Bombay High Court
Arbitration and MediationCivil Procedure and Evidence

An express contractual bar on interest precludes pendente lite interest under Section 31(7)(a).

The Kolhapur Municipal Corporation vs Fairdeal Construction

Bombay High CourtJUDGMENT: October 08, 20263 MIN READSOURCE JUDGMENT
An express contractual bar on interest precludes pendente lite interest under Section 31(7)(a).. The Kolhapur Municipal Corporation vs Fairdeal Construction. Bombay High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Corporation appointed Fairdeal as its agent to collect octroi for a one-year period beginning 1 November 1995.

Source reference: p. 3

After the Corporation terminated the agreement on 23 April 1996, Fairdeal challenged the termination and sought arbitration.

Source reference: p. 3

The arbitral award upheld the termination but awarded Fairdeal Rs. 24,06,50,119.03, interest at 18% per annum from 1 January 1997 through payment, and Rs. 1.5 crore in costs.

Source reference: paras. 4(iv)–(x), 4(xxviii); pp. 3–4, 8, 32

The Corporation’s Section 34 petition challenged the monetary award, both components of interest, and costs; it principally argued that the sums were unsupported or inconsistent with the Arbitrator’s findings, and that Clause 24 barred interest.

Source reference: paras. 6–20; pp. 9–25
02

Issues

1. Whether the monetary award of Rs. 24,06,50,119.03 was perverse or patently illegal, including because it allegedly relied on collections outside the contractual period and speculative estimates.

Source reference: paras. 30–35; pp. 32–41

2. Whether Clause 24 of the agreement barred the Arbitrator from awarding pendente lite interest under Section 31(7)(a) of the Arbitration and Conciliation Act, 1996.

Source reference: paras. 36–48; pp. 44–65

3. Whether the award of post-award interest at 18% per annum could stand under Section 31(7)(b), as applicable to the award dated 1 April 2019.

Source reference: paras. 49–50; pp. 65–70

4. Whether the award of Rs. 1.5 crore in costs was contrary to Section 31A or otherwise warranted interference under Section 34.

Source reference: paras. 51–53; pp. 71–75
03

Law Applied

Section 34(2A) permits a court to set aside a domestic award for patent illegality appearing on its face, but not merely to reappreciate evidence or substitute its view for a plausible arbitral finding; perversity may arise where a finding rests on no evidence, ignores vital evidence, or is one no reasonable decision-maker could reach (Ssangyong Engineering & Construction Co. Ltd. v. NHAI; Associate Builders v. DDA).

Source reference: para. 35; pp. 41–43

Under Section 31(7)(a), the tribunal’s power to award pre-award interest is subject to the parties’ agreement; an express contractual bar must be given effect (Sree Kamatchi Amman Constructions v. Divisional Railway Manager (Works), Palghat; Union of India v. Bright Power Projects (India) Pvt. Ltd.; Garg Builders v. Bharat Heavy Electricals Ltd.).

Source reference: paras. 38–43; pp. 46–60

Section 31(7)(b) provides for post-award interest at two percentage points above the current rate unless the award directs otherwise.

Source reference: para. 49; pp. 65–66

Section 31A empowers the tribunal to award reasonable costs, having regard to the circumstances specified in that section.

Source reference: para. 51; pp. 71–72

A court may sever or modify an award where the relevant portions are separable, including modifying post-award interest, within the limits explained in Gayatri Balasamy v. ISG Novasoft Technologies Ltd.

Source reference: para. 50; pp. 67–70
04

Reasoning

The Court declined to revisit the monetary calculation because the Arbitrator had assessed the parties’ records and an expert accountant’s report, and the Corporation’s objections would require reappreciation of evidence; the Court also treated the bid amount as distinct from actual octroi collections.

Source reference: paras. 31–35; pp. 32–41

By contrast, Clause 24 expressly barred the agent from claiming “any kind of interest” on its claims under the Interest Act or any other provision. Applying Section 31(7)(a), the Court held that the Arbitrator could not override that agreement by relying on alleged misconduct or public policy, and set aside the pendente lite interest.

Source reference: paras. 36–48; pp. 44–65

For post-award interest, the Court held that the amended Section 31(7)(b) governed the 2019 award and substituted 9% per annum for the awarded 18%.

Source reference: para. 49; pp. 65–66

It upheld the costs award, finding that the Arbitrator had considered both parties’ cost statements, the lengthy proceedings, and the Corporation’s conduct under Section 31A.

Source reference: paras. 51–52; pp. 71–74
05

Holding

The Court left undisturbed the principal award of Rs. 24,06,50,119.03 and the costs award of Rs. 1.5 crore, but set aside the pendente lite interest and modified post-award interest from 18% to 9% per annum.

The petition was disposed of in part.

Source reference: paras. 48–53; pp. 65–75

The Court directed that any amount deposited in Court be released one month after the judgment was uploaded and granted a three-week stay of the judgment’s operation following pronouncement.

Source reference: para. 53; pp. 75–76
06

Acts & Sections Cited

15 provisions across 4 statutes referred to in this judgment. Each provision opens on LawLens.

Arbitration and Conciliation Act, 199610 provisions

Interest Act, 19782

Indian Contract Act, 18722

India International Arbitration Centre Act, 20191

Bombay High Court

Original Court PDF

The Kolhapur Municipal CorporationvsFairdeal Construction

Bombay High Court · October 08, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment