01Facts
The appellant (ITD) was awarded a contract for underground metro tunneling in Kolkata.
¶ 15On August 31, 2019, a major water ingress incident occurred during tunneling, causing extensive surface property damage and subsequent litigation.
¶ 15The appellant initiated arbitration regarding liability for the accident.
The Arbitral Tribunal (AT) passed an award on August 6, 2023, largely exonerating the appellant.
¶ 16The respondent (Kolkata Metro) challenged this under Section 34 of the Arbitration and Conciliation Act, 1996.
A Single Judge of the High Court set aside the award, finding it patently illegal and perverse.
¶ 2The appellant then filed this appeal under Section 37 of the Act.
¶ 102Issues
i.Whether the Arbitral Tribunal committed patent illegality by substituting its members' personal professional knowledge for tangible evidence to discard expert reports.
¶ 17-18ii.Whether the Arbitral Tribunal violated Section 18 of the Act by applying "double standards" in accepting the appellant's pre-retrieval reports while summarily rejecting the respondent's post-retrieval expert reports.
¶ 19-21iii.Whether the Arbitral Tribunal’s failure to consider specific contractual clauses (GCC 4.1, 4.23, and 14.5) regarding third-party liability and unforeseen conditions rendered the award perverse.
¶ 26-2803Law Applied
The court applied Section 34 (Setting aside an award) and Section 37 (Appeals) of the Arbitration and Conciliation Act, 1996.
¶ 1It relied on the "patent illegality" and "public policy" grounds established in Ssangyong Engineering & Construction Co. Ltd. v. NHAI, Associate Builders v. DDA, and Ramesh Kumar Jain v. Bharat Aluminum Co. Ltd.
¶ 13, 71, 30The court followed the principle that while an arbitrator can use technical expertise to interpret evidence, they cannot use personal knowledge of facts not on record to supplant evidence (P.R. Shah Shares & Stock Brokers Pvt. Ltd. v. B.H.H. Securities).
¶ 22-23The court also applied Section 18 of the Act, which mandates equal treatment of parties.
¶ 21, 71Provisions in the judgment · 4 · Linked ones open on LawLens
Arbitration and Conciliation Act, 1996 Section 34Section 37Section 18Section 31
04Reasoning
The Court found that the AT members improperly used their personal backgrounds (e.g., being an IIT Delhi alumnus) to discard the respondent's Soil Penetration Test (SPT) data without scientific counter-evidence.
¶ 17-18, 58The AT was found to have violated Section 18 by rejecting the respondent's expert reports—submitted 900 days late due to the time required to retrieve the damaged Tunnel Boring Machine (TBM)—as "litigation-driven," while accepting the appellant's reports despite both being prepared for the proceedings.
¶ 21, 68-70Furthermore, the AT ignored vital contractual terms in the General Conditions of Contract (GCC), specifically Clause 4.23, which required written reporting of unforeseen conditions, and Clause 4.1, which placed the risk of third-party damage on the contractor regardless of the Engineer's approval.
¶ 26-29, 87By shifting liability to the respondent against the express terms of the contract without assigning reasons, the AT’s view was deemed not a "plausible" interpretation but a perverse one.
¶ 28-3305Holding
The Court dismissed the appeal and upheld the Single Judge's decision to set aside the arbitral award.
¶ 43-44It held that the AT exceeded its mandate by ignoring the contract and treating parties unequally.
¶ 31, 42The Court concluded that the scope of Section 37 is limited to ensuring the Section 34 court acted within its jurisdiction; here, the Single Judge rightly identified patent illegality and perversity in the award.
¶ 36-37, 43The appeal was dismissed without costs.
¶ 44Original Court PDF
ITD-ITD CEM Joint VentureVs.Kolkata Metro Rail Corporation Limited [2026:CHC-OS:81-DB]
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
![Arbitrators cannot supplant evidence with personal knowledge or discard expert reports without rational justification.. ITD-ITD CEM Joint Venture Vs. Kolkata Metro Rail Corporation Limited [2026:CHC-OS:81-DB]. Calcutta High Court. LawLens](/stories/thumbnails/arbitrators-cannot-supplant-evidence-with-personal-knowledge-or-discard-expert-reports-wit-253754319e6740aebdc705d7a73effd6.webp)