01Facts
Bangalore International Airport Limited (BIAL), operator of Kempegowda International Airport, Bengaluru (KIAB), appealed under Section 18(2) of the Airports Economic Regulatory Authority of India Act, 2008 (AERA Act) against AERA’s tariff order dated 28 August 2021 for the Third Control Period, 1 April 2021 to 31 March 2026.
¶ 1–2The appeal challenged AERA’s treatment of, among other matters, COVID-related project costs, capital expenditure, revenue and expense allocation, depreciation, taxation, and AERA’s jurisdiction over particular airport activities.
¶ 3–42BIAL later withdrew Issues XXVIII and XXIX; the Tribunal therefore adjudicated the 27 remaining issues.
¶ 39–41, 86–8902Issues
i.1. Whether additional PMC costs incurred because COVID-19 restrictions delayed Terminal 2 were recoverable.
¶ 89, 90–132ii.2. Whether financing allowance was payable on work-in-progress assets capitalised during the Third Control Period.
¶ 89, 133–165iii.3. Whether the AERA Act’s tariff methodology could govern the period 24 May 2008 to 31 August 2009, and whether pre-control-period expenditure should be recognised.
¶ 89, 166–216iv.4. Whether capital and related costs for the Eastern Connectivity Tunnel, Terminal 2 apron transportation, KIA West Metro Station and metro-enabling works were admissible in the RAB.
¶ 89, 217–347v.5. Whether AERA could impute notional lease rentals from BAHL or AAI, or notional income from commercial land development.
¶ 89, 242–296, 348–367vi.6. Whether AERA could cap the cost of debt, refuse recognition of COVID-19 airline discounts, or cap pre-operative and design/PMC costs.
¶ 89, 368–426vii.7. Whether AERA’s depreciation determinations—including useful lives and asset-level allocation—were lawful.
¶ 89, 427–505viii.8. Whether AERA could defer ₹940.63 crore of ARR, include interest income in tariff calculations, or exclude the 30% non-aeronautical revenue used for cross-subsidy from the tax base.
¶ 89, 506–5599.9. Whether AERA had jurisdiction over land-development revenue and CGF-related services and revenues.
¶ 89, 560–63810.10. Whether AERA’s estimates of O&M and personnel expenses, penalty/readjustment, tax treatment, asset allocation and classification of specified cost centres were lawful; and whether AERA had to implement unstayed Tribunal judgments.
¶ 89, 639–91103Law Applied
Section 13(1)(a) of the AERA Act requires AERA to consider, among other matters, capital expenditure, service quality, efficiency, viable airport operations, revenue received from non-aeronautical services and concessions granted by the Central Government; Section 13(4) requires consultation, transparency and reasoned decisions.
¶ 101, 126, 234, 599, 700The 2011 Airport Tariff Guidelines govern the treatment of work-in-progress, commissioned assets, cost of debt and depreciation, subject to lawful amendment.
¶ 142–164, 234–238, 341–343The Tribunal applied the presumption against retrospectivity in *CIT v. Vatika Township Pvt. Ltd.* and *Keshavan Madhava Menon v. State of Bombay*.
¶ 171–175The distinction between actual revenue and hypothetical earning capacity under Section 13(1)(a)(v).
¶ 248–257, 269–274The Tribunal also relied on regulatory consistency and reasoned decision-making, and held that an appeal does not stay an order unless a competent court grants a stay, applying *Bhopal Sugar Industries Ltd. v. ITO*, *Union of India v. Kamlakshi Finance Corp.* and *Collector of Customs v. Krishna Sales (P) Ltd.*
¶ 887–895Provisions in the judgment · 20 · Linked ones open on LawLens
Airports Economic Regulatory Authority of India Act, 2008 14 provisions
Section 2Section 3Section 13Section 14Section 15Section 18Section 31Section 32Section 37Section 38Section 39Section 41Section 42Section 47Code of Civil Procedure, 1908 Section 10Section 11
Companies Act, 2013 Section 129
Airports Authority of India Act, 1994 Section 22
Motor Vehicles Act, 1988 Section 58Section 68
04Reasoning
The Tribunal found that AERA accepted COVID-19-related delay but rejected the resulting PMC costs without identifying unnecessary or imprudent expenditure, contrary to its earlier assurance that justified overruns would be considered at true-up.
¶ 113–130It held that AERA could not apply the later statutory tariff methodology retrospectively to 24 May 2008–31 August 2009, although the remitted historical claim had to be examined under the Concession Agreement and other project agreements; it separately directed consideration of qualifying pre-control-period expenses.
¶ 187–216For the infrastructure claims, the Tribunal relied on actual use, approved project treatment, regulatory consistency and the evidence of costs and operational need; it directed recognition or true-up of the qualifying expenditure, subject to the stated verification requirements.
¶ 225–241, 297–347It rejected notional revenues unsupported by actual receipts or contractual accrual, and held that AERA could not bring non-airport land-development activity within its jurisdiction merely because it occurred on the leased Site.
¶ 264–274, 287–296, 568–584It found that AERA’s caps and forecasts for financing, pre-operative, design/PMC, O&M and personnel costs were not adequately reasoned or supported by an appropriate prudence review; it directed actual-cost true-up where specified, while preserving verification against audited records and admissibility.
¶ 375–380, 402–409, 412–426, 663–693It also revised the depreciation and allocation approach, rejected the ARR carry-forward and penalty, and required tax and revenue calculations to follow the statutory and regulatory framework.
¶ 488–505, 519–525, 539–559, 699–723, 742–757, 758–818On cost-centre allocation, it set aside AERA’s classification because the order did not adequately examine the functions actually performed, and required a fresh reasoned decision.
¶ 832–87305Holding
The appeal was allowed to the extent of the 27 issues adjudicated.
¶ 774, 912–913The Tribunal set aside or modified the challenged determinations and directed AERA to carry out the issue-specific true-ups, recalculations, study and fresh decision described in the judgment—including giving effect to qualifying adjustments in the Fourth Control Period.
¶ 774, 912–913It further directed AERA to implement Tribunal judgments unless stayed, modified or reversed by the Supreme Court.
¶ 912–913AERA was directed to carry out the directions within three months of receiving the judgment; pending miscellaneous applications were disposed of.
¶ 911–913Original Court PDF