01Facts
The dispute arose from a 2008 contract for setting up two units at the Bokaro Steel Plant.
¶ 2–4SAIL deducted ₹5,53,00,925 from amounts payable to Primetals, claiming a shortfall in the minimum guaranteed CENVAT credit (MGCC).
¶ 2–4Primetals challenged the deduction in arbitration and also claimed reimbursement of excise duty.
¶ 2–4The tribunal allowed both claims; the Section 34 challenge was dismissed by the Single Judge.
¶ 2–4SAIL appealed under Section 37, pressing limitation and the interpretation of the MGCC clause in relation to Claim 1.
¶ 2–4, 10–12, 16–18, 28–3002Issues
i.1. Whether Primetals’ claim for recovery of the MGCC deduction was barred by limitation.
¶ 14–15, 40–44ii.2. Whether the tribunal’s interpretation of Clause 14.5.6 and the Note to Appendix 1—permitting any MGCC shortfall adjustment only against the Gross Contract Price, and not the Net Contract Price—warranted interference under Sections 34 and 37 of the Arbitration and Conciliation Act, 1996.
¶ 37–39, 45–5703Law Applied
Under Sections 34 and 37 of the Arbitration and Conciliation Act, 1996, a court exercising appellate jurisdiction under Section 37 cannot exceed the limited grounds available under Section 34 or reappraise the merits merely because another view is possible; a plausible arbitral interpretation ordinarily stands.
¶ 33–35 · Jan De Nul Dredging India Pvt. Ltd. v. Tuticorin Port Trust, (2026) 3 SCC 186Under Section 34(2)(b)(ii), disregarding a binding judgment of a superior court may contravene the fundamental policy of Indian law, subject to the statutory limits on review.
¶ 51–52 · OPG Power Generation (P) Ltd. v. Enexio Power Cooling Solutions (India) (P) Ltd., (2025) 2 SCC 417The Court also relied on the need for consistency in interpreting identical contractual provisions where a party is common.
¶ 52 · National Highway Authority of India v. Progressive-MVR (JV), (2018) 14 SCC 688Clause 12.1.6, read with Clause 12.1.7, was applied to determine when the payment dispute crystallised; the tribunal found that the relevant cause of action arose when SAIL communicated its recovery decision on 9 March 2019.
¶ 40, 44Provisions in the judgment · 4 · Linked ones open on LawLens
Arbitration and Conciliation Act, 1996 Section 37Section 34Section 33Section 48
04Reasoning
The Court held that the tribunal’s limitation finding was supported by the contract and the record: the disputed deduction was communicated on 9 March 2019, and arbitration was invoked within three years, so the claim was timely.
¶ 40, 43–44On the merits of Claim 1, the contractual provision was pari materia with one previously interpreted by the Delhi High Court between the same parties, and that interpretation had been affirmed on appeal.
¶ 47–56The tribunal therefore did not err by following that interpretation; the adjustment could be made only against the Gross Contract Price, not the Net Contract Price.
¶ 47–56The Court also noted that SAIL reimbursed duty only to the extent actually paid after the duty reduction and received corresponding CENVAT credit; it had not suffered the alleged shortfall and would be unjustly enriched if allowed to retain the deduction.
¶ 58–63SAIL did not press oral submissions on Claim 2, and the Court found no basis for interference with the tribunal’s excise-duty award.
¶ 30, 64–6705Holding
The Court answered the limitation issue in Primetals’ favour and found no ground to interfere with the tribunal’s interpretation or award of Claim 1.
¶ 44, 57It also upheld Claim 2 and dismissed SAIL’s Section 37 appeal.
¶ 63, 67–68Original Court PDF
Steel Authorlty Of India ImitedvsPrimetals Technologies India Pvt. Ltd
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
