01Facts
The Petitioner (MBL Infrastructure) was awarded a canal restoration contract in Bihar and issued a Work Order to the Respondent (Pradeep Colonisers) in 2015
¶ 14(a)-(b)In March 2017, Corporate Insolvency Resolution Process (CIRP) was initiated against the Petitioner under the IBC
¶ 14(e)The Respondent submitted a claim of ₹7.29 Crores to the Interim Resolution Professional (IRP), which was partially verified in the List of Creditors but ultimately excluded from the final Resolution Plan approved by the NCLT on 18.04.2018
¶ 14(f)-(i)After the Plan was upheld by the Supreme Court in 2022, an Arbitral Tribunal was constituted to resolve contractual disputes
¶ 14(l)-(m)The Arbitrator held that the counter-claims were maintainable because the Petitioner’s management had not changed (promoter-led resolution) and the Respondent was recognized as an "Operational Creditor" by the Supreme Court during impleadment
¶ 2102Issues
i.1. Whether the counter-claims of the Respondent were maintainable before the learned Arbitrator in light of the approval of a Resolution Plan under the Insolvency and Bankruptcy Code, 2016
¶ 3, 9, 13ii.2. Whether the "Clean Slate Theory" is inapplicable if the Resolution Plan is submitted by the existing promoter/management rather than a third-party applicant
¶ 12, 5003Law Applied
Section 31(1) of the Insolvency and Bankruptcy Code (IBC), 2016, which stipulates that an approved Resolution Plan is binding on the corporate debtor, creditors, and all stakeholders
¶ 27The "Clean Slate Theory" as established in Ghanshyam Mishra & Sons Pvt. Ltd. v. Edelweiss Asset Reconstruction Co. Ltd., holding that all claims not part of the approved Resolution Plan stand extinguished
¶ 15(XIV), 30Principle from Committee of Creditors of Essar Steel India Ltd. v. Satish Kumar Gupta, which prohibits "undecided" claims from popping up after resolution to ensure commercial certainty
¶ 15(XIV), 30Section 238 of the IBC regarding the overriding effect of the IBC over other inconsistent laws
¶ 35Provisions in the judgment · 4 · Linked ones open on LawLens
Insolvency and Bankruptcy Code, 2016. Section 36
Code of Civil Procedure, 1908 Section 47
Indian Contract Act, 1872 Section 23
Competition Act, 2002 Section 5
04Reasoning
The Court found that the learned Arbitrator committed a patent illegality by carving out an exception to the IBC based on the identity of the Resolution Applicant
¶ 50-51Section 31 of the IBC does not distinguish between third-party applicants and existing promoters; the binding nature of a Plan attaches to the corporate debtor as a legal entity
¶ 53-54The Respondent had actively participated in the CIRP by filing Form-B but failed to challenge the exclusion of its claims from the Plan before the NCLT or NCLAT
¶ 31, 36The Respondent cannot bypass the "complete code" of the IBC by using arbitration as a collateral route to revive extinguished debts
¶ 35, 46The Supreme Court’s order allowing the Respondent’s impleadment did not grant substantive relief or revive the debt; since the Supreme Court ultimately declined to disturb the Plan, the Respondent’s claims remained extinguished
¶ 41-43, 6505Holding
The Court held that the Respondent's counter-claims were not maintainable as they stood extinguished upon the approval of the Resolution Plan under Section 31 of the IBC
¶ 73-74The Arbitral Award was set aside to the extent that it upheld and granted relief on the counter-claims
¶ 76Execution Petition filed by the Respondent (O.M.P. (ENF.) (COMM) 281/2025) was dismissed
¶ 78Original Court PDF
M/S Mbl Infrastructure LtdvsM/S Pradeep Colonisers And Suppliers Pvt Ltd
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
