Delhi High Court

Arbitral Tribunal’s Determination of a "Reasonable Period" for Performance in Absence of Contractual Timelines is Legally Sustainable.

National Highways Authority Of India vs M/S Atlanta Infra Assets Ltd

Delhi High CourtJUDGMENT: May 26, 20263 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The National Highway Authority of India (NHAI) awarded a project for widening NH-6 to a consortium, leading to a Concession Agreement (CA) dated 09.12.2005.

Source reference: para. 6-9

Due to delays in land availability, a Supplementary Agreement (SA) was executed on 22.09.2011 to complete remaining works within 120 days of land being made available, though the SA did not specify a timeline for NHAI to hand over the land.

Source reference: para. 12, 37

Post-PCC disputes led to arbitration where the majority Arbitral Tribunal (AT) awarded damages to Atlanta but determined 18 months as a "reasonable period" for land handover rather than the 12 months stipulated in the original CA.

Source reference: para. 16, 20

NHAI also filed counterclaims for Atlanta’s failure to perform maintenance (Bituminous Overlay), for which the AT awarded only "token damages" of 0.1% of the cost without multiplying by the days of delay.

Source reference: para. 17, 72

Both parties challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996.

Source reference: para. 1-4
02

Issues

1. Whether the AT exceeded its jurisdiction or acted with patent illegality by interpreting 18 months as a "reasonable period" for land handover under the SA instead of 12 months

Source reference: para. 19-20

2. Whether the AT’s award of 10% interest for the petitioner and 12% for the respondent was discriminatory or contrary to party agreement

Source reference: para. 26-27

3. Whether the AT erred in awarding only token damages to NHAI for maintenance defaults by failing to calculate damages "for each day of default" as per Clause 18.13

Source reference: para. 42-44, 75
03

Law Applied

Section 34 of the Arbitration and Conciliation Act, 1996, which restricts judicial interference to grounds of patent illegality or conflict with the fundamental policy of Indian law.

Source reference: para. 48

The court relied on Hungerford Investment Trust Ltd. v. Haridas Mundhra to hold that where no time is prescribed for an act, the law implies a "reasonable time" based on facts.

Source reference: para. 58

Under Section 31(7) of the Act and Hyder Consulting (UK) Ltd. v. State of Orissa, the AT has discretionary power to award interest at rates it deems reasonable.

Source reference: para. 68-69

Section 74 of the Indian Contract Act, 1872, as interpreted in NHAI v. Patel Knr Heavy Infrastructure, dictates that liquidated damages require proof of actual loss unless the stipulated sum is a genuine pre-estimate.

Source reference: para. 82-83
04

Reasoning

Regarding the 18-month timeline, the Court found the AT’s reasoning plausible because the SA deliberately omitted the 12-month stipulation found in the CA; thus, the AT did not rewrite the contract but interpreted a "reasonable period" using the land acquisition process as context.

Source reference: para. 60-61

On the issue of interest, the Court held that the 12% rate recorded in previous proceedings was a limited settlement for specific claims and did not bind the AT’s discretion for the entire award.

Source reference: para. 65-67

For Counterclaim 4(c), the Court upheld the award of "token damages." It reasoned that NHAI failed to prove actual loss and that the formula proposed by the Independent Consultant relied on policy guidelines from 2016 which could not be retroactively applied to a 2005 Agreement.

Source reference: para. 74, 80

The Court emphasized that interpreting contractual clauses and assessing evidence for damages falls exclusively within the AT’s domain.

Source reference: para. 85
05

Holding

The determination of 18 months as a reasonable period was a plausible interpretation not subject to interference.

The interest rate of 10% was within the AT's discretion under Section 31(7).

Source reference: para. 70

The award of token damages (Rs. 88,564/-) under Counterclaim 4(c) was legally sound as liquidated damages cannot be mechanically awarded without demonstrated actual loss.

Source reference: para. 84-86

The Court dismissed both petitions and upheld the Arbitral Award, finding it did not suffer from patent illegality or perversity.

Source reference: para. 87
Delhi High Court

Original Court PDF

National Highways Authority Of IndiavsM/S Atlanta Infra Assets Ltd

Delhi High Court · May 26, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment