Calcutta High CourtArbitration and MediationContract Law

Acceptance of debt servicing post-recall notice waives termination and precludes Section 9 interim relief.

SREI EQUIPMENT FINANCE LIMITEDv.BENGAL SHRISTI INFRASTRUCTURE DEVELOPMENT LTD

Acceptance of debt servicing post-recall notice waives termination and precludes Section 9 interim relief.. SREI EQUIPMENT FINANCE LIMITED vs BENGAL SHRISTI INFRASTRUCTURE DEVELOPMENT LTD. Calcutta High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the Petitioner is entitled to interim protection under Section 9, such as the attachment of receivables or creation of an escrow account, in the absence of a repayment default

The court held

The court declined the Petitioner’s prayer for an Escrow Account or the appointment of Special Officers, finding no immediate incident of default necessitating such drastic interim relief

It also directed

The court held that since the principal repayment does not commence until 2029 and interest is being paid, the Petitioner’s apprehensions were speculative

The court disposed of the application with a direction that the Respondent must inform the Petitioner of any future sales or leases of units and disclose the quantum of money received therefrom

The Petitioner remains at liberty to seek further interim orders before the yet-to-be-constituted Arbitral Tribunal

01Facts

The Petitioner provided a Rupee Term Loan of Rs. 273.48 crores to the Respondent (a Joint Venture between Shristi Infrastructure and Asansol Durgapur Development Authority/ADDA) under an agreement dated April 2, 2019

¶ 1

The loan was to be secured by a mortgage on land, contingent upon the Respondent obtaining a No Objection Certificate (NOC) from ADDA within 60 days of receipt

¶ 3, 4

The Petitioner alleged several "incidents of default," including the Respondent's failure to obtain the NOC, unauthorized changes in the JV's constitution, and financial instability

¶ 4, 5

Consequently, the Petitioner issued a loan recall notice on December 11, 2024, claiming dues exceeding Rs. 461.11 crores

¶ 7, 8

The Respondent countered that they had consistently paid interest installments as per the schedule—even after the recall notice—and that the failure to create a mortgage was due to ADDA’s non-compliance, which was currently subject to legal proceedings

¶ 10-12

The Petitioner sought interim relief under Section 9 of the Arbitration and Conciliation Act, 1996, specifically the creation of an Escrow Account for all project receivables

¶ 5

02Issues

i.1. Whether the Petitioner is entitled to interim protection under Section 9, such as the attachment of receivables or creation of an escrow account, in the absence of a repayment default

¶ 25, 32

ii.2. Whether the failure to create a mortgage constitutes a willful breach of contract when the condition is dependent on a third party (ADDA)

¶ 17, 20

iii.3. Whether the Petitioner’s acceptance of interest payments after the loan recall notice constitutes a waiver of the alleged termination

¶ 11, 20

03Law Applied

The court primarily applied Section 9 of the Arbitration and Conciliation Act, 1996, regarding interim measures

¶ 1

It relied on the principles of Order XXXVIII Rule 5 of the Code of Civil Procedure (CPC), as elucidated in Sanghi Industrial Limited v. Ravin Cables Ltd., which requires specific allegations of attempts to defeat a future award to justify securing the amount in dispute

¶ 10, 24

The court further applied the doctrine of "election" and "affirmation of contract" from STOCZNIA GDANSKA SA v. Latvian Shipping Company [para 21] and Ganga Retreat and Towers Ltd. v. State of Rajasthan [para 22], establishing that a party cannot treat a contract as terminated while continuing to accept performance.

¶ 21, 22

Finally, it invoked the equitable principle "delay defeats equity" as discussed in Future Corporate Resources Pvt. Ltd. v. Edelweiss Special Opportunities Fund

¶ 26

Provisions in the judgment · 2 · Linked ones open on LawLens

Arbitration and Conciliation Act, 1996 Section 9Section 34

04Reasoning

The court found that the Respondent had regularly serviced the loan interest from 2019 through 2025 without default

¶ 16, 20

Crucially, the Petitioner accepted multiple installments after issuing the loan recall notice in December 2024, which the court viewed as an affirmation of the contract, estopping the Petitioner from claiming immediate termination based on prior alleged defaults

¶ 11, 20, 25

Regarding the mortgage, the court noted the default was not "willful" as the Respondent had pursued arbitration against ADDA to obtain the necessary NOC

¶ 18-20

The court distinguished this case from previous precedents (AP COM 110/163) where actual interest defaults had occurred

¶ 29-31

It reasoned that appointing Special Officers to manage an Escrow Account would be an "extra-contractual" penal action that would unnecessarily interfere with the Respondent's regular business and the ongoing housing project

¶ 25, 32

The court concluded that the Petitioner failed to demonstrate a prima facie case of imminent dissipation of assets that would frustrate a future arbitral award

¶ 23, 32

05Holding

The court declined the Petitioner’s prayer for an Escrow Account or the appointment of Special Officers, finding no immediate incident of default necessitating such drastic interim relief

¶ 32

The court held that since the principal repayment does not commence until 2029 and interest is being paid, the Petitioner’s apprehensions were speculative

¶ 25, 28

The court disposed of the application with a direction that the Respondent must inform the Petitioner of any future sales or leases of units and disclose the quantum of money received therefrom

¶ 32, 33

The Petitioner remains at liberty to seek further interim orders before the yet-to-be-constituted Arbitral Tribunal

¶ 32
Calcutta High Court

Original Court PDF

SREI EQUIPMENT FINANCE LIMITEDvsBENGAL SHRISTI INFRASTRUCTURE DEVELOPMENT LTD

Calcutta High Court · March 19, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment