Facts
The petitioner, M/s. Arohi Elevators Pvt. Ltd., was engaged by the Steel Authority of India Limited (SAIL) under a maintenance contract for lifts at the Bokaro Steel Plant
Source reference: para 7SAIL observed that the petitioner was failing to comply with the Payment of Wages Act, a mandatory requirement under the work orders
Source reference: para 8On August 16, 2025, the petitioner sent an email to SAIL expressing an inability to modify its established wage payment system to align with the Central Labour Commissioner (CLC) requirements for a single contract and requested foreclosure of the contract
Source reference: para 9SAIL subsequently issued two show-cause notices regarding the banning of future business dealings
Source reference: para 10On February 24, 2026, SAIL issued the impugned order banning the petitioner from business dealings for two years, effective from October 3, 2025, to October 2, 2027
Source reference: para 2The petitioner challenged this order, alleging it was non-speaking and violated the principles of natural justice
Source reference: para 3Issues
1. Whether the impugned order dated 24.02.2026 was a non-speaking order that violated the principles of natural justice and fair play
Source reference: para 32. Whether there was any procedural impropriety or unfairness in SAIL’s decision-making process leading to the two-year ban
Source reference: para 14Law Applied
The court applied the administrative law principles of natural justice, specifically the requirement for "speaking orders" (reasoned decisions) and the necessity of providing a fair opportunity to be heard before passing adverse orders
Source reference: para 3, 12It also emphasized the statutory obligation of employers to comply with the Payment of Wages Act as incorporated into contractual terms
Source reference: para 8The court relied on the principle that if the reasons for an administrative action are clearly discernible from the record and the correspondence between parties, the order cannot be deemed non-speaking
Source reference: para 13Reasoning
The court rejected the petitioner's contention that the order was non-speaking. It observed that the petitioner’s own communication dated August 16, 2025, explicitly admitted an inability to modify its wage system to meet statutory requirements
Source reference: para 9, 11The court noted that SAIL issued two separate show-cause notices, ensuring the petitioner had an opportunity to respond
Source reference: para 10In its replies, the petitioner did not deny the allegations of non-compliance but instead raised external issues such as delayed payments by SAIL
Source reference: para 11The court reasoned that since the petitioner flatly refused to comply with statutory provisions on the grounds of internal company policy, SAIL’s decision to ban the firm was neither unfair nor a result of non-application of mind
Source reference: para 12The court concluded that the reasons for the ban were clearly outlined in the order and supported by the petitioner’s own admissions in previous correspondence
Source reference: para 13Holding
The court held that there was no illegality, procedural impropriety, or unfairness in the decision-making process
The impugned order was found to be a reasoned order passed after following the principles of natural justice
Source reference: para 13Consequently, the petition was dismissed without costs
Source reference: para 14Additionally, the court directed the Registry to send the order to the Payment of Wages Authority at Bokaro/Dhanbad to investigate the petitioner’s wage structure regarding its workmen
Source reference: para 15-16Original Court PDF
M/S AROHI ELEVATORS PVT. LTD., THROUGH ITS DIRECTOR, BAJRANG BAHADUR SINGHvsTHE STEEL AUTHORITY OF INDIA LTD., THROUGH ITS CHAIRMAN-CUM-MANAGING DIRECTOR
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in