Facts
The Appellant (landowner) and Respondent (collaborator) entered into a Collaboration Agreement on 07.06.2016 for the commercial development of land in Gurugram
Source reference: para. 2, 7The Respondent failed to adhere to payment schedules and construction timelines, including the critical task of removing an overhead electricity line
Source reference: para. 13-14Consequently, the Appellant terminated the Agreement on 15.06.2019 and invoked arbitration
Source reference: para. 19, 21The Sole Arbitrator upheld the termination, ordered the handover of possession, and awarded mesne profits of ₹30,00,000 per month from 01.07.2019 to 30.11.2023 (totaling ₹15,90,00,000) based on "guesswork," noting that neither party led evidence on quantification
Source reference: para. 3, 29In a Section 34 petition, the learned Single Judge set aside the award to the limited extent of the mesne profits, holding the quantification lacked evidentiary support
Source reference: para. 5, 37The Appellant challenged this interference under Section 37 of the Arbitration and Conciliation Act, 1996 ("the Act")
Source reference: para. 1Issues
1. Whether the learned Single Judge exceeded the scope of Section 34 by interfering with the Arbitrator’s quantification of mesne profits
Source reference: para. 6, 382. Whether an Arbitral Tribunal can award damages based on "honest guesswork" in the total absence of evidence or reasoning
Source reference: para. 59-60Law Applied
The Court applied Section 34 and Section 37 of the Arbitration and Conciliation Act, 1996, regarding the limited scope of judicial interference with arbitral awards
Source reference: para. 51-52It relied on the doctrine of "Patent Illegality" under Section 34(2-A), which includes findings based on "no evidence" or awards devoid of reasoning [DMRC Ltd. v. Delhi Airport Metro Express (P) Ltd., para. 81]
Source reference: para. 81The Court further applied the principle that while "honest guesswork" or a "rough and ready" method is permissible for assessing unliquidated damages, such estimation must be anchored in some foundational material or discernible reasoning [Bharat Heavy Electricals Ltd. v. Delkon India Pvt. Ltd., para. 64; New Okhla Industrial Development Authority v. Harnand Singh, para. 75]
Source reference: para. 64, 75Reasoning
The Court observed that the Arbitrator expressly recorded that "no evidence is led in this behalf by either party" regarding the quantification of loss
Source reference: para. 58, 73While acknowledging that Indian law permits "honest guesswork" when exact mathematical precision is impossible, the Court clarified that such discretion is not unfettered; it must have a rational nexus with the material on record
Source reference: para. 66, 70In this case, the Tribunal rejected the only valuation report provided (CBRE report) and failed to cite any other benchmark (such as the Colliers report) or provide a methodology for arriving at the ₹30 Lakhs per month figure
Source reference: para. 71-73The Court held that an award without reasons or based on "no evidence" constitutes patent illegality
Source reference: para. 79, 83The Court rejected the Appellant's argument that the figure was traceable to the record, noting that the Court cannot supplement or reconstruct the Arbitrator’s reasoning with material the Arbitrator himself explicitly stated did not exist
Source reference: para. 73, 79Holding
The Court dismissed the appeal and upheld the Single Judge’s order setting aside the mesne profits
It held that the Arbitral Award, to the extent of the ₹15,90,00,000 award, suffered from patent illegality as it was both unsupported by evidence and devoid of reasons
Source reference: para. 89The Court affirmed that while the Appellant is entitled to seek mesne profits due to the Respondent's wrongful possession, such damages cannot be "conjured out of thin air"
Source reference: para. 83-84The Court maintained the liberty granted to the Appellant to pursue the claim for mesne profits in accordance with the law
Source reference: para. 90No order as to costs
Source reference: para. 92Original Court PDF
Radiance Infracon And Developers Pvt LtdvsGls Infratech Pvt Ltd
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in