Supreme Court

Arbitral tribunal cannot award pre-reference or pendente lite interest where contract specifically prohibits such payment.

Union of India & Ors. v. Larsen & Tubro Limited (L&T) [2026 INSC 203]

Supreme CourtJUDGMENT: no citation3 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The dispute arose from a 2011 turnkey agreement for the modernization of the Jhansi Workshop, North Central Railways.

Source reference: paras 4-5

Completion was delayed by 40 months beyond the original 18-month deadline, leading L&T (Respondent) to seek arbitration for outstanding payments and interest.

Source reference: paras 4-5

An Arbitral Tribunal (AT) awarded L&T ₹5,53,57,597, which included "financing charges" and interest components under Claims 1, 3, and 6, despite Clause 16(3) and 64(5) of the General Conditions of Contract (GCC) prohibiting interest on amounts payable under the contract.

Source reference: paras 8, 10

The Union of India challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996 ("the Act"), and subsequently under Section 37, but both the Commercial Court and the Allahabad High Court upheld the award.

Source reference: paras 11-13
02

Issues

Whether the Arbitral Tribunal was justified in awarding pre-award/pendente lite interest, styled as compensation, despite contractual prohibitions in Clause 16(3) and 64(5) of the GCC.

Source reference: para 29(A)

Whether the Arbitral Tribunal was justified in awarding post-award interest and if the rate was reasonable.

Source reference: para 29(B)

Whether the lower courts erred in their oversight of the Arbitral Award under Sections 34 and 37 of the Act.

Source reference: para 29(C)
03

Law Applied

The Court applied Section 28(3) and Section 31(7)(a) of the Arbitration and Conciliation Act, 1996, which mandate that an arbitrator must decide in accordance with the contract terms and that the power to award interest is subject to the agreement of the parties.

Source reference: paras 33-34

It relied on Union of India v. Bright Power Projects (India) (P) Ltd. (2015), establishing that when a contract bars interest, the arbitrator lacks jurisdiction to award it.

Source reference: para 40

The principle of ejusdem generis was evaluated via Union of India v. Manraj Enterprises (2022) to hold that "amounts payable under the contract" is an independent category.

Source reference: para 38

Regarding post-award interest, the Court applied Section 31(7)(b) of the Act and the precedent in R.P. Garg v. Chief General Manager, Telecom Department (2024), which distinguishes post-award interest as a statutory right not subject to party autonomy.

Source reference: paras 48, 56

Lastly, it applied Gayatri Balasamy v. M/s. ISG Novasoft Technologies Ltd. (2025) regarding the court's power to modify interest rates.

Source reference: para 59
04

Reasoning

The Court noted that Section 31(7)(a) is qualified by the phrase "Unless otherwise agreed by the parties," making the contract paramount regarding pre-award interest.

Source reference: para 35

Clause 16(3) of the GCC explicitly barred interest on "amounts payable to the contractor," and the Court rejected the Respondent’s attempt to limit this clause via ejusdem generis, ruling that the bar applied to all claims for delayed payments.

Source reference: paras 38-39

The AT's attempt to award interest under the guise of "compensation" (Claims 1, 3, 6) was found to be a violation of the contractual bar and Section 28(3).

Source reference: paras 52-53

Conversely, for post-award interest, Clause 64(5) only barred interest "till the date the award is made," leaving the post-award period open.

Source reference: para 50

Under Section 31(7)(b), post-award interest is a statutory mandate intended to ensure prompt compliance; however, the Court found the 12% rate lacked justification and was excessive in the current economic context.

Source reference: paras 57-58
05

Holding

The Court partly allowed the appeal.

It held that the AT lacked jurisdiction to grant pre-award or pendente lite interest (Claims 1, 3, and 6) due to the express bar in Clauses 16(3) and 64(5) of the GCC.

Source reference: para 61(A)

The award of post-award interest was upheld as a statutory right under Section 31(7)(b), but the rate was modified from 12% per annum to 8% per annum from the date of the award until realization.

Source reference: para 61(B)

The judgments of the High Court and Commercial Court were set aside to the extent they affirmed the pre-award interest.

Source reference: para 62
Supreme Court

Original Court PDF

Union of India & Ors. v. Larsen & Tubro Limited (L&T) [2026 INSC 203]

Supreme Court · no citation

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment