Calcutta High Court

### Anticipatory Breach Requires Absolute Refusal to Perform; Advanced Payment Inextricable Without Express Forfeiture Clause Synopsis: In a consolidated judgment involving the transfer of controlling shares in a company (M/s Bhoomi Minerals), the High Court at Calcutta addressed two critical aspects of contract law: anticipatory breach and the forfeiture of earnest money. Anticipatory Breach (Section 39, Indian Contract Act): The purchasers (Kanodias) terminated the Memorandum of Understanding (M.O.U.) alleging an anticipatory breach after the sellers (Agarwallas) proposed amendments to security clauses. The Court ruled that for Section 39 to be invoked, there must be a "total refusal" to perform the contract in its entirety or an act that destroys the contract's core. Since the sellers remained willing to transfer the shares—merely proposing a novation of interregnum security terms—there was no "unqualified and positive refusal." Consequently, the purchasers' premature termination constituted a breach of contract, making them liable for damages. Damages and Forfeiture: 1. Damages: The Court upheld the sellers' claim for damages (the difference between the M.O.U. price and the eventual lower sale price to a third party) to put the aggrieved party in the position they would have been in had the contract been performed. 2. Forfeiture of Earnest Money: Following the principle in *Fateh Chand v. Balkishan Dass*, the Court held that in the absence of an "explicit and clear" forfeiture clause within the M.O.U., any advance payment or earnest money cannot be forfeited, even if the depositor is in breach. Conclusion: The Court decreed damages of ₹5.51 crores in favor of the sellers while simultaneously ordering the refund of the ₹1 crore advance to the purchasers, allowing for the adjustment of these amounts between the parties.

UMADEVI AGARWALLA & ORS. vs NIRMAL KANODIA & ORS.

Calcutta High CourtJUDGMENT: May 12, 20263 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Agarwallas (original plaintiffs in CS/124/2011) owned M/s Bhoomi Minerals Ltd., a company with a sponge iron unit in Jharkhand that was heavily indebted to the Indian Overseas Bank

Source reference: p. 2

On 20/09/2010, they entered into a Memorandum of Understanding (MOU) to sell the company to the Kanodias for ₹28.01 crores. The Kanodias paid ₹1 crore as advance/earnest money

Source reference: p. 3-5

Following the execution, the Agarwallas proposed an amended MOU modifying the share transfer ratio (retaining 51% instead of 49% as interim security), which the Kanodias refused to sign

Source reference: p. 11-12

Asserting that the Agarwallas committed an anticipatory breach by changing terms and suppressing the fact of the bank mortgage, the Kanodias terminated the MOU via SMS on 24/09/2010 and sought a refund of ₹1 crore

Source reference: p. 12, 19

The Agarwallas, claiming the Kanodias breached the contract, were forced to sell the unit to a third party at a lower price (₹22.5 crores) and sued for damages of ₹5.51 crores

Source reference: p. 5-6
02

Issues

1. Whether the MOU dated 20/09/2010 was legal, valid, or binding upon the parties?

Source reference: p. 18 / para. 8

2. Whether the Agarwallas committed an anticipatory breach of contract by proposing amendments?

Source reference: p. 19, 24-26

3. Whether the Kanodias are liable to pay damages for breach of contract?

Source reference: p. 18 / para. 6

4. Whether the Agarwallas are entitled to forfeit the earnest money in the absence of a forfeiture clause?

Source reference: p. 22, 28-29
03

Law Applied

Section 39 of the Indian Contract Act, 1872, regarding the refusal of a party to perform a promise in its entirety, noting it requires the "destruction" of the contract

Source reference: p. 24-25

Manindra Chandra Nandy v. Aswini Kumar Acharjya, which defined anticipatory breach as an unqualified refusal to perform

Source reference: p. 19, 24

Maharashtra State Electricity Distribution Co. Ltd. v. Datar Switchgear Ltd., holding the injured party must be put in as good a position as if the contract had been performed

Source reference: p. 27-28

Section 74 of the Indian Contract Act and the precedents in Fateh Chand v. Balkishan Dass and Satish Batra v. Sudhir Rawal, which establish that earnest money cannot be forfeited without an express "clear and explicit" forfeiture clause in the contract

Source reference: p. 28-29
04

Reasoning

The court found the MOU was valid and not void ab initio, as the Kanodias terminated it rather than avoiding it for misrepresentation

Source reference: p. 23-24

It held there was no "anticipatory breach" by the Agarwallas because their proposed amendment—retaining a majority stake only as interim security until bank guarantees were released—did not signal a refusal to perform the contract "in its entirety"

Source reference: p. 26

Since the original MOU remained subsisting and the Kanodias unilaterally terminated it, the breach lay with the Kanodias

Source reference: p. 27

Regarding damages, the court accepted the Agarwallas' evidence of loss (₹5.51 crores) resulting from the forced sale at a lower price

Source reference: p. 27-28

However, regarding the ₹1 crore advance, the court observed the MOU lacked a forfeiture clause. Consequently, under Section 74, the Agarwallas had no legal right to retain the money as a penalty and were bound to refund it, notwithstanding the Kanodias' breach

Source reference: p. 28-29
05

Holding

The court held that the Kanodias committed the breach of contract but the Agarwallas could not forfeit the earnest money without a contractual provision.

In CS 124/2011, the court decreed ₹5.51 crores in favor of the Agarwallas with 7% interest p.a. from the date of institution. In CS 264/2012, the court decreed the refund of ₹1 crore in favor of the Kanodias with 7% interest p.a. from the date of institution. The parties were granted liberty to adjust the decretal amounts against each other.

Source reference: p. 30
Calcutta High Court

Original Court PDF

UMADEVI AGARWALLA & ORS.vsNIRMAL KANODIA & ORS.

Calcutta High Court · May 12, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment