Facts
The petitioner sought a writ of mandamus directing the respondent authorities to allot funds and pay the outstanding amount due for works executed by him, along with interest.
Source reference: para. 1The works concerned schemes for tubewells/chapa-kals in the Runnisaidpur Assembly Constituency and were entrusted to the petitioner for implementation.
Source reference: para. 3After completion of the works, Measurement Books were prepared and part payment was made, subject to availability of funds.
Source reference: para. 3The Executive Engineer requested allotment of funds for payment of the outstanding dues by Letter No. 564 dated 28 March 2023.
Source reference: para. 4In response to an application under the Right to Information Act, the department confirmed by Letter No. 582 dated 3 April 2023 that ₹11,94,158 remained payable to the petitioner and that payment had not been made due to lack of funds.
Source reference: para. 4The respondents also acknowledged that further requests for fund allotment had been made between 2023 and 2026.
Source reference: para. 5In their supplementary counter-affidavit, the respondents stated that the balance would be paid after receipt of the requisite allotment.
Source reference: para. 6The work had admittedly been completed in 2010.
Source reference: para. 8Issues
Whether the petitioner was entitled to a direction for payment of the admitted outstanding amount of ₹11,94,158 despite the respondents’ plea of non-availability of funds?
Source reference: paras. 8–12Whether the petitioner was entitled to interest on the delayed payment?
Source reference: paras. 1, 13Law Applied
The Court applied the public-law principle that an admitted and verified contractual or work-related liability of the State cannot be withheld indefinitely merely because funds have not yet been allotted.
Source reference: paras. 8–9It further applied the principle governing issuance of a writ of mandamus, namely, that where a public authority has acknowledged a subsisting legal or monetary obligation, the Court may direct performance of that obligation.
Source reference: no citationThe Court did not cite any specific statute or judicial precedent; the claim for interest was left to be determined by the competent authority in accordance with applicable rules and law.
Source reference: para. 13Reasoning
The respondents’ own records established that the works had been completed, the Measurement Books had been prepared, and ₹11,94,158 had been verified and admitted as payable.
Source reference: paras. 3–4, 8Since the entitlement was not disputed, the plea of non-availability of funds could not justify indefinite withholding of payment, particularly when the liability arose from work completed in 2010.
Source reference: para. 9The Court therefore considered it unnecessary to keep the writ petition pending and directed the competent authorities to secure the requisite allotment, if necessary, without delaying payment through inter-departmental correspondence.
Source reference: paras. 10–12The issue of interest was not adjudicated on merits and was left for consideration by the competent authority.
Source reference: para. 13Holding
The writ petition was disposed of with a direction to the respondent authorities to ensure payment of the admitted balance amount of ₹11,94,158 to the petitioner within three months from the date of receipt or production of a copy of the order.
If further fund allotment was required, the authorities were directed to take all necessary steps and not defer payment merely because of inter-departmental correspondence.
Source reference: para. 12The petitioner’s claim for interest was left open for consideration by the competent authority under the applicable law and rules.
Source reference: para. 13Original Court PDF
Bhadra ram SinghvsThe State of Bihar
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
