Delhi High Court

Arbitrator’s Finding of Irregularity Based on "No Evidence" and Undisclosed Particulars Constitutes Patent Illegality

D V Anand vs Hindustan Petroleum Corporation Ltd

Delhi High CourtJUDGMENT: July 01, 20263 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Appellant, an LPG distributor for the Respondent since 1981, executed a Dealership Agreement on 31.10.2013.

Source reference: para. 8

In 2014, the Respondent received complaints alleging 826 fake LPG connections in the Appellant's database.

Source reference: para. 10

Verification letters sent to a sample of 387 consumers were returned undelivered, and physical inspections in specific areas failed to locate the consumers.

Source reference: para. 11

The Respondent issued a Show Cause Notice (SCN) and subsequently imposed a penalty of ₹2,24,89,020 based on the Marketing Disciplinary Guidelines (MDG), citing 826 fake connections and 25,181 unaccounted refills.

Source reference: para. 12-16

The dispute was referred to a Sole Arbitrator who upheld the penalty (adjusted to ₹2,03,12,102).

Source reference: para. 28

The Appellant’s challenge under Section 34 of the Arbitration and Conciliation Act, 1996, was dismissed by a Single Judge.

Source reference: para. 29

The Appellant then filed this intra-court appeal under Section 37.

Source reference: para. 1
02

Issues

1. Whether the learned Arbitrator became ineligible to continue the proceedings under Section 12(5) of the Arbitration Act, 1996, following the 2015 Amendment.

Source reference: para. 49

2. Whether the findings of the Arbitral Tribunal regarding the existence of 826 fake connections were based on "no evidence" and thus patently illegal.

Source reference: para. 35, 95

3. Whether the arbitral award can be partially set aside or modified under the doctrine of severability.

Source reference: para. 158
03

Law Applied

Section 26 of the 2015 Amendment Act, which stipulates that amendments do not apply to arbitral proceedings commenced before 23.10.2015 unless parties agree otherwise.

Source reference: para. 51-52

Reliance on Rajasthan Small Industries Corpn. Ltd. v. Ganesh Containers Movers Syndicate, confirming Section 12(5) is prospective.

Source reference: para. 55

Section 34(2-A) and principles from Associate Builders v. DDA and Ssangyong Engg. & Construction Co. Ltd. v. NHAI, which define "patent illegality" as findings based on "no evidence" or ignoring vital evidence.

Source reference: para. 99-100

Doctrine of severability from Gayatri Balasamy v. ISG Novasoft Technologies Ltd., allowing courts to partially set aside an award if the valid and invalid portions are separable.

Source reference: para. 159-160
04

Reasoning

The Court first held the Arbitrator was eligible because the proceedings commenced in 2014, prior to the 2015 Amendment.

Source reference: para. 66

For "Set I" (446 connections), the Court found the Arbitrator’s decision plausible as particulars were provided in the SCN and the Appellant admitted to data manipulation by employees.

Source reference: para. 86-90

For "Set II" (380 connections), the Court found the award patently illegal. The Respondent provided no particulars for these connections, conducted no investigation, and the Appellant’s letters seeking their identity were ignored.

Source reference: para. 106, 145

The Arbitrator’s shifting of the burden of proof to the Appellant to prove the genuineness of unidentified consumers was deemed perverse and based on "no evidence".

Source reference: para. 126, 155

The Court concluded that while the first two penalty heads (fixed penalty and per-connection fine for Set I) were severable and calculable, the third head (unaccounted refills) was inseparably linked to all 826 connections and required fresh fact-finding, making it unsustainable.

Source reference: para. 166-169
05

Holding

The Court held that the Arbitrator had jurisdiction under the unamended Act.

The Court modified the award by maintaining the penalty for the 446 verified fake connections (Set I) while setting aside the findings for the remaining 380 connections (Set II).

Source reference: para. 173

Specifically, it sustained ₹3,15,472 (critical irregularity) and ₹22,30,000 (penalty for 446 connections @₹5000 each).

Source reference: para. 173

It set aside the ₹1,64,81,665 penalty for unaccounted refills as it was based on an unsegregated figure for all 826 connections.

Source reference: para. 174

The Court partially allowed the appeal and reduced the final recoverable Counter-Claim to ₹25,45,472.

Source reference: para. 176
Delhi High Court

Original Court PDF

D V AnandvsHindustan Petroleum Corporation Ltd

Delhi High Court · July 01, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment