Facts
The parties entered into a contract on 08.08.2018
Source reference: p. 1Following disputes, the Petitioner invoked arbitration on 28.10.2022 and subsequently filed a Section 11 petition
Source reference: p. 1A Sole Arbitrator was appointed on 03.07.2023
Source reference: p. 2Pleadings were completed on 16.05.2024, and the proceedings reached the stage of cross-examination of the respondent’s witness
Source reference: p. 2Earlier, under O.M.P. (Misc.) (Comm.) No. 664/2025, the Court had extended the arbitrator’s mandate until 31.03.2026
Source reference: p. 2The Petitioner filed the present petition under Section 29A(4) of the Arbitration and Conciliation Act, 1996 ("the Act"), seeking a further extension until 31.03.2027, citing the complexity of the evidence and the advanced stage of the proceedings
Source reference: p. 1-2The Respondent expressed no objection to the extension
Source reference: p. 2Issues
1. Whether sufficient cause exists under Section 29A(4) and (5) of the Act to extend the mandate of the Sole Arbitrator for the conclusion of arbitral proceedings
Source reference: p. 1 / para. 1, 10Law Applied
The court primarily applied Section 29A of the Arbitration and Conciliation Act, 1996, which stipulates the statutory timelines for making an arbitral award and provides for the extension of the arbitrator's mandate by the court upon the showing of "sufficient cause"
Source reference: para. 11It further relied on the precedent established in Rohan Builders (India) Private Limited v. Berger Paints India Limited (2024 SCC OnLine SC 2494), which clarified the scope, ambit, and mandatory nature of the timelines and extension provisions under Section 29A
Source reference: para. 12Reasoning
The Court observed that the arbitral proceedings had progressed substantially, having moved past the claimant's evidence to the cross-examination of the respondent's witness
Source reference: para. 3It noted that the failure to conclude within the previously extended timeline was attributable to the nature of the disputes and the requirement for detailed evidence, rather than lack of diligence
Source reference: para. 6Applying Section 29A(5), the Court found that the "interest of justice" and the need for "continuity and consistency" in the proceedings constituted sufficient grounds for extension
Source reference: para. 10Crucially, the Court highlighted that since both parties were ad idem (in agreement) regarding the necessity of the extension, there was no legal impediment to granting the relief
Source reference: para. 10Holding
The Court allowed the petition and extended the mandate of the learned Sole Arbitrator until 31.03.2027
Furthermore, the Court ordered that the period from the expiry of the previous mandate (31.03.2026) until the date of the present order be regularized
Source reference: para. 14The petition and all pending applications were disposed of accordingly
Source reference: para. 15Original Court PDF
M/S Anj Vc JvvsNational Highways Authority Of India
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in