Delhi High Court
Arbitration and MediationContract Law

Additional work attracts no compensation when contractual preconditions for approval are unmet.

D. S. Partnership vs Natrip

Delhi High CourtJUDGMENT: September 02, 20264 MIN READSOURCE JUDGMENT
Additional work attracts no compensation when contractual preconditions for approval are unmet.. D. S. Partnership vs Natrip. Delhi High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

NATRIP Implementation Society engaged D. S. Partnership (“Petitioner”) under Contract-I dated 7 August 2009 to provide consultancy services for evaluating and validating designs of utilities forming part of civil works, for a capped consideration of GBP 71,200 and an allocation of 520 man-hours.

Source reference: paras. 3–6; pp. 2–3

The parties subsequently entered into Contract-II dated 13 April 2010, a lump-sum contract for detailed mechanical and electrical utility designs for GBP 119,500.

Source reference: paras. 7–8; p. 3

During Contract-II, the Petitioner undertook additional work concerning modifications to existing utility designs, harmonisation of utilities, and changes to General Arrangement drawings.

Source reference: paras. 9–12; pp. 3–4

NATRIP disputed liability, contending that the work was either included within Contract-II or had been undertaken without the prior written approval required by Clause 8.2 of Contract-I.

Source reference: paras. 13–14; p. 4

The three-member Arbitral Tribunal rejected NATRIP’s jurisdictional objection and held that the dispute substantially arose under Contract-I.

Source reference: para. 15; p. 4

The Tribunal also rejected the alternative claim based on quantum meruit under Section 70 of the Indian Contract Act, 1872.

Source reference: paras. 15–20; pp. 4–6

The Petitioner challenged the award dated 2 April 2016 under Section 34 of the Arbitration and Conciliation Act, 1996.

Source reference: para. 1; p. 1
02

Issues

Whether the Arbitral Tribunal’s finding that the Petitioner was not entitled to payment for additional work, due to non-compliance with the prior written approval requirement under Clause 8.2 of Contract-I, warranted interference under Section 34 of the Act.

Source reference: paras. 37–47; pp. 19–23

Whether the communications, meetings, and conduct of NATRIP’s officials constituted prior written approval, waiver, or acquiescence sufficient to satisfy Clause 8.2 of Contract-I.

Source reference: paras. 42–46; pp. 21–23

Whether the Tribunal’s findings concerning the non-raising of proforma invoices under Clause 8.3 warranted interference under Section 34.

Source reference: paras. 45–47; pp. 22–23

Whether the Petitioner was entitled to compensation on a quantum meruit basis under Section 70 of the Indian Contract Act, 1872, notwithstanding the express contractual procedure governing additional work.

Source reference: paras. 48–54; pp. 23–25

Whether the award conflicted with the public policy of India, including the fundamental policy of Indian law or the most basic notions of morality or justice.

Source reference: paras. 31–35, 55–58; pp. 9–19, 25–27
03

Law Applied

The Court applied Section 34(2)(b)(ii) of the Arbitration and Conciliation Act, 1996, including Explanations 1 and 2, under which an award may be set aside on public-policy grounds only if it involves fraud or corruption, contravenes the fundamental policy of Indian law, or conflicts with the most basic notions of morality or justice; review on the merits is impermissible.

Source reference: paras. 32–35; pp. 9–10

Since the arbitration was an international commercial arbitration, the additional ground of patent illegality under Section 34(2A) was unavailable.

Source reference: paras. 31–33; p. 9

Relying on OPG Power Generation (P) Ltd. v. Enexio Power Cooling Solutions (India) (P) Ltd., Ssangyong Engineering & Construction Co. Ltd. v. NHAI, and related authorities, the Court held that mere legal or factual error, contractual misinterpretation, or an alternative possible view does not justify interference, absent a violation of fundamental legal principles or elementary justice.

Source reference: paras. 34–35; pp. 10–19

Section 18 requires equal treatment of parties, while Section 28(3) requires the Tribunal to take the contract and applicable trade usages into account.

Source reference: paras. 22, 56; pp. 6–7, 26

Under Section 70 of the Indian Contract Act, quantum meruit requires, inter alia, lawful non-gratuitous work, absence of an operative contractual provision governing the work, acceptance of the work, and appropriate pleadings; the doctrine cannot be used to override express contractual terms, as recognised in Alopi Parshad & Sons Ltd. v. Union of India and Mahanagar Telephone Nigam Ltd. v. Tata Communications Ltd.

Source reference: paras. 48, 52–54; pp. 23–25
04

Reasoning

The Court held that performance of additional work and entitlement to remuneration were distinct questions; payment depended on compliance with the contractual conditions governing additional work.

Source reference: paras. 37–40; pp. 19–21

Clause 8.2 required prior written approval before proceeding with work likely to exceed the 520-hour allocation, and the expression “shall necessarily take prior written approval” made the requirement mandatory.

Source reference: paras. 39–41; pp. 20–21

The Tribunal found that no such approval had been obtained from Mr. Y.V. Narsimha Rao, the authorised representative under Contract-I.

Source reference: paras. 42–47; pp. 21–23

Its treatment of communications involving officials designated under Contract-II, and discussions with other senior officials, involved factual appreciation of the evidence.

Source reference: paras. 42–47; pp. 21–23

Reconsidering whether those communications amounted to approval, waiver, or acquiescence would impermissibly require re-appreciation of evidence under Section 34.

Source reference: paras. 42–47; pp. 21–23

The same reasoning applied to the Tribunal’s finding that the required proforma invoices had not been raised in advance under Clause 8.3(iii).

Source reference: paras. 45–47; pp. 22–23

Because Contract-I expressly governed additional work and prescribed the approval procedure, quantum meruit could not be invoked to bypass that procedure.

Source reference: paras. 52–54; pp. 24–25

Even if the Tribunal’s legal view were erroneous, the alleged error did not amount to a contravention of the fundamental policy of Indian law or a conflict with the most basic notions of morality or justice.

Source reference: para. 53; p. 25
05

Holding

The Court held that the Tribunal’s conclusions—that the Petitioner had not obtained the mandatory prior written approval, had not complied with the invoicing procedure, and was not entitled to quantum meruit—were plausible findings based on the contractual terms and evidence.

They did not disclose any violation of natural justice, fundamental policy of Indian law, or the most basic notions of morality or justice.

Source reference: paras. 47, 54–58; pp. 23–27

As patent illegality was unavailable in an international commercial arbitration and no ground under Section 34(2)(b)(ii) was established, the petition challenging the award was dismissed.

Source reference: paras. 58–60; p. 27

All pending applications, if any, were also disposed of.

Source reference: paras. 58–60; p. 27
06

Acts & Sections Cited

10 provisions across 2 statutes referred to in this judgment. Each provision opens on LawLens.

Indian Contract Act, 18722

Delhi High Court

Original Court PDF

D. S. PartnershipvsNatrip

Delhi High Court · September 02, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment