Facts
The Appellant was appointed as the sole selling agent for Manipur State Online Lotteries via a contract dated 05.04.2001, modified on 20.11.2002
Source reference: para 4, 7The modified agreement (Clause 10.4) stipulated that the first draw must commence within six months (by 20.05.2003), failing which a compensation of ₹35 crores was payable
Source reference: para 7, 8The first draw was delayed until 01.12.2003
Source reference: para 11Following disputes, an Arbitral Tribunal (AT) awarded the State (Respondent) ₹10 crores as liquidated damages for the delay (Counter-claim 1) and ₹19,48,111 for construction costs (Counter-claim 4)
Source reference: para 8, 11The Appellant challenged this award under Section 34 of the A&C Act, which was dismissed by the District Judge, Imphal East, on 24.02.2021
Source reference: para 4The Appellant subsequently filed this appeal under Section 37
Source reference: para 5Issues
1. Whether the award of ₹10 crores as liquidated damages, without evidence of legal injury or loss, is in conflict with the public policy of India or vitiated by patent illegality
Source reference: para 112. Whether the award of ₹19,48,111 for actual construction costs should be sustained or severed
Source reference: para 34Law Applied
The court applied Section 74 of the Indian Contract Act, 1872, noting that while it dispenses with proof of "actual loss," it requires the existence of "legal injury" to award compensation
Source reference: para 20, 26The court relied on the Constitution Bench in Fateh Chand v. Balkishan Dass, which held that compensation must be reasonable and based on settled principles
Source reference: para 26Maula Bux v. Union of India and Kailash Nath Associates v. DDA established that if loss can be calculated, it must be proved; liquidated damages are only awarded without proof when loss is impossible or difficult to estimate
Source reference: para 27, 28Regarding "public policy," the court applied the "fundamental policy of Indian law" test from ONGC v. Saw Pipes and CORE-II, asserting that disregarding binding Supreme Court precedents constitutes such a violation
Source reference: para 15, 23, 31The principle of "severability" from ISG Novasoft Technologies v. Gayatri Balasamy was used to separate distinct claims
Source reference: para 34, 35Reasoning
The court found that although the AT treated Clause 10.4 as a liquidated damages provision, the State failed to lead any evidence regarding the loss suffered due to the delay
Source reference: para 18, 22The AT arbitrarily arrived at the figure of ₹10 crores without any inferential process or mathematical basis
Source reference: para 28, 33The High Court reasoned that since lottery business is res extra commercium, the State could not have suffered a standard commercial loss justifying such high damages
Source reference: para 29, 38By awarding a sum without proof of injury and ignoring the mandates of Fateh Chand and Kailash Nath, the AT committed a patent illegality and violated the fundamental policy of Indian law
Source reference: para 33, 39Conversely, Counter-claim 4 for ₹19,48,111 represented actual, unpaid construction costs for a facility built for the Appellant; this was a factual recovery of expenditure, not damages, and thus did not suffer from legal infirmity
Source reference: para 34, 37Holding
The Court allowed the appeal in part
The Court set aside the Section 34 Court’s order and the Arbitral Award insofar as they granted ₹10 crores in damages under Counter-claim 1, holding it was patently illegal and against public policy
Source reference: para 43(i), (iii)The Court sustained the award of ₹19,48,111 under Counter-claim 4, as it was a distinct, proven debt for construction costs
Source reference: para 43(ii), (iv)No order as to costs was made
Source reference: para 43(vi)Original Court PDF
MWC MARKET SERVICES PVT. LTD.vsSTATE OF MANIPUR AND 4 OTHERS
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in