Source reference: p. 7 / para 112. Whether the Respondent can legally retain advance payments in the absence of a forfeiture clause and proof of actual loss under Section 73 of the Contract Act
Source reference: p. 9 / para 123. Whether the dismissal of the counter-claim constitutes patent illegality or a violation of public policy
Source reference: p. 12 / para 17Law Applied
Section 31(3) of the Arbitration and Conciliation Act, 1996, which mandates that an award must state the reasons upon which it is based
Source reference: p. 7Dyna Technologies Pvt. Ltd. v. Crompton Greaves Ltd. and Som Datt Builders Ltd. v. State of Kerala, establishing that reasoning must be intelligible and adequate
Source reference: p. 7-8Section 73 of the Indian Contract Act, 1872, and the principles from Central Bank of India v. Shanmugavelu and Kailash Nath Associates v. DDA, which dictate that in the absence of a forfeiture clause, advance payments must be returned unless the seller proves actual damage or loss
Source reference: p. 9-10The doctrine of severability under Section 34 as clarified in Gayatri Balasamy v. ISG Novasoft Technologies Ltd.
Source reference: p. 12Reasoning
The Court found the Arbitrator's dismissal of the counter-claim to be "bereft of reasons" and "non-speaking"
Source reference: p. 8It noted that the Arbitrator correctly found that both parties failed to adhere to the MoU, rendering the project a "non-starter," yet inconsistently allowed the Respondent to keep the advance
Source reference: p. 11-12The Court reasoned that since there was no forfeiture clause in the MoU, the Respondent was required under Section 73 of the Contract Act to prove legal injury or actual loss to justify retaining the money
Source reference: p. 9-10Since the Arbitrator specifically found that "no work was done" and "neither the brand name was used nor technical support granted," there was no basis for damages
Source reference: p. 11-12Failing to direct a refund despite these findings constituted a patent illegality and a violation of public policy
Source reference: p. 12Holding
The Court answered the issues in the affirmative, holding that the dismissal of the counter-claim was unreasoned and legally unsustainable.
Applying the principle of severability, the Court allowed the petition in part
Source reference: p. 13-14The arbitral award dated 01.07.2023 was set aside specifically to the extent that it dismissed the Petitioner's counter-claim for a refund of the advance amount
Source reference: p. 14Original Court PDF
M/S Sarvpriya Securities Pvt LtdvsM/S Ank Hotels Pvt Ltd
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in